This document is a detailed cost estimate and work breakdown structure (WBS) for two bathroom renovation projects at the Boncompagni Community Center (BCC) and a secondary facility (MSB).
The BCC project encompasses comprehensive renovation of multiple bathroom areas including women's, ADA-compliant, men's, and charforce rooms, plus corridor modifications and office conversion. Work is organized into thirteen major categories: demolition and removal (Section A), framing and partitions (Section B), plumbing with full replacement systems (Section C), electrical work (Section D), HVAC and ventilation including a MOBAS RT hydronic system (Section E), floor and wall finishes using ceramic stoneware tiles (Section F), suspended ceiling structures with two-level design (Section G), fixtures and accessories (Section H), MEP coordination and penetrations (Section I), painting and sealants (Section L), and site services with compliance and documentation (Section M). All line items are currently priced at 0.00€, indicating this is a template requiring unit price completion. Quantities are specified by lump sum, square meters, or individual units as appropriate for each work item.
The MSB project follows a similar structure with demolition (Section N), framing and partitions including new masonry walls and infill construction (Section O), complete plumbing systems (Section P), electrical modifications (Section Q), mechanical ventilation (Section R), finishes with ceramic tiles (Section S), fixtures and accessories (Sections T), painting and sealants (Section U), site services (Section V), and safety costs per Italian Legislative Decree 81/2008 (Section Z). Both projects require COR (Contracting Officer Representative) concurrence on materials, colors, and technical specifications. All subtotals currently display 0.00€ pending unit price inputs, with Grand Total and MSB Total fields prepared for final summation once pricing is provided.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers - 191T7026Q0024.pdf | ||
| Attachment 1 - Techincal Specifications.pdf | ||
| RFQ 191T7026Q0024.pdf | ||
| Attachment 3 - Drawings.pdf | ||
| SF-1449 - 191T7026Q0024.pdf | ||
| Cover Letter - 191T7026Q0024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Code Work Description Unit Qty Unit Price (€) Total (€)
A1.01 Removal of existing fixtures (wc, shower, basins, lights, ecc), doors, cabinets. partition, wall tiles incl.disposal
A1.02 To accommodate the HVAC hydronic box installation, retain the existing false ceiling; provide only a localized opening sized for the hydronic box with reinforced blocking and trim, preserving original elevations.
A1.03 Demolish and removal of the existing floor tiles with demolition of the screed up to cm 10 of entire area
A1.04 Disconnect and permanently cap the gas pipe stub-out from the lower level that currently terminates within the women's restroom. Ensure proper capping and sealing in compliance with local gas codes.
A1.05 Remove existing ceiling exhaust/ventilation unit incl. grille and duct stub — Women's Bathroom
A1.06 Create a partition to create singular wc stall in front of the entrance
0.00 €
A2.01
Demolition of existing closet/niche: partitions, doors, equipment incl. disposal. Removal of the existing carpet tiles and floor saw-cut for LAN cable bundle relocation to conduit in corridor wall with accessible junction box. Junction box will be recessed in the wall by the corridor. The new location will be concurred with the COR. Relocation of electrical transformer to corridor ceiling plenum incl.
hardware and safety blocking and extending the walkway in the false ceiling to accommodate the transformer. Construction of new perimeter wall for ADA bathroom with transit grille lump 1.00
0.00 €
A3.01
Removal of existing fixtures (wc, shower, basins, lights, ecc), doors, cabinets. partition, wall tiles incl.disposal.To accommodate the HVAC hydronic box installation, retain the existing false ceiling;
provide only a localized opening sized for the hydronic box with reinforced blocking and trim, preserving original elevations. Demolish and removal of the existing floor tiles with demolition of the screed up to cm 10 of entire area. Remove existing ceiling exhaust/ventilation unit incl. grille and duct stub — Men's Bathroom lump 1.00
0.00 €
A4.01
Demolition and relocation of corridor wall and fire door (new position for men's bathroom + charforce doors) incl. partial rebuild and painting. Including floor replacement. Removal of existing alarm devices. Relocation of fire alarm horn/strobe to new position past door incl. re-wiring and testing. 45-degree beveled cut at end segment of corridor wall interfacing with event hall — subject to COR concurrence before proceeding. Removal and set aside for future reinstallation of existing drinking fountain by corridor incl. capping and finish restoration lump 1.00
0.00 €
A5.01 Removal of all existing fixtures (wc, shower, basins, lights, cabinets, doors, ecc), removal of existing wall tiles incl. disposal. Removal of decommissioned plumbing and electrical. Demolish and removal of the existing floor tiles with demolition of the screed up to cm 10 of entire area lump 1.00
0.00 €
A6.01 Reconstruction and refinish plaster on all walls and ceiling where tiles have been removed — all areas involved in the project. Apply primer + rough coat + finish coat, ready for tile or paint lump 1.00
0.00 €
A7.01 New mortar bed with engineered drain slopes — all bathrooms (women's, ADA, men's, charforce).
Liquid waterproof membrane + primer under all bathrooms' tile floors (women's, ADA, men's, charforce) lump 1.00
0.00 €
Subtotal A1 A2 — ADA Bathroom (former tech closet / LAN niche)
Subtotal A2 A3 — Men's Bathroom (existing: 3 WC + 2 urinals)
Subtotal A3 A4 — Corridor and Charforce room: demolitions and relocations
BONCOMPAGNI COMMUNITY CENTER (BCC) — BATHROOMS RENOVATION
Women's Bathroom (3 stalls) | ADA Bathroom (new) | Men's Bathroom (3 stalls+1 urinal) | Charforce Room (new) | Corridor | Office Conversion
A — DEMOLITION, REMOVAL AND CONSTRUCTION
A1 — Women's Bathroom (existing: 2 WC + shower) lump 1.00
Subtotal A7
Subtotal A4 A5 — Conversion of end-of-corridor bathroom to office/storage
Subtotal A5 A6 — Wall and ceiling plaster reconstruction
Subtotal A6 A7 — Mortar bed, waterproofing and slopes (bathrooms and charforce)
B1.01
Supply and install floor-to-ceiling WC partitions - Women's bathroom:
Full height: about maximum of 2500 mm with minimum floor clearance.
Panels: 30 mm thick melamine-coated chipboard panels.
All visible edges should be rounded ABS edges (radius 2 mm), impact-resistant and safety-oriented.
Profiles: All profiles in anodized aluminum.
Ceiling connections made with aluminum profiles.
Wall connections made with U-shaped aluminum profiles creating an elegant shadow gap.
Floor and ceiling joints made with aluminum profiles.
Doors: Made of the same material as the front wall, flush-mounted and therefore always aligned on the external side of the cubicle regardless of the door opening direction.
Rubber seals to ensure silent closing.
On the hinge side, the gap should be sealed with a grooved rubber profile.
Hinges: Special three-wing aluminum hinges (Ø 20 mm, length 145 mm), with stainless steel shaft, including stainless steel pin.
One spring hinge ensures automatic door closing or opening.
Locks and hardware: Single-turn lock with GS 25 aluminum handle, Ø 25 mm, length 80 mm.
Integrated free/occupied indicator, mechanical version selectable.
Colors: Walls and doors color should be submitted to the C.O.R.
Profiles, hinges, hardware, feet, and accessories in anodized aluminum.
Composition 1 (left side from the entrance): 1 front wall, length 2060 mm ;2 doors, width 700 mm, height 2100 mm, with upper fixed cut on site panels; 1 partition wall, length 1600 mm between the stalls; 2 aluminum coat hooks/door stops; 2 HPL shelves (1 per each stall) Composition 2: 1 front wall, length 1000 mm; 1 door, width 700 mm, height 2100 mm, with upper fixed panel;1 aluminum coat hook/door stop; 1 HPL shelf lump 1.00
B1.02
Supply and install floor-to-ceiling WC partitions – Men’s bathroom:
Full height: about maximum of 2500 mm with minimum floor clearance.
Panels: 30 mm thick melamine-coated chipboard panels.
All visible edges should be rounded ABS edges (radius 2 mm), impact-resistant and safety-oriented.
Profiles: All profiles in anodized aluminum.
Ceiling connections made with aluminum profiles.
Wall connections made with U-shaped aluminum profiles creating an elegant shadow gap.
Floor and ceiling joints made with aluminum profiles.
Doors: Made of the same material as the front wall, flush-mounted and therefore always aligned on the external side of the cubicle regardless of the door opening direction.
Rubber seals to ensure silent closing.
On the hinge side, the gap should be sealed with a grooved rubber profile.
Hinges: Special three-wing aluminum hinges (Ø 20 mm, length 145 mm), with stainless steel shaft, including stainless steel pin.
One spring hinge ensures automatic door closing or opening.
Locks and hardware: Single-turn lock with GS 25 aluminum handle, Ø 25 mm, length 80 mm.
Integrated free/occupied indicator, mechanical version selectable.
Colors: Walls and doors color should be submitted to the C.O.R.
Profiles, hinges, hardware, feet, and accessories in anodized aluminum.
Composition: 1 front wall, length 2900 mm; 3 doors, width 700 mm, height 2100 mm, with upper fixed panels;• 2 partition walls, length 1800 mm; 3 aluminum coat hooks/door stops; 3 HPL shelves (one per each stall) lump 1.00
B1.03 Supply and install urinal privacy partition — Men's Bathroom ea 1.00
B1.04 Supply and install new laminated access door with frame, lock, handle and hinges — Women's Bathroom. Size 80×210 cm. Incl. air transfer grille at bottom (max air speed 2 m/s). ea 1.00
B1.05 Supply and install new laminated access door with frame, lock, handle and hinges — Men's Bathroom. Size 80×210 cm. Incl. air transfer grille at bottom (max air speed 2 m/s). ea 1.00
B1.06 ADA Bathroom door with ventilation louver 36"×84", outswing ea 1.00
0.00 €
B2.01 Construction of new perimeter wall for Charforce room. Wall opening in corridor for Charforce Room pocket door lump 1.00
B2.02 Supply and install a pocket door 40" incl. ventilation louver for Charforce Room ea 1.00
0.00 €
B3.01 Create interior partition wall for storage room and apply skim coat to the walls and ceiling. Supply and install new entry door lump 1.00
B3.02 Supply and install new laminated access door with frame, lock, handle and hinges. Size 80×210
cm. Incl. air transfer grille at bottom (max air speed 2 m/s). lump 1.00
0.00 €
B — FRAMING, WALLS & PARTITIONS
B1 — Floor-to-ceiling WC partitions and doors
Subtotal B1 B2 — Charforce Room
Subtotal B2 B3 — Office/storage build-out (former end-of-corridor bathroom)
Subtotal B3
C1.01
Supply, install and connect water distribution manifold for Women's zone: serving women's, ADA, hall sink. With panelable box included.
Supply and install water distribution manifold for Men's zone: serving Men's and Charforce room.
With panelable box included. Supply and install 2×40 liter water heaters recessed in ceiling plenum incl. Hardware and blocking. With dedicated switch. Supply and install 2× accessible inspection/cleanout access panels in suspended ceiling for water heaters (one per zone) lump 1.00
C1.02 Removal and disposal of existing water heaters ea 2.00
C1.03
Supply and install new plumbing system made by multilayers pipe to feed flushing mechanism and drainage systems in grey PVC and diameter no less than 40 mm for faucets and no less than 90 mm for water closet, new water distribution manifold pre-assembled in boxes with individual shut-off valves. Connection for all fixtures involved lump 1.00
0.00 €
C2.01 Supply, install and connect wall-mounted monolithic sink 83"×16" incl. mounting hardware and under LED light ea 1.00
C2.02 Supply, install and connect sensor-activated (touchless) faucets connected to hot and cold supply ea 3.00
C2.03 Spply and install an Oval mirror 71"×31" ea 1.00 C2.04 Supply and install a mirror 83"×31" up to vanity zone ea 1.00 C2.05 Supply, install and connect one-piece WC with exposed flush tank and cover ea 3.00 C2.06 Supply, install and connect hand-held bidet sprayers (cold water) with holder ea 3.00
C2.07 Floor drain with channel, waterproof membrane sleeve for wet area cleanup (location will be decided with COR) ea 1.00
0.00 €
C3.01 Supply and install ADA-compliant WC at correct height with required side clearance ea 1.00 C3.02 Supply and install ADA-compliant pneumatic flush valve ea 1.00 C3.03 Supply and install ADA-compliant lavatory with shelf (knee clearance below, rim at 34") ea 1.00
C3.04 Supply, install and connect ADA-compliant backlit LED mirror — ADA Bathroom (tilting, correct mounting height)
C3.05 Supply and install lever-handle faucet with insulated (soft anti-scald) drain and P-trap cover ea 1.00 C3.06 Supply and install and connect Hand-held bidet sprayer ea 1.00
C3.07 Supply and install ADA-compliant grab bar set (side + rear at WC) — stainless Ø1.5" wall-reinforced lump 1.00
C3.08 Supply and install ADA-compliant grab bar at sink area — stainless steel Ø38mm, slip-resistant, per ADA Standards Section 606. Wall blocking provided prior to tiling. ea 1.00
C3.09 Supply and install floor drain with channel and waterproof membrane sleeve ea 1.00
0.00 €
C4.01 Supply and install Wall-mounted monolithic sink 83"×16" incl. mounting hardware and under LED light ea 1.00
C4.02 Supply and install sensor-activated (touchless) faucets connected to supply ea 3.00 C4.03 Supply and install wall-hung urinal with integral flush tank incl. fittings ea 1.00 C4.04 Supply and install a mirror 83"×31" up to the vanity ea 1.00 C4.05 Supply and install one-piece WC with exposed flush tank ea 3.00 C4.06 Supply and install hand-held bidet sprayers (cold water) with holder ea 3.00 C4.07 Floor drain with channel and waterproof membrane sleeve ea 1.00
0.00 €
C5.01 Supply, install and connect mop sink with hot and cold mixing faucet incl. fittings and drain ea 1.00 C5.02 Floor drain with channel and waterproof membrane sleeve ea 1.00
0.00 €
C6.01 Hot and cold supply and drain for hall sink — connection from event hall wall side lump 1.00
0.00 €
Subtotal C1 C2 — Women's Bathroom
Subtotal C2
C — PLUMBING (full replacement) C1 — Manifolds and water heaters
Subtotal C4 C5 — Charforce Room
C3 — ADA Bathroom
Subtotal C3 C4 — Men's Bathroom
Subtotal C5 C6 — Event Hall connection sink
Subtotal C6
D1.01 Modify existing electrical system to feed electrical features. Feeding lines must be hook-up under a 10 mA GFI breaker (16 Amps. 10 mA GFI breaker is part of the furniture to be supplied). All samples should be submitted to the C.O.R.
D1.02 Supply and install light switches in each room entrance, including cover plates, mechanisms, and all necessary components for complete installation
D1.03 Supply and install two (2) duplex electrical power outlets per bathroom (4 total: 1 UNEL outlet+10/16A outlet), complete with wiring (Women's, ADA, Men's = 6 total)
D1.04 Install new lighting system recessed into the new false ceiling panel. The exhaust fan shall be activated by the same switch of lighting and it shall turn off after at least 5 minutes from the lights shut off. Sample should be submitted to the C.O.R.
D1.05 Supply and install warm white LED strip 2700K–3000K high-density (min 120 LEDs/lf, CRI>90) in cove channel (in the center and by the border) — double run: 1 strip facing up (ceiling wash) + 1 strip facing down (partition base glow) — all bathrooms
D1.06 Supply and install anodized aluminum LED channel profile with opal diffuser lens recessed into cove — all bathrooms
D1.07 Wiring from LED drivers to existing electrical panel incl. dedicated circuit breaker per bathroom
D1.08
Supply, install and connect two recessed IP65-rated LED downlights, complete with dedicated switching control, to be installed above the washbasin area. The item shall include all electrical connections, wiring, fixings, testing, commissioning, and all accessories necessary for a complete and operational installation.
D1.09 Supply and install strip LED lights all around the partition. By the top and by the bottom. Supply and install LED strip lights below the sinks. All LED lights should be activated by the central lights
D1.10 Supply and install in new electrical panel: 6A magnetothermal-differential circuit breaker + kWh energy meter + weekly programmable timer switch — one set per bathroom (Women's, ADA, Men's, Charforce)
0.00 €
D2.01
Provide, install and connect recessed IP65-rated LED spotlights within the suspended ceiling. The item shall include all electrical connections, wiring, fixings, testing, commissioning, and all accessories necessary for a complete and operational installation.:
• Women’s bathroom eight (8)
• ADA’s Bathroom two (2)
• Men’s Bathroom eight (8)
• Charforce room one (1)
D2.02 Supply, install an Emergency exit light in each room
0.00 €
D3.01 Replacement recessed lighting for new office and storage lump 1.00
0.00 €
E1.01 Supply, install and connect to existing system 4-way ceiling cassette hydronic fan coil unit — complete with flush ceiling panel, remote control, and electrical kit ea 2.00
E1.02 Mechanical installation: ceiling mounting with support brackets, connection to existing 2-pipe hydronic circuit (supply + return), 2-way motorized valve, fittings, and pipe insulation ea 2.00
E1.03 Electrical connection: power supply, fan motor wiring, connection to wall thermostat / BMS, control board wiring ea 2.00
E1.04 Commissioning, startup, and functional test — all 4 fan speeds, cooling and heating modes ea 2.00
E1.05 Rebalancing of existing hydronic circuit after addition of 2 new units — verify system pressures and flow rates lump 1.00
E1.06 Relocate the fan coil cabinet currently located in the existing women's restroom to the new room at the end of the corridor. This work includes preparation for fan coil pipe risers and condensate drain drop with two (2) electrical conduits.
lump 1.00
E1.07
Supply and install one (1) new built-in axial centrifugal fans in self-extinguishing resin, 250m3/h create a new ducted system for air exhaust, with all the aluminum vent pipes necessary for ducting, the intake grilles (one in each bathroom and one in the charforce room) recessed in the false ceiling panels and connect this to the new air outlet grille, and provide to connect it to the electrical system and air exhaust system, including timer. (One for women's bathroom to serve ADA bathrooms too and one for Man's bathroom to serve Charforce room also) All samples should be submitted to the C.O.R.
lump 1.00
0.00 €
E2.01 Supply and install New exhaust/supply ventilation system per stall at Women's Bathroom (3 stalls), using existing shafts but replacing ducts
E2.02 Supply and install New exhaust/supply ventilation per stall — Men's Bathroom (3 stalls), using existing shafts but replacing ducts
E2.03 Connect ADA Bathroom to the exhaust ventilation system of women's bathroom E2.04 Connect Charforce room to the exhaust ventilation of men's bathroom
0.00 €
Ceiling indirect LED cove lighting system - warm white LED strip in cove channel (light washes ceiling up and glows down) (Women's and Men's Bathroom)
Subtotal D1 D2 — Bathroom lighting lump 1.00
D — ELECTRICAL
D1 — General and panel lump 1.00
Subtotal E1 E2 — Mechanical ventilation bathrooms (new individual-stall system) lump 1.00
Subtotal D2 D3— Office lighting (former end-of-corridor bathroom)
Subtotal D3
E — HVAC & VENTILATION
E1 — HVAC replacement (MOBAS RT hydronic system)
Subtotal E2
F1.01 Supply and install ceramic stoneware tiles 120x120cm 48"x48" floor tile R10 grip — Women's Bathroom. On mortar bed: C2TE adhesive, grout, SS edge trims, grout color TBD with COR Sqm 21.00
F1.02 Supply and install ceramic stoneware tiles 120x120cm 48"×48" wall tile — max height cm 240.
Adhesive, grout, edge profiles. Grout color TBD with COR — Women's Bathroom Sqm 55.00
F1.03 Supply and install ceramic stoneware tiles 120x120cm 48"x48" floor tile R10 grip — ADA's Bathroom. On mortar bed: C2TE adhesive, grout, SS edge trims, grout color TBD with COR Sqm 7.00
F1.04 Supply and install ceramic stoneware tiles 120x120cm 48"×48" wall tile — max height cm 240.
Adhesive, grout, edge profiles. Grout color TBD with COR — ADA's Bathroom Sqm 22.00
F1.05 Supply and install ceramic stoneware tiles 120x120cm 48"x48" floor tile R10 grip - Men's Bathroom.
On mortar bed: C2TE adhesive, grout, SS edge trims, grout color TBD with COR Sqm 19.00
F1.06 Supply and install ceramic stoneware tiles 120x120cm 48"×48" wall tile — max height cm240.
Adhesive, grout, edge profiles. Grout color TBD with COR — Men's Bathroom Sqm 40.00
F1.07
Supply and installation of resilient flooring finish, including all necessary substrate preparation works to receive the new floor finish. The item shall include cleaning of the existing substrate, preparation of the existing substrate including localized repairs as required, application of primer where necessary, provision and application of self-levelling compound to achieve a smooth, level and uniform surface suitable for the installation of the new flooring finish, supply and application of manufacturer-approved adhesive, installation of resilient flooring, cutting, fitting, trimming, joints, perimeter finishing, transitions to adjacent floor finishes, and all accessories necessary for a complete installation in accordance with the manufacturer's specifications and project requirements.
Sqm 25.00
0.00 €
F2.01 Supply and install white floor tiles incl. cove base special pieces for wet area Sqm 3.00
F2.02 Supply and install wall tiles (height 120cm) with cove base and special pieces white porcelain wall tile. Sqm 8.00
F2.03 Supply and install shelving units for cleaning supplies (2) lump 1.00
0.00 €
G1.01 Supply and install galvanized steel framing for perimeter dropped cove soffit (UD+CD 60/27 track and stud) — Women and Men bathrooms
G1.02 Supply and install 1/2" moisture-resistant drywall on cove soffit — vertical outer fascia (~10" / 25 cm drop)
G1.03 Supply and install 1/2" moisture-resistant drywall on cove soffit — horizontal soffit face (~14" / 35 cm width)
G1.04 Tape, mud, and skim coat cove soffit — all faces incl. primer coat
0.00 €
G2.01 Supply and install galvanized steel main tee and cross-tee framing for upper center ceiling plane, limited to the localized HVAC cassette openings (Women and Men Bathroom)
G2.02 Supply and install 1/2" moisture-resistant drywall on center ceiling plane incl. reinforced blocking at each cassette opening.
G2.03 Tape, mud, skim coat and prime center ceiling plane — ready for paint
0.00 €
H1.01 Supply and install Fold-out children's step stool under vanity ea 1.00 H1.02 Supply and install Toilet paper holder per WC stall ea 3.00
0.00 €
H2.01 Supply and install Wall-mounted coat hooks at ADA-compliant height ea 2.00 H2.02 Supply and install Toilet paper holder — ADA Bathroom ea 1.00
0.00 €
H3.01 Supply and install Toilet paper holder per WC stall ea 3.00
0.00 €
I1.01 Core-drill drywall for hydronic pipe penetrations (supply + return, 1-1/4" to 1-3/8" OD) + insulate bore edges
I1.02 Cut drywall openings for ceiling exhaust/supply air grilles — all bathrooms (3 grilles per bathroom)
I1.03 Supply and install flush linear or square exhaust/supply air grilles in brushed stainless steel — set flush with center ceiling plane
I1.04 Miscellaneous patching and skim coat at unforeseen penetrations — allowance
0.00 €
Subtotal F1 F2 — Charforce Room
Subtotal F2
F — FINISHES: FLOORS & WALL TILE
F1 — Ceramic Stoneware
Subtotal G1 G2 — Upper center ceiling plane (HVAC cassette zone) lump 1.00
G — CEILINGS AND NEW TWO-LEVEL SUSPENDED CEILING STRUCTURE
G1 — 2 Bathrooms Perimeter dropped cove soffit lump 1.00
Subtotal H1 H2 — ADA Bathroom
Subtotal H2
Subtotal G2
H — FIXTURES & ACCESSORIES
H1 — Women's Bathroom
Subtotal I
H3 — Men's Bathroom
Subtotal H3
I — PENETRATIONS, MEP COORDINATION & GRILLES
ea 1.00
L.01
Refinishing and painting the walls above tiles with transpiring and washable water-based paint for interior surfaces, based on vinyl copolymers in emulsion, selected pigments and high coverage mineral fillers. The color will be submitted to C.O.R. Perimeter silicone sealant (floor-wall joints, sinks, fixtures, floor drains) lump 1.00
0.00 €
L1.01
Apply waterproof anti-mold paint, pure white, 2 coats, center ceiling plane and all interior cove faces in all bathrooms. Apply waterproof anti-mold paint — outer vertical cove fascia (wall-facing side).
Apply white mold-resistant silicone sealant at cove-to-wall and cove-to-ceiling-plane joints. Repair the portions of the false ceiling damaged during demolition works — skim coat + white paint walls and ceiling lump 1.00
0.00 €
M1.01 Site protection: dust barriers, floor protection films, temporary enclosures to isolate active event hall and corridor during construction. Final site clean-up. Hydraulic pressure tests, and all system tests lump 1.00
0.00 €
0.00 €
L — PAINTING & SEALANTS
Subtotal L L1 — Ceiling and soffit painting with waterproof anti-mold paint
Subtotal L1
M — SITE SERVICES, COMPLIANCE & DOCUMENTATION
Subtotal M
BCC TOTAL
Code Work Description Unit Qty Unit Price (€) Total (€)
N1.01 Removal of existing partition walls N1.02 Removal of all existing fixtures (WC, lavatories, shower, lights, cabinets) N1.03 Removal of existing floor and wall tile incl. disposal N1.04 Removal of existing doors and frames (historical entry door excluded) N1.05 Demolish and remove floor screed to 10 cm depth — full area N1.06 Remove all existing piping, including unused lines N1.07 Removal and disposal of the existing radiators
N2 — Men's Bathroom N2.01 Demolish partition wall between existing women's and men's bathroom N2.02 Removal of existing partition walls
N2.03 Removal of all existing fixtures (WC, urinal, lavatories, lights, cabinets, water heater) incl. disposal
N2.04 Removal of existing floor and wall tile incl. disposal N2.05 Removal of existing doors and frames (historical entry door excluded) N2.06 Demolish and remove floor screed to 10 cm depth — full area N2.07 Removal and disposal of the existing radiators
N3 - Storage conversion
N3.01 Demolish full partition wall between Men's Bathroom and storage room incl. all finishes, plaster, and debris removal. Structural verification required before proceeding
N3.02 Demolish existing partition wall between Women's and Men's Bathroom in current position incl. all finishes, tile backing, and MEP within wall
N3.03 Remove existing storage room floor finish and screed to 10 cm depth
N3.04 Remove all existing storage room wall finishes, ceiling, and MEP installations (wiring, fixtures, distribution board if present)
0.00 €
O1.01
Supply and install floor-to-ceiling WC partitions (max 10 cm by the floor and by the hard ceiling) with 30 mm thick melamine-coated chipboard panels, with doors in the same finishes, flush-mounted and therefore always aligned on the external side of the cubicle regardless of the door opening direction.
All profiles in anodized aluminum. Ceiling connections made with aluminum profiles.
Rubber seals to ensure silent closing.
On the hinge side, the gap should be sealed with a grooved rubber profile.
Including hinges and one spring hinge ensures automatic door closing or opening.
With Locks and hardware, integrated free/occupied indicator.
Material, walls and doors color should be submitted to the C.O.R.
Composition:
1 front wall, length 3000 mm 3 doors, width 700 mm, height 2100 mm, with upper fixed panel 2 partition walls, length 2300 mm 3 aluminum coat hooks/door stops 3 HPL (High-Pressure Laminate) shelves LED installed to the bottom and to the top included Provide and install a custom-made partition adjacent to the window to complete the cubicle configuration and ensure adequate separation between the stalls.
lump 1.00
O1.02
Supply and install floor-to-ceiling WC partitions (max 10 cm by the floor and by the hard ceiling) with 30 mm thick melamine-coated chipboard panels, with doors in the same finishes, flush-mounted and therefore always aligned on the external side of the cubicle regardless of the door opening direction.
All profiles in anodized aluminum. Ceiling connections made with aluminum profiles.
Rubber seals to ensure silent closing.
On the hinge side, the gap should be sealed with a grooved rubber profile.
Including hinges and one spring hinge ensures automatic door closing or opening.
With Locks and hardware, integrated free/occupied indicator.
Material, walls and doors color should be submitted to the C.O.R.
Composition:
1 front wall, length 2650 mm 1 door width 1100 mm, height 2100 mm, with upper fixed panel 1 front wall length 1150mm 1 partition wall, length 2000 mm 1 door width 1100 mm, height 2100 mm, with upper fixed panel 2 aluminum coat hooks/door stops 1 HPL (High-Pressure Laminate) shelves LED installed to the bottom and to the top included lump 1.00
0.00 € lump 1.00
Subtotal N1+N2+N3
MSB BATHROOMS RENOVATION
Women's Bathroom (3 stalls) | Men's Bathroom (3 stalls) | - GSO side
N — DEMOLITION & REMOVAL
N1 — Women's Bathroom
O — FRAMING, WALLS & PARTITIONS
O1 — WC Partitions
Subtotal O1
O2.01
Supply and installation of an internal partition wall between the two restrooms subject to renovation, constructed using hollow/cellular masonry blocks with the following dimensions: Height: 25 cm, Width: 25 cm, Length: 25 cm. Wall Lenght 480cm Height 310cm The wall shall be built using hollow clay blocks or autoclaved aerated concrete (AAC) blocks, laid in staggered horizontal courses, with bastard cement mortar dosed at 350 kg of Portland cement 32.5 R per cubic meter of screened sand (type M5 or M10 per UNI EN 998-2), with the addition of natural hydraulic lime in a 1:1:6 ratio (cement : lime : sand), suitable for ensuring adequate workability, adhesion, and mechanical strength for use in humid environments such as restrooms. Mortar joint thickness shall be approximately 10 mm minimum, both horizontally and vertically.
The new wall shall be bonded and tied into the existing perimeter masonry by means of vertical chases cut into the existing walls for toothed block insertion.
The wall shall extend from the floor to the roof slab, with the upper head joint sealed using expansive cement mortar or high-density polyurethane foam, to ensure continuity and the absence of acoustic bridges.
Included in this line item is the supply and installation of smooth finish plaster on both faces of the wall, up to the level of the ceramic tile cladding, comprising the following layers:
Scratch coat (first layer): cement and coarse sand mortar, applied by spray or by hand, approximately 5 mm thick, serving as a bonding layer;
Brown coat (second layer): bastard cement-lime-sand mortar, applied and leveled with a straightedge and float to a thickness of approximately 10–12 mm. Finish coat: white finish plaster, applied with a fine float and finished with a steel trowel to achieve a smooth surface ready for subsequent ceramic tile installation or painting. The lime putty finish coat shall be applied exclusively to the portion of the wall above the ceramic tile installation level. The lower portion, intended to receive ceramic tiles, shall receive only the scratch coat and brown coat, leaving the surface rough and suitable for tile adhesive bonding.
O2.02 Create counter-wall in front of existing heritage door galvanized steel stud + moisture-resistant GWB, full height, min. 3 cm air gap. Hystorical oor shall not be altered in any way
O2.03 Construction of an infill wall below the existing window(s) to accommodate the concealed WC flushing cistern, including all supporting works and infilling of a small opening/void on the perimeter wall of the Women's Bathroom
O2.04 Modify the existing window, including all necessary adjustments, to ensure full operability and unobstructed opening within the new WC stall configuration.
O2.05 Supply and install a shelf below the window at Men's bathroom
0.00 €
P1.01
Complete plumbing and sanitary system for both bathrooms (lump sum): electric water heater ≥60 L to be installed by the hard ceiling, with brackets, safety supports; multilayer hot/cold water distribution to all points; grey PVC drainage Ø≥40 mm (lavatories) and Ø≥90 mm (WC); two (2) manifolds with individual shut-off valves per fixture and inspectable panel box; two (2) wall mounted radiators connected to the existing heating network with thermostatic valves, fittings, and piping;
pressure test with signed report to the COR.
lump 1.00
0.00 €
P2.01
Supply, install and connect a double-basin vanity unit with two sinks in Dekton or Laminam material, measuring approximately ~ 472"x20" (1200 x 500 mm). Included a shelf by right side. The item shall include all necessary fixings, connections to water supply and drainage systems, sealing, testing, and all accessories required for a complete and operational installation., incl. mounting hardware and wall anchors and LED below. Sample and technical sheet to COR
P2.02 Supply, install, and connect two (2) faucets. Incl. all wiring and transformers if sensor type selected
P2.03 Supply, install, and connect one (1) utility/service faucet under vanity
P2.04 Supply and install three (3) floor mounted WC fixtures with exposed tank flush mechanism. The monobloc WC with integrated cistern shall not exceed 830 mm in height and shall be installed to maintain full operability and opening of the existing window
P2.05 Supply, install, and connect three (3) hand-held bidet sprayers (cold water) with wall-mounted holder — one per WC stall
P2.06 Supply and install one (1) floor drain with channel and waterproof membrane sleeve
0.00 €
P3.01
Supply, install and connect a double-basin vanity unit with two sinks in Dekton or Laminam material, measuring approximately ~472"x18" (1200 x 4500 mm). Included 2 shelves by the both sides. The item shall include all necessary fixings, connections to water supply and drainage systems, sealing, testing, and all accessories required for a complete and operational installation., incl. mounting hardware and wall anchors and LED below. Sample and technical sheet to COR
P3.02 Supply, install, and connect two (2) faucets. Incl. all wiring and transformers P3.03 Supply and install two (2) WC fixtures with flush mechanism — type TBD with COR
P3.04 Supply, install, and connect two (2) hand-held bidet sprayers (cold water) with wall-mounted holder
— one per WC stall
P3.05 Supply, install, and connect one (1) urinal P3.06 Supply and install one (1) floor drain with channel and waterproof membrane sleeve
O2 - Storage conversion, partion wall and infill wall lump 1.00
Subtotal P2 P3 — Men's Bathroom fixtures lump 1.00
Subtotal O2
P — PLUMBING
P1 — Supply system and shared water heater
Subtotal P1 P2 — Women's Bathroom fixtures lump 1.00
0.00 €Subtotal P3
Q1.01
Modify existing electrical system to feed all new features. All feeding lines under 10 mA GFI breaker 16A (GFI supplied). Samples to COR. The item shall include all electrical connections, wiring, fixings, testing, commissioning, and all accessories necessary for a complete and operational installation.
lump 1.00
Q1.02 Supply and install light switches in each room entrance, including cover plates, mechanisms, and all necessary components for complete installation lump 1.00
Q1.03 Supply and install two (2) duplex electrical power outlets per bathroom (4 total: 1 UNEL outlet+10/16A outlet), complete with wiring ea 4.00
Q1.04 Supply and install ceiling mounted spotlight IP65 per WC stall, and 3 for general lighting, flat ceiling, both bathrooms. Warm white 2700K–3000K, CRI>90. — allowance: 6 spots per bathroom = 12 total. Incl. back-boxes, wiring, trim rings (finish TBD with COR), connection to GFI circuit ea 12.00
Q1.05 Supply and install strip LED lights all around the perimetral wall of the partition. By the top and by the bottom. Supply and install LED strip lights below the sinks lump 1.00
Q1.06 Supply, install and connect an Emergency exit light in each bathroom ea 2.00
Q1.07 Supply and install in new electrical panel: 6A magnetothermal-differential circuit breaker + kWh energy meter + weekly programmable timer switch — one set per bathroom (Women's, Men's) lump 1.00
0.00 €
Q2.01 Supply and install a rectangular mirror up to the vanity. Women's Bathroom. Sample to COR ea 1.00 Q2.02 Supply and install a rectangular mirror un to the vanity. Men's Bathroom. Sample to COR ea 1.00
0.00 €
Q3.01 Remove all existing electrical installations in former storage room. Extend new electrical system into integrated area: wiring, circuit protection, GFI breaker, IP55 switches, lighting consistent with Men's Bathroom specification lump 1.00
0.00 €
R1.01
Supply and install one (1) new built-in axial centrifugal fans in self-extinguishing resin, 250m3/h create a new ducted system for air exhaust, with all the aluminum vent pipes necessary for ducting, the intake grilles (one in each bathroom) recessed in the false ceiling panels and connect this to the new air outlet grille, and provide to connect it to the electrical system and air exhaust system, including timer.
lump 1.00
R1.02 Cut drywall openings for ceiling exhaust/supply grilles (3 grilles each = 6 total) R1.03 Supply and install flush ceiling exhaust/supply grilles R1.04 Miscellaneous patching at unforeseen penetrations
0.00 €
S1.01 Reconstruction and refinishing of wall plaster on all walls where tiles removed — both bathrooms.
Primer + rough coat + finish coat. Surface ready for tile or paint before COR inspection lump 1.00
0.00 €
S2.01 Supply and install Ceramic stoneware floor tiles Matte R10 sized 60×60 on mortar bed: C2TE adhesive, grout, SS edge trims. Grout color TBD with COR Sqm 16.00
S2.02 Supply and install ceramic stoneware wall tiles Glossy marble effect. Thick 6mm sized 60×120 up to 300cm. C2TE adhesive, grout, edge profiles Sqm 47.00
0.00 €
S3.01 Supply and install Ceramic stoneware floor tiles Matte R10 60X60 on mortar bed: C2TE adhesive, grout, SS edge trims. Grout color TBD with COR Sqm 15.00
S3.02 Supply and install ceramic stoneware wall tiles Glossy 6mm 60×120 up to 300cm C2TE adhesive, grout, edge profiles Sqm 45.00
0.00 €
S4.01 New mortar bed with engineered drain slopes ≥1.5% toward floor drain. Liquid waterproof membrane + primer under all tile floors lump 1.00
0.00 €
Subtotal Q1 Q2 — Mirrors
Subtotal Q2
Q — ELECTRICAL
Q1 — General electrical system
Subtotal R1
S — FINISHES: FLOORS & WALL TILE
S1 — Wall plaster reconstruction
Subtotal S1 S2 — Floors and walls — Women's Bathroom
Q3 - Storage conversion
Subtotal Q3
R — MECHANICAL VENTILATION
R1 — Mechanical ventilation lump 1.00
S4 — Mortar bed, waterproofing and slopes- both bathrooms
Subtotal S4
Subtotal S2 S3 — Floors and walls — Men's Bathroom
Subtotal S3
T1.01 Supply and install one shelf close to the vanity ea 1.00 T1.02 Supply and install toilet paper holder per WC stall ea 3.00
0.00 €
T2.01 Supply and install one shelf close to the vanity ea 1.00 T2.02 Toilet paper holder per WC stall ea 2.00
0.00 €
U1.01 Paint all wall surfaces above tile height: washable mold-inhibiting interior paint U1.02 Perimeter mold-resistant silicone sealant at all floor-wall joints, fixture bases, drain surrounds
U1.03 Mold-resistant silicone sealant at all perimeter ceiling-to-wall joints
0.00 €
V1.01 Site protection, dust barriers, floor protection, temporary enclosures, adjacent active areas. Final site clean-up. Hydraulic pressure tests, and all system test lump 1.00
0.00 €
0.00 €
Z1.01
Temporary Shoring System; Working Platforms; Personal Protective Equipment (PPE); Site Perimeter Fencing; Protection of Existing Elements. All additional measures, labor, materials, and incidental work necessary to ensure full compliance with Italian Legislative Decree No. 81/2008 (Testo Unico sulla Salute e Sicurezza sul Lavoro) and its subsequent amendments and integrations, for the entire duration of the Works lump 1.00
0.00 €
T — FIXTURES & ACCESSORIES
T1 — Women's Bathroom
U — PAINTING & SEALANTS
U1 — Paint and sealants lump 1.00
Subtotal T1 T2 — Men's Bathroom
Subtotal T2
Z — SAFETY COSTS
Z1 — Safety Measures
Subtotal Z1
Grand TOTAL
Subtotal U1
V — SITE SERVICES, COMPLIANCE & DOCUMENTATION
V1 — Compliance, documentation and tests
Subtotal V1
MSB TOTAL
BOQ MSB+BCC