Attachment 2 - 1330-52.215-70 Schedule of Deliverables.docx

DOCX document 3 MB Posted

Attached to
Draft RFP: NESDIS Consolidated Antenna and Ground Systems Services (NCAGSS)
Solicitation number
Not on record
Issued by

About this file

This is a Schedule of Deliverables document outlining all required deliverables across four primary Task Orders (TO1-TO4) and three sub-task orders (TO2.1, TO2.2, TO3.1) for the NESDIS Consolidated Antenna and Ground Systems Services (NCAGSS) contract, effective January 2026. The document specifies deliverable identification numbers, submission frequencies, distribution methods, and cross-references to corresponding Performance Work Statement requirements for each task order component.

TO1 (Program Integration) requires 42 deliverables including program management plans, integrated master schedules, earned value management reports, configuration change requests, systems engineering management plans, quality assurance procedures, risk management reports, property audits, security control assessments, and monthly financial/progress reports, with submission frequencies ranging from initial proposal submission through monthly, quarterly, and annual intervals. TO2 (Operations) and its sub-orders TO2.1 (Day 1 Commercial Data Services Operations) and TO2.2 (Day 1 Operations) collectively require 28 primary deliverables focused on operational support including metric reports, weekly status reports, daily logs, training materials, staffing reports, test plans, security incident reports, continuity of operations plans, quality assurance documentation, risk management reports, and financial/progress reporting, with most submitted weekly, monthly, or as-needed based on operational events. TO3 (Maintenance) and TO3.1 (Day 1 Maintenance) specify 52 maintenance-related deliverables encompassing system maintenance schedules, service level agreements, quality assurance plans, network/system event reports, VLAN matrices, IP management reports, system hardening reports, patch vulnerability reports, firewall rulesets, IT asset inventories, antenna system maintenance plans and records, and capacity planning reports, submitted on daily, weekly, monthly, quarterly, or annual schedules. TO4 (Sustainment) requires 50 deliverables including sustainment project plans, phase-in transition plans, inventory baselines, software and hardware sustainment plans, obsolescence management plans, configuration change requests, test plans, quality assurance documentation, security patching plans, risk management reports, and monthly progress reports, with submission timelines tied to contract award, quarterly updates, and monthly reporting cycles. All deliverables are to be submitted to an Electronic Documentation Repository or specified government systems such as the ECMT (Engineering Change Management Tool), with specific distribution to government technical and contract personnel.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

30-52.215-70 SCHEDULE OF DELIVERABLES

F.1. SCHEDULE OF DELIVERABLES (JAN 2026)

The following is a schedule of all deliverables, including administrative deliverables, required during the period of performance of this contract. The column “Item” contains the applicable Task Order (TO) number (i.e. TO1, Program Integration, TO2, Operations, TO2.1 Operations Day 1 Commercial Data Services Operations, TO2.2 Day 1 Operations, TO3, Maintenance, TO3.1 Day 1 Maintenance, and TO4 Sustainment.

TO1: Program Integration Deliverables

Deliverable

ID #

Deliverable

Frequency

Distribution TO Reference Section(s) (Requirement ID)

D-TO1-001
Program Management Plan
Initial with proposal submission, final one month after contract award. Subsequent updates as mutually agreed
Electronic Documentation Repository

3.2.1 Management Plans and Integration

(PWS-TO1-PI01)

D-TO1-002
Program Management Review Package
Quarterly - 1 day before the quarterly Program Review meeting
Electronic Documentation Repository
3.2.8 Program Management Reviews

and Other Reviews

(PWS-TO1-PR01)

D-TO1-003
Integrated Master Schedule (IMS)
Monthly - no later than the 10th of each month
Electronic Documentation Repository
3.2.6 Schedule

(PWS-TO1-SC01)

D-TO1-004
Consolidated Contract Financial Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.2.2 Financial Management (PWS-TO1-FM04)
D-TO1-005
Earned Value Management Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.2.4 Earned Value Management (EVM)

(PWS-TO1-EV03)

D-SOW-006
Integrated Baseline Review
120 calendar days after contract award
Electronic Documentation Repository
3.2.5 Integrated Baseline Review (IBR)

(PWS-TO1-IB01)

D-TO1-007
Contract Fund Status Report (for each TO)
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.2.2 Financial Management

(PWS-TO1-FM02)

D-TO1-008

Release Backlog
Within 120 days after award, thereafter, reviewed monthly with the Sustainment teams
Electronic Documentation Repository
3.2 Program Management and Integration (PWS-TO1-PI10)

D-TO1-009

Release Backlog Report
Weekly - on the second business day of the week
Electronic

Documentation Repository

3.2 Program Management and Integration (PWS-TO1-PI10)

D-TO1-010
Weekly Status Report
Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PM03)

D-TO1-011
Staffing Plan
Initially submitted with proposal

Final consolidated plan within 5 business days after contract award

Subsequent updates provided at each PMR and upon issuance of new TOs and as required when key personnel or organizational changes occur Electronic Documentation Repository

3.2.2 Financial Management

(PWS-TO1-FM05)

D-TO1-012

Deleted

D-TO1-013
Meeting minutes, agendas, action item lists, lessons learned, etc.
One week after the meeting or one day prior to the next scheduled meeting, whichever is less
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PM03)

D-TO1-014
Configuration Change Requests (CCRs)
As required
ECMT
3.1 Program Management

(PWS-TO1-PM04)

D-TO1-015
Configuration Change Requests (CCRs) Report
Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PM04)

D-TO1-016

D-TO1-017
Systems Engineering Management Plan (SEMP)
Initial with proposal, updated as required
Electronic Documentation Repository
3.3.2 SE Management Planning

(PWS-TO1-SM01)

D-TO1-018
Quality Assurance Standard Operating Procedures (SOP)
60 days after contract award, updated annually no later than May 29th, or as requested by the Government
Electronic Documentation Repository
3.2.10 Quality Assurance

(PWS-TO1-QA03)

D-TO1-019
Consolidated Risk Management Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.9 Risk Management

(PWS-TO1-RM02)

D-TO1-020
Property Audit Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PMG01)

D-TO1-021
Discrepancy Property Audit Report
Semi-annually/Annually as scheduled in the IMS
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PM02)

D-TO1-022
Security Control Assessment (SCA) Artifacts
Annually for each antenna system per the agreed schedule. (SCA occurs yearly at a time chosen by NSOF).
Electronic Documentation Repository
3.2.12 Cyber Security

(PWS-TO1-CS01)

D-TO1-023
POA&M Milestone Status Report
Weekly, on the second business day of the week
Electronic Documentation Repository
3.2.12 Cyber Security

(PWS-TO1-CS02)

D-TO1-024
Program Quality Assurance Plan
Initial with proposal, updated as required (with the issuance of any new task order)
Electronic Documentation Repository
3.2.10 Quality Assurance

(PWS-TO1-QA01)

D-TO1-025

D-TO1-026
System Maintenance Schedule
Weekly, on the second business day of the week
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PM05)

D-TO1-027
Contractor Metric Report (compiled from other TOs)
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PM02)

D-TO1-028
Contract Review
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.2.8 Program Management Reviews and Other Reviews

(PWS-TO1-PR02)

D-TO1-029
Configuration Management Plan
Initial with proposal, updated as required (with the issuance of any new TOs)
Electronic Documentation Repository
3.3.7 Configuration Management

(PWS-TO1-CM01)

D-TO1-030
Integrated Sustainment Plan
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PI07)

D-TO1-031
Integrated Obsolescence Plan
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PI08)

D-TO1-032
Consolidated Monthly Progress Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.2.1 Management Plans and Integration

(PWS-TO1-PI09)

SOW Ref 3.1.2

D-TO1-033

Contract Phase-In Transition Plan
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Program Management (PWS-TO1-PI05)

SOW Ref 3.1.2

D-TO1-034

Contract Phase Out Transition Plan
As required - 60 days prior to the transition
Electronic Documentation Repository
3.1 Program Management (PWS-TO1-PI05)

SOW Ref 3.1

D-TO1-035

Associate Contractor Agreement (ACA)
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Program Management (PWS-TO1-PM07)

SOW Ref 3.1f

D-TO1-036

Consolidated Contractor Spend Plan
Initial submitted 60 days after award, annually thereafter.
Electronic Documentation Repository
3.2.2 Financial Management

(PWS-TO1-FM06]

D-TO1-037
NAaaS Asset Inventory Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.2.1 Management Plans and Integration

(PWS-TO1-PI12)

D-TO1-038
Document Tree
Initial submitted 60 days after award, updates quarterly
Electronic Documentation Repository
3.2.9 Document Management

(PWS-TO1-DM02)

D-TO1-039
Supply Chain Risk Management Plan
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.9 Risk Management

(PWS-TO1-RM05)

D-TO1-040
PI Kickoff Meeting
Within 10 days of contract award
Electronic Documentation Repository
3.1 Program Management

(PWS-TO1-PI15)

D-TO1-041
Mission Quality Assurance Implementation Plan
Initial submitted 60 days after award, annually thereafter.
Electronic Documentation Repository
3.2.10 Quality Assurance

(PWS-TO1-QA07)

D-TO1-042
RMS Report
Annually for each TO
Electronic Documentation Repository
3.2.10 Quality Assurance (PSW-TO1-QA08)

TO2: Operations Deliverables

Deliverable ID #
Deliverable
Frequency
Distribution
PWS Reference Section(s)

(Requirement ID)

D-TO2-001

Contractor(s) metric reports
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management (PWS-TO2-PM03)
D-TO2-002
Weekly Status Report
Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Project Management (PWS-TO2-PM04)
D-TO2-003
Standard Operating Procedures and Documentation updates
Annually - no later than May 29th
Electronic Documentation Repository
3.3 Operations (PWS-TO2-OP01)
D-TO2-004
Daily Log Report
Daily - on business days by 9:00am, EST
Electronic Documentation Repository
3.3 Operations (PWS-TO2-OP01)
D-TO2-005
Training Materials
As required - no later than 7 business days before the training event
Electronic Documentation Repository
3.3.1.1. Operations Training & Presentation Support (PWS-TO2-OP07)
D-TO2-006
Employee Training Log/Status Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.1.1. Operations Training & Presentation Support (PWS-TO2-OP07)
D-TO2-007
Satellite and Special Support Staffing Report/List
At least 30 days prior to launch and/or as requested by the Government
Electronic Documentation Repository
3.3.1.3. Satellite Launch and Special Activity Support (PWS-TO2-OP12)
D-TO2-008
Operations Test Plans
As needed
Electronic Documentation Repository
3.3.1 Satellite and Antenna Operational Support (PWS-TO2-OP03)
D-TO2-009
Enterprise Tools Status Report (supporting security operations)
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.7 Network and Security Operations

(PWS-TO2-OP18)

D-TO2-010

Operations Event Report
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.1 Satellite and Antenna Operations Support (PWS-TO2-OP01)

D-TO2-011

Project Management Review
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2-PM13)

D-TO2-012
Security Incident Summary Reports
As required by the OSPO IT Security Incident Reporting Policy
NCIRT - NIRRA
3.3.7.3. Security Data Analysis Services (PWS-TO2-OP21)
D-TO2-013
Continuity of Operations Plan Updates
Annually - no later than May 29th
Electronic Documentation Repository
3.3.8 Continuity of Operations (COOP) (PWS-TO2-OP23)
D-TO2-014
System Backup Schedule Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4 Continuity of Operations (PWS-TO2-OP23)
D-TO2-015
Quality Assurance Plan
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.1 Project Management (PWS-T03-PM01)
D-TO2-016
Quality Assurance Standard Operating Procedures
Initial with Proposal and updated as needed
Electronic Documentation Repository
3.1 Project Management (PWS-TO2-PM01)
D-TO2-017
Risk Management Report
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.3.6 Risk Management (PWS-TO2-RM02)

SOW Ref 3.1.2

D-TO2-018

Contract Phase-In Transition Plan

Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO2-CT01)

SOW Ref 3.1.2

D-TO2-019

Contract Phase-Out Transition Plan
As required - 60 days prior to the transition
Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO2-CT01)

D-TO2-020
Monthly Progress Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2-PM07)

D-TO2-021
Contract Financial Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2-PM08)

SOW Ref 3.1

D-TO2-022

Associate Contractor(s) Agreement (ACA)
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Project Management (PWS-TO2-PM09)

SOW Ref 3.1 k.

D-TO2-023

Contractor(s) Spend Plan
Initial submitted 60 days after award, annually thereafter.
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2-PM10)

D-TO2-024
Maintenance Project Management Plan
Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2-PM11)

D-TO2-025
Security Patch Plan
60 days after contract award
Electronic Documentation Repository
3.3.3 Network and Security Operations

(PWS-TO2-OP19)

D-TO2-026
Regression Test Plan
60 days after contract award
Electronic Documentation Repository
3.3.1 Satellite and Antenna Operations Support (PWS-TO2-OP03)
D-TO2-027
Project Kickoff Meeting
Within 10 days of contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2-PM14)

D-TO2-028
Continuous Monitoring Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.3.5 Information and Cybersecurity Support

(PWS-TO2-S02)

TO2.1 Operations Day 1 Commercial Data Services

Deliverable ID #
Deliverable
Frequency
Distribution
PWS Reference Section(s)

(Requirement ID)

D-TO2.1-001
JPSS Antenna Maintenance & Sparing
Initial updated submitted with proposal

Final consolidated plan 30 days after contract award

Electronic Documentation Repository
4.1 Project Management

(PWS-TO2.1-PM04)

D-TO2.1-002

Service Level Agreement
Initial updated submitted with proposal

Final consolidated plan 30 days after contract award

Electronic Documentation Repository
4.1 Project Management

(PWS-TO2.1-PM11)

D-TO2.1-003
Associate Contractor Agreement
Initial submitted with proposal

Final consolidated plan 30 days after contract award

Electronic Documentation Repository
4.1 Project Management

(PWS-TO2.1-PM06)

D-TO2.1-004
Project Implementation Plan
Initial submitted with proposal

Final consolidated plan 30 days after contract award

Electronic Documentation Repository
4.1 Project Management

(PWS-TO2.1-PM07)

D-TO2.1-005
Management (Status) Report
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
4.1 Project Management

(PWS-TO2.1-PM10)

D-TO2.1-006
Contract Management Plan
Initial submitted with proposal

Final consolidated plan 30 days after contract award

Electronic Documentation Repository
4.2 Contract Transition

(PWS-TO2.1-CT01)

D-TO2.1-007
Weekly Status Report
Weekly
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP02)

D-TO2.1-008
Anomaly Report (Notification)
As soon as possible but at least within 60 minutes
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP02)

D-TO2.1-009
Vendor Antenna Maintenance Summary Report and Recommendations
Annually
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP03)

D-TO2.1-010
Training Materials
As Needed
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP08)

D-TO2.1-011
JPSS3 and JPSS4 Pre-launch Testing/Mission Rehearsal Summary
Event driven
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP06)

D-TO2.1-012
Facility Hosting Summary Status
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP08)

D-TO2.1-014
Security Solutions Mapping
Initial submitted with proposal

Final consolidated plan 30 days after contract award

Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

( PWS-TO2.1-OP12)

D-TO2.1-015

D-TO2.1-016
JPPS-3 and JPSS-4 LEO&A Summary and Observations
Event Driven
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP22)

D-TO2.1-017
Special Support Staffing Report/List
Event Driven
Electronic Documentation Repository
4.3.1 Satellite and Antenna Operational Support

(PWS-TO2.1-OP22)

D-TO2.1-018
IT Security Plan
Initial submitted with proposal

Final consolidated plan 30 days after contract award

Electronic Documentation Repository
4.3.5 Network and Security Operations

(PWS-TO2.1-OP25)

D-TO2.1-019
Outage Report
As soon as possible but at least within 60 minutes
Electronic Documentation Repository
4.3.5 Network and Security Operations

( PWS-TO2.1-OP32)

D-TO2.1-020
KSAT Network Trouble Tickets
Within 24 hours of issue
Electronic Documentation Repository
4.3.5 Network and Security Operations

(PWS-TO2.1-OP32)

D-TO2.1-021
Special Study Reports
As needed
Electronic Documentation Repository
4.4 Other Services

( PWS-TO2.1-OS01)

TO2.2 Operations Day 1 Deliverables

Deliverable ID #
Deliverable
Frequency
Distribution
PWS Reference Section(s)

(Requirement ID)

D-TO2.2-001

Contractor(s) metric reports
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management (PWS-TO2.2-PM03)
D-TO2.2-002
Weekly Status Report
Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Project Management (PWS-TO2.2-PM04)
D-TO2.2-003
Standard Operating Procedures and Documentation updates
Annually - no later than May 29th
Electronic Documentation Repository
3.3 Operations (PWS-TO2.2-OP01)
D-TO2.2-004
Daily Log Report
Daily - on business days by 9:00am, EST
Electronic Documentation Repository
3.3 Operations (PWS-TO2.2-OP01)
D-TO2.2-005
Training Materials
As required - no later than 7 business days before the training event
Electronic Documentation Repository
3.3.1.1. Operations Training & Presentation Support (PWS-TO2.2-OP07)
D-TO2.2-006
Employee Training Log/Status Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.1.1. Operations Training & Presentation Support (PWS-TO2.2-OP07)
D-TO2.2-007
Satellite and Special Support Staffing Report/List
At least 30 days prior to launch and/or as requested by the Government
Electronic Documentation Repository
3.3.1.3. Satellite Launch and Special Activity Support (PWS-TO2.2-OP12)
D-TO2.2-008
Operations Test Plans
As needed
Electronic Documentation Repository
3.3.1 Satellite and Antenna Operational Support (PWS-TO2.2-OP03)
D-TO2.2-009
Enterprise Tools Status Report (supporting security operations)
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.7 Network and Security Operations

(PWS-TO2.2-OP18)

D-TO2.2-010

Operations Event Report
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.1 Satellite and Antenna Operations Support (PWS-TO2.2-OP01)

D-TO2.2-011

Project Management Review
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2.2-PM13)

D-TO2.2-012
Security Incident Summary Reports
As required by the OSPO IT Security Incident Reporting Policy
NCIRT - NIRRA
3.3.7.3. Security Data Analysis Services (PWS-TO2.2-OP21)
D-TO2.2-013
Continuity of Operations Plan Updates
Annually - no later than May 29th
Electronic Documentation Repository
3.3.8 Continuity of Operations (COOP) (PWS-TO2.2-OP23)
D-TO2.2-014
System Backup Schedule Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4 Continuity of Operations (PWS-TO2.2-OP23)
D-TO2.2-015
Quality Assurance Plan
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.1 Project Management (PWS-T03-PM01)
D-TO2.2-016
Quality Assurance Standard Operating Procedures
Initial with Proposal and updated as needed
Electronic Documentation Repository
3.1 Project Management (PWS-TO2.2-PM01)
D-TO2.2-017
Risk Management Report
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.3.6 Risk Management (PWS-TO2.2-RM02)

SOW Ref 3.1.2

D-TO2.2-018

Contract Phase-In Transition Plan

Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO2.2-CT01)

SOW Ref 3.1.2

D-TO2.2-019

Contract Phase-Out Transition Plan
As required - 60 days prior to the transition
Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO2.2-CT01)

D-TO2.2-020
Monthly Progress Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2.2-PM07)

D-TO2.2-021
Contract Financial Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2.2-PM08)

SOW Ref 3.1

D-TO2.2-022

Associate Contractor(s) Agreement (ACA)
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Project Management (PWS-TO2.2-PM09)

SOW Ref 3.1 k.

D-TO2.2-023

Contractor(s) Spend Plan
Initial submitted 60 days after award, annually thereafter.
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2.2-PM10)

D-TO2.2-024
Maintenance Project Management Plan
Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2.2-PM11)

D-TO2.2-025
Security Patch Plan
60 days after contract award
Electronic Documentation Repository
3.3.3 Network and Security Operations

(PWS-TO2.2-OP19)

D-TO2.2-026
Regression Test Plan
60 days after contract award
Electronic Documentation Repository
3.3.1 Satellite and Antenna Operations Support (PWS-TO2.2-OP03)
D-TO2.2-027
Project Kickoff Meeting
Within 10 days of contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO2.2-PM14)

D-TO2.2-028
Continuous Monitoring Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.3.5 Information and Cybersecurity Support

(PWS-TO2.2-S02)

TO3: Maintenance Deliverables

Deliverable ID #
Deliverable
Frequency
Distribution
PWS Reference Section(s)

(Requirement ID)

D-TO3-001

Contractor(s) metric reports

Monthly - no later than the 10th of the month

Electronic Documentation Repository
3.1 Program Management

(PWS-TO3-PM03)

D-TO3-002
Weekly Status Report
Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Program Management (PWS-TO3-PM04)
D-TO3-003
System Maintenance Schedule
As defined at project start and updated Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Program Management

(PWS-TO3-PM06)

D-TO3-004
Contractor(s) Service Level Agreements
Initial with proposal and final within 30 days after contract award
Electronic Documentation Repository and emailed to the CO, CS, COR, and PM
3.1 Project Management

(PWS-TO3-PM02)

D-TO3-005
Quality Assurance Plan
Initial with proposal, updated as required (with the issuance of any new task order)
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM01]

D-TO3-006
Event Reports (e.g., network issues, network performance degradation, network equipment failures, and connection issues/outages)
Initiated within two hours of the event and updated in accordance with the OSPO Incident Reporting Policy
Google Docs shared with the GSE, PAL, and Government Network Manager
3.4.3.1 Networks Fault Management

(PWS-TO3-NM02)

D-TO3-007
VLAN Matrix
Monthly - no later than the 10th of the month.
Electronic Documentation Repository

3.4.3.1 Networks Fault Management

D-TO3-008
IP Address/Subnet Management Report
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.4.3.1 Networks Fault Management
D-TO3-009
Project Management Review
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM18)

D-TO3-010
Components Compliance Report (software, firmware, and engineering levels at all sites)
Annually - no later than May 29th
Electronic Documentation Repository
3.3.3.1 Networks Fault Management

(PWS-TO3-NM02)

D-TO3-011
System Hardening Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository
3.4.3.7 System Administration Performance Management

(PWS-TO3-SA01)

D-TO3-012
Configuration Management Process Forms (for all system installations, upgrades, and configuration changes)
As required by the OSPO CM Policy
Electronic Documentation Repository and ECMT
3.3.3.1 Networks Fault Management

(PWS-TO3-NM02)

D-TO3-013
System Account Reviews Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository and ECMT
3.3.3.2 Networks Account Administration Management

(PWS-TO3-NA01)

D-TO3-014
Spare Parts Plan
Within 30 days after contract award
Electronic Documentation Repository
3.3.3.2 Networks Account Administration Management

PWS-TO3-NA01

D-TO3-015
Dynamic Host Configuration Protocol (DHCP), static IP addresses reservations Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.3.2 Networks Account Administration Management

PWS-TO3-NA01

D-TO3-016
Network Utilization for external devices
Weekly - on the second business day of the week
Electronic Documentation Repository
3.3.3.3 Network Performance Management

(PWS-TO3-NP01)

D-TO3-017
Network Utilization for internal devices
Weekly - on the second business day of the week
Electronic Documentation Repository
3.3.3.3 Network Performance Management (PWS-TO3-NP01)
D-TO3-018
Critical Alerts Report (including IDS)
Daily - on business days by 9:00am, EST if required
Electronic Documentation Repository
3.3.3.4 Network Security Management (PWS-TO3-M05)
D-TO3-019
Patch Vulnerability Report (identify critical and high vulnerabilities that impact OSPO systems)
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.3.4 Networks Security Management

(PWS-TO3-SM05)

D-TO3-020
Firewall Ruleset Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository
3.3.3.4 Networks Security Management

(PWS-TO3-SM05)

D-TO3-021
Ports, Protocols and Services Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository
3.3.3.4 Networks Security Management

(PWS-TO3-SM05)

D-TO3-022
Post-Incident Reports for major system anomalies
The next business day or as defined in the OSPO Incident Reporting Policy
Electronic Documentation Repository
3.3.6 System Administration

(PWS-TO3-SF01)

D-TO3-023
Network and System Performance Status Report
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.3.7 System Administration Performance Management

(PWS-TO3-SA01)

D-TO3-024
System component utilization, and efficiency report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.3.10 Capacity Planning

(PWS-TO3-CP01)

D-TO3-025
Preventive Maintenance Work Package (to include test plans)
Quarterly - per the IMS
Electronic Documentation Repository
3.3.4.1 Replacement Parts Modifications and Upgrades

(PWS-TO3-RP01

D-TO3-026 Deleted

D-TO3-027
Maintenance Plan
Annually - Within 30 days after all Annual Obsolescence/Out-of-Support Reports
Electronic Documentation Repository
3.4.4.3 Obsolescence Prevention and Remediation

(PWS-TO3-OP01)

D-TO3-028
IT Asset Management, System Hardware and Software Inventory Report (inventory and surplus movement, assets that are in excess or disposed)
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3-AM01)

D-TO3-029
Audit of IT Assets (for Antenna System assets under each Task Order)
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory (PWS-TO3-AM01)
D-TO3-030
Software and Hardware License Review/Status Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3-AM01)

D-TO3-031
System Inventory Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3-AM03)

D-TO3-032
Annual listing of all purchased software and hardware (include End of Service (EOS)/End of Life (EOL) dates)
Annually - no later than May 29th
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3-AM01)

D-TO3-033
OSPO Inventory Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3-AM01)

D-TO3-034
Configuration Management Baseline Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3-AM04)

D-TO3-035
Antenna System Maintenance Plan
30 days after contract award, Annual updates thereafter no later than May 29th
Electronic Documentation Repository
3.4.2 Antenna Maintenance

(PWS-TO3-AT01)

D-TO3-036
Antenna System Maintenance Records
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.4.2 Antenna Maintenance

(PWS-TO3-AT02)

D-TO3-037
Audit Discrepancy Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Software Inventory

(PWS-TO3-AM01)

D-TO3-038
Risk Management Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.6 Risk Management

(PWS-TO3-RM02)

D-TO3-039

Delete

D-TO3-040
Training Materials
As required - no later than 7 business days before the training event
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3-AM01)

SOW Ref 3.1.2

D-TO3-041

Contract Phase-In Transition Plan Initial submitted with proposal Final consolidated plan 30 days after contract award

Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO3-CT01)

SOW Ref 3.1.2

D-TO3-042

Contract Phase-Out Transition Plan
As required - 60 days prior to the transition
Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO3-CT01)

D-TO3-043
Monthly Progress Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM06)

D-TO3-044
Contract Financial Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM08)

SOW Ref 3.1

D-TO3-045

Associate Contractor(s) Agreement (ACA)
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM09)

SOW Ref 3.1f

D-TO3-046

Contractor(s) Annual Spend Plan
Initial submitted 60 days after award, annually thereafter.
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM10]

D-TO3-047
Maintenance Project Management Plan
Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM11)

D-TO3-048
Quality Assurance Standard Operating Procedures
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM01)

D-TO3-049
Security Patch Plan
60 days after contract award
Electronic Documentation Repository
3.3.5 Information and Cybersecurity Sustainment (PWS-TO3-S02)
D-TO3-050
Regression Testing Plan
60 days after contract award
Electronic Documentation Repository
3.3.7 System Engineering 3.2.7.1 General

(PWS-TO3-SE03)

D-TO3-051
Project Kickoff Meeting
Within 10 days of contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3-PM14)

D-TO3-052
Continuous Monitoring Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.3.5 Information and Cybersecurity Support

(PWS-TO3-S03)

TO3.1 Day 1 Maintenance Deliverables

Deliverable ID #
Deliverable
Frequency
Distribution
PWS Reference Section(s)

(Requirement ID)

D-TO3.1-001

Contractor(s) metric reports

Monthly - no later than the 10th of the month

Electronic Documentation Repository
3.1 Program Management

(PWS-TO3.1-PM03)

D-TO3.1-002
Weekly Status Report
Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Program Management (PWS-TO3.1-PM04)
D-TO3.1-003
System Maintenance Schedule
As defined at project start and updated Weekly - on the second business day of the week
Electronic Documentation Repository
3.1 Program Management

(PWS-TO3.1-PM06)

D-TO3.1-004
Contractor(s) Service Level Agreements
Initial with proposal and final within 30 days after contract award
Electronic Documentation Repository and emailed to the CO, CS, COR, and PM
3.1 Project Management

(PWS-TO3.1-PM02)

D-TO3.1-005
Quality Assurance Plan
Initial with proposal, updated as required (with the issuance of any new task order)
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM01]

D-TO3.1-006
Event Reports (e.g., network issues, network performance degradation, network equipment failures, and connection issues/outages)
Initiated within two hours of the event and updated in accordance with the OSPO Incident Reporting Policy
Google Docs shared with the GSE, PAL, and Government Network Manager
3.4.3.1 Networks Fault Management

(PWS-TO3.1-NM02)

D-TO3.1-007
VLAN Matrix
Monthly - no later than the 10th of the month.
Electronic Documentation Repository

3.4.3.1 Networks Fault Management

D-TO3.1-008
IP Address/Subnet Management Report
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.4.3.1 Networks Fault Management
D-TO3.1-009
Project Management Review
Monthly - no later than the 10th of the month.
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM18)

D-TO3.1-010
Components Compliance Report (software, firmware, and engineering levels at all sites)
Annually - no later than May 29th
Electronic Documentation Repository
3.3.3.1 Networks Fault Management

(PWS-TO3.1-NM02)

D-TO3.1-011
System Hardening Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository
3.4.3.7 System Administration Performance Management

(PWS-TO3.1-SA01)

D-TO3.1-012
Configuration Management Process Forms (for all system installations, upgrades, and configuration changes)
As required by the OSPO CM Policy
Electronic Documentation Repository and ECMT
3.3.3.1 Networks Fault Management

(PWS-TO3.1-NM02)

D-TO3.1-013
System Account Reviews Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository and ECMT
3.3.3.2 Networks Account Administration Management

(PWS-TO3.1-NA01)

D-TO3.1-014
Spare Parts Plan
Within 30 days after contract award
Electronic Documentation Repository
3.3.3.2 Networks Account Administration Management

PWS-TO3.1-NA01

D-TO3.1-015
Dynamic Host Configuration Protocol (DHCP), static IP addresses reservations Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.3.2 Networks Account Administration Management

PWS-TO3.1-NA01

D-TO3.1-016
Network Utilization for external devices
Weekly - on the second business day of the week
Electronic Documentation Repository
3.3.3.3 Network Performance Management

(PWS-TO3.1-NP01)

D-TO3.1-017
Network Utilization for internal devices
Weekly - on the second business day of the week
Electronic Documentation Repository
3.3.3.3 Network Performance Management (PWS-TO3.1-NP01)
D-TO3.1-018
Critical Alerts Report (including IDS)
Daily - on business days by 9:00am, EST if required
Electronic Documentation Repository
3.3.3.4 Network Security Management (PWS-TO3.1-M05)
D-TO3.1-019
Patch Vulnerability Report (identify critical and high vulnerabilities that impact OSPO systems)
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.3.4 Networks Security Management

(PWS-TO3.1-SM05)

D-TO3.1-020
Firewall Ruleset Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository
3.3.3.4 Networks Security Management

(PWS-TO3.1-SM05)

D-TO3.1-021
Ports, Protocols and Services Report
Quarterly - no later than the 10th day of the quarter
Electronic Documentation Repository
3.3.3.4 Networks Security Management

(PWS-TO3.1-SM05)

D-TO3.1-022
Post-Incident Reports for major system anomalies
The next business day or as defined in the OSPO Incident Reporting Policy
Electronic Documentation Repository
3.3.6 System Administration

(PWS-TO3.1-SF01)

D-TO3.1-023
Network and System Performance Status Report
Weekly - on the second business day of the week.
Electronic Documentation Repository
3.3.3.7 System Administration Performance Management

(PWS-TO3.1-SA01)

D-TO3.1-024
System component utilization, and efficiency report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.3.10 Capacity Planning

(PWS-TO3.1-CP01)

D-TO3.1-025
Preventive Maintenance Work Package (to include test plans)
Quarterly - per the IMS
Electronic Documentation Repository
3.3.4.1 Replacement Parts Modifications and Upgrades

(PWS-TO3.1-RP01

D-TO3.1-026 Deleted

D-TO3.1-027
Maintenance Plan
Annually - Within 30 days after all Annual Obsolescence/Out-of-Support Reports
Electronic Documentation Repository
3.4.4.3 Obsolescence Prevention and Remediation

(PWS-TO3.1-OP01)

D-TO3.1-028
IT Asset Management, System Hardware and Software Inventory Report (inventory and surplus movement, assets that are in excess or disposed)
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3.1-AM01)

D-TO3.1-029
Audit of IT Assets (for Antenna System assets under each Task Order)
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory (PWS-TO3.1-AM01)
D-TO3.1-030
Software and Hardware License Review/Status Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3.1-AM01)

D-TO3.1-031
System Inventory Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3.1-AM03)

D-TO3.1-032
Annual listing of all purchased software and hardware (include End of Service (EOS)/End of Life (EOL) dates)
Annually - no later than May 29th
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3.1-AM01)

D-TO3.1-033
OSPO Inventory Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3.1-AM01)

D-TO3.1-034
Configuration Management Baseline Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3.1-AM04)

D-TO3.1-035
Antenna System Maintenance Plan
30 days after contract award, Annual updates thereafter no later than May 29th
Electronic Documentation Repository
3.4.2 Antenna Maintenance

(PWS-TO3.1-AT01)

D-TO3.1-036
Antenna System Maintenance Records
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.4.2 Antenna Maintenance

(PWS-TO3.1-AT02)

D-TO3.1-037
Audit Discrepancy Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.4.5.1 System Software Inventory

(PWS-TO3.1-AM01)

D-TO3.1-038
Risk Management Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.6 Risk Management

(PWS-TO3.1-RM02)

D-TO3.1-039

Delete

D-TO3.1-040
Training Materials
As required - no later than 7 business days before the training event
Electronic Documentation Repository
3.3.4.5.1 System Hardware and Software Inventory

(PWS-TO3.1-AM01)

SOW Ref 3.1.2

D-TO3.1-041

Contract Phase-In Transition Plan Initial submitted with proposal Final consolidated plan 30 days after contract award

Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO3.1-CT01)

SOW Ref 3.1.2

D-TO3.1-042

Contract Phase-Out Transition Plan
As required - 60 days prior to the transition
Electronic Documentation Repository
3.2 Contract Transition

(PWS-TO3.1-CT01)

D-TO3.1-043
Monthly Progress Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM06)

D-TO3.1-044
Contract Financial Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM08)

SOW Ref 3.1

D-TO3.1-045

Associate Contractor(s) Agreement (ACA)
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM09)

SOW Ref 3.1f

D-TO3.1-046

Contractor(s) Annual Spend Plan
Initial submitted 60 days after award, annually thereafter.
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM10]

D-TO3.1-047
Maintenance Project Management Plan
Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM11)

D-TO3.1-048
Quality Assurance Standard Operating Procedures
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM01)

D-TO3.1-049
Security Patch Plan
60 days after contract award
Electronic Documentation Repository
3.3.5 Information and Cybersecurity Sustainment (PWS-TO3.1-S02)
D-TO3.1-050
Regression Testing Plan
60 days after contract award
Electronic Documentation Repository
3.3.7 System Engineering 3.2.7.1 General

(PWS-TO3.1-SE03)

D-TO3.1-051
Project Kickoff Meeting
Within 10 days of contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO3.1-PM14)

D-TO3.1-052
Continuous Monitoring Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.3.5 Information and Cybersecurity Support

(PWS-TO3.1-S03)

TO4: Sustainment Deliverables Deliverable

ID #

Deliverable
Frequency
Distribution
PWS Reference Section(s) (Requirement ID)
D-TO4-001
Antenna Systems Sustainment Project Plan
Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly
Electronic

Documentation Repository

3.3.1 General

(PWS-TO4-GS02)

D-TO4-002
NAaaS Sustainment Phase-In Transition Plan
Initial draft plan submitted with proposal; a final plan submitted within 60 days after contract award
Electronic

Documentation Repository

3.3.11 Contract Transition

(PWS-TO41-CT01)

D-TO4-003
NAaaS Sustainment Phase-In Transition Plan Status Report
Monthly - on the first business day of the month
Electronic

Documentation Repository Integrate

3.3.11 Contract Transition

(PWS-TO4-CT02)

D-TO4-004
Sustainment Stakeholder Contact List
Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly
Electronic

Documentation Repository

3.3.1 General

(PWS-TO4-GS03)

D-TO4-005
Integrated Sustainment

Schedule

Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates monthly
Electronic

Documentation Repository

3.3.1 General

(PWS-TO4-GS04)

D-TO4-006
Sustainment Inventory

Baseline Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly Electronic Documentation Repository

3.3 Sustainment

(PWS-TO4-GS15)

D-TO4-007
Technology Refresh Analysis
As required
Electronic

Documentation Repository

3.3.1 Sustainment (PWS-TO4-GS20)

D-TO4-008
Contractor Metric Performance Report
Weekly - on the first business day of the week and aggregated in a monthly report on the first business day of the month
Electronic

Documentation Repository

3.1 Project Management

(PWS-TO4-PM04)

D-TO4-009
Software Sustainment Plan
Initial draft submitted with proposal; a final document submitted within 120 days
Electronic

Documentation Repository

3.3.3.1 Software Sustainment

(PWS-TO4-SS01)

D-TO4-010
Sustainment Requirements Baseline
Initial draft submitted with proposal; a final submitted within 120 days after

contract award, and updates quarterly Electronic Documentation Repository

3.3.9 System Engineering

(PWS-TO4-SE03)

D-TO4-011
System Engineering Management Plan Tailored Sustainment
Initial submitted with proposal; a final tailored SEMP within 60 days after contract award
Electronic

Documentation Repository

3.3.9 System Engineering

(PWS-TO4-SE04)

D-TO4-012
Sustainment Life-Cycle Cost Prediction Report
Submitted within 120 days after contract award
Electronic

Documentation Repository

3.3.9 System Engineering

(PWS-TO4-SE06)

D-TO4-013
Modified source code
As required per each CCR
Configuration Management

Repository

3.3.3.1 Software Sustainment

(PWS-TO4-SS01)

D-TO4-014
Configuration Change

Requests (CCRs)

As required
ECMT
3.3.3.1 Software Sustainment

(PWS-TO4-SS01)

D-TO4-015
Configuration Change Requests Report
As required
ECMT
3.3.3.1 Software Sustainment

(PWS-TO4-SS02)

D-TO4-016
Sustainment Project Milestone Plan
Initial draft submitted with proposal; a final submitted within 120 days after contract award, and updates quarterly
Electronic

Documentation Repository

3.3.1 General

(PWS-TO4-GS04)

D-TO4-017
Integration and Test Plans
Two weeks prior to sustainment solution technical review meeting; a final due no later than 2 weeks prior to the test
Electronic

Documentation Repository

3.3.3.1 Software Sustainment

(PWS-TO4-SS01)

D-TO4-018
Sustainment Installation Plan
Two weeks prior to the technical review meeting
Electronic

Documentation Repository

3.3.3.2 System Integration, Installation and Test

(PWS-TO4-SI03)

D-TO4-019
Hardware Sustainment Plan
Initial draft submitted with proposal; a final document submitted within 120 days after contract award, and updates quarterly
Electronic

Documentation Repository

3.3 Sustainment Hardware

(PWS-TO4-HW01)

D-TO4-020
Test and Calibration Reports
No more than 2 weeks after Government acceptance
Electronic

Documentation Repository

3.3.6.2 Radio Frequency Equipment

(PWS-TO4-RF02)

D-TO4-021
IT Security Services BOM Cost Estimate
Within 2 weeks of receipt of BOM
Electronic

Documentation Repository

3.3.7.1 IT Security Other Direct Costs

(PWS-TO4-ITS14)

D-TO4-022
Training Materials and Media
2 weeks prior to conducting the training
Electronic

Documentation Repository

3.3.8 Training

(PWS-TO4-T03)

D-TO4-023
Obsolescence Management Plan
Initial draft submitted with proposal; a final document submitted within 120 days after contract award, and updates quarterly
Electronic

Documentation Repository

3.3.2 Antenna and Radio Frequency Equipment

(PWS-TO4-SER02)

D-TO4-024
Release Backlog Report
Monthly - on the first business day of the month
Electronic

Documentation Repository

3.1 Project Management

(PWS-TO4-PM03)

D-TO4-025
Software Sustainment Life-Cycle Plan
To be delivered within 120 days after award as part of the Software Sustainment Plan.
Electronic

Documentation Repository

3.3.3.1 Software Sustainment

(PWS-TO4-SS03)

D-TO4-026
Interface Control Documents (ICD)
Within 45 days from implementation of sustainment capabilities.
Electronic

Documentation Repository

3.3.9 System Engineering

(PWS-TO4-SE08)

D-TO4-027
Electronic Documentation Repository containing initial sustainment risks with recommendations
Part of proposal submission and updates monthly
TBD
3.3.10 Risk Management

(PWS-TO4-RM02)

D-TO4-028
Risk Management Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.3.10 Risk Management

(PWS-TO4-RM02)

D-TO4-029
Monthly Progress Report
Monthly - no later than the 10th of the month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO4-PM05)

D-TO4-030
Contract Financial Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO4-PM06)

SOW Ref 3.1

D-TO4-031

Associate Contractor Agreement (ACA)
Initial submitted with proposal Final consolidated plan 30 days after contract award
Electronic Documentation Repository
3.1 Project Management (PWS-TO4-PM07)

SOW Ref 3.1 k.

D-TO4-032

Contractor Spend Plan
Initial submitted 60 days after award, annually thereafter.
Electronic Documentation Repository
3.1 Project Management

(PWS-TO4-PM08)

D-TO4-033
General Sustainment Plan
Initial draft submitted with proposal; a final document submitted within 120 days after contract award, and updates quarterly
Electronic

Documentation Repository

3.3.2.3 Antenna and RF Equipment Systems Engineering

(PWS-TO4-SER01)

D-TO4-034
Weekly Status Report
Weekly
Electronic

Documentation Repository

3.3.1 General

(PWS-TO4-GS19)

D-TO4-035
Quality Assurance Plan
Initial with proposal, updated as required (with the issuance of any new task order)
Electronic Documentation Repository
3.1.1 Quality Assurance

(PWS-TO4-QA01)

D-TO4-036
Quality Assurance Surveillance Plan (QASP)
Initial with proposal, updated as required (with the issuance of any new TOs)
Electronic Documentation Repository
3.1.1 Quality Assurance

(PWS-TO4-QA03)

D-TO4-037
Quality Assurance Standard Operating Procedures (SOP)
60 days after contract award, updated annually no later than May 29th, or as requested by the Government
Electronic Documentation Repository
3.1.1 Quality Assurance

(PWS-TO4-QA03)

D-TO4-038
Sustainment Status Report
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.3.1 General

(PWS-TO4-GS19)

D-TO4-039
Meeting minutes, agendas, action item lists, lessons learned, etc.
One week after the meeting or one day prior to the next scheduled meeting, whichever is less
Electronic Documentation Repository
3.3.1 General

(PWS-TO4-GS19)

D-TO4-040
Test and Calibration Report
No more than 2 weeks after Government acceptance
Electronic Documentation Repository
3.3.2.1 RF Equipment (PWS-TO4-RF02]
D-TO4-041
Transition to Operations Package
Upon completion of new sustainment solution
Electronic Documentation Repository
3.3.1 General (PWS-TO4-GS21)
D-TO4-042
Sustainment Configuration Management Plan
Initial with proposal, updated as required (with the issuance of any new TOs)
Electronic Documentation Repository
3.3.7 IT Security Sustainment

(PWS-TO4-ITS06)

D-TO4-043
Use Case Cost Estimates
With proposal submission
Electronic Documentation Repository
3.3.1 General

(PWS-TO4-GS22)

D-TO4-044
Security Patching Plan
60 days after contract award
Electronic Documentation Repository
3.3.5 IT Security Sustainment

(PWS-TO4-ITS11)

D-TO4-045
Regression Testing Plan
60 days after contract award
Electronic Documentation Repository
3.3.9 System Engineering

(PWS-TO4-SE05)

D-TO4-046
NAaaS Study Reports
As requested
Electronic Documentation Repository
3.1 Project Management

(PWS-TO4-PM13)

D-TO4-047
Project Kickoff Meeting
Within 10 days of contract award
Electronic Documentation Repository
3.1 Project Management

(PWS-TO4-PM14)

D-TO4-048
Project Management Review
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.1 Project Management

(PWS-TO4-PM19)

D-TO4-049
Software Review Package
As requested
Electronic Documentation Repository
3.3.3.1 Software Sustainment

(PWS-TO4-SS14)

D-TO4-050
Continuous Monitoring Reports
Monthly- no later than the 10th of each month
Electronic Documentation Repository
3.3.7 IT Security (PWS-TO4-IT13)

File details come from the government source that posted it. Updated .