Attachment 2- HVAC Schedule (POPs).xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- Rental of Temporary HVAC & Exhaust System
- Solicitation number
- N3904026Q3045
About this file
The file is an Excel spreadsheet (Attachment 2) detailing a HVAC Schedule with Periods of Performance for a temporary HVAC and exhaust system rental solicitation by the Department of the Navy Naval Sea Systems Command. The schedule outlines multiple HVAC equipment components with specific rental periods across base and optional performance periods from February 2026 to April 2028. Required equipment includes Triple/Double Coil HVAC units, Exhaust Blowers, 230 Ton Chillers, Chilled Water (CHW) Pumps, various CHW hoses and elbows, CHW Manifolds, Adapters, and E-Stop Equipment. Optional equipment includes Electric Fan Coil Units with intermittent rental periods primarily during cooler months. The solicitation (N3904026Q3045) covers rental periods that are segmented into base periods and up to three option periods, with some equipment having more limited rental windows, particularly the chiller and related chilled water infrastructure components.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PIECE NO. Component Required Equip. vs. Optional Equip. Base Period of Performance Option 1 Period of Performance Option 2 Period of Performance Option 3 Period of Performance End
| V -01/02 | Triple/Double Coil HVAC | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 | |
| V -01/02 | Triple/Double Coil HVAC | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 | |
| V -01/02 | Triple/Double Coil HVAC | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 | |
| V -03 | Exhaust Blower | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 | |
| V -03 | Exhaust Blower | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 | |
| V -03 | Exhaust Blower | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 | |
| V -03 | Exhaust Blower | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 | |
| V -04 | Electric Fan Coil Unit | Optional | 10/1/2026 -to- 4/28/2027 | 9/4/2027 -to- 2/4/2028 | 2/5/2028 -to- 3/3/2028 | 3/4/2028 -to- 3/31/2028 | 4/1/2028 -to- 4/28/2028 |
| V -04 | Electric Fan Coil Unit | Optional | 10/1/2026 -to- 4/28/2027 | 9/4/2027 -to- 2/4/2028 | 2/5/2028 -to- 3/3/2028 | 3/4/2028 -to- 3/31/2028 | 4/1/2028 -to- 4/28/2028 |
| V -04 | Electric Fan Coil Unit | Optional | 10/1/2026 -to- 4/28/2027 | 9/4/2027 -to- 2/4/2028 | 2/5/2028 -to- 3/3/2028 | 3/4/2028 -to- 3/31/2028 | 4/1/2028 -to- 4/28/2028 |
| V -04 | Electric Fan Coil Unit | Optional | 10/1/2026 -to- 4/28/2027 | 9/4/2027 -to- 2/4/2028 | 2/5/2028 -to- 3/3/2028 | 3/4/2028 -to- 3/31/2028 | 4/1/2028 -to- 4/28/2028 |
| V -04 | Electric Fan Coil Unit | Optional | 10/1/2026 -to- 4/28/2027 | 9/4/2027 -to- 2/4/2028 | 2/5/2028 -to- 3/3/2028 | 3/4/2028 -to- 3/31/2028 | 4/1/2028 -to- 4/28/2028 |
| V -04 | Electric Fan Coil Unit | Optional | 10/1/2026 -to- 4/28/2027 | 9/4/2027 -to- 2/4/2028 | 2/5/2028 -to- 3/3/2028 | 3/4/2028 -to- 3/31/2028 | 4/1/2028 -to- 4/28/2028 |
| V -04 | Electric Fan Coil Unit | Optional | 10/1/2026 -to- 4/28/2027 | 9/4/2027 -to- 2/4/2028 | 2/5/2028 -to- 3/3/2028 | 3/4/2028 -to- 3/31/2028 | 4/1/2028 -to- 4/28/2028 |
| V -05 | 230 Ton Chiller | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -05 | 230 Ton Chiller | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V-06 | CHW Pump 600 gpm | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V-06 | CHW Pump 600 gpm | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -07 | 6 IN Dia CHW Hose | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -08 | 6 IN Dia 90° Elbow | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -09 | 4 IN Dia CHW Hose | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -10 | 4 IN Dia 90° Elbow | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -11 | CHW X Manifold | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -11 | CHW X Manifold | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -11 | CHW X Manifold | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -12 | CHW Adapators | Required | 3/19/2026 -to- 9/16/2026 | 3/24/2027-to-9/21/2027 | N/A | N/A | |
| V -13 | E-Stop Equipment | Required | 2/4/2026 -to- 2/2/2027 | 2/3/2027 -to- 2/1/2028 | 2/2/2028 -to- 3/28/2028 | 3/29/2028 -to- 4/27/2028 |