This is a specification document for dockside repairs to the USCGC Bristol Bay (WTGB-140), a 140-foot Class River Buoy Tender Cutter homeported in Detroit, Michigan. The specification outlines 42 work items encompassing comprehensive maintenance and repair services for both the tender vessel and its accompanying 120-foot barge, with a performance period from June 2 to July 13, 2026.
The work items are organized into major categories including tank cleaning and inspection (potable water, lube oil, ballast, fuel, grey water, and sewage systems); exhaust system cleaning (main diesel engine, ship service diesel generator, boiler, and bubbler engine); ventilation duct cleaning (engine room, galley, and other spaces); deck systems and equipment servicing (circuit breakers, compressed air receivers, capstan, davit, winches, and hull fittings); and specialized systems (firemain valves, piping cleaning and flushing, electrical deck matting, and mechanical chain stoppers). Critical inspection items must be completed within the first 25% of the contract period, including compressed air receivers, capstan, davit, pelican hook, chain stoppers, anchor winch, traction winches, gypsy winches, and deck covering work. The specification incorporates Surface Forces Logistics Center (SFLC) Standard Specifications for general requirements, welding, preservation, ventilation cleaning, auxiliary machine systems, and deck covering installation. Government-furnished property includes replacement parts kits and hardware for various systems. The contractor must maintain comprehensive documentation including quality assurance inspection forms, tank assessment forms, operational test reports, and nondestructive examination results throughout the availability period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC BRISTOL BAY (WTGB 102)
USCG 120 BARGE (12002)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2026
Developed By: Kalee J Campbell
(Rev-2, 19 February 2026)
USCGC BRISTOL BAY (WTGB-140) DOCKSIDE AVAILABILITY FY2026
ii (Rev-2)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics - Tug, IceBreaking ................................................................................................ xi Principal Characteristics - Barge ................................................................................................................ xii General Requirements WORK ITEM 1: Fire Prevention Requirements «TYPE» WORK ITEM 2: Tank (Water Mist), Clean And Inspect WORK ITEM 3: Tanks, Hydraulic Oil Stowage and Service, Clean and Inspect WORK ITEM 4: Tanks, Potable Water, Clean and Inspect WORK ITEM 5: Tanks, Lube Oil, Clean and Inspect WORK ITEM 6: Tanks, Ballast, Clean and Inspect WORK ITEM 7: Voids, Accessible, Clean and Inspect WORK ITEM 8: Tanks, Dirty Oil and Waste, Clean and Inspect WORK ITEM 9: Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean WORK ITEM 10: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean WORK ITEM 11: Boiler Exhaust Stack Uptakes, Commercial Clean WORK ITEM 12: Bubbler Diesel Engine Exhaust Piping, Commercial Clean WORK ITEM 13: Circuit Breakers (60 Hz), Inspect and Test WORK ITEM 14: Vent Ducts, Engine And Motor Room, All, Commercial Cleaning WORK ITEM 15: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning WORK ITEM 16: Vent Ducts, All Other, Commercial Cleaning WORK ITEM 17: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift ... 66 WORK ITEM 18: Vertical Capstan, Inspect and Service WORK ITEM 19: Hull Fittings (Mooring and Towing), Inspect and Test - Barge WORK ITEM 20: Single Point Davit, Inspect and Service WORK ITEM 21: Hydraulic Release Pelican Hook, Inspect and Service - Tender WORK ITEM 22: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 23: Sewage Holding Tanks, Clean and Inspect WORK ITEM 24: Grey Water Piping, Clean and Flush WORK ITEM 25: Sewage Piping, Clean and Flush WORK ITEM 26: Tanks, MP Fuel Service, Clean and Inspect - Barge WORK ITEM 27: Tanks, Potable Water, Clean and Inspect - Barge WORK ITEM 28: Tanks, Ballast, Clean and Inspect - Barge WORK ITEM 29: Voids, Accessible, Clean and Inspect - Barge WORK ITEM 30: Boiler Exhaust Stack Uptakes, Commercial Clean - Barge WORK ITEM 31: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning - Barge WORK ITEM 32: Vent Ducts, All Other, Commercial Cleaning - Barge WORK ITEM 33: Hull Fittings, Weight Handling Rigging Hardware, Inspect and Test - Barge WORK ITEM 34: Mechanical Chain Stoppers, Inspect and Service WORK ITEM 35: Anchor Winch, Inspect and Service - Barge WORK ITEM 36: Traction Winches, Inspect and Service - Barge WORK ITEM 37: Gypsy Winches (Appleton Model AMD-865), Overhaul - Barge WORK ITEM 38: Grey Water Holding Tanks, Clean and Inspect - Barge WORK ITEM 39: Sewage Holding Tanks, Clean and Inspect - Barge WORK ITEM 40: Deck Covering, Electrical Matting, Renew WORK ITEM 41: Fireman Valves, Overhaul or Renew iii (Rev-2)
WORK ITEM 42: Hull Fittings (Mooring and Towing), Inspect and Test - Barge iv (Rev-2)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-2)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 101 WTGB 259-001, Rev L, Diesel Exhausts & Steam Generator Exhausts System
A & D Coast Guard Drawing 101 WTGB 514-002, Rev X, Ventilation & A/C Arrangements & Details Coast Guard Drawing 101 WTGB 528-001, Rev L, Sanitary & Deck Drain System Diagram Coast Guard Drawing 101 WTGB 528-003, Rev C, Grey Water Mods & Tank Transitions Coast Guard Drawing 101 WTGB 589-001, Rev B, Barge Quick Release Modification Coast Guard Drawing 101-WTGB-320-6, Rev L, Power System One Line Diagram Coast Guard Drawing 120 Barge 120-001, Rev B, Longitudinal and Transverse Bulkheads Coast Guard Drawing 120 BARGE 167-001, Rev C, Access & Closures Coast Guard Drawing 120 BARGE 185-003, Rev A, Traction Winch Foundation Coast Guard Drawing 120 Barge 581-001, Rev B, Mooring and Towing Arrangement Coast Guard Drawing 120 Barge 611-001, Rev C, Hull Fittings Coast Guard Drawing 120 BARGE-130-001. Rev D, Main & Focs’le Decks Coast Guard Drawing 120 BARGE-601-001. Rev C, General Arrangement & Profile Coast Guard Drawing 120-BARGE 111-1, Rev C, Bottom Framing & Plating Coast Guard Drawing 120-BARGE 120-1, Rev B, Longitudinal & Transverse Bulkheads Coast Guard Drawing 120-BARGE 601-1, Rev C, General Arrangement and Profile Coast Guard Drawing 120-BARGE-512-1, Rev B, HVAC Diag & Install Dets Coast Guard Drawing 120-CGB 533-1, Rev D, Potable Water System Coast Guard Drawing 120-CGB 581-001, Rev C, Anchor Handling Arrangement Coast Guard Drawing 120-CGB 593-1, Rev C, Sewage & Plumbing Drains Coast Guard Drawing 120-CGB 601-1, Rev C, General Arrangement and Profile Coast Guard Drawing 120-CGB 801-4, Rev A, Tank Capacity Curves Coast Guard Drawing 120-CGB 801-5, Rev A, Tank Sounding Tables Coast Guard Drawing 140 WTGB 259-001, Rev -, Diesel Exhaust Systems, Arrangements & Details Coast Guard Drawing 140 WTGB 259-002, Rev B, Exhaust Modifications to Suit Bubbler Installation Coast Guard Drawing 140 WTGB 551-001, Rev -, Compressed Air System Diagram Coast Guard Drawing 140-WTGB 123-2, Rev B, Structural Mods Incidental to Water Mist Tank 4-24-1-
W vi (Rev-2)
Coast Guard Drawing 140-WTGB 528-002, Rev -, Sanitary & Deck Drains Diag Coast Guard Drawing 140-WTGB 528-003, Rev -, Sanitary & Deck Drains A&D Coast Guard Drawing 140-WTGB 528-004, Rev -, Grey Water Mods & Tank Transition Coast Guard Drawing 140-WTGB 555-2, Rev C, Water Mist System Installation A&D Coast Guard Drawing 140-WTGB 555-4, Rev C, Water Mist System Diagram Coast Guard Drawing 140-WTGB 801-3, Rev -, Booklet of General Plans Coast Guard Drawing 140-WTGB-167-001, Rev A, Closures & Window List Coast Guard Drawing 140-WTGB-167-007, Rev -, Flush WT Escape Scuttle Coast Guard Drawing 140-WTGB-320-1, Rev L, Power System One-Line Wiring Diagram Coast Guard Drawing 140-WTGB-801-003, Rev B, Booklet of General Plans Coast Guard Drawing FL 1204-3, Rev A, Welded Padeyes & Links Coast Guard Drawing FL 3801-67, Rev B, Sheets 1 through 10 of 50 (General Notes – Ductwork) and
Sheet 39 (Handholes for W.T. and N.W.T. Ducts) Contact SES to provide and update record file.
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual Coast Guard Technical Publication (TP) 10000, May 2015, Manufacturer's Instruction Book - SWBS
Group(s) 583, Single Point Davit, – Model PLA-2000 Coast Guard Technical Publication (TP) 3386, SWBS 582, Section A, June 2013, Mooring and Towing
Systems Coast Guard Technical Publication (TP) 3386, SWBS 582, Section O, Feb 1991, Appleton Marine
Installation, Operation, and Maintenance Manual for Gypsy Winch Model AMD-865 Coast Guard Technical Publication (TP) 3456, 2001, Ship Information Book, Section B Coast Guard Technical Publication (TP) 3478, Dec 2020, Manufacturer's Instruction Book-SWBS
Group(s) 324 Coast Guard Technical Publication (TP) 3483, SWBS Groups 580-583, Feb 2012, Vertical Capstan Coast Guard Technical Publication (TP) 5415, SWBS 581-A, Mar 2013, Anchor Winch - Model 525-
HAW
Fire Prevention and Response Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes vii (Rev-2)
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0740, 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC Electrical Motors
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior
Deck Covering Systems
OTHER REFERENCES
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System
Components - Health Effects American Society for Testing and Materials (ASTM) International F1508, 2021, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and
Welding End American Society of Mechanical Engineers (ASME) B16.34, 2025, Valves-Flanged, Threaded, and
Welding End ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health
Standards for Shipyard Employment viii (Rev-2)
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2013, Occupational Safety and Health Standards for Shipyard Employment
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment
Commercial Item Description (CID) A-A-59316, 2003, Abrasive Materials for Blasting Federal Specification (Fed Spec) DDD-C-95, Mar 1972, Carpets and Rugs, Wool, Nylon, Acrylic, Modacrylic Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2019 Edition, Pressure Testing Of Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2022 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2019 Edition, Bronze Gate, Globe, Angle and Check Valves MIL-C-81309F, May 2005, Corrosion Preventive Compounds, Water Displacing, Ultra-Thin Film MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of
Reliability Is Required MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cutback, Cold-Application National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2017, Guidelines for
Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications
NAVSEA 803-6397268, Rev B, Doors Watertight, Quick Acting Arrangement NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and
Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and
Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and
Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) 2006, Joint Surface Preparation
Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning Underwriters Laboratories Inc. (UL) 489, May 2016, Molded Case Circuit Breaker ix (Rev-2)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
20 N Parts Kit, Boat Davit 5-
Year Inspection/Overhaul
NSN: 2030-01-F18-5589 PN:
18379
1 ea 22,369.00
21 N **Release Hook Model No. CSRH-50 6E888 (Cage 50194)
2 ea. 8,000.00
35 N Rope, Wire NSN: 4010-01-690-6075 PN:
CGWR1500637BCSS
1 ea. 3,423.52
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter x (Rev-2)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
17 Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift
18 Vertical Capstan, Inspect and Service
20 Single Point Davit, Inspect and Service
21 Hydraulic Release Pelican Hook, Inspect and Service - Tender
34 Mechanical Chain Stoppers, Inspect and Service
35 Anchor Winch, Inspect and Service - Barge
36 Traction Winches, Inspect and Service - Barge
37 Gypsy Winches (Appleton Model AMD-865), Overhaul - Barge
40 Deck Covering, Electrical Matting, Renew xi (Rev-2)
PRINCIPAL CHARACTERISTICS - TUG, ICEBREAKING
140’ WTGB (TUG, ICEBREAKING)
PHYSICAL
Length overall 140' 0" Length between perpendiculars 130' 0" Breadth, extreme 37' 7-1/4" Depth, molded 18' 2-3/8" Frame spacing 1' 6" Full load (Winter) draft (at ) 12' 1-1/2" Full load (winter) displacement 687 Long tons (LT) Full load (winter) center of gravity Above base (kg) 13' 1" Full load trimming moment (forward) 75.6 Ft-LT Min. operating condition draft (at ) 11' 6-3/8" Min. operating condition displacement 640 Long tons Min. operating condition center of gravity
Above base (kg) 13' 4-1/4" Min. operating condition trimming moment
Forward 76.8 Ft-LT Height of vessel above DWL Approx. 62' 0"
MACHINERY
Main Propulsion Engine Type Diesel-electric Number of units: 2 Total shaft horsepower: 2500 Propeller Number of propellers 1 Number of blades 4 Diameter of propeller 8' 6" Pitch Fixed
NOTE
Stability values above are for representative tug. Draft and longitudinal lever values provided above are for tugs in fresh water. Longitudinal lever values are provided to adjust tug's design drag of 1.0 feet by the stern.
xii (Rev-2)
PRINCIPAL CHARACTERISTICS - BARGE
120' CGB, BARGE
PHYSICAL
Length overall 125' 0" Breadth, extreme 52' 0" Frame spacing 1' 0" Full load draft 5' 7" Full load displacement 690 Long tons
DIESEL GENERATORS
Number of units 2 Rated power 75 kw, 450 V, 3 Ph
DIESEL HYDRAULIC POWER UNIT
Number of units 2 Rated power 75 kw, 450 V, 3 Ph
BOW THRUSTER
Number of units 1
PROPELLERS
Type Vertical Mount in Recessed Tunnel Number 1 Number of blades 3 Diameter 12"
1 (Rev-2)
00000_0725_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-2)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.
3.2 Contractor-provided fire extinguishers. The Contractor must provide portable fire extinguishers.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3 (Rev-2)
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Strenx 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Strenx 900, all welding procedures and welder qualifications for welding Strenx 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.
3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.
3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.
4 (Rev-2)
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Strenx 900 are considered the same as those for welding HY-130.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
5 (Rev-2) ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-2)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK
ITEM #
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
7 (Rev-2)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL # WORK
ITEM # WORK ITEM TITLE
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER
COAT, BARRIER COAT, TOP
COAT, ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFAC
E
AMBIEN
T
ΔT
| DP -
SURFACE |
8 (Rev-2)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-2)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
10 (Rev-2)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK
ITEM #
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-2)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
COATING MFG PRODUCT NAME BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-2)
4.2 Tank and Void Assessment form.
13 (Rev-2)
14 (Rev-2)
55500_ACC_0323_IBCT
WORK ITEM 1: Fire Prevention Requirements «TYPE»
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to minimize shipboard fire risk and to clarify the Contractors’ role in fire prevention and response.
NOTE
This work item is not separately priced. Factor fire prevention and response costs into bid of affected work items.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire
Prevention and Response
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 Fire Plan. The Contractor must develop and implement a written fire plan in accordance SFLC Std Spec 5550. The Contractors Fire Plan must address Fire Protection and Response specifics as required in this Work Item.
3.1.1 The availability’s specific Fire Plan must always address the following:
• material condition and fire protection boundary obstruction mitigations
• inoperable fittings log
15 (Rev-2)
• fire alarms
• firefighting equipment disposition
3.1.2 The Fire Plan must also address the following:
• fire protection system status
• communication links
• temporary services
• power disconnects
• fire prevention and safety inspections
3.2 Fire Prevention Responsible Party. The Contractor must appoint a Fire Prevention Responsible Party (FPRP) who acts as the Contractor’s Responsible Person for fire prevention concerns during the entire availability.
3.3 Fire Prevention and Response Conference. The Contractor must participate in the Fire Prevention and Response Conference as required in Std Spec 5550, paragraph 3.12. The participants must address the contents of SFLC Std Spec 5550, paragraph 3.12.1, as applicable.
3.4 Fire Responsibility Familiarization Tour and Initial Inspection. The Contractor must participate in the Fire Responsibility Familiarization Tour and Initial Inspection as required in Std Spec 5550, paragraphs
3.12.2 through 3.12.4.
3.5 Material Condition and Fire Protection Boundary Obstruction Mitigation Requirements. The Contractor must conform to all material condition and fire protection boundary obstruction mitigation requirements detailed in SFLC Std Spec 5550, paragraph 3.2.
3.6 Inoperable Fittings Log Requirements. The Contractor must conform to all inoperable fittings log requirements detailed in SFLC Std Spec 5550, paragraph 3.3.
3.6.1 The Contractor must maintain an Inoperable Fittings log. The logs must contain the same information as a Damage Control Closure Log found in Appendix A of SFLC Std Spec 5550. The log must remain at the access point of the vessel available for inspection or use by authorized personnel, i.e., casualty response. Deliver all logs to the CG when requested and at the end of the availability.
3.7 Fire Prevention Service Particulars. The Contractor must conform to the below listed fire prevention service requirements, in accordance with SFLC Std Spec 5550.
TABLE 1 – FIRE PREVENTION SERVICE SELECTION
*SUB-
PARAGRAPH TITLE
Y/N Guidance/suggested use (see Fire Prevention WI Companion
Doc for more commentary).
3.4 Fire prevention system status N
3.4.1 Temporary firefighting system proposal N
3.4.2 Emergent firefighting system inoperability
approval and notification
N
3.4.3 “Disabled equipment” signage for disabled initial responder equipment
N
3.4.4 Firefighting system inoperability allowance for
removed hazards
N
16 (Rev-2)
*SUB-
PARAGRAPH TITLE
Y/N Guidance/suggested use (see Fire Prevention WI Companion
Doc for more commentary).
3.4.5 Maintain sprinkling zone operability N
3.4.6 including all subparagaphs
Hazard mitigation for maintenance of fixed extinguishing systems
N
3.4.7 Procedure implementation for enabling/disabling
fire suppression systems
N
3.4.8 Portable water pumping requirement for vessels
w/o installed capability
N
3.4.9 Limitations on operation of major machinery
while firefighting systems are offline
N
3.4.10 Liquid fuel pumping requirement for operational
permanent or temporary firefighting systems
N
3.4.11 Mechanical AFFF equipment must be available
to initial responders in compartments with risk of flammable/combustible liquid spillage
N
3.4.12 including all subparagraphs
Portable fire extinguisher requirements N
3.4.13 Hose and reel protection N
3.4.14 including all subparagraphs
Drydock firefighting requirements N
3.4.15 Fire protection system status in Fire Plan N
3.5 Fire response related communication links in
Fire Plan N
3.6 Fire response related temporary services in Fire
Plan
N
3.6.1 Minimize downtime of fixed extinguishing
systems
N
3.6.2 through 3.6.10
Firemain and related equipment requirements N
3.6.11 Permanent lighting requirements Y
3.6.12 including all subparagraphs
Temporary lighting requirements Y
3.6.13 Electrical power, firefighting water, and lighting
source location and testing identified in Fire Plan
N
3.7 including all subparagraphs
Fire alarm requirements Y
3.8 Shore power manual disconnect locations
identified in Fire Plan
Y
3.9 Other power manual disconnect locations
identified in the Fire Plan
N
3.10 including subparagraph
Vessel firefighting equipment placement and disposition info in Fire Plan
Y
3.11 Fire prevention and safety inspections in Fire
Plan
Y
3.11.1 Initial and daily inspection requirements Y
3.11.2 Additional details in fire inspection reports Y
*Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 5550.
17 (Rev-2)
3.5 Extended fire prevention services. If the performance period of the contract is extended by the KO, the contractor must continue to provide all fire prevention services as specified herein for the extension period.
4. NOTES
This section is not applicable to this work item.
18 (Rev-2)
12300_MWC_0917_140WTGB
WORK ITEM 2: Tank (Water Mist), Clean And Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 - TANKS
TYPE OF TANK LOCATION CAPACITY - 100%
(GALLONS)
LOW SUCTION
(GALLONS)
Water Mist 4-24-1-W 1,261 100
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 140-WTGB 123-2, Rev B, Structural Mods Incidental to Water Mist Tank
4-24-1-W Coast Guard Drawing 140-WTGB 555-2, Rev C, Water Mist System Installation A&D Coast Guard Drawing 140-WTGB 555-4, Rev C, Water Mist System Diagram Coast Guard Drawing 140-WTGB 801-3, Rev -, Booklet of General Plans
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
19 (Rev-2)
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
•…