This solicitation and related documents outline requirements for a small business set-aside contract to provide snow removal equipment and services to the Department of the Air Force Air Combat Command. Offerors must submit pricing and technical proposals addressing the equipment to be delivered, maintenance, delivery, and pick-up plans by the deadline specified on SAM.gov. Proposals will be evaluated based on price and technical acceptability, with award going to the lowest priced technically acceptable offerors until two are identified. Pricing must remain valid for 60 days and will be analyzed for reasonableness and potential unbalanced pricing. The solicitation utilizes FAR Part 13 simplified procedures and will make award without discussions if possible.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4600-21-Q-0049

ATTACHMENT 2: Addendums to FAR 52.212-1 Instructions and FAR 52.212-2 Evaluations

ADDENDUMS 52.212-1/ 52.212-2

ADDENDUM TO 52.212-1, PROPOSAL PREPARATION INSTRUCTIONS

A. To assure timely and equitable evaluation of the proposal, the offeror must follow the instructions contained herein. The proposal must be complete, self-sufficient, and respond directly to the requirements of this solicitation. The response shall consist of two parts:

Part I – Price Part II – Technical Capability

B. The contracting officer has determined there is a high probability of adequate price competition in this acquisition. Upon examination of the initial offers, the contracting officer will review this determination and if, in the contracting officer's opinion, adequate price competition exists no additional data will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this competition the contracting officer determines that adequate price competition no longer exists; offerors may be required to submit cost data to the extent necessary for the contracting officer to determine the reasonableness and affordability of the price.

C. Quotes shall be submitted to russell.mihely@us.af.mil and anthony.wilson.2@us.af.mil no later than the deadline in the solicitation posting found on sam.gov.

D. Specific Instructions:

In order for a proposal to be considered, it must include:

1) A pricing proposal (completed and signed SF 1449 to include pricing for each CLIN except 0007 and 1007).

2) A technical capabilities proposal.

1. PART I – PRICING – The offeror is required to submit one electronic copy of the completed SF 1449.

(a) Complete all fields on the SF 1449 to include company information and pricing for all of the CLINs except 0007 and 1007. The offeror must fill out the solicitation completely and submit a signed copy of the SF 1449. In doing so, the offeror accedes to the proposed contract terms and conditions as written in the solicitation, with all attachments.

2. PART II – TECHNICAL CAPABILITY – Offerors are required to submit only one technical proposal document with the following:

(a) The offeror must provide:

1. A list of the equipment to be delivered which includes the characteristics of the equipment.

2. A maintenance execution plan.

3. A delivery execution plan.

4. A pick-up execution plan.

(End of Provision)

ADDENDUM TO FAR 52.212-2, EVALUATIONS

BASIS FOR CONTRACT AWARD: This is a solicitation that utilizes FAR Part 13, Simplified Acquisition Procedures, and will utilize the best value to the Government evaluation procedures and fair and reasonable price determination. By submission of its offer in accordance with the instructions provided in clause FAR 52.212-1, Instructions to Offerors, the offeror accedes to the terms of this solicitation. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. The evaluation process shall proceed as follows:

A. Price Evaluations.

A.1 Pricing must be good for a minimum of 60 days from submission of proposal.

A.2 Reasonableness: For a price to be reasonable, it must represent a price to the Government that a prudent person would pay in the conduct of competitive business. The Government will determine prices fair and reasonable through the use of one or more of the price analysis techniques at FAR 15.404-1(b)(2).

A.3 Unbalanced pricing: Contractors are cautioned against submitting an offer that contains unbalanced pricing. Unbalanced pricing may increase performance risk and could result in payment of unreasonably high prices. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one (1) or more contract line items is significantly over or understated. The Government shall analyze offers to determine whether they are unbalanced with respect to separately priced line items or sub-line items. An offer that is determined to be unbalanced may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.

B. Technical Capabilities Evaluations.

B.1 The technical capability of each responsive offeror will be evaluated as either acceptable or unacceptable based on the Government’s evaluation of the offeror’s submission of the following:

- A list of the equipment to be delivered which includes the characteristics of the equipment.

- A maintenance execution plan.

- A delivery execution plan.

- A pick-up execution plan.

C. Completeness of Quote.

Offerors are cautioned to submit sufficient information and in the format specified in the RFQ to permit a meaningful assessment of technical acceptability. Offerors may be asked to clarify certain aspects of their proposal.

D. Award.

The Government will start evaluations by identifying the three quotes with the lowest prices first. The Government will then evaluate those quotes for price and technical capability. If at least two quotes are determined to be technically acceptable, then the Government shall award to the offeror with the lowest price and no other evaluations will take place. If only one quote is considered acceptable then the Government shall evaluate the next lowest price quote(s) until there are two acceptable quotes. The Government intends to award the contract without discussions. If the Government decides to conduct discussions, all offerors will be notified as soon as possible.