Attachment 11 Architect- Engineering Experience Form.docx
DOCX document 21 KB Posted
- Attached to
- USDA-FS GWJ NF Call for Quals Design-Build Virginia Creeper Bridge(s) /Trail(s) Reconstruction
- Solicitation number
- 12445125R0002
- Issued by
-
Department of Agriculture Forest Service
About this file
Attachment 11 is an Architect-Engineering Experience Form for the USDA Forest Service's Virginia Creeper Bridge and Trail Reconstruction Design-Build project (Solicitation 12445125R0002). The form is designed for prime contractors to document their previous construction project experience relevant to this design-build opportunity. Contractors must provide detailed information about past projects, including project title, contract number, location, award and completion dates, contract type, contract value, owner information, and a comprehensive description of their firm's specific role and self-performed work.
The associated federal contract opportunity is a $200-300 million design-build project to reconstruct an 18-mile section of the Virginia Creeper National Recreation Trail in Washington and Grayson Counties, Virginia. The project aims to restore trail infrastructure, including 31 trestle bridges and treadway, following extensive damage from Tropical Storm Helene in September 2024. The solicitation is unrestricted with a small business subcontracting plan, using a Best Value Tradeoff Process. Key dates include a non-mandatory pre-proposal meetings on 06/02/2025 and 06/09/2025, with a Call for Qualifications deadline of 07/09/2025 at 1:00 PM ET.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12445125R0002 VA Creeper Bridge and Trail Restoration Design-Build
| Attachment 11 | Architect- Engineering Experience Form |
| PRIME CONTRACTOR: |
Experience For: (Firm Name)
Point of Contact:
Phone:
Construction Project Information:
Construction Project Title:
Contract / Project Number:
Location:
Award Date:
Completion Date:
Explain Difference:
Award Amount:
Final Amount:
Explain Difference:
Owner:
Point of Contact for Owner:
Phone:
Email:
| Type of Contract: |
| Firm Fixed Price Cost Reimbursement |
Other (Explain) :
| Role: |
| Prime Contractor Sub Contractor Joint Venture |
Other (Explain):
Provide a detailed description of the project and the relevancy to the project requirements of this RFP (i.e.: unique features, square footage, construction methods).
Provide a detailed description of what work your firm self-performed on this project:
Other Information: