Attachment 2 810 Fire System Replacement SOW.pdf

PDF 379 KB Posted

Attached to
Schriever SFB B810 Fire Riser Replacement
Solicitation number
FA255024Q0048
Issued by

About this file

This document appears to be a Statement of Work (SOW) for the replacement of an existing fire riser system in Building 810 at Schriever Space Force Base (SSFB). The 50th Civil Engineer Squadron (CES) at SSFB is seeking a contractor to remove the current Victaulic Series 756 Dry riser and replace it with a new dry riser system. The work includes demolition of the old system, installation of the new 6-inch dry riser in accordance with NFPA 13 and UFC 3-600-01, and testing of the new system. The contractor must provide all labor, materials, tools, and equipment necessary to complete the work within 120 business days. All work must comply with OSHA, safety, and other federal, state, and local requirements. The work is a 100% small business set-aside, with a response deadline of September 12, 2024 and an RFI due date of September 5, 2024. The contracting agency is the Department of the Air Force Space Command.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 4

1. INTRODUCTION AND BACKGROUND

1.1 The 50th Civil Engineer Squadron (CES) at Schriever Space Force Base (SSFB) is seeking a contractor to remove the existing Victaulic Series 756 Dry riser and replace with a dry riser in building 810. The current riser has required an excessive amount of maintenance and the 50 CES Plumbing shop would like to have the riser replaced.

2. SCOPE OF WORK

2.1 Contractor shall provide the personnel, supervision, labor, supplies, tools, materials, transportation, and equipment necessary to demolish and remove old fire system and install new shotgun riser and piping.

2.2 The scope of the work will include:

a. Contractor shall provide all the manpower and materials necessary to complete the work on-site.

b. Contractor shall remove and dispose of existing riser.

c. Contractor shall install dry riser in accordance with NFPA 13 and UFC 3- 600-01.

d. Contractor shall test the new riser in accordance with NFPA standards.

e. The riser shall have the following specifications:

• 6 inch

• Roll grooved

• Dry valve system

• Standard trim with low pressure actuator

• Shut off valve

• Pressure switches

• Drain kit

f. All equipment and materials shall be warrantied to their specified factory standard, and the warranty shall start once acceptance of the work has been completed by the Government.

Page | 5

3. WORK REQUIREMENTS

3.1 50 CES will facilitate access to the Base Restricted Area and access to the North Portal.

3.2 Contractor’s on-site work shall be completed within 120 business days, Monday- Friday (section 5.1).

4. OTHER PROJECT REQUIREMENTS

4.1 The contractor shall comply with all OSHA, safety, Federal, State, and local laws, regulations, base-specific standards, and applicable Unified Facilities Criteria (UFC) in accordance with the SOW provided. Where there is a conflict between the referenced standards, the most stringent shall take precedence. All work accomplished by Contractor shall follow these criteria unless a waiver is obtained from the Air Force when conditions warrant such consideration.

4.2 All work shall be subject to stoppages and delays due to critical Schriever SFB mission requirements.

4.3 The Contractor shall ensure project clean-up of site, to include the removal of all materials, tools and trash pertaining within the work area.

5. WORK HOURS

5.1 Standard work hours under this contract are Monday through Friday, 7:30 a.m. to 4:00 p.m. Mountain Standard Time (MST). Upon written request from the Contractor to the Contracting Officer (CO), permission may be granted to deviate from the standard work hours on a case-by-case basis. A Request to the CO for non-standard work hours shall be provided at least 48 hours in advance. In addition to non-standard work hours, the Contractor shall not work on federal holidays without written approval from the CO.

6. CONTRACT COMPLETION

6.1 The Government has the right to inspect the work performed throughout completion at any time.

6.2 Contractor shall conduct a final inspection with the Government when work is completed and state the completion details during the final meeting. The contractor shall also provide O&M manuals, specifications, and warranty documents to 50 CES upon completion.

Page | 7 employee possessing a permanent restricted/controlled area badge with escort authority.

Contractor employees entering Schriever Space Force Base will obtain their visitor badge from the 50th SFS, Building 200. The visitor badge will be returned to the NECF each time the employee departs the Schriever Space Force Base controlled area. While within the Schriever Space Force Base controlled area, contractor personnel will display the visitor badge on their outer garment above the waist and shall remain at all times within view of the escort official.

Procedures are as follows: The escort official will identify and verify the official need of all visitors and give them the escort briefing prior to taking them into the restricted area. Prior to entry into the restricted area, the escort official will search hand carried items (and vehicle, if applicable) in possession of escorted personnel. Items identified as not necessary for use within the area must be secured by the escort and will not be left at the Entry Control Facility. The escort official will enter the restricted area through the Special Portal. Each escorted person will then process through the portal, one at a time. Once inside the area, the escort official is responsible for the conduct of the visitor. The escort official may turn over escort duties to anyone authorized unescorted entry. Personnel being escorted will depart the area through the special portals prior to the escort official.

5. Reporting of lost badges: The contractor shall immediately report the occurrence of lost badge(s) to the COR, who will in turn report to SFS. If the COR is not available, the loss shall be reported directly to 50th SFS within one duty day of loss. Replacement badge will not be issued until reporting procedures are satisfactorily completed.