About this file
This is a Technical Specifications document for thermal system piping components required to support a Multimegawatt (MMW) Electrolysis project at the National Laboratory of the Rockies (NLR). The procurement is for piping, fittings, valves, and pipe connections designed to cool Proton Exchange Membrane (PEM) electrolyzer stacks using a 50/50 propylene glycol/water process fluid. The cooling system is critical for temperature control and must minimize downtime for repair and maintenance.
All components must meet stringent technical requirements including: compatibility with the specified process fluid; maximum allowable working pressure exceeding 150 psi; maximum allowable working temperature exceeding 200°F; minimum allowable working temperature below -22°F; outdoor rating; Victaulic Original Groove System (OGS) end connections; Iron Pipe Size (IPS) category; and EPDM seals/seats. Unless specifically noted, all components must be Victaulic brand and designed to applicable ASME pressure codes. The specifications document includes a detailed bill of materials containing 48 line items across various component types, including butterfly valves, strainers, reducers, elbows, tees, flanged adapters, couplers, and schedule 40 carbon steel piping in sizes ranging from 4 to 10 inches. The contractor must include all delivery costs and freight to NLR Flatirons Campus in Arvada, Colorado. Delivery is required by end of December 2026, with notification requested if specific items cannot meet this lead time as longer delivery periods may be negotiable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment No. 1 - RFQ No. 2026030827.pdf | ||
| Request for Quote (RFQ) No. 2026030827.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1
Technical Specifications
"Thermal System Piping”
July 14, 2026
BACKGROUND
This purchase is to acquire piping, fittings, valves, and pipe connections for the thermal systems which cool the Proton Exchange Membrane (PEM) electrolyzer stacks being tested as part of the Multimegawatt (MMW) Electrolysis project. The process fluids will be 50/50 propylene glycol/water. This cooling system is required for successful execution of the MMW electrolysis project.
OBJECTIVE
The purpose of this procurement is to purchase the equipment needed to connect National Laboratory of the Rockies (NLR) large dry coolers to the PEM electrolyzer balance of plant. The cooling system is critical for temperature control of the experiment requiring a reliable system that minimizes down time for repair and maintenance.
SPECIFICATIONS:
REQUIRED CAPABILITIES
• Materials of construction shall be compatible with the process fluid of 50/50 propylene glycol/water
• Maximum allowable working pressure (MAWP) shall be > 150 psi (10.3 bar) for all components
• Maximum allowable working temperature (MAWT) shall be > 200°F (93°C) for all components
• Minimum allowable working temperature shall be < -22°F (-30°C) for all components
• All components shall be outdoor rated
• All components, unless specifically noted, shall have end connections meeting the Victaulic
Original Groove System (OGS) Specifications and meet the requirements (e.g., pipe size and squareness) of the Victaulic Field Installation Handbook o Victaulic Original Groove System (OGS) Specifications document for reference:
https://assets.victaulic.com/assets/uploads/literature/25.01.pdf o Victaulic Field Installation Handbook document for reference:
https://assets.victaulic.com/assets/uploads/literature/I-100.pdf The maximum allowable tolerance from square-cut pipe ends is 1/16 inch/1.6 mm for 4 – 24-inch/DN100 – DN600 sizes. This is measured from the true square line (from page 4 of the Field Installation Handbook)
• All components, unless specifically noted, shall be of the Iron Pipe Size (IPS) category
• All components shall have Ethylene Propylene Diene Monomer (EPDM) seals/seats in alignment with the table below
• All components, unless specifically noted, shall be Victaulic brand https://assets.victaulic.com/assets/uploads/literature/25.01.pdf https://assets.victaulic.com/assets/uploads/literature/I-100.pdf
• Pressure-containing portions of the equipment (see table below) shall be designed to the applicable sections of ASME pressure codes.
• Include delivery costs and freight to NLR Flatirons Campus: 19001 W 119th Ave, Arvada, CO 80007
A list of components to be purchased is provided below:
General Description
Catalog Description Quantity Notes
Flanged Reducing Elbow , 90 LR, 6"flg x 8"grv
Victaulic_IPS_Elb Base Sprt Redc_No R100F (OGSxFLG)_08.0x06.0 (200x150)
Tee, 8 in, groove Victaulic_IPS_Tee_No 20
(OGS)_8 (200)
Elbow, 90 LR, 8 in, groove
Victaulic_IPS_Elb 90 Deg LR_No 100 (OGS)_8 (200)
6 1 ½ D
Cross, 8 in, groove Victaulic_IPS_Cross_No 35
(OGS)_8 (200)
Butterfly Valve, 8 in, groove, Vic-300 MasterSeal Lever Lock EPDM green - 30 F to 230 F, Victaulic_IPS_Valve Butterfly Vic-300 Masterseal Lever Handle_ (OGS)_8 (200) 761 series
8 Disk: Standard, Ductile Iron. Seat:
EPDM. Stem:
Standard 416 Stainless Steel.
Butterfly Valve, 10 in, groove, Vic-300 MasterSeal 10- Position Handle EPDM green -30 F to 230 F
Victaulic_IPS_Valve Butterfly Vic-300 Masterseal 10- Position Handle_ (OGS)_10 (200)
1 Disk: Standard, Ductile Iron. Seat:
EPDM. Stem:
Standard 416 Stainless Steel.
Wye Strainer, 8 in, groove
Victaulic_IPS_Strainer Wye_Type_Series 732
(OGS)_8 (200)
2 8 – 12"/DN200 –
DN300: 0.188"/4.76
mm diameter perforations on 0.25"/6.35 mm centers, 51% open area. Underlaid with wire mesh with greater than 45% open area
Reducing Tee, 8 x
1.5 in FNPT Branch
Victaulic_IPS_Tee Redc Thd_No 29F (OGSxFPT)_08.0x01.5 (200x40)
Eccentric Reducer, 8 x 6 in, groove
Victaulic_IPS_Rdcr Ecc_No 51 (OGS)_08.0x06.0 (200x150)
Flange to Nipple adapter, 6 in, groove
Victaulic_IP_Flgd Adptr Nip_CL 150 F_No 45R (OGSxFLG)_6 (150)
Flange to Nipple adapter, 10 in, groove
Victaulic_IPS_Flgd Adaptr Nip_CL 150FF_No 45F (OGSxFLG)_10
Flanged Reducing Elbow, 90 LR, 4"flg x 8"grv
Victaulic_IPS _Elb Base Sprt Redc_No R100F (OGSxFLG)_08.0x04.0 (200x100)
Reducing Tee, 8 x 2 in FNPT Branch
Victaulic_IPS_Tee Redc Thd_No 29F (OGSxFPT)_08.0x02.0
Eccentric Reducer, 10 x 8 in, groove
Victaulic_IPS_Rdcr Ecc_No 51 (OGS)_10.0x08.0 (250x200)
Elbow, 45 LR, 8 in, groove
Victaulic_IPS_Elb 45 Deg LR_No 110 (OGS)_8 (200)
Reducing Wye, 10 x 8 in, groove
Victaulic_IPS_Latl 45 Deg Redc_No 30-R SWS (OGS)_10.0x08.0 (250x200)
Reducing Tee, 10 x 8 in, groove
Victaulic_IPS_Tee Redc_No 25 (OGS)_10.0x08.0 (250x200)
Elbow, 90 LR, 10 inch, Flange to groove
Victaulic_IPS_Elb Base Sprt_No 100F (OGSxFLG)_10 (250)
2 1 ½ D
Reducing Tee, 10 x 2 in FNPT Branch
Victaulic_IPS_Tee Redc Thd_No 29F (OGSxFPT)_10.0x02.0 (250x50)
Elbow, 90 LR, 10 in, groove
Victaulic_IPS_Elb 90 Deg LR_No 100 (OGS)_10 (250)
11 1 ½ D
Reducing Tee, 10 x 4 in, groove
Victaulic_IPS_Tee Redc_No 25 (OGS)_10.0x04.0 (250x100)
Elbow, 90, 4 in, groove
Victaulic_IPS_Elb 90 Deg_No
10 (OGS)_4(100)
Flange to Nipple adapter, 4 in, groove
Victaulic_IPS_Flgd Adptr Nip_CL 150 RF_No 45r (OGSxFLG) 4 (100)
Elbow, 45, 4 in, groove
Victaulic_IPS_Elb 45 Deg_No
11 (OGS)_4 (100)
Butterfly Valve, 4 in, groove, Vic-300 MasterSeal EPDM green
Victaulic_IPS_Valve Btfl Vic- 300 MS Lvr Hdl_Series 761
(OGS) 4 (100)
10 Disk: Standard, Ductile Iron. Seat:
EPDM. Stem:
Standard 416 Stainless Steel.
Reducing Tee, 4 x
1.5 in, groove
Victaulic_IPS_Tee Redc_No 25 (OGS)_04.0x01.5 (100x40)
Conentric Reducer, 6 x 4 in, groove
Victaulic_IPS_Rdcr Conc_No 50 (OGS)_06.0 (165.1)x04.0 (150x100)
Flange to Nipple adapter, 6 in, groove
Victaulic_IPS_Flgd Adptr Nip_CL 150 FF_No 45F (OGSxFLG)_6 (150)
Flex Coupler, 4 in Victaulic_IPS_Cplg Flex_Style 177N (OGS) 4 (100) Green EPDM
54 Bolt option: Stainless steel oval neck track bolts w/ nuts
Flex Coupler, 6 in Victaulic_IPS_Cplg Flex_Style 177N (OGS) 6 (150) Green EPDM
5 Bolt option: Stainless steel oval neck track bolts w/ nuts
Flex Coupler, 8 in Victaulic_IPS_Cplg Flex_Style 177N (OGS) 8 (200) Green EPDM
38 Bolt option: Stainless steel oval neck track bolts w/ nuts
Ridged Coupler, 8 in
Victaulic_IPS_Cplg Rgd_Style
107N (OGS)_8 (200)
Green EPDM
35 Bolt option: Stainless steel oval neck track bolts w/ nuts
10 in sch. 40 Pipe, 120in +/- 1/8 inch long
16 Schedule 40 carbon steel pipe with grooved ends per Victaulic OGS specifications. Not required to be Victaulic brand.
10 in sch 40 Pipe, 11.34in +/- 1/16in long
4 Schedule 40 carbon steel pipe with grooved ends per Victaulic OGS specifications. Not required to be Victaulic brand.
10 in sch 40 Pipe, 65in +/- 1/16in long
11 Schedule 40 carbon steel pipe with grooved ends per Victaulic OGS specifications. Not required to be Victaulic brand.
10 in sch 40 Pipe,
64.91 in +/- 1/16in long
2 Schedule 40 carbon steel pipe with grooved ends per Victaulic OGS specifications. Not required to be Victaulic brand.
10 in sch 40 Pipe, 58.91in +/- 1/16in long
2 Schedule 40 carbon steel pipe with grooved ends per Victaulic OGS specifications. Not required to be Victaulic brand.
8 in sch 40 Pipe Standard Length Est. 20 ft.
5 Schedule 40 carbon steel pipe with grooved ends per Victaulic OGS specifications. Not required to be Victaulic brand.
4 in sch 40 Pipe Standard Length Est. 20 ft.
4 Schedule 40 carbon steel pipe with grooved ends per Victaulic OGS specifications. Not required to be Victaulic brand.
TECHNICAL OR SAFETY REQUIREMENTS
• Pressure-containing portions of the equipment (see table) shall be designed to the applicable sections of ASME pressure codes.
• Space Requirements/ Limitations o Installation will be by the NLR research group into an already allocated dedicated space.
There are no plans for any subcontracts or operations work for the installation of this equipment.
TIMELINE
TM: Delivery needed by end of December 2026. If there are specific items that cannot be delivered within this lead time please let the buyer know as longer/later lead times may be accepted.
| Attachment 1 |
| Technical Specifications |
| "Thermal System Piping” |
| July 14, 2026 |
| BACKGROUND |
| OBJECTIVE |
| SPECIFICATIONS: |
| REQUIRED CAPABILITIES |
| TECHNICAL OR SAFETY REQUIREMENTS |
| TIMELINE |
File details come from the government source that posted it. Updated .