Attachment 2 - Chambers and Basement.pdf

PDF 18 MB Posted

Attached to
Renovation of High Reservoir #2
Solicitation number
GDP-B0061-5P
Issued by

About this file

This document is a technical specification and visual guide for renovation and replacement work on an industrial tank system and associated piping infrastructure. The project encompasses comprehensive demolition and installation tasks across multiple system components.

The scope of work includes: demolition and replacement of the complete drain pipe system using stainless steel (1.4401) with all associated valves, leverage mechanisms, and hand wheels; replacement of extraction lines (stainless steel 1.4001/1.4401) up to valve connections, including core drilling and sealing; installation of new overflow pipelines connected to the drain system (stainless steel 1.4401); installation of a new hydrostatic level/pressure measurement system per specifications in the Statement of Work; installation of a new flammable sampling valve; and replacement of the drain pipe with core drilling and sealing. Additional work includes demolition and closure of multiple wall penetrations, replacement of lighting with new LED fixtures, demolition and relocation of the ladder directly under the access point, demolition of old level indicators and filling lines with installation of new level indicators near the ladder, and fabrication of a stainless steel gutter to cover the drain (approximately 1.57m x 0.8m). The photographic documentation on pages 1-6 shows the existing equipment layout and identifies specific components requiring replacement, with annotated arrows and labels indicating work locations throughout the tank chamber and supporting pump systems.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

demolish old level indicator and install new level indicator near ladder

Replace old extraction line with shorter stainless steel (1.4401) line

(ca. 1m)

Replace lighting with new LED lights

Replace wall penetration with new sealing (incl.

core drilling) Replace old drain pipe with stainless steel pipe, incl. wall penetration, new sealing, and core drilling

Close wall penetration

Demolish pipelines and close wall penetration

Demolish pipeline and close wall penetration

Demolish old ladder, install new ladder directly under access point

Demolish pipeline and close wall penetration

Demoslish old overflow, close wall penetration

Demolish sheet metal

Demolish plastic cover and seal drillings

Install new overflow with new sealing (incl. core drilling) ca 80cm

Replace complete drain pipe system (stainless steel 1.4401) incl. all valves (incl. leverage + hand weel) and necessary peripherie

Demolish pipelines and close wall penetration

Install new overflow pipeline and connect to drain system (stainless steel 1.4401)

Install new overflow pipeline and connect to drain system (stainless steel 1.4401)

Replace extraction line (stainless steel 1.4001) up to valve, incl. core drilling, sealing and all asscoiated work

Replace extraction line (stainless steel 1.4401) up to valve, incl. core drilling, sealing and all asscoiated work

Demolish pipelines and close wall penetration

Replace complete drain pipe system (stainless steel 1.4401) incl. all valves (incl. leverage + hand weel) and necessary peripherie

Install new overflow pipeline and connect to drain system (stainless steel 1.4401)

Install new overflow pipeline and connect to drain system (stainless steel 1.4401)

Replace extraction line (stainless steel 1.4401) up to valve, incl. core drilling, sealing and all asscoiated work

Replace extraction line (stainless steel 1.4001) up to valve, incl. core drilling, sealing and all asscoiated work

Replace drain pipe (stainless steel 1.4401) incl. core drilling, sealing

Installation of new hydrostatic level/ pressure measurement system (specs see

SOW)

Installation of new flammable sampling valve

Replace valve incl.

steel leverage and hand weel

Demolish old level indicator filling line

R ep la ce pi pe lin e

(m at er ia ls ta in le ss st ee l1 .4 1)

Fa br ic at e St ee l gu tte rt o co ve rd ra in ca .1 .5 7m x 0.

8m

D em ol is h ol d le ve l in di ca to r

D em ol is h ol d le ve l in di ca to rf illi ng lin e

File details come from the government source that posted it. Updated .