Attachment 2 - Performance Work Statement.docx

DOCX document 27 KB Posted

Attached to
Chemical Resistant Epoxy Repair/Recoat of Floors and Walls
Solicitation number
W91ZLK-24-R-0020
Issued by

About this file

This document is a Performance Work Statement (PWS) for a federal contract opportunity to repair and recoat the floors and walls with chemical resistant epoxy at the Chemical Transfer Facility (CTF) and Sample Receipt Facility (SRF) at Aberdeen Proving Ground, MD.

The objective is to repair and recoat the floors in the CTF and SRF laboratories and storage rooms to ensure containment of hazardous or aggressive chemicals in the event of a leak. The contract is a Firm Fixed-Price with a base requirement for 1,000 sq ft in the SRF and 31 options for additional rooms in the CTF and SRF totaling over 10,000 sq ft. The period of performance is 3 months for the base and 3 months for each option. Offerors must demonstrate 5 years' experience repairing and recoating floors with chemical resistant epoxy. The contract will be awarded as a Small Business Set-Aside using Lowest Price Technically Acceptable source selection. A site visit is scheduled for June 27, 2024. Proposals are due by a date to be specified in the full solicitation.

View the file

Other files

File Type Posted
B01 Draft Combined SS.docx DOCX document
Attachment 3 - Quality Assurance Surveillance Plan.docx DOCX document
Attachment 1 - Provisions and Clauses.docx DOCX document
Attachment 4 - Price List.xlsx XLSX spreadsheet
Combined SS.DOCX DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SYNOPSIS/SOLICITATION

W91ZLK-24-R-0020

Attachment 2 – Performance Work Statement

PERFORMANCE WORK STATEMENT

Repair and Recoat Floors and Walls with Chemical Resistant Epoxy at The Chemical Transfer Facility (Bldg. E3832) and Sample Receipt Facility (Bldg. E3401), Aberdeen Proving Ground Md 21010

1. INTRODUCTION: The U.S. Army Combat Capabilities Development Command – Chemical Biological Center (DEVCOM-CBC) Chemical Transfer Facility (CTF) is a repository for research and development stock of toxic chemical agents. The facility includes a critical system of storage tanks and piping. The Sample Receipt Facility (SRF) is designed for the receipt and handling of hazardous materials and performance of hazardous operations related to Chemical and Biological threats. Surfaces in portions of the CTF and SRF are coated with epoxy that is resistant to hazardous and aggressive chemicals.

1.1 BACKGROUND: The U.S. Army Combat Capabilities Development Command – Chemical Biological Center (DEVCOM-CBC) CTF and SRF require the repair and recoat of floors with chemical resistant epoxy portions where the current coating is failing due to being greater than 15 years old.

1.2 OBJECTIVE: The objective of this contract is to repair and recoat the floor of the CTF and SRF laboratories and storage rooms to ensure containment of any hazardous or aggressive chemicals, should there ever be a leak in the system.

2.0 GENERAL: The Government will award a Firm Fixed-Price contract for repair and recoating of the floor of the CTF and SRF laboratories and storage rooms.

2.1. Period of Performance - The Contractor shall provide services in the “Base” table below within three (3) months from the date of award. Should the option be exercised, the Contractor shall provide services in the “Option” table below within three (3) months from the date of the option being exercised. The Government will be required to exercise the option(s) within twelve (12) months from the date of award.

2.2. Place of Performance – The CTF and SRF are on the Edgewood Area of Aberdeen Proving Ground. The Contractor shall be required to get a pass upon entering APG at the Visitor Center located at either Aberdeen North or Aberdeen South (Edgewood). Visitor Center information is available at www.home.army.mil/apg/index.php/about/visitor-information.

2.3. Business hours are 7:00AM – 5:00PM EST, Monday through Friday, excluding federal Holidays. Contractor shall not be required to perform services on the following Holidays:

· New Year's Day (January 1).

· Birthday of Martin Luther King, Jr. (Third Monday in January).

· Washington's Birthday (Third Monday in February).

· Memorial Day (Last Monday in May).

· Juneteenth National Independence Day (June 19).

· Independence Day (July 4).

· Labor Day (First Monday in September).

· Columbus Day (Second Monday in October).

· Veterans Day (November 11).

· Thanksgiving Day (Fourth Thursday in November).

· Christmas Day (December 25).

3.0. TECHNICAL REQUIREMENTS: The Contractor, as an independent Contractor and not as an agent of the Government, shall provide sufficient personnel possessing the skills, knowledge, training, and experience to perform the required tasks. All training, education and certification will be accomplished outside of this contract.

3.1. The Contractor shall provide proof of a minimum of five (5) years’ experience repairing and recoating floors and walls with chemical resistant epoxy.

4.0. PERFORMANCE REQUIREMENTS: The U.S. Army Combat Capabilities Development Command, Chemical Biological Center (DEVCOM-CBC) requires the floor and walls of the CTF and SRF floors in select laboratories and storage rooms to be stripped of old epoxy surface and recoated with an epoxy that is resistant to hazardous and aggressive chemicals including organic solvents, strong acids (such as hydrochloric and sulfuric), strong bases (such as 20% sodium hydroxide solution), and oxidizing/bleach (such as 10% Sodium Hypochlorite solution). For the Base Requirement and Options, epoxy shall be applied in two coats. The base coat shall be 10-12 mil thickness and the topcoat shall be 14-18 mil thickness to ensure the floor surface is as smooth as possible. The coating shall be sufficiently resilient that it will be undamaged by the traffic of heavy rolling carts or forklifts up to 10,000lbs. The coating shall be sufficiently adhered to the concrete substrate that if a scratch, crack, or chip occurs, the coating will not further flake off in sheets or cracks spread. Coatings without solvents or VOCs are preferred. In 2022, many rooms in the CTF were recoated using Belzona 4911 Magma TX Conditioner, Belzona 4131 Magma Screen, Belzona 5811 Immersion Grade (Gray) and top coated with Belzona 4311 Magma CR1. Under this contract, the Contractor shall use an epoxy coating that meets or exceeds the capabilities of the materials used in 2022 as listed above.

The Contractor shall utilize a system to capture the dust generated during stripping and shall dispose of project waste and debris. The Chemical Transfer Facility is located in Building E3832 on the Edgewood Area of Aberdeen Proving Ground. The Sample Receipt Facility is located in Building E3401 on the Edgewood Area of Aberdeen Proving Ground. Subject to the availability of Government escorts, the vendor may be able to work in more than one room at a time. In order to not disrupt operations in the CTF and SRF, the vendor cannot, however, strip and prepare all rooms at once prior to applying epoxy. If the Government awards multiple options at the same time, building tenants will work with Contractor to optimize workflow while minimizing disruption to ongoing building operations.

BASE REQUIREMENT

Area
Description
Additional Details
SRF Room 149
Approx. 1,000 sq. ft.

OPTIONS

Area
Description
Additional Details
SRF Foyer to Room 149
Approx. 96 sq. ft.
Incl. approx. 15 sq. ft. of Safety Yellow
SRF Foyer to Room 167
Approx. 23 sq. ft.
SRF Room 167
Approx. 789 sq. ft.
Incl. approx. 70 sq. ft. of Safety Yellow
SRF Room 157
Approx. 86 sq. ft.
Incl. approx. 35 sq. ft. of Safety Yellow
SRF Room 166
Approx. 472 sq. ft.
SRF Room 137
Approx. 1743 sq. ft.
Incl. approx. 208 sq. ft. of Safety Yellow
SRF Hallway
Approx. 2069 sq. ft.
SRF Room 165
Approx. 515 sq. ft.
SRF Bathroom Hallway
Approx. 358 sq. ft.
Incl. approx. 600 CI of rebuild/repair

Incl. approx. 288 CI of expansion joint

SRF Bathroom
Approx. 267 sq. ft.
Incl. approx. 864 CI of expansion joint
CTF Room 1
Approx. 200 sq. ft.
These rooms may have approximately 10% of flooring in Safety Yellow and may have existing berms, spill containment troughs, and spill containment side-coves.
CTF Room 4
Approx. 200 sq. ft.
CTF Room 5
Approx. 200 sq. ft.
CTF Room 6
Approx. 200 sq. ft.
CTF Room 7
Approx. 200 sq. ft.
CTF Room 8
Approx. 200 sq. ft.
CTF Room 12
Approx. 200 sq. ft.
CTF Room 13
Approx. 200 sq. ft.
CTF Room 22
Approx. 235 sq. ft.
CTF Room 23
Approx. 200 sq. ft.
CTF Room 24
Approx. 90 sq. ft.
CTF Room 27
Approx. 400 sq. ft.
CTF Room 30
Approx. 300 sq. ft.
CTF Room 32
Approx. 300 sq. ft.
CTF Walkin- Freezers
Approx. 251 sq. ft.
CTF Locker Room #20
Approx. 84 sq. ft.
Incl. approx. 160 CI of expansion joint
CTF Locker Room #21
Approx. 200 sq. ft.
Incl. approx. 400 CI of expansion joint
CTF Bathroom #17
Approx. 80 sq. ft.
Incl. approx. 200 CI of expansion joint
CTF Mechanical Room
Approx. 1447 sq. ft.
Incl. approx. 3000 CI of expansion joint
CTF Operational Hallway
Approx. 2175 sq. ft.
CTF Office Hallway
Approx. 197 sq. ft.
Incl. approx. 300 CI of expansion joint

4.1. The Contractor shall remove and dispose of all refuse/waste generated as a result of this project.

4.2. The Contractor shall warranty their labor to be free from material defect for one (1) year or 12-months following completion of the contract.

4.3. The Government will provide access to electricity and restrooms. The Government certifies that the project area contains no lead paint or asbestos.

5.0. SECURITY: All personnel will have a valid Government-issued ID and may be subject to search of belongings upon entry and exit of facility. All personnel will sign in at the front office and receive a Safety and Security brief. All personnel are to remain in approved areas with a facility-assigned escort.

5.1. Access and general protection/security policy and procedures. This standard language is for Contractor employees with an area of performance within an Army controlled installation, facility, or area. Contractor and all associated subcontractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.

5.2. For contractors that do not require a CAC, but require access to a DoD facility or installation. Contractor and all associated sub-Contractor employees shall comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC- Ill) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/ facility access and local security policies and procedures (provided by Government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

6.0 ENVIRONMENTAL

6.1 The Contractors shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulations and policies. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR) as well as the Director of Engineering & Public Works.

6.2 The Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and Director of Engineering & Public Works.

7.0 SAFETY AND HEALTH

7.1 The Contractor personnel or any representative of the Contractor shall abide by all federal and Department of the Army safety regulations while working on the Aberdeen Proving Grounds. The Contractor shall have a written Confined Space Entry Program. The Contractors confined space entry program will be available for review ten (10) days prior commencing work upon award of contract.

7.2 Should Contractor operational or confined space procedures indicate the requirement for respiratory protection the Contractor shall have and meet all requirements in a respiratory protection program IAW the current versions of 29 CFR 1910.134.

7.3 The Contractor personnel shall comply with all on-site safety requirements which may include but not limited to sign in/out, daily building safety briefs and the use of PPE.

7.4 The Contractor shall notify the Government Contracting Officer’s Representative (COR) of any accident or incident mishap related to, or incurring during the performance of, this contract immediately.

8.0. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP): (See Attached)

File details come from the government source that posted it. Updated .