Attachment 2 - IMB-20001953 DRAWING PACKAGE.pdf
PDF 2 MB Posted
- Attached to
- Demolition/Installation of the Tower Platform, (IMB) VHF Omnidirectional Range (VOR), Kimberly, Oregon
- Solicitation number
- 697DCK-23-R-00225
About this file
This package includes drawings and specifications for the Demolition/Installation of the Tower Platform at the Kimberly, Oregon VHF Omnidirectional Range (VOR). The project involves demolishing existing tower handrails, ladders, and attachments; selectively demolishing insufficient deck; excavating for a new foundation; installing a new slab-on-grade, exterior staircase, safety handrail; and coating exposed wood surfaces. The contractor must furnish all labor, equipment, and materials, including any additional items required to complete the project. The Federal Aviation Administration Southwestern Region is the agency soliciting this opportunity under solicitation number 697DCK-23-R-00225.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
$F
IL
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
SHEET INDEX
G001 COVER SHEET
G002 SITE PLAN AND GENERAL NOTES
D001 TOWER DEMOLITION PLAN
A001 SITE RESTORATION PLAN
S001 STAIRCASE ELEVATION PLAN
S002 STAIRWELL PLAN VIEW AND FOUNDATION
S003 STRUCTURAL DETAILS
E001 EQUIPMENT ROOM RESTORATION PLAN
E002 CABLE RESTORATION ROUTING AND GROUNDING
E003 CABLE GROUNDING DETAILS
E004 GENERAL GROUNDING DETAILS
IMB VOR
TOWER SAFETY PROJECT
KIMBERLY OREGON
APRIL 2023
OWNER: U.S. GOVERNMENT - BUREAU OF LAND MANAGEMENT - PRINEVILLE OREGON
LOCATION: SECTION 3, T.11 S., R.25 E., W.M., WHEELER COUNTY, OREGON
LONGITUDE: 119° 42' 37"
LATITUDE: 044° 38' 53"
ELEVATION: 5217 M.S.L.
POWER: COLUMBIA POWER CO-OOP - MOUNUMENT, OREGON
TELEPHONE: BLUE MOUNTAIN TELEPHONE INC. - SPRAY, OREGON
VICINITY MAP
NOT TO SCALE
NOTES:
AutoCAD SHX Text A
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text T
AutoCAD SHX Text R
AutoCAD SHX Text A
AutoCAD SHX Text N
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text A
AutoCAD SHX Text T
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text N
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text A
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text A
AutoCAD SHX Text T
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text T
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text A
AutoCAD SHX Text T
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text N
AutoCAD SHX Text L
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text F
AutoCAD SHX Text T
AutoCAD SHX Text R
AutoCAD SHX Text A
AutoCAD SHX Text T
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text N
AutoCAD SHX Text S
AutoCAD SHX Text I
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text M
AutoCAD SHX Text D
AutoCAD SHX Text A
AutoCAD SHX Text T.10 S
AutoCAD SHX Text T.11 S.
AutoCAD SHX Text T.12 S.
AutoCAD SHX Text R.25 E.
AutoCAD SHX Text R.26 E.
AutoCAD SHX Text
RANCH
AutoCAD SHX Text
STATE PARK
AutoCAD SHX Text
STATE PARK
AutoCAD SHX Text
STATE PARK
AutoCAD SHX Text U.S. 26
AutoCAD SHX Text
TO REDMOND
AutoCAD SHX Text U.S. 26
AutoCAD SHX Text
TO JOHN DAY
AutoCAD SHX Text
FAA ROAD 7.9 MI.
AutoCAD SHX Text
7.8 MI.
AutoCAD SHX Text
11.8 MI.
AutoCAD SHX Text
GRANT COUNTY
AutoCAD SHX Text
DAYVILLE
AutoCAD SHX Text
STATE RD.19
AutoCAD SHX Text
TO KIMBERLY
AutoCAD SHX Text
HQ
AutoCAD SHX Text
WHEELER COUNTY
AutoCAD SHX Text
VOR/DME PROJECT SITE
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-G001
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
VC
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
COVER SHEET
AutoCAD SHX Text
GENERAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
AutoCAD SHX Text
CONSTRUCTION
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A30' 0 30' 60'
SCALE: 1" = 30'
A001
SCALE: 1" = 30'-0"
SITE PLAN
AutoCAD SHX Text
TERMINAL POLE
AutoCAD SHX Text
TELCO LINE
AutoCAD SHX Text
CONTROL CABLE
AutoCAD SHX Text
35' F.A.S. ANTENNA
AutoCAD SHX Text
MAST 2' FROM BUILDING
AutoCAD SHX Text
GRADED OUT TO
AutoCAD SHX Text
BLDG. SITE ELEVATION
AutoCAD SHX Text
ROCK BACKSLOPE
AutoCAD SHX Text 1 1/2 : 1
AutoCAD SHX Text E/G
AutoCAD SHX Text
RM
AutoCAD SHX Text
VOR BLDG.
AutoCAD SHX Text
SOLID ROCK
AutoCAD SHX Text
BACKSLOPE 1 1/2 : 1
AutoCAD SHX Text R O C K L E D G E A R E A
AutoCAD SHX Text
1000 GAL. FUEL
AutoCAD SHX Text
TANK ABOVE GND.
AutoCAD SHX Text
(DIESEL)
AutoCAD SHX Text
VEHICLE
AutoCAD SHX Text
GUARDS
AutoCAD SHX Text
4 : 1 SLOPE
AutoCAD SHX Text A
AutoCAD SHX Text Z
AutoCAD SHX Text I
AutoCAD SHX Text M
AutoCAD SHX Text U
AutoCAD SHX Text T
AutoCAD SHX Text H
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text O
AutoCAD SHX Text U
AutoCAD SHX Text N
AutoCAD SHX Text D
AutoCAD SHX Text P
AutoCAD SHX Text O
AutoCAD SHX Text S
AutoCAD SHX Text I
AutoCAD SHX Text T
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text
FENCE
AutoCAD SHX Text
FENCE
AutoCAD SHX Text
EL. 5217'
AutoCAD SHX Text
14' GATE
AutoCAD SHX Text
12' GRAVELED ROAD
AutoCAD SHX Text
TOE OF SLOPE LINE
AutoCAD SHX Text
GRADED OUT TO
AutoCAD SHX Text
BLDG. SITE ELEV.
AutoCAD SHX Text
TO HWY 19
AutoCAD SHX Text
TRUE NORTH
AutoCAD SHX Text
MAG. NORTH
AutoCAD SHX Text MAG. DECL. 20%%d-24" E.
AutoCAD SHX Text
BEARINGS ARE TRUE
AutoCAD SHX Text N
AutoCAD SHX Text 14'-0"
AutoCAD SHX Text
CONCRETE
AutoCAD SHX Text
MARKER
AutoCAD SHX Text
NORTH
AutoCAD SHX Text
CONCRETE
AutoCAD SHX Text
CONCRETE
AutoCAD SHX Text
RCL ANTENNA PLATFORM
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-G002
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
VC
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
SITE PLAN AND GENERAL NOTES
AutoCAD SHX Text
GENERAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
GENERAL LEGEND:
X
X
CONSTRUCTION KEY
NOTE
DEMOLITION KEY
NOTE
DRAWING TITLE
SECTION CUT
DETAIL REFERENCE
SECTION TITLE
DETAIL TITLE
SCALE OR OTHER INFORMATION
DRAWING TITLE
X X001
SECTION LETTER
SECTION LETTER
SHEET NUMBER WHERE
SECTION IS REFERENCED
DEMOLITION CALL OUT
CONSTRUCTION CALL
OUT
SHEET NUMBER SECTION IS
REFERENCED FROM
DETAIL NUMBER
X001
DETAIL LETTER
SHEET NUMBER WHERE
DETAIL IS REFERENCED
1. THE CONTRACTOR CONSTRUCTION SAFETY MANUAL SHALL COMPLY WITH OSHA 29 CFR 1910 AND 29 CFR 1926.
2. LOCATIONS AND ELEVATIONS OF EXISTING FEATURES TO BE VERIFIED BY FIELD MEASUREMENTS PRIOR TO
CONSTRUCTION OF NEW WORK.
3. ALL DIMENSIONS ARE TO BE VERIFIED IN THE FIELD. ANY DISCREPANCIES FOUND BETWEEN THE DRAWINGS AND SPECIFICATIONS AND SITE CONDITION OR ANY INCONSISTENCIES OR AMBIGUITIES IN THE DRAWINGS OR SPECIFICATIONS SHALL BE IMMEDIATELY REPORTED TO THE RESIDENT ENGINEER (RE) IN WRITING, WHO SHALL CORRECT SUCH INCONSISTENCIES OR AMBIGUITIES IN WRITING. THE CONTRACTOR SHALL NOT
PERFORM ANY WORK BEFORE VERIFICATION AND AFTER DISCOVERY OF SUCH DISCREPANCIES,
INCONSISTENCIES, OR AMBIGUITIES WITHOUT WRITTEN RE AUTHORIZATION. ANY WORK PERFORMED BY THE CONTRACTOR AFTER DISCOVERY OF SUCH DISCREPANCIES WITHOUT PRIOR WRITTEN AUTHORIZATION BY
RE WILL BE CONSIDERED TO BE DONE AT THE CONTRACTOR'S RISK.
4. FINISHED GRADE SHALL BE SLOPED AT A UNIFORM SLOPE BETWEEN SPOT ELEVATIONS.
5. ALL FILL MATERIAL SHALL MEET REQUIREMENTS AS OUTLINED IN THE PROJECT SPECIFICATIONS.
6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ENSURING THAT ALL SLOPES ARE BUILT IN ACCORDANCE WITH THESE PLANS. IF THERE IS ANY QUESTION REGARDING THESE PLANS, THE CONTRACTOR SHALL
REQUEST AN INTERPRETATION BEFORE DOING ANY WORK. THE CONTRACTOR SHALL ALSO TAKE
NECESSARY STEPS TO PROTECT THE PROJECT AND ADJACENT PROPERTY FROM ANY EROSION AND SILTATION THAT RESULT FROM THEIR OPERATIONS BY APPROPRIATE MEANS, (SAND BAGS, TEMPORARY DESILTING BASINS, DIKES, ETC.) UNTIL SUCH TIME THAT THE PROJECT IS COMPLETED AND ACCEPTED BY
FAA.
7. PRIOR TO ANY EXCAVATIONS UNDER THIS CONTRACT, THE CONTRACTOR SHALL PERFORM GPRS UTILITY LOCATE TO IDENTIFY ALL UTILITIES AT THE SITE. SUBCONTRACTOR SHALL POTHOLE AND HAND EXCAVATE
NEAR KNOWN UTILITY LINES TO PREVENT EXCAVATION DAMAGE TO UNDERGROUND UTILITIES.
8. THE CONTRACTOR SHALL TAKE PRECAUTIONARY MEASURES TO PROTECT WITHIN THE SITE, ALL UTILITY LINES, EXISTING PERMANENT STRUCTURES AND ANY OTHER EXISTING LINES THAT ARE NOT OF RECORD OR SHOWN ON PLANS. ANY UTILITIES OR STRUCTURES DAMAGED DURING THE COURSE OF CONSTRUCTION SHALL BE IMMEDIATELY REPAIRED AND/OR REPLACED BY THE SUBCONTRACTOR, UNLESS APPROVED OTHERWISE BY THE RE, TO A CONDITION EQUAL TO OR BETTER THAN THE EXISTING AND AS APPROVED BY
THE RE.
9. THE CONTRACTOR SHALL BE RESPONSIBLE FOR RESTORING ANY MONUMENTATION AND/OR BENCHMARKS THAT ARE DISTURBED OR DESTROYED BY CONSTRUCTION. SUCH POINTS SHALL BE REFERENCED AND REPLACED WITH APPROPRIATE MONUMENTATION BY A LICENSED SURVEYOR AT THE CONTRACTOR'S SOLE
EXPENSE.
10. THE CONTRACTOR SHALL SECURE ANY REQUIRED PERMITS FOR CONSTRUCTION PRIOR TO THE START OF
CONSTRUCTION.
11. THE CONTRACTOR IS HEREBY NOTIFIED THAT ESSENTIAL AND PERTINENT INFORMATION REGARDING THE CONSTRUCTION AND COMPLETION OF WORK FOR THIS PROJECT IS CONTAINED IN THE CONTRACT DOCUMENTS AND SPECIFICATIONS. IT IS THE CONTRACTOR'S RESPONSIBILITY TO READ AND REVIEW THIS INFORMATION TO THEIR OWN SATISFACTION PRIOR TO PERFORMING ANY WORK. ANY DEFICIENT, INCOMPLETE OR INCORRECT WORK SHALL BE REDONE TO MEET REQUIREMENTS AT THE CONTRACTOR'S
SOLE EXPENSE.
12. THE CONTRACTOR SHALL DESIGN, CONSTRUCT, AND MAINTAIN ALL SAFETY DEVICES, AND SHALL BE SOLELY RESPONSIBLE FOR CONFORMING TO ALL LOCAL, STATE, AND FEDERAL SAFETY AND HEALTH STANDARDS, LAWS AND REGULATIONS.
13. THE CONTRACTOR AGREES TO ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION OF THIS PROJECT, INCLUDING SAFETY OF ALL PERSONS AND PROPERTY. CONTRACTOR FURTHER AGREES THAT THIS REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS AND THAT THE CONTRACTOR SHALL DEFEND; INDEMNIFY AND HOLD THE FAA HARMLESS FROM ANY AND ALL LIABILITY, REAL OR ALLEGED IN CONNECTION WITH THE
PERFORMANCE OF WORK ON THIS PROJECT.
14. EXISTING VEHICULAR ACCESS TO SITE SHALL BE KEPT IN SERVICE DURING THE COURSE OF CONSTRUCTION.
THE CONTRACTOR SHALL PREPARE A PLAN SHOWING PROPOSED LOCATIONS OF STAGING, STORAGE OF MATERIALS, AND VEHICLES ON SITE TO BE SUBMITTED TO THE RESIDENT ENGINEER FOR REVIEW, COMMENT AND/OR APPROVAL PRIOR TO START OF CONSTRUCTION. DUE TO LIMITED SPACE ON SITE, CONTRACTOR SHALL COORDINATE WITH RE FOR ADDITIONAL AREAS REQUIRED FOR MATERIAL AND EQUIPMENT STORAGE.
VEHICLES SHALL NOT EXCEED SPEED LIMITS AS DICTATED BY OWNER.
15. THE NORMAL ACTIVITIES WITHIN THE FACILITY WILL CONTINUE DURING CONSTRUCTION. CONTRACTOR SHALL DEVISE A DETAILED WORK SCHEDULE AND CLOSELY COORDINATE WITH THE RE FOR ALL ACTIVITIES.
THE CONTRACTOR SHALL USE GREAT CARE AND CAUTION WHILE WORKING WITHIN THE EXISTING FACILITY
(SITE AND BUILDINGS) AS NOT TO DISRUPT THE FUNCTIONS OF THIS FAA FACILITY.
16. IT IS ABSOLUTELY MANDATORY THAT THE CONTRACTOR PROTECT ALL NEW AND EXISTING COMMUNICATION EQUIPMENT, ELECTRICAL AND MECHANICAL EQUIPMENT, BOTH INSIDE AND OUTSIDE THE BUILDING FROM
DAMAGE.
17. STAGING AND STORAGE OF CONSTRUCTION MATERIAL AND EQUIPMENT SHALL BE LIMITED TO THE
CONSTRUCTION STAGING AREA.CONTRACTOR'S PARKING AREA SHALL BE DETERMINED AT THE
PRE-CONSTRUCTION CONFERENCE. MATERIALS SHALL BE NEATLY STORED AND PROTECTED AT ALL TIMES.
UPON COMPLETION OF WORK THE CONTRACTOR SHALL RESTORE THIS AREA BACK TO ITS ORIGINAL
PRE-CONSTRUCTION CONDITION.
18. ALL CONSTRUCTION MATERIAL SHALL BE PREASSEMBLED TO AN OPTIMUM SIZE AND WEIGHT TO MINIMIZE ACTIVITIES WITHIN THE FACILITY. CONTRACTOR SHALL VERIFY ACCESS PATHWAYS WITH RE BEFORE START
OF CONSTRUCTION.
19. WELDING REQUIRES A HOT WORK PERMIT. WELDING AND HEAVY CONSTRUCTION SHALL BE DONE OUTSIDE IN TEMPORARY CONSTRUCTION AREAS AS DETERMINED BY THE RE AND TO BE CLEANED UP AT THE END OF THE DAY. CONTRACTOR SHALL PROVIDE THEIR OWN POWER FOR THESE OPERATIONS. NO WELDING OR HEAVY CONSTRUCTION IS PERMITTED INSIDE THE BUILDING AS IT MAY DAMAGE OR INTERFERE WITH
ELECTRONICS EQUIPMENT.
20. THE CONTRACTOR SHALL PROVIDE, OPERATE AND MAINTAIN THE CONSTRUCTION LIGHTING NECESSARY TO ILLUMINATE THE AREA ADEQUATELY FOR SAFE WORK. ALL LIGHTING SHALL BE SUBMITTED TO AND APPROVED BY FAA BEFORE USE. UPON COMPLETION OF CONSTRUCTION, REMOVE ALL CONSTRUCTION LIGHTING. ALL AREAS AND SURFACES DISTURBED SHALL BE REPAIRED OR REPLACED BY THE CONTRACTOR.
21. ENCLOSED DUMPSTERS FOR DISPOSAL OF CONSTRUCTION DEBRIS SHALL BE PROVIDED BY THE CONTRACTOR WITHIN AREA DESIGNATED BY RE AT THE PRE-CONSTRUCTION MEETING. THE AREA AROUND THE DUMPSTERS SHALL BE KEPT CLEAN AND FREE OF EXCESS DEBRIS AND DUST DURING CONSTRUCTION.
ALL DEBRIS SHALL BE REMOVED BY CONTRACTOR. ANY WASTE THAT CAN ATTRACT WILDLIFE SHALL BE REMOVED FROM THE SITE DAILY. FAA DUMPSTER SHALL NOT BE USED BY CONTRACTOR. CONSTRUCTION
DEBRIS MUST BE REMOVED DAILY.
22. CONTRACTOR SHALL PROVIDE TEMPORARY UTILITIES DURING CONSTRUCTION. VERIFY TEMPORARY
UTILITIES LOCATIONS AND USE AS PERMITTED BY RE.
23. THE CONTRACTOR SHALL PROVIDE SANITARY TOILET FACILITIES WITH WATER FOR THE WORKERS AND RE.
24. THE CONTRACTOR SHALL PROVIDE TEMPORARY POWER FOR ALL CONSTRUCTION ACTIVITIES.
CONSTRUCTION TOOLS SHALL BE POWERED FROM THE TEMPORARY POWER SOURCE ONLY. ALL POWER
TOOLS SHALL BE PRE-APPROVED BY THE RE.
25. THE CONTRACTOR SHALL ENSURE THAT ALL WALL PENETRATIONS, NEW AND EXISTING ARE WATER SEALED.
PROVIDE WATERTIGHT ASSEMBLY FOR OPENINGS REQUIRING NEW SEALANT APPLICATION. CONTRACTOR
SHALL INFORM THE RE PRIOR TO INSTALLATION OF WATERTIGHT ASSEMBLY.
26. SHUTDOWN AND CUTOVERS OF ENVIRONMENTAL AND ELECTRICAL SYSTEMS SHALL BE PERFORMED BY FAA PERSONNEL AND NOT BY CONTRACTOR. ALL PREPARATORY WORK FOR SHUTDOWN AND CUTOVER SHALL BE SCHEDULED AND COORDINATED WITH THE RE A MINIMUM OF 10 WORKING DAYS IN ADVANCE.
27. WHERE NEW WORK IS TO BE CONNECTED TO EXISTING WORK, EXERCISE CARE NOT TO DISTURB OR
DAMAGE EXISTING WORK.
28. THE CONTRACTOR SHALL PROVIDE 7-PIN REMOVABLE CORE CORMAX BEST LOCK PADLOCKS FOR EACH LOCKABLE DEVICE, EQUIPMENT, ETC. THIS INCLUDES EXTERNAL CABINETS, PANELS, DISCONNECT SWITCHES, TOWER HATCH DOORS, ANTI-CLIMB DEVICES, ETC. THE PADLOCKS SHALL BE SIZED APPROPRIATELY FOR THE PARTICULAR EQUIPMENT AND USE. ALL PADLOCKS SHALL BE DYE STAMPED IN ACCORDANCE WITH FAA REQUIREMENTS AND DISPLAY THE NUMBER PS1173X1175. THE LOCKS SHALL BE
EQUIPPED WITH CONSTRUCTION CORES AND A CONSTRUCTION CORE REMOVAL KEY.
29. USE SACRIFICIAL LAYERS OF PROPER MATERIAL AT THE POINT OF CONNECTIONS BETWEEN DISSIMILAR
METALS OUTSIDE OF EQUIPMENT ROOM WHERE IT APPLIES.
30. CONTRACTOR TO PROPERLY DISPOSE/REMOVE HAZARDOUS MATERIALS IN ACCORDANCE WITH
SPECIFICATION SECTION 02 82 00.
31. CONTRACTOR SHALL COORDINATE WITH RE FOR PROPER REMOVAL AND TURNOVER OF TOWER ANTENNAS
AND CABLES.
32. REPAIR DAMAGED GALVANIZATION PER SPECIFICATIONS SECTION 09 97 00, SPECIAL COATINGS.
33. ALL HOT-DIPPED GALVANIZED METALS SHALL BE PAINTED PER SPECIFICATIONS SECTION 09 97 00, SPECIAL
COATINGS.
1. ALL WORK INCLUDING BUT NOT LIMITED TO STRUCTURAL SHALL BE IN ACCORDANCE WITH THE LATEST REQUIREMENTS OF TIA STANDARD, TIA-222-H EFFECTIVE JANUARY 1, 2018. "STRUCTURAL STANDARDS FOR
ANTENNA SUPPORTING STRUCTURES..."
2. ALL TOWERS SHALL BE CLASSIFIED AS TYPE III - ESSENTIAL COMMUNICATION.
3. SEISMIC ANALYSIS PROCEDURE (METHOD 1). SITE CLASS D, IMPORTANCE FACTOR=1.5, Ss=0.522, S =0.159, SEISMIC DESIGN CATEGORY=D.
4. WIND EXPOSURE CATEGORY C.
4.1. MINIMUM BASIC WIND SPEED = 120 MPH (3 SEC GUST, SERVICE)
4.2. IMPORTANCE FACTOR WITHOUT ICE = 1.15.
5. ICE THICKNESS = 1/4 INCH.
6. PLATFORM LIVE LOAD REQUIREMENT UNIFORM: 100 LBS/ SQ. FT
7. PLATFORM SNOW LOAD REQUIREMENTS: 30 LBS/ SQ. FT.
1. ALL FRAMING LUMBER SHALL BE DOUGLAS FIR/LARCH #2 OR BETTER. STUDS AND PLATES MAY BE
CONSTRUCTION GRADE MATERIAL.
2. PRESERVATIVE-TREATED WOOD SHALL NOT BE USED ON PROJECT. WOOD MEMBERS SHALL BE COATED IN LOW-TO-NO VOC (<50G/L) WEATHERPROOFING TREATMENT EITHER POST INSTALL OR PRE-INSTALL WITH
TOUCH-UPS AFTER INSTALL.
3. ALL METAL HARDWARE AND CONNECTORS SHALL BE SIMPSON STRONG TIE OR EQUAL. USE NAILS PER SIMPSON CATALOG. CONSULT ENGINEER FOR NAIL ALTERNATIVES. USE STAINLESS STEEL WHERE FEASIBLE.
4. MINIMUM NAILING/SCREWS FOR CONNECTIONS NOT INDICATED IN THE PLANS SHALL BE IN ACCORDANCE
WITH TABLE 2304.10.1 OF THE CBC/IBC.
5. MACHINE BOLTS FOR WOOD MEMBERS ARE A307. PROVIDE STANDARD CUT WASHERS AT ALL BOLT HEADS
AND NUTS BEARING ON WOOD.
6. TIMBER SIZES ARE PRESCRIBED MINIMUMS. LARGER SIZES MAY BE SUBSTITUTED. DETAILED CONNECTORS
MAY REQUIRE MODIFICATIONS IF SUBSTITUTIONS ARE MADE.
7. HOLD-DOWN NUTS SHALL BE RE-TIGHTENED JUST PRIOR TO COMPLETION.
1. CONCRETE CONSTRUCTION SHALL CONFORM TO THE LATEST EDITION OF ACI 301 AND ACI 318. ALL CAST-IN-PLACE STRUCTURAL CONCRETE SHALL BE IN ACCORDANCE WITH ACI AND SHALL HAVE A MINIMUM
COMPRESSIVE STRENGTH OF F' C =4000 PSI AT 28 DAYS (NORMAL WEIGHT).
2. REINFORCING STEEL - ALL DETAILING, FABRICATION AND ERECTION OF REINFORCING BARS, UNLESS NOTED OTHERWISE, SHALL BE IN ACCORDANCE WITH THE MANUAL OF STANDARD PRACTICE FOR DETAILING
REINFORCED CONCRETE STRUCTURES (ACI315), LATEST EDITION.
3. ALL REINFORCEMENT SHALL BE NEW BILLET STEEL, DEFORMED BARS, CONFORMING TO ASTM A615, GRADE 60 WITH A MINIMUM YIELD STRENGTH OF FY = 60000 PSI. SPLICES IN REINFORCEMENT SHALL NOT BE
ALLOWED UNLESS OTHERWISE INDICATED.
4. CONCRETE COVER - CONCRETE CLEAR COVER FOR REINFORCING BARS SHALL BE AS FOLLOWS
4.1. CONCRETE CAST AGAINST GROUND - 3"
4.2. CONCRETE IN CONTACT WITH GROUND OR EXPOSED TO WEATHER - 3"
4.3. CONCRETE NOT PERMANENTLY EXPOSED TO GROUND OR WEATHER - 3"
5. EXPOSED EDGES OF CONCRETE SHALL BE CHAMFERED 1" X 1" MINIMUM.
6. TOP OF FOUNDATION EXPOSED TO WEATHER SHALL BE SLOPED FROM THE CENTER TO THE OUTSIDE EDGE
A MINIMUM OF 1/4" PER FOOT. PROVIDE A FLOATED FINISH.
7. CONCRETE SHALL BE PLACED AGAINST UNDISTURBED SOIL WHEN FOUNDATION IS BEARING ON SOIL.
8. CONCRETE SHALL BE PLACED IN A MANNER THAT WILL PREVENT SEGREGATION OF CONCRETE MATERIALS AND OTHER OCCURRENCES WHICH MAY DECREASE THE STRENGTH OR DURABILITY OF THE FOUNDATION.
9. LOOSE MATERIAL SHALL BE REMOVED FROM BOTTOM OF EXCAVATION PRIOR TO CONCRETE PLACEMENT.
SIDES OF EXCAVATION SHALL BE ROUGH AND FREE OF LOOSE CUTTINGS. IN THE EVENT THAT THE SIDES DO
NOT REMAIN VERTICAL THE CONTRACTOR FORM THE SIDES.
10. WELDING IS PROHIBITED ON REINFORCING STEEL AND EMBEDMENTS.
11. MAXIMUM AGGREGATE SIZE SHALL NOT EXCEED 3/4".
12. FLOAT FINISH TOP OF PAD FOOTINGS WHEN EXPOSED TO VIEW.
1. ESTABLISH BENCHMARKS ON SURROUNDING STRUCTURES AND PAVEMENT PRIOR TO ANY EXCAVATION AND
IDENTIFY AND PROTECT ANY EXISTING UNDERGROUND UTILITIES, LINES OR OBSTRUCTIONS.
2. COORDINATE, MAINTAIN AND PROVIDE A SAFE ENVIRONMENT DURING TRENCHING, EXCAVATION, AND COMPACTION IN ACCORDANCE WITH OSHA SAFETY MANUALS. IN TRENCHES WHERE DEPTH EXCEED 4 FEET, SUBCONTRACTOR SHALL SUBMIT A DETAILED PLAN TO THE RE FOR APPROVAL SHOWING DESIGN OF SOIL AND RETENTION SYSTEM PREPARED BY A PROFESSIONAL ENGINEER LICENSED IN THE STATE OF
CONSTRUCTION. ALL WORK SHALL BE IN ACCORDANCE WITH THE GEOTECHNICAL REPORT.
3. FOUNDATION FOR THE TOWER SHALL BE DESIGNED IN ACCORDANCE WITH THE RECOMMENDATION OF THE GEOTECHNICAL REPORT AND SIGNED AND SEALED BY A REGISTERED ENGINEER IN THE STATE OF
CONSTRUCTION.
4. THE BACKFILL SHALL BE PLACED IN 8" LAYERS AND COMPACTED TO 95% OF MAXIMUM DRY DENSITY AT OPTIMUM MOISTURE CONTENT IN ACCORDANCE WITH ASTM D698. ADDITIONALLY, STRUCTURAL BACKFILL
MUST HAVE A MINIMUM COMPACTED UNIT WEIGHT OF 100 POUNDS PER CUBIC FOOT.
5. EXISTING UTILITIES SHALL BE VERIFIED PRIOR TO THE CONSTRUCTION/EXCAVATION OF CONCRETE PADS, FOUNDATIONS AND DUCTBANKS.
1. DEMOLITION DETAILS ARE AVAILABLE ON DRAWING D001.
2. SHOULD FIELD CONDITIONS DIFFER FROM EXISTING CONDITIONS SHOWN ON SHEET IMB-20001953-D001 & D002, ALERT THE RESIDENT ENGINEER AND AWAIT DIRECTION BEFORE PROCEEDING WITH DEMOLITION
OPERATIONS.
3. THE SUBCONTRACTOR SHALL MAKE ALL PROVISIONS TO PROTECT THE PREMISES TREES AND NATIVE
PLANTS OUTSIDE OF THE PROJECT AREA FROM DAMAGE DURING DEMOLITION WORK.
4. THE SUBCONTRACTOR SHALL BE RESPONSIBLE FOR MOVING AND PROTECTING ALL OWNER-OWNED
FURNITURE, EQUIPMENT, ETC. AS REQUIRED DURING PERFORMANCE OF THIS PROJECT.
5. WHERE THE USE OF CUTTING TORCHES ARE REQUIRED, PROVIDE A MEANS TO VENTILATE THE SPACE TO REMOVE SMOKE AND ODORS. COORDINATE ALL TORCH CUTTING OPERATIONS WITH THE OWNER AND OBTAIN NECESSARY BURN PERMITS. PROVIDE A DOCUMENTED FALL SAFETY PLAN PRIOR TO CUTTING OPERATIONS AND INSTRUCT ALL PERSONNEL ON THE PLAN'S IMPLEMENTATION. FIRE EXTINGUISHERS
SHALL BE PRESENT AT ALL TIMES.
6. THE SUBCONTRACTOR SHALL DISPOSE OF ALL DEMOLITION MATERIALS, FOLLOWING LOCAL, STATE, FEDERAL, AND FAA REQUIREMENTS, EXCEPT WHERE NOTED OTHERWISE.
7. PROVIDE A DOCUMENTED FALL SAFETY PLAN PRIOR TO PERFORMING ANY WORK ON THE ROOF AND
INSTRUCT ALL PERSONNEL ON THE SAFETY PLAN IMPLEMENTATION.
8. SEE FACILITY HAZARDOUS MATERIAL REPORTS. IF HAZARDOUS MATERIAL SUCH AS ASBESTOS OR LEAD PAINT IS SUSPECTED OR FOUND, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE RESIDENT ENGINEER
FOR WRITTEN DIRECTION BEFORE PROCEEDING.
9. THE SELECTED CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, AND SUPERVISION FOR
THE DEMOLITION WORK AND INSTALLATION OF THE KIMBERLY VOR TOWER SAFETY PROJECT.
1. INSTALLATION PLAN VIEW DETAILS ARE AVAILABLE ON DRAWING A001
2. VERIFY TOP PLATFORM HEIGHT OF DESIGNED STAIRCASE IS SUFFICIENT FOR EXISTING RCLT PLATFORM.
ONLY PROCEED WITH INSTALLATION UPON APPROVAL OF THE ENGINEER.
3. CONCRETE BATCH PLAN CUT SHEET SHALL BE RECEIVED AND REVIEWED UPON DELIVERY. REJECT CONCRETE THAT DOES NOT CONFORM WITH SPECIFICATIONS. WATER SHALL NOT BE ADDED TO REDI-MIX
CONCRETE UPON OR DURING DELIVERY TO SITE UNLESS SPECIFIED IN BATCH PLANT DESIGN.
4. CONCRETE SHALL BE ALLOWED TO CURE FOR A MINIMUM OF 24-48 HOURS AND REACH 50% OF 28 -DAY
STRENGTH BEFORE PERFORMING TOWER STAIR INSTALLATION.
5. NO WOOD CONSTRUCTION MATERIALS SHALL BE PRESSURE TREATED, POST INSTALLATION TREATMENTS SHALL NOT CONTAIN COPPER OR CONDUCTIVE METALS. NO TREATMENT SHALL HAVE VOC GREATER THAN 50G/L.
6. ALL WOOD SURFACES SHALL BE PREPPED FOR COATING, AND INSPECTED FOR CURING AFTER
MANUFACTURE'S PRESCRIBED DURATION.
7. CONTRACTOR SHALL INSTALL NEW ICE BRIDGE AND CABLE RUN FROM EXISTING EQUIPMENT CABINETS TO
NEW TOWER WITH GROUNDING SYSTEM. THE FAA SHALL BE RESPONSIBLE FOR TERMINATING
CABLES/TESTING RESULTING EQUIPMENT FOR COMPLETION OF PROJECT.
8. CONTRACTOR SHALL RETURN SURROUNDING SITE TO ORIGINAL CONDITION AFTER INSTALLATION IS
COMPLETED.
AB AGGREGATE BASE
ABDN ABANDON
AGG AGGREGATE
ALIGN ALIGNMENT
AWOS AUTOMATED WEATHER OBSERVING SYSTEMS
BLDG BUILDING
CL CENTERLINE
CLR CLEAR, CLEARANCE
CMU CONCRETE MASONRY UNIT
CO CONTRACTING OFFICER
COMM COMMUNICATION
CONC CONCRETE
CONT CONTINUOUS
CS CONTRACTING SPECIALIST
DC DIRECT CURRENT
DIA DIAMETER
DEB DIRECT EARTH BURIAL
E EASTING, EXISTING
EA EACH
EES EARTH ELECTRODE SYSTEM
EG EXISTING GRADE
ELEC ELECTRICAL
EL ELEVATION
EMERG EMERGENCY
EQ EQUAL
EQUIP EQUIPMENT
EW EACH WAY
EX EXISTING
FAA FEDERAL AVIATION ADMINISTRATION
FF FINISHED FLOOR
GALV GALVANIZED
GEOR GEOTECHNICAL ENGINEER ON RECORD
GPRS GROUND PENETRATING RADAR SYSTEMS
HDG HOT-DIPPED GALVANIZED
HDPE HIGH DENSITY POLYETHYLENE
HH HANDHOLE
INV INVERT
JB JUNCTION BOX
LBS POUNDS
LF LINEAR FOOT
MAX MAXIMUM
MIN MINIMUM
N.I.C NOT IN CONTRACT
OC ON CENTER
PSI POUNDS PER SQUARE INCH
PVC POLYVINYL CHLORIDE
PWR POWER
R RADIUS
RC RELATIVE COMPACTION
RCLT RADIO COMMUNICATION LINK TERMINAL
RD ROAD
RE RESIDENT ENGINEER
REINF REINFORCEMENT, REINFORCING
RGSC RIGID GALVANIZED STEEL CONDUIT
SQ SQUARE
SS STAINLESS STEEL
SSC SYSTEM SUPPORT CENTER
TEL TELECOMMUNICATIONS
TEMP TEMPORARY
TSC TECHNICAL SERVICE CENTER
TYP TYPICAL
VAR VARIABLE
W WIDE
W/O WITHOUT
XFMR TRANSFORMER
GENERAL NOTES:ABBREVIATIONS
STRUCTURAL NOTES:
STRUCTURAL LUMBER NOTES:
REINFORCED CONCRETE NOTES:
EXCAVATION AND FOUNDATION NOTES:
GENERAL DEMOLITION NOTES:
GENERAL CONSTRUCTION NOTES:
SCALE OR OTHER INFORMATION
DRAWING TITLE
X001 A
SCALE OR OTHER INFORMATION
DRAWING TITLE1
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-G003
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
VC
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
GENERAL NOTES
AutoCAD SHX Text
GENERAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
4X DECK "JOIST" O/ 4X DECK BEAMS, TYP.
2X6 OR 2X8 DECKING FASTENED
TO BEAM BELOW, TYP.
WOODEN STAIRS MOUNTED TO
POLE SUPPORTS
4X PERIMETER DECK BEAMS THRU-BOLTED
TO POLES, TYP.
QTY (3) TOWER WOODEN POLES
WOODEN GUARDRAIL SYSTEM.
TOP RAIL NOT SHOWN FOR CLARITY.
ABANDONED ANTENNA SUPPORT SYSTEM
MOUNTED TO POLE
NORTH ELEVATION
WEST ELEVATIONEAST ELEVATION
APPROX. 1
2'-
3/
8"
VERIFY
IN
FI
ELD
APPROX. 13'-1"
VERIFY IN FIELD
APPRO
X. 10'-10 1/4"
VERIFY IN FIELD
CONDUIT SUPPORT BEAM.
FULL DETAIL NOT SHOWN FOR CLARITY
ABANDONED ANTENNA SUPPORT SYSTEM
MOUNTED TO POLE
DEMO EXISTING STAIRS
BRACKET MOUNTED ANTENNA FIXTURE.
FULL DETAIL NOT SHOWN DUE TO LACK OF
INFORMATION; REMOVE AND RETAIN ON SITE.
4X BEAMS THRU-BOLTED TO POLES
TOP RAIL SYSTEM; ATTACHMENT METHOD
VARIES BY ELEVATION.
3' -6
" M
IN
AB
O
VE
D
EC
K
2X6 INTERIOR TOE KICK OVER DECKING
2X4 GUARDRAIL BALUSTERS, TYP.
QTY (3) TOWER WOODEN POLES
AP
PR
O X.
8'
-2 " A
BO
VE
G R
AD
E
GUY-WIRES CONNECTING
TO EACH ADJACENT
POLE W/ TURNBUCKLES.
TURNBUCKLES THRU-
BOLTED TO POLES.
$F
IL
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A1' 0 3' 5'
SCALE: 1/2" = 1'-0"
1' 2' 4'
KEYED DEMOLITION NOTES:
PERFORM REMOVAL OF RCLT AND ASSOCIATED ANTENNAS FROM PLATFORM THROUGH
USE OF MAN-LIFT. RELOCATE TO NEW STAIRWELL PLATFORM.
PERFORM DISMANTLING AND DISPOSAL OF EXISTING TRIANGULAR ANTENNA PLATFORM
AND SUPPORTING STRUCTURE AFTER INSTALLATION OF NEW STAIRCASE PLATFORM AND
FAA APPROVES ANTENNA RELOCATION IS SUCCESSFUL.
LEGEND:
REMOVE AND DISPOSE
B D001
SCALE: 1/2" = 1'-0"
TOWER DEMOLITION PLAN VIEW
D001 B
SCALE: 1/2" = 1'-0"
TOWER DEMOLITION NORTH FACE
A001 A
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-D001
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
VC
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
TOWER DEMOLITION PLAN
AutoCAD SHX Text
DEMOLITION
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
APPROX 36'
60"
29'-5"
13'-7 1/2"
$F
IL
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A2' 0 2' 6'
SCALE: 3/8" = 1'-0"
4'
KEYED CONSTRUCTION NOTES:
EXCAVATE TO A DEPTH OF 36" BELOW EXISTING GRADE AND INSTALL 6" DRAINAGE GRAVEL AND COMPACT TO 90% MDD INSTALL CONCRETE FOUNDATION PAD PER DETAILS ON S001. ALLOW PAD TO CURE 24HOURS AND VERIFY
SUITABILITY PRIOR TO INSTALLATION OF STAIRWELL.
EXCAVATE HILLSIDE BACK TO PRODUCE FLAT LEVEL TERRAIN, DEPOSIT AT FAA OR STATE APPROVED DISPOSAL
SITES.
VERIFY INSTALLATION DESIGN HEIGHT FOR STAIRCASE PER S001. INSTALL STAIRCASE 24-48 HOURS AFTER
FOUNDATION PAD HAS CURED OR BEEN APPROVED FOR USE.
INSTALL WALL NIPPLE FOR THREE (3) CABLES AND ICE BRIDGE BETWEEN EXISTING BUILDING AND NEW TOWER. SEE
E001 FOR DETAILS REGARDING INSTALLATION REQUIREMENTS/DETAILS.
RELOCATE ANTENNAS FROM EXISTING TOWER TO NEW TOWER LOCATION WITH APPROVED EQUIPMENT MOUNTS.
EXCAVATE TO SUFFICIENT DEPTH IN AREA TO PROVIDE FOR FOUNDATION AS INDICATED ON S001 AND S002.
EXISTING SLOPE SHALL BE IMPACTED BY EXCAVATION EFFORTS. COORDINATE WITH FAA FOR DISPOSAL OF
MATERIAL ON SITE.
IMB VOR SHELTER
ROCK BACKSLOPE
1 1/2: 1
RCLR TOWER PLATFORM SHALL
REMAIN IN PLACE UNTIL NEW
ANTENNA LOCATION IS APPROVED
GRADED OUT TO
BUILDING SITE
ELEVATION
DOWN
TOP PLATFORM
16'-4"
ROUGHLY
A
S001
A
D001
5 4
60"
SCALE: 1/4" = 1'-0"
SITE RESTORATION PLAN
G002
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-A001
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
VC
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
SITE RESTORATION PLAN
AutoCAD SHX Text
ARCHITECTURAL
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
8'-11 1/2"
4'-9 1/2"4'
6' -4
5'
-1 0"
5' -1
0"
26'-5"
3'-10"
26'
4' -1
0"
10'-2 1/2"
6'-2 5/8"
13'-7"24'-9"
7'-9 1/2"
M
AX
10'-5" 10'-10 3/16"
3'-11"
" M
AX
" M
IN
AB
O
VE
D
EC
K
M
AX
M
AX
$F
IL
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
CONSTRUCTION NOTES:
1. ALL DIMENSIONS TO BE FIELD VERIFIED.
2. ALL PAINTED MATERIAL TO BE TRANSPARENT OR CLEAR UNLESS OTHERWISE DIRECTED.
CONTRACTOR TO SUBMIT COLOR SAMPLES TO PROJECT ENGINEER FOR APPROVAL.
3. PERFORM LOCATES PRIOR TO EXCAVATION. VERIFY AREA IS CLEAR OF UNDERGROUND
CONDUITS OR UTILITIES PRIOR TO START.
4. BOLT CONNECTIONS AND FASTENERS ARE EXCLUDED FOR CLARITY ON OPPOSING VIEWS
BUT ARE TYPICAL FOR ALL CONNECTIONS.
5. WHERE HOT WORK IS REQUIRED, OBTAIN NECESSARY HOT WORK PERMITS. FIRE
EXTINGUISHERS SHALL BE PRESENT AT ALL TIMES.
6. ALL WOOD STRUCTURAL MEMBERS SHALL BE PAINTED WITH PRIMER PRIOR TO
INSTALLATION. AFTER INSTALLATION PERFORM REQUIRED INTERMEDIATE/TOP COATS TO
ACHIEVE REQUIRED UV/WATER PROTECTION.
7. MECHANICALLY FASTEN NON-SLIP STAIR TREADS TO EACH TREAD.
STRUCTURAL NOTES:
1. ALL ANCHORS/FASTENERS SHALL BE HOT-DIPPED GALVANIZED OR STAINLESS STEEL.
2. BOLTS SHALL BE 5/8" HG HEX AND LENGTH SELECTED TO MEET THICKNESS OF
STRUCTURAL MEMBERS.
3. ALL WOOD MATERIAL SHALL BE NON-PRESSURE TREATED DOUGLAS FIR #1 OR EQUAL. AND
WEATHER TREATED AFTER INSTALLATION
4. HANDRAILS SHALL BE CLEANED AND PLANED OF SPLINTERS.
5. ALL STEPS SHALL HAVE A NO-SLIP STRIPS/PADS INSTALLED AFTER INSTALLATION.
6. THE FOLLOWING ARE DESIGN CONSIDERATIONS FOR THE NEW STRUCTURE:
· LOCATION: KIMBERLY OREGON, GRANT COUNTY
· LOCATION: 44°38'55.0"N 119°42'37.8"W
· FROST DEPTH: 24"
· WIND SPEED: 110MPH
· SNOW LOAD (ROOF): 30PSF
· LIVE LOAD: 100PSF
· SEISMIC: D1
2X12 LATERAL
BRACE TYP
EACH SIDE
3X12 STRAP
BRACE TYP
EACH SIDE &
PLATFORM
3X14 STRINGER
TYP2 EACH STAIR RUN
2X4 4' VERTICAL
HANDRAIL POST
SIMPSON CO.
MPB88Z POST BASE
EA 8X8 POST
NEW CONCRETE SLAB
FOUNDATION WITH #4
REBAR EACH WAY @
16" ON CENTER TOP
AND BOTTOM OF SLAB
6" OF 1"-1.5"
DRAINAGE GRAVEL
BENEATH PAD
2X6 DECKING
MIN 1" OVERHANG
1/8" SPACING
5/8" HEX HEAD
BOLTS 2 EACH
CONNECTION
SQUARE WASHER
EA SIDE TYP
2X4 TOE
BOARD TYP
2X4 MIDRAIL
TYP
A
S002
B
S002
S003
1&2
S003
5&10
S003
S002
S003
2X4 MIDRAIL
2X4 TOP RAIL TYP
2X4 TOP RAIL
2X4 TOEBOARD
2X4 MID
RAIL
2" DIA HAND RAIL
30" ABOVE LEADING
EDGE OF STEP
2X4 GUARD RAIL 42"
ABOVE LEADING
EDGE OF STEP
S003
S003
S003
S003
GRADE1" PERIMETER
CHAMFER
B
S001
BOLT THROUGH EA. PAIR LATERAL
BRACE SPAN DISTANCE WITH (2) 6"
SECTIONS OF 2X6 TYP
S003
SCALE: 1/2" = 1'-0"
STAIRWELL ELEVATION B
S001 B
SCALE: 1/2" = 1'-0"
STAIRWELL ELEVATION A
A001 A
3 FOOT TALL POSTS ON
BACKSIDE OF TOWER FOR
EQUIPMENT MOUNTING
PERIMETER HANDRAIL NOT
SHOWN ON BACKSIDE FOR
CLARITY TO SHOW WALKING
ACCESS FROM STARCASE
AutoCAD SHX Text
AutoCAD SHX Text 1'
AutoCAD SHX Text 2'
AutoCAD SHX Text 5'
AutoCAD SHX Text
SCALE: 1/2" = 1'-0"
AutoCAD SHX Text 1'
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-S001
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
STAIRWELL ELEVATION PLAN
AutoCAD SHX Text
STRUCTURAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
9' -7
26'
4'
1' -6
4'-6 1/2"
9' -7
8'-5 1/2"
2' 4'-6 1/2" 4'-6 1/2" 2' 7'-10" 2' 4'-5 1/2" 2'
29'-4 1/2"
2' 4'
-9
/2
4' -9
/2
2'
13'-1"
'-7
3" 6"
2' -6
$F
IL
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
CONSTRUCTION NOTES:
1. ALL DIMENSIONS TO BE FIELD VERIFIED.
2. PERFORM LOCATES PRIOR TO EXCAVATION OR CONSTRUCTION. VERIFY AREA IS CLEAR OF
UNDERGROUND CONDUITS OR UTILITIES PRIOR TO START.
3. WHERE HOT WORK IS REQUIRED, OBTAIN NECESSARY HOT WORK PERMITS. FIRE
EXTINGUISHERS SHALL BE PRESENT AT ALL TIMES.
4. FOUNDATION SURFACE SHALL BE SLOPED 2% AWAY FROM CENTER TO DRAIN WATER.
STRUCTURAL NOTES:
1. EXCAVATE CONCRETE PAD TO A MINIMUM OF 24", DO NOT IMPACT EXISTING TOWER.
2. PROVIDE A MINIMUM OF 6" DRAINAGE GRAVEL BENEATH CONCRETE PAD.
3. CONCRETE SHALL BE 4000PSI TYPE 1 PROVIDED BY LOCAL BATCHING PLANT NO GREATER
THAN 90MIN FROM SITE.
4. PERFORM SLUMP TEST AND COLLECT 2 CYLINDERS RANDOMLY FROM CONCRETE BATCHES
5. DO NOT ADD ADDITIONAL WATER TO THE CONCRETE DELIVERIES UNLESS DIRECTED BY
BATCH PLANT.
6. PERFORM SINGLE POUR FOR FOUNDATION PADS.
7. THE FOLLOWING ARE DESIGN CONSIDERATIONS FOR THE NEW STRUCTURE:
7.1. LOCATION: KIMBERLY OREGON, GRANT COUNTY
7.2. LOCATION: 44°38'55.0"N 119°42'37.8"W
7.3. FROST DEPTH: 24"
7.4. WIND SPEED: 110MPH
7.5. SNOW LOAD (ROOF): 30PSF
7.6. LIVE LOAD: 100PSF
7.7. SEISMIC: D13X14 STRINGER
FOUNDATION
3X12
STRAP
BRACE
2x6 JOISTS SPACED
14" O.C. STRAPPED TO
3X12 SPANNING BEAM
USING (1) SIMPSON
H1A FIXED EACH SIDE
#4 REBAR
SPACED 16" O.C.
EACH WAY
3"
4" DRAINAGE
ROCK
3" TYP
1" PERIMETER CHAMFER
2x6 DECKING ALL
PLATFORMS, SHALL
EXTEND 1" OVER EDGE
OF STRAP BRACE ON ALL
NON-STAIR SIDES, AND
SPACED NOMINALLY 1/4"
APART
8X8 POST
(1) 2X6 AND (1) 2X8
TREADS TYP.
SLOPE 2%
SLOPE 2%
SLOPE 2%
SLOPE 2%
SLOPE 2%
SLOPE 2%
SLOPE 2%
SLOPE 2%
2% SLOPE
TO EDGE
3X12
LEDGER
3X12 DECK BEAM
5/8" BOLT WITH
WIDE WASHER
TYPICAL
SCALE: 1/2" = 1'-0"
PAD CONSTRUCTION PLAN VIEW
S001 B
SCALE: 1/2" = 1'-0"
STAIRWAY CONSTRUCTION PLAN VIEW
S001 A
SCALE: 1" = 1'-0"
FOUNDATION DETAIL
S001
AutoCAD SHX Text
AutoCAD SHX Text 1'
AutoCAD SHX Text 2'
AutoCAD SHX Text 5'
AutoCAD SHX Text
SCALE: 1/2" = 1'-0"
AutoCAD SHX Text 1'
AutoCAD SHX Text
AutoCAD SHX Text 1'
AutoCAD SHX Text 1'
AutoCAD SHX Text 2'
AutoCAD SHX Text
SCALE: 1" = 1'-0"
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-S002
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
JF
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
STAIRWELL PLAN VIEW AND FOUNDATION
AutoCAD SHX Text
STRUCTURAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
" M
AX
" M
IN
AB
O
VE
D
EC
K
M
AX
M
AX
$F
IL
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
/2
1/2" HEX HEAD
BOLTS SPACED NO
LESS THAN 2.5X
DIA. FROM
CO-LOCATED
BOLTS, FLAT
WASHER EA SIDE
AND NYLON LOCK
NUT
3X14 CEDAR
STRINGER
3X14
MOUNTED
EACH SIDE OF
STAIR RUN
SIMPSON TA9Z
MOUNTED EACH
STEP EACH SIDE
FASTEN WITH
(5) SIMPSON
SDS25112 EACH
2X8
STEP
TYP
(1) SIMPSON WP312X-
SLD30 EACH TOP
STRINGER FASTEN WITH
(6) SIMPSON SD9212
2X6 JOIST
SPACED 12"
MIN O.C.
8X8 POST
3X12
LEDGER
(1) SIMPSON
LUS26-2
FIXED WITH
(8) SD9212
1/
4" M
IN
1 1/4"
12"
5"
2X10 RISER
3X12
LEDGER
2X6 JOIST SPACED 14" MIN O.C.
3X14
STRINGER
8X8 COLUMN
GENERAL NOTES:
1. ALL DESIGNATIONS TO SPECIFIC PRODUCTS ARE USED AS REFERENCE TO REQUIRED
CONNECTIONS NECESSARY FOR APPROVED ALTERNATIVES.
2. CONTRACTOR SHALL VERIFY DIMENSIONS AND QUANTITIES OF CONNECTORS/FASTENERS IN
DRAWINGS PRIOR TO PERFORMANCE OF WORK.
3. FAILED/DAMAGED CONNECTIONS/FASTENERS SHALL BE REPLACED BY CONTRACTOR AT NO
COST TO OWNER.
4. ALTERNATIVE FASTENING METHODS SHALL BE SUBMITTED AND APPROVED PRIOR TO WORK
START.
5. ALL FASTENERS SHALL BE HOT-DIPPED GALVANIZED.
6. ALL WOOD PRODUCTS SHALL BE DOUGLAS FIR STRUCTURAL RATED AND BE FREE FROM
DEFORMATIONS AND TWISTING OR BETTER. COATED TWICE WITH APPROVED PRIMER.
7. AFTER INSTALLATION WOOD MEMBERS SHALL BE COATED ONCE WITH APPROVED CLEAR
PRIMER.
8. ALL HANDRAILS SHALL BE OSHA COMPLAINT WITH THE FOLLOWING LOADING
CONSIDERATIONS:
8.1. UPPER HANDRAIL SHALL RESIST 200LB VERTICAL OR LATERAL POINT LOAD FORCE, OR
50LB PER FOOT VERTICAL OR LATERAL UNIFORM LOAD
8.2. MID-RAIL SHALL PROVIDE SPACING NO LARGER THAN 19 INCHES FROM TOP RAIL TO
TOE-BOARD AND RESIST 150LB VERTICAL OR LATERAL POINT LOAD FORCE
8.3. TOE-KICK SHALL HAVE MINIMUM HEIGHT OF 4" WITH 1/4" DRAINAGE GAP AND RESIST 50
POUNDS HORIZONTAL POINT LOAD
(1) SIMPSON ML23Z
INSIDE FOR MID-RAIL
AND TOE-BOARD
FASTEN WITH (4) 14"
WOOD SCREWS
2X4
MID-RAIL
2X4
TOE-BOARD
ELEVATED 14"
FROM DECK
2X4 POST
5/8" CARRIAGE
BOLT WITH
FLAT WASHER
AND NYLON
LOCK NUT 4
EA POST
2"
ROUND
HANDRAIL
WITH
HANDRAIL
BRACKET
3X14 STRINGER
2X6
JOIST
SPACED 14"
MIN O.C.
8x8 COLUMN
3X12 LEDGER
(1) SIMPSON
LUS26-2
FIXED WITH
(8) SD9212
TYPICAL STEP
6.5" RISE
12" RUN
SHAVED
2X8 RISER
13X5
CONCRETE
STEP
5/8" HEX HEAD
BOLTS TYP
3X12 STRAP
6X6
POST
(1) SIMPSON WP312X-
SLU30 EACH BOTTOM
STRINGER FASTEN
(6) SIMPSON SD9212 (1) SIMPSON ML23Z
EACH SIDE OF BACK
STEP FASTEN WITH (4)
SD
(1) SIMPSON
H1A FIXED
WITH (4)
SD9212 EA
BEAM
(1) SIMPSON
ML23Z EACH SIDE
FASTEN WITH (4)
4" WOOD SCREWS
2X4
TOE-BOARD
ELEVATED 14"
ABOVE DECK
2X6 JOISTS
14" O.C.
SIMPSON TA9Z
MOUNTED EACH
STEP EACH SIDE
FASTEN WITH
(5) SIMPSON
SDS25112 EACH
(1) SIMPSON ML23Z
EACH SIDE OF
BACK STEP FASTEN
WITH (4) SD
FINISHED
CONCRETE
GRADE
8X8 COLUMN
SIMPSON MBP88Z
EACH POST TYP
FASTENED WITH
(36) SDS25300
SCREWS
SET POST
BASE DURING
FOUNDATION
CURING
4" GAP
TYP.
4" GAP
TYP.
4" GAP
TYP.
4" GAP
TYP.
TREAD-
LOCKER
TYP. EA.
STEP
2X4
TOP-RAIL
PREDRILL AND DROP
IN(1) SIMPSON 1/2"
THREADED ROD
EACH SIDE OF
STRINGER USE
SIMPSON ET-HP22-N
EPOXY
(1) SIMPSON DTT1Z
OR DTT2Z EACH
EXTERIOR SIDE OF
STRINGER FASTEN
WITH (6-8) SD
2X10 RISER TYP
2X6
STEP
TYP
(2) 2X4 STEP SUPPORT
SPACED EQUALLY TYP
EACH STEP
(1) SIMPSON ML23Z
EACH END OF STEP
SUPPORT FASTEN
WITH (4) SD
1'-2"
TYP. 2X6 JOISTS
14" O.C. TYP
2X4 DECK
3X12 DECK
BEAM
3X12
LEDGER
5/8" HEX HEAD
BOLTS TYP
8X8 COLUMN
(1) SIMPSON
H1A FIXED
WITH (4)
SD9212 EA
BEAM
(1) SIMPSON
H1A FIXED
WITH (4)
SD9212 EA
BEAM
8X8 COLUMN
8X8 COLUMN
BOTTOM
OF 3X12
LEDGER
3X14
STRINGER
SCALE: 1-1/2" = 1'-0"
SAFETY RAIL DETAIL6
SCALE: 1-1/2" = 1'-0"
PLATFORM DETAILS 11
SCALE: 1-1/2" = 1'-0"
PLATFORM DETAILS 22
SCALE: 1-1/2" = 1'-0"
PLATFORM DETAILS 33
SCALE: 1-1/2" = 1'-0"
STEPS AND FASTENERS4
SCALE: 1-1/2" = 1'-0"
STRINGER BASE INT.5
SCALE: 1-1/2" = 1'-0"
STRAP CONNECTION7
SCALE: 1-1/2" = 1'-0"
TOWER BRIDGING8
SCALE: 1-1/2" = 1'-0"
POST BASES9
SCALE: 1-1/2" = 1'-0"
STRINGER BASE EXT.10
SCALE: 1-1/2" = 1'-0"
JOIST TO DECK BEAM11
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-S003
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
JF
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
STRUCTURAL DETAILS
AutoCAD SHX Text
STRUCTURAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text 1'
AutoCAD SHX Text
AutoCAD SHX Text 1'
AutoCAD SHX Text 3"
AutoCAD SHX Text 6"
AutoCAD SHX Text 9"
SCALE: 1 1/2" = 1'-0"
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
SCALE: 3/8" = 1'-0"
EQUIPMENT ROOM LAYOUT AND PARTIAL FLOOR PLAN
2' 0 2' 6'
SCALE: 3/8" = 1'-0"
4'
KEYED CONSTRUCTION NOTES:
INSTALL APPROXIMATELY 5 LINEAR FEET OF ICE BRIDGE BETWEEN SOUTH WALL AND TOWER. INSTALL
AN ADDITIONAL 16 LINEAR FEET TO WEST CORNER OF SOUTH FALL FOR CABLE ROUTING INTO
FACILITY. SEE E002 FOR GROUNDING AND INSTALLATION REQUIREMENTS.
INSTALL GROUNDING PROTECTION FOR CABLES/TOWER SEE DETAILS ON E002 AND E003.
INSTALL NEW LIGHTNING PROTECTION SYSTEM INCLUDING AIR TERMINALS AND GROUND RODS.
INTEGRATE ITEMS INTO EXISTING EARTH ELECTRODE SYSTEM (EES). SEE DETAILS ON DRAWING E004.
ANTENNA EQUIPMENT SHALL BE REMOVED BY OTHERS FROM EXISTING TOWER AND RELOCATED TO NEW POSITION ON TOWER. AFTER RELOCATION AWAIT PERFORMANCE OF CABLE TERMINATION AND
ANTENNA CALIBRATION. SEE E004 FOR DETAILS REGARDING MOUNTING OF ANTENNAS.
INSTALL RCLR ANTENNA MOUNT, SITEPRO-1 DCH8 CHAIN MOUNT WITH STIFF ARM OR APPROVED
EQUAL.
ICE BRIDGE TO BE INSTALLED
3/4" X 10' COPPER CLAD GROUND ROD INSTALLED VERTICALLY 12" BELOW GRADE
GROUND WELL WITH GROUND ROD
5/8"X24" AIR TERMINAL TO BE INSTALLED ABOVE NEW EQUIPMENT.
EARTH ELECTRODE SYSTEM (EES) INSTALLED 24" BELOW GRADE
RF CABLE INSTALL ROUTE (TO BE PERFORMED BY OTHERS)
COAXIAL CABLE INSTALL ROUTE (TO BE PERFORMED BY OTHERS)
DOWN CONDUCTOR FROM STRUCTURE TO EES
LEGEND:
A E002
DOWN
RCLT
ANTENNA
NBPM PARROT
ANTENNA (X2)
VOR EQUIPMENT ROOM
HVAC UNIT WITH
OVERHEAD JUNCTION
BOX FOR GROUNDING
RF CAVITY FILTER (6 PL)
RCO RCAG LPA
CH 56 CH 56
RCAG LPA
CH 35 CH 35
CABLE TRAY (TYP)
BATTERY
STACK
BATTERY
CHARGER
LDRCL NBPM
"F" PANEL
AUX SPGP
LDRCL DEMARK
LDRCL BACKBOARD
TELCO
ENTRANCE
TELCO-GRND
J-BOX
SURGE PROTECTION
ENCLOSURE
SUPPLEMENTAL
MPGP
SPGP
MGP
MPGP
4/0 ORG/GRN
"D" PANEL
4/0 ORG/GRN
60"
MPGP
RADIO EQUIPMENT ROOM
LOCATE EXISTING EES
AND INTEGRATE WITH
APPROPRIATE CADWELD
DOWN
CONDUCTOR
LOCATE EXISTING EES
AND INTEGRATE WITH
APPROPRIATE CADWELD
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-E001
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
TV
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
EQUIPMENT ROOM RESTORATION PLAN
AutoCAD SHX Text
ELECTRICAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text EXIST 4x4
SQ. DUCTDUCT
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
SCALE: 1/2" = 1'-0"
RCLR TOWER CABLE AND GROUNDING ELEVATION VIEW
E001 A
SCALE: 1/2" = 1'-0"
RCLR TOWER CABLE AND GROUNDING ELEVATION VIEW
E002 B
GENERAL CONSTRUCTION NOTES:
KEYED CONSTRUCTION NOTES:
CABLE INSTALL AND GROUNDING SHALL BE PERFORMED BY ANOTHER GROUP. CABLE SUPPORTS
SHALL BE INSTALLED AT LEAST OF EVERY THREE (3) FEET OF CABLE RUN.
CONTRACTOR SHALL INSTALL APPROXIMATELY 21 LINEAR FEET ICE BRIDGE AND GROUND
APPROPRIATELY TO NEW/EXISTING EARTH ELECTRODE COUNTERPOISE SYSTEM (EECS)
CONTRACTOR SHALL INSTALL NEW GROUNDING BAR ON TOWER LEG FACING INTERIOR OF THE TOWER
FOR ACCESS FROM PLATFORM.
SEE DETAIL 6 ON E004
PROVIDE AND INSTALL THOMSON 28R DOWN CONDUCTOR IN 1" PVC CONDUIT
PROVIDE AND INSTALL AIR TERMINALS CLASS 2 AND ALL ASSOCIATED ACCESSORIES
SEE DETAIL 2&3 ON E003
1. CABLES SUPPORTS SHALL BE INSTALLED EVERY THREE FEET OF CABLE RUN. VERTICAL RUNS
SHALL HAVE MOUNTING POINTS INSTALLED AT STRUCTURAL BRACES, LEDGERS, AND POSTS OF
THE CABLE RUNNING PATH. A DRIP LOOP SHALL BE INSTALLED PRIOR TO CONNECTING TO THE
ANTENNA EQUIPMENT WITH BENDS NOT EXCEEDING MANUFACTURER'S SPECIFICATIONS. CABLES
SHALL BE INSTALLED BY ANOTHER PARTY AFTER COMPLETION OF THE CONDUIT GROUNDING
AND PATHS. CONTRACTOR IS PERMITTED TO RUN FSJ4 "DUMMY CABLE" TO VERIFY INSTALLATION
MEETS REQUIREMENTS.
2. EXOTHERMICALLY WELD THE GROUNDING ELECTRODE CONDUCTORS DIRECTLY TO GROUND
ROD
3. INTEGRATE THE GROUND ROD INTO THE EARTH ELECTRODE SYSTEM (EES). IF EES IS NOT
PRESENT, DRIVE SECOND GROUND ROD 10 FEET AWAY FROM FIRST GROUND ROD. REFER TO
CURRENT NEC 780, AND THE LATEST VERSION OF FAA-C-1217H, GROUNDING SHALL BE IN
COMPLIANCE WITH CURRENT VERSION OF FAA-STD-019F, CHANGE 3.
MICROWAVE DISH TO BE
INSTALLED BY OTHERS
' M
IN
SHELTER
WIREWAY
BATTERY
CHARGER
LDRCL
RACK
3-1/2" DIAM.
GALVANIZED
ICE-BRIDGE
COLUMN
CONCRETE SHAFT
FOUNDATION
6' -4
60"
COLUMN GROUND
TO EES
B E0
MICROWAVE DISH TO BE
INSTALLED BY OTHERS
NBPM
RACK
RBPM ANTENNAS TO BE
INSTALLED BY OTHERS
CABLE TRAY
ICE-BRIDGE
2X PARROT ANTENNAS TO
BE INSTALLED BY OTHERS
WALL
MOUNTED
HVAC
NEW POST AND
EQUIPMENT TO
BE INSTALLED
NO CLOSER
THAN 3FT
AWAY FROM
EXISTING HVAC
EQUIPMENT
USE EXISTING
GROUNDING BOX
TO GROUND
CABLED BEFORE
ENTERING
BUILDING
CABLE SHALL ENTER
BUILDING FROM EXISTING
WALL PENETRATION ON
WEST END OF WALL
4' -6
1'-0"
3"
AIR TERMINAL (TYP)
GROUNDING BAR
DOWN CONDUCTOR (TYP)
GROUNDING BAR
PVC SCHEDULE 40
CONDUIT
TO EXISTING EES
4 /0 AWG
GROUNDING
TO EXISTING EES
TO EXISTING EES
DOWN CONDUCTOR (TYP)5
CONNECTION POINT
CABLES SUPPORT (TYP)
CONNECTION POINT4
3' -0
3' -0
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
$WATERMARK$
AutoCAD SHX Text
SL
AutoCAD SHX Text
IMB-D-20001953-E001
AutoCAD SHX Text 20001953
AutoCAD SHX Text
MGR: ENGINEERING - SEATTLE
AutoCAD SHX Text
PROJECT ENGINEER
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
TV
AutoCAD SHX Text
CASEY BROWNE
AutoCAD SHX Text
JAY KAMANI
AutoCAD SHX Text
KIMBERLY
AutoCAD SHX Text
OR
AutoCAD SHX Text
TOWER SAFETY PROJECT
AutoCAD SHX Text
CABLE RESTORATION ROUTING AND GROUNDING
AutoCAD SHX Text
ELECTRICAL
AutoCAD SHX Text
VOR
AutoCAD SHX Text
INFRASTRUCTURE OPS
AutoCAD SHX Text
ENGINEERING SERVICES
AutoCAD SHX Text
ATO - TECHNICAL OPERATIONS
AutoCAD SHX Text
WESTERN SERVICE AREA
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
COLD SHRINK EXTENDS 1" OUT
AT EACH SIDE
NOT TO SCALE
COLD SHRINK DETAIL6
4/0" AWG
MOUNTING
BRACKET
NOT TO SCALE
GROUNDING PLATES DETAIL8
STAND-OFF
GROUND
PLATE
MOUNTING
BRACKET
NOT TO SCALE
4/0 TO PLATE WELD DETAIL7
GROUND
PLATE
1" PVC