CLIN SUMMARY SHEET
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| RFQ No. N4008426Q7004 |
| Hangar Doors, Automatic Sliding Doors, and Automatic Sliding Gate Maintenance for NAFM, Japan |
| Company Name: |
| Unique Entity ID Number: |
| CAGE/NCAGE Code: |
ITEM NO. SUPPLIES/SERVICES Qty UNIT AMOUNT
| 0001 | RECURRING WORK (Base Period) | | | |
| Price to perform Recurring work, for the 12-month Base Period, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0002 | NON-RECURRING (Base Period) | | | |
| Price to perform Non-Recurring work, for the 12-month Base Period, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0003 | RECURRING WORK (Option Period One) | | | |
| Price to perform Recurring work, for the 12-month Option Period One, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0004 | NON-RECURRING (Option Period One) | | | |
| Price to perform Non-Recurring work, for the 12-month Option Period One, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0005 | RECURRING WORK (Option Period Two) | | | |
| Price to perform Recurring work, for the 12-month Option Period Two, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0006 | NON-RECURRING WORK (Option Period Two) | | | |
| Price to perform Non-Recurring work, for the 12-month Option Period Two, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0007 | RECURRING (Option Period Three) | | | |
| Price to perform Recurring work, for the 12-month Option Period Three, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0008 | NON-RECURRING WORK (Option Period Three) | | | |
| Price to perform Non-Recurring work, for the 12-month Option Period Three, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0009 | RECURRING (Option Period Four) | | | |
| Price to perform Recurring work, for the 12-month Option Period Four, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
| 0010 | NON-RECURRING WORK (Option Period Four) | | | |
| Price to perform Non- Recurring work, for the 12-month Option Period Four, in accordance with all the terms of this contract. | 1 | YR | ¥ - |
TOTAL (CLINS 0001 THROUGH 0010) ¥ -
SCHEDULE OF WORK
ITEM NO. SUPPLIES/SERVICES AMOUNT
| 9000 | Exhibit Line Items (ELINS) Base Period | |
| See Attachment J-0200000-12, Exhibit Line Item Numbers, Recurring and Non-Recurring Work | ¥ - |
| 9001 | Exhibit Line Items (ELINS) Option Period One | |
| See Attachment J-0200000-12, Exhibit Line Item Numbers, Recurring and Non-Recurring Work | ¥ - |
| 9002 | Exhibit Line Items (ELINS) Option Period Two | |
| See Attachment J-0200000-12, Exhibit Line Item Numbers, Recurring and Non-Recurring Work | ¥ - |
| 9003 | Exhibit Line Items (ELINS) Option Period Three | |
| See Attachment J-0200000-12, Exhibit Line Item Numbers,Non-Recurring Work | ¥ - |
| 9004 | Exhibit Line Items (ELINS) Option Period Four | |
| See Attachment J-0200000-12, Exhibit Line Item Numbers, Recurring and Non-Recurring Work | ¥ - |
TOTAL PRICE FOR CONTRACT LINE ITEMS 9000 THROUGH 9004 ¥ -
ELINS-Base Period Recurring
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0001 - Recurring Work - Base Period | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | |
| ELIN/Sub-ELINs A001AA through A001AF | | | | | | | | |
| ELIN/ | | | | | | | | |
| Sub-ELIN | | Annex/Sub-annex | | | | | | | |
| Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total Price | | | |
| | | 1502000 | | Facility Investment | | | | |
| | | | | Emergency, Urgent, and Routine (E/U/R) Work | | | | |
| A001 | AA | 1502000 | 3.1.1 | Emergency | 1 | EA | ¥ - | ¥ - |
| A001 | AB | 1502000 | 3.1.2 | Urgent | 2 | EA | ¥ - | ¥ - |
| A001 | AC | 1502000 | 3.1.3 | Routine | 2 | EA | ¥ - | ¥ - |
| | | | | Preventive Maintenance | | | | |
| A001 | AD | 1502000 | 3.2.1 | Hangar Doors | 12 | MO | ¥ - | ¥ - |
| A001 | AE | 1502000 | 3.2.2 | Automatic Sliding Doors | 12 | MO | ¥ - | ¥ - |
| A001 | AF | 1502000 | 3.2.3 | Automatic Sliding Gate | 12 | MO | ¥ - | ¥ - |
| Total Recurring Work: | | | | | | | | ¥ - |
ELINS-Base Period Non-Recurring
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0002 - Non-Recurring Work - Base Period | | | | | | |
| Provide Prices for Non-Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELIN/Sub-ELINs A700 through A701 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Total Price |
| A700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO. | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.1 Labor Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
Task order completion times will be specified on each task order.
| 50 | LH | ¥ - | ¥ - 0 |
| A701 | Direct Material and Construction Equipment - MUST BE NEGOTIATED BY KO. | The Contractor shall provide all materials and construction equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.2 Direct Material and Construction Equipment Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Direct Material Costs and Construction Equipment.
| Task order completion times will be specified on each task order. | 2 | LS | ¥ - | ¥ - 0 | |
| TOTAL NON-RECURRING WORK - BASE PERIOD | | | | ¥ - 0 |
ELINS-1st Option Period Recurri
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0003 - Recurring Work - 1st Option Period | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | |
| ELIN/Sub-ELINs B001 AA through B001AF | | | | | | | | |
| ELIN/ | | | | | | | | |
| Sub-ELIN | | Annex/Sub-annex | | | | | | | |
| Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total Price | | | |
| | | 1502000 | | Facility Investment | | | | |
| | | | | Emergency, Urgent, and Routine (E/U/R) Work | | | | |
| B001 | AA | 1502000 | 3.1.1 | Emergency | 1 | EA | ¥ - | ¥ - |
| B001 | AB | 1502000 | 3.1.2 | Urgent | 2 | EA | ¥ - | ¥ - |
| B001 | AC | 1502000 | 3.1.3 | Routine | 2 | EA | ¥ - | ¥ - |
| | | | | Preventive Maintenance | | | | |
| B001 | AD | 1502000 | 3.2.1 | Hangar Doors | 12 | MO | ¥ - | ¥ - |
| B001 | AE | 1502000 | 3.2.2 | Automatic Sliding Doors | 12 | MO | ¥ - | ¥ - |
| B001 | AF | 1502000 | 3.2.3 | Automatic Sliding Gate | 12 | MO | ¥ - | ¥ - |
| Total Recurring Work: | | | | | | | | ¥ - |
ELINS-1st Option Period Non-Rec
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0004 - Non-Recurring Work - 1st Option Period | | | | | | |
| Provide Prices for Non-Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELIN/Sub-ELINs B700 through B701 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Total Price |
| B700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO. | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.1 Labor Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
Task order completion times will be specified on each task order.
| 50 | LH | ¥ - | ¥ - 0 |
| B701 | Direct Material and Construction Equipment - MUST BE NEGOTIATED BY KO. | The Contractor shall provide all materials and construction equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.2 Direct Material and Construction Equipment Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Direct Material Costs and Construction Equipment.
| Task order completion times will be specified on each task order. | 2 | LS | ¥ - | ¥ - 0 | |
| TOTAL NON-RECURRING WORK - BASE PERIOD | | | | ¥ - 0 |
ELINS-2nd Option Period Recurri
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0005 - Recurring Work - 2nd Option Period | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | |
| ELIN/Sub-ELINs C001AA through C001AF | | | | | | | | |
| ELIN/ | | | | | | | | |
| Sub-ELIN | | Annex/Sub-annex | | | | | | | |
| Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total Price | | | |
| | | 1502000 | | Facility Investment | | | | |
| | | | | Emergency, Urgent, and Routine (E/U/R) Work | | | | |
| C001 | AA | 1502000 | 3.1.1 | Emergency | 1 | EA | ¥ - | ¥ - |
| C001 | AB | 1502000 | 3.1.2 | Urgent | 2 | EA | ¥ - | ¥ - |
| C001 | AC | 1502000 | 3.1.3 | Routine | 2 | EA | ¥ - | ¥ - |
| | | | | Preventive Maintenance | | | | |
| C001 | AD | 1502000 | 3.2.1 | Hangar Doors | 12 | MO | ¥ - | ¥ - |
| C001 | AE | 1502000 | 3.2.2 | Automatic Sliding Doors | 12 | MO | ¥ - | ¥ - |
| C001 | AF | 1502000 | 3.2.3 | Automatic Sliding Gate | 12 | MO | ¥ - | ¥ - |
| Total Recurring Work: | | | | | | | | ¥ - |
ELINS-2nd Option Period Non-Rec
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0006 - Non-Recurring Work - 2nd Option Period | | | | | | |
| Provide Prices for Non-Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELIN/Sub-ELINs C700 through C701 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Total Price |
| C700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO. | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.1 Labor Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
Task order completion times will be specified on each task order.
| 50 | LH | ¥ - | ¥ - 0 |
| C701 | Direct Material and Construction Equipment - MUST BE NEGOTIATED BY KO. | The Contractor shall provide all materials and construction equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.2 Direct Material and Construction Equipment Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Direct Material Costs and Construction Equipment.
| Task order completion times will be specified on each task order. | 2 | LS | ¥ - | ¥ - 0 | |
| TOTAL NON-RECURRING WORK - BASE PERIOD | | | | ¥ - 0 |
ELINS-3rd Option Period Recurri
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0007 - Recurring Work - 3rd Option Period | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | |
| ELIN/Sub-ELINs D001AA through D001AF | | | | | | | | |
| ELIN/ | | | | | | | | |
| Sub-ELIN | | Annex/Sub-annex | | | | | | | |
| Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total Price | | | |
| | | 1502000 | | Facility Investment | | | | |
| | | | | Emergency, Urgent, and Routine (E/U/R) Work | | | | |
| D001 | AA | 1502000 | 3.1.1 | Emergency | 1 | EA | ¥ - | ¥ - |
| D001 | AB | 1502000 | 3.1.2 | Urgent | 2 | EA | ¥ - | ¥ - |
| D001 | AC | 1502000 | 3.1.3 | Routine | 2 | EA | ¥ - | ¥ - |
| | | | | Preventive Maintenance | | | | |
| D001 | AD | 1502000 | 3.2.1 | Hangar Doors | 12 | MO | ¥ - | ¥ - |
| D001 | AE | 1502000 | 3.2.2 | Automatic Sliding Doors | 12 | MO | ¥ - | ¥ - |
| D001 | AF | 1502000 | 3.2.3 | Automatic Sliding Gate | 12 | MO | ¥ - | ¥ - |
| Total Recurring Work: | | | | | | | | ¥ - |
ELINs-3rd Option Period Non-Rec
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0008 - Non-Recurring Work - 3rd Option Period | | | | | | |
| Provide Prices for Non-Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELIN/Sub-ELINs C700 through C701 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Total Price |
| D700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO. | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.1 Labor Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
Task order completion times will be specified on each task order.
| 50 | LH | ¥ - | ¥ - 0 |
| D701 | Direct Material and Construction Equipment - MUST BE NEGOTIATED BY KO. | The Contractor shall provide all materials and construction equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.2 Direct Material and Construction Equipment Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Direct Material Costs and Construction Equipment.
| Task order completion times will be specified on each task order. | 2 | LS | ¥ - | ¥ - 0 | |
| TOTAL NON-RECURRING WORK - BASE PERIOD | | | | ¥ - 0 |
ELINS-4th Option Period Recurri
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0009 - Recurring Work - 4th Option Period | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | |
| ELIN/Sub-ELINs E001AA through E001AF | | | | | | | | |
| ELIN/ | | | | | | | | |
| Sub-ELIN | | Annex/Sub-annex | | | | | | | |
| Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total Price | | | |
| | | 1502000 | | Facility Investment | | | | |
| | | | | Emergency, Urgent, and Routine (E/U/R) Work | | | | |
| E001 | AA | 1502000 | 3.1.1 | Emergency | 1 | EA | ¥ - | ¥ - |
| E001 | AB | 1502000 | 3.1.2 | Urgent | 2 | EA | ¥ - | ¥ - |
| E001 | AC | 1502000 | 3.1.3 | Routine | 2 | EA | ¥ - | ¥ - |
| | | | | Preventive Maintenance | | | | |
| E001 | AD | 1502000 | 3.2.1 | Hangar Doors | 12 | MO | ¥ - | ¥ - |
| E001 | AE | 1502000 | 3.2.2 | Automatic Sliding Doors | 12 | MO | ¥ - | ¥ - |
| E001 | AF | 1502000 | 3.2.3 | Automatic Sliding Gate | 12 | MO | ¥ - | ¥ - |
| Total Recurring Work: | | | | | | | | ¥ - |
ELINs-4th Option Period Non-Rec
| ATTACHMENT (2) OFFEROR PRICING SCHEDULE |
| Exhibit Line Item Numbers (ELINs) |
| Solicitation/Contract No.: N4008426Q7004 |
| Line Item 0010 - Non-Recurring Work - 4th Option Period | | | | | | |
| Provide Prices for Non-Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELIN/Sub-ELINs E700 through E701 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Total Price |
| E700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO. | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.1 Labor Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
Task order completion times will be specified on each task order.
| 50 | LH | ¥ - | ¥ - 0 |
| E701 | Direct Material and Construction Equipment - MUST BE NEGOTIATED BY KO. | The Contractor shall provide all materials and construction equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Items 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work and 2.15.2.1.2 Direct Material and Construction Equipment Requirements.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Direct Material Costs and Construction Equipment.
| Task order completion times will be specified on each task order. | 2 | LS | ¥ - | ¥ - 0 | |
| TOTAL NON-RECURRING WORK - BASE PERIOD | | | | ¥ - 0 |