ATTACHMENT 1 STATEMENT OF WORK (SOW).pdf

PDF 289 KB Posted

Attached to
Construct Cooperative Science Center, Mauna Loa Observatory Federal contract opportunity
Solicitation number
1305M323RNRMJ0016
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

This statement of work describes requirements for the design and construction of a new cooperative science center building at the Mauna Loa Observatory site in Hawaii. The project includes demolishing existing buildings and constructing a new approximately 3,600 square foot facility to support eight cooperative science partner rooms for data collection, air sampling, and analysis. Support spaces such as a conference room, mechanical room, and loading dock area are also required. The facility must avoid using materials on NOAA's banned substances list and incorporate sustainability features. The roof deck will support solar radiation monitoring equipment. Site improvements involve concrete walkways, stairs, and retaining walls. The selected contractor will complete both the design and construction of the project to result in a finished, occupiable building.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MLO - Cooperative Science Center Mauna Loa, Hawaii

PART 3

STATEMENT OF WORK / PROJECT PROGRAM - Page 1

NOAA Global Monitoring Laboratory Mauna Loa Observatory

COOPERATIVE SCIENCE CENTER

Mauna Loa, HI

Part 3 Statement of Work / Project Program

Table of Contents

CHAPTERS

1. PROJECT DESCRIPTION

CLIN. 01: Base contract: Design - Cooperative Science Center Building

CLIN. 02: Option - Construction - Cooperative Science Center Building

CLIN. 03: Option - LEED Certification

CLIN. 04: Option - Roof-top solar system

CLIN. 05: Option - Conductive concrete

2. PROJECT OBJECTIVES

3. SITE ANALYSIS

4. BUILDING REQUIREMENTS

5. ROOM REQUIREMENTS

6. ENGINEERING SYSTEMS REQUIREMENTS

A10 Foundations A20 Basement Construction B10 Superstructure B20 Exterior Closure B30 Roofing C10 Interior Construction C20 Stairs C30 Interior Finishes D10 Conveying Systems D20 Plumbing

D30 HVAC

D40 Fire Protection Systems D50 Electrical Power and Lighting

STATEMENT OF WORK / PROJECT PROGRAM - Page 2

E10 Equipment E20 Furnishings F10 Special Construction F20 Selective Building Demolition G10 Site Preparations G20 Site Improvements G30 Site Mechanical Utilities G40 Site Electrical Utilities

1.0 PROJECT DESCRIPTION

Provide all design and construction services as required to complete a new Cooperative Science Center building at the National Oceanic and Atmospheric Administration’s (NOAA) Mauna Loa Atmospheric Baseline Observatory (MLO) site, located at approximately 11,141 ft. above sea level on the north flank of the Mauna Loa volcano.

The project will include:

1. Demolition and disposal of the old building and supporting infrastructure (decks, walkways, power lines, obsolete concrete pads, etc.) located at the proposed site for the new Cooperative Science Center. Buildings to be removed include the:

a. Ground Winds Building

b. Uchida Building

c. Visitor Building

d. Schnell Building

e. Army Comms Building (tentative)

2. A new, energy-efficient ~3,600 gross square foot (gsf) facility to support up to eight cooperative science partner rooms that each include modern laboratory facilities for data collection, air sampling, and analysis. Support spaces such as a conference room with kitchenette, a mechanical room, and a loading bay/workshop area for equipment unloading and repair, are also required. A water tank holding area (exterior primary and interior secondary) and an indoor bathroom facility are required.

3. Providing static dissipation system - ground bars in each room tied to panel.

4. A roof deck ( ~1,400 sq.ft.) with access to roof-mounted equipment for study of solar radiation, and other research and equipment related to climate monitoring, is required.

5. A concrete apron area extending out on all four sides of the facility to serve as a walkway and science staging areas.

This project will be awarded as a traditional design/build contract and the intent is for the contractor that wins the award to complete both portions of the project.

Base contract - Design

● Provide a finalized design for the Cooperative Science Center including all necessary architectural, structural, mechanical, civil, etc. drawings & engineering required for the construction of the building.

STATEMENT OF WORK / PROJECT PROGRAM - Page 3

Optional items (to be priced separately) include:

● Construction for the designed building to result in a finished product that NOAA can take occupancy of.

● Leadership in Energy and Environmental Design (LEED) certification with U.S.

Green Building Council (USGBC). Target for a LEED Silver, or better, facility.

● Addition of a complete photovoltaic system with solar panels mounted on the open roof area that is not covered in the roof deck. The proposal for this option shall provide a description of the anticipated power generating capabilities of the new system along with the costs to install.

● Use conductive concrete for the Cooperative Science Center mat slab foundation to create an Ufer ground in lieu of standard concrete mix design.

a. Conductive concrete contains carbon.

b. Prior to pouring concrete, install copper cabling to the reinforcement steel

(rebar) to bond the concrete pad to the site grounding system.

c. Ensure that copper cabling is protected from damage where it exits concrete.

d. Connect copper ground to the site grounding system.

BACKGROUND

The NOAA Mauna Loa Atmospheric Baseline Observatory (MLO) is the flagship facility of the four long-term observatories operated by the NOAA Global Monitoring Laboratory (GML). The other observatories are located in Utqiagvik (Barrow), Alaska; Tula, American Samoa; and South Pole, Antarctica. The MLO site is often regarded as the “premier atmospheric science site on earth” and is home to numerous high-profile data sets including the “Keeling Curve” that first documented the rise in carbon dioxide in our global atmosphere. The observatory conducts well over 250 daily climatological measurements, some as precise as 1 part in a trillion.

The MLO facility is located at the end of an 18-mile one-lane access road reachable from Saddle Road. The start of the Mauna Loa Access Road is located just to the east of the more well-known access to the Mauna Kea Visitor Center and telescopes. Logistically, the site is at over 11,141 feet in altitude and the sun (UV) conditions can be strong and the air temp significantly cooler than elsewhere on the island. The 18-mile driveway can be challenging for longer vehicles due to the narrow width, rolling topography, and occasional sharp corners. The power lines do cross over the road in multiple locations along the upper half of the MLO access road and may pose an overhead obstruction issue for very tall vehicles (no known issues with the powerlines obstructing access to the site historically). The one-way commute time to the MLO site from either Hilo or Kona typically takes ~90-min.

Scientific measurements obtained at MLO often represent the global background conditions for the atmospheric research community. As such, the measurements taken at the site are highly precise and need to be safeguarded to ensure that indoor room air and/or local site contamination does note negatively impact the long-term records. NOAA has

STATEMENT OF WORK / PROJECT PROGRAM - Page 4 developed a comprehensive banned construction materials (chemicals) list and each product used at the site must be cleared against this banned chemical list prior to use. The banned construction materials list will be provided to vendors and NOAA can assist with reviewing individual products as needed. Furthermore, it will be required to keep the science at MLO operational as much as possible throughout construction activities. All new construction work shall meet current code requirements.

The Federal government is required to follow the National Environmental Protection Act (NEPA) process for all Federal actions. NEPA does apply to this construction effort and NOAA is actively working to get the necessary approvals from the State of Hawaii (Division of Land and Natural Resources (DLNR) / State Historic Preservation Office (SHPO)) and finalize the NEPA process. The NEPA process is running in parallel with this procurement effort and it is anticipated that the NEPA will be finalized after this procurement has been awarded. As such, it is imperative that any/all outcomes resulting from the NEPA process shall be incorporated into the final design before a notice to proceed can be issued and construction begins.

NOAA is interested in building sustainably, using robust materials that support low maintenance over the long-term, and incorporating the elements of LEED building practices (and certification) wherever possible. Thus, the biddable documents shall include the opportunity for bidders to provide alternate approach and products based on reliability and longevity and include value enhancing options to allow for LEED elements.

2.0 PROJECT OBJECTIVES

To provide a state of the art, energy efficient and sustainable facility that is safe and functional for current and future users at the MLO site.

The research at this facility includes collection and monitoring of air samples so the work must avoid the use of the banned construction materials listed in Part 6 - Attachments.

2.1 APPLICABLE CODES AND STANDARDS

In addition to the codes and standards listed in Part 4 - Generic Specifications, the design and construction must be in accordance with the latest revision/edition of the following referenced codes and standards. The term "Latest Revision/Edition" is defined as the version as of the project award date.

1. GML list of banned construction material. See Part 6 - Attachments

2. NOAA Office of the Chief Information Officer (OCIO) Facility IT Standards Guide 2007 V. 1.0 Rev 2. See Part 6 - Attachments

3. State of and county of Hawaii building codes.

4. NOAA Anti-terrorism requirements. See checklist in Part 6 - Attachments

STATEMENT OF WORK / PROJECT PROGRAM - Page 5

Department of Defense (DOD) UNIFIED FACILITIES CRITERIA (UFC) or UNIFIED FACILITY GUIDE SPECIFICATIONS (UFGS) referenced in this RFP will apply as if this were a DOD facility.

2.2 SUSTAINABLE DESIGN

Design and construct project per sustainability requirements identified in UFC 1-200-02:

HIGH PERFORMANCE AND SUSTAINABLE BUILDING REQUIREMENTS.

Additional specific sustainability requirements are found in this document.

Comply with Federal Energy Management Program’s Guiding Principles for Sustainable Federal Buildings. (https://www4.eere.energy.gov/femp/requirements/guidelines_filtering)

OPTION: Provide LEED certification

2.3 STORMWATER MANAGEMENT - LOW IMPACT

DEVELOPMENT (LID)

Comply with State and Local stormwater management program permit requirements. The designer of record must balance all applicable requirements (Federal, State, Local and the above stated policies), and acquire required regulatory permits when managing stormwater generated on this project.

3.0 SITE ANALYSIS

National Environmental Policy Act (NEPA) documentation is being prepared under a separate contract. The final outcome of that document will be incorporated into the design of the facility.

3.1 EXISTING SITE CONDITIONS

The vendor shall minimize impacts to ongoing operations at the rest of the MLO site.

The MLO site operates on an 8-acre land parcel and consists of multiple research buildings. The Keeling Building is the original structure at the site and is a sixty-five year old (built in 1956), single story, rectangular, cinder block structure ~1,250 sq.ft. with an A-frame wood truss roof system that is clad with a vented corrugated metal roof. Due to the age of the Keeling building and significance of the science that it represents, NOAA has determined that the original cinder block constructed building is likely eligible for the national historical register. However, it has not been listed as such.

STATEMENT OF WORK / PROJECT PROGRAM - Page 6

Adjacent to the Keeling building, are the Hawaiian Telcom block building and the Army’s fiberglass communications building (both structures to remain in place). Additional facilities on site include the National Detection for Atmospheric Composition Change (NDACC) facility and multiple smaller astronomy domes and metal-clad buildings.

A preliminary floor plan design was completed in 2021 and updated in 2022. The design and associated documents are included in Part 6 - Attachments.

NOTE: PREVIOUS DESIGN DOCUMENTS ARE INCLUDED FOR REFERENCE

ONLY AND DO NOT NECESSARILY REPRESENT THE FINAL CONFIGURATION

OF THE FACILITY. THE CONTRACTOR’S DESIGNER OF RECORD IS

RESPONSIBLE FOR THE FINAL DESIGN OF THIS PROJECT.

Any Government provided design or geotechnical data is included for the Contractor’s information only, and while it is considered to represent subsurface conditions existing on the project site anticipated at this time, it is not guaranteed to fully represent all subsurface conditions. The Contractor will be responsible for providing the services of a geotechnical engineer to conduct any subsurface exploration, investigation, testing, and analysis that the Designer of Record deems necessary for the design and construction of the proposed facility and site improvements. The geotechnical engineer must be registered as a Professional Engineer (Geotechnical Engineer where required by law) and experienced with soil conditions in the region where the project site is located. The geotechnical engineer must prepare a report addressing any elements of the work requiring his services.

The report must be submitted to the Contracting Officer accompanied by a letter from the Designer of Record certifying that the Geotechnical Engineer has reviewed the construction documents and that the design reflects the recommendations of the geotechnical report.

3.2 SITE DEVELOPMENT

The building footprint indicated on draft design documents is conceptual but the orientation and relationship to the existing structures has been vetted with the customer and is to be maintained to the greatest extent possible.

Building finished floor height shall be no higher than 8” above the existing grade.

Pedestrian Access and Circulation Requirements

An exterior concrete apron around all four sides of the facility is required. The walkway should be nominally 4’ wide on the south and west side, 8’ wide on the north side, and 20’ wide on the east. The concrete apron on each side should have the appropriate slope to drain rainwater AWAY from the building, but also be usable as a walkway and scientific staging area.

The walkway should include a ramp from the finished height to grade on the east side to facilitate walking to the front door. In addition, a ramp structurally capable of supporting

STATEMENT OF WORK / PROJECT PROGRAM - Page 7 a vehicle carrying supplies is required to support vehicles backing into the loading bay on the east side.

Redesign walkway and stairs from west end of the new facility to provide access to the Hawaiian Telcom building and to the parking lot at the east side of the Keeling Building.

Existing wooden walkways and stairs should be removed and disposed of. All new walkways should match existing galvanized walking surfaces on site and stairs should be either concrete or galvanized. Walkway height shall be coordinated with the slab height and matched to the greatest extent possible.

A concrete retaining wall may be necessary on the south side of the building as the building site’s grade is a multiple feet below the adjacent parking lot. Currently, the hillside between the parking lot grade and that of the existing buildings is a loose lava rock of various sizes.

Roof Platform Requirements A roof platform (nominally 1,400 sf) and railings with exterior stair access is required.

The roof deck can be added to either end of the building that best accommodates overall building design. Roof platform will support sensitive solar radiation equipment and should have zero vibration when staff walk on the deck surface.

Include power to the roof platform including a minimum of quad outlets located every six feet around the perimeter and additionally two rows (North-South) of quad outlets located every six feet for instrument tables splitting the deck into thirds. No more than three quad outlets on any circuit. Power circuits should be all weather and meet all code requirements.

Roof instrument tables should be provided using 80/20 T-slot aluminum uni-strut. Table tops should be ~2” below railing height, 30-36” wide, and secured to the platform decking to not move. The table tops can be the same aluminum metal bar grating used for the deck surface, or similar material.

PVC conduits (4” diameter) shall be installed every ~10-12’ to route instrument signal cables from the roof deck down into the laboratory spaces below. On the exterior, all exterior PVC tubes should also be capped with rubber covers and the conduits should each have two 90-degree radius bends so the tube is facing down to keep water from entering the system. Exterior conduits inlet should be ~ half the distance from the deck surface to the table top. On the interior, these conduits should drop into the laboratory spaces and terminate ~4” above the interior cable trays.

Railing shall have a gate that opens outward on the south side to allow for materials to be loaded from the parking lot. Gate should be a minimum of 6’ wide and be securely closed when not in use.

Roof platform structure, stairs and railings shall be non corrosive metal. Decking to be aluminum metal bar grating sized for anticipated loads.

Site utilities

STATEMENT OF WORK / PROJECT PROGRAM - Page 8

Electricity is available on site. There is no water or sewer service at the site. A gutter rain-water catchment system is required and should be incorporated into the design for use in the sinks and toilet. Note the water catchment system will NOT be used for drinking water and no external cistern is available and existing for this new building. The facility's wastewater will need to be incorporated into the existing septic system, if possible, or an additional septic system will need to be incorporated into the design.

4.0 BUILDING REQUIREMENTS

4.1 Space Tabulation (tentative based on draft floor plan)

Space Name # of spaces

Unit

SF

(Net)

Total

SF

(Net) Remarks

Conference room 1 380 380 Kitchenette area 1 80 80 Loading dock 1 450 450 Includes closet/ storage for mop Bathroom 1 60 60 Mechanical 1 80 80 Science laboratory 8 240 1920 Corridor 1 320 320

Subtotal Net Area 3290 Net to Gross Factor 1.10

TOTAL GROSS AREA 3619

The design build contractor shall provide actual area in both square feet and square meters in proposals.

4.2 Space Relationships

See Section 5.0 Room Requirements below and the Concept Layout blocking diagram attachment in Part 6 - Attachments

4.3 Exterior Character

Coordinate with existing facilities. North facing exterior wall color will differ from the other three wall colors. North wall should be a darker shade than the other three walls.

The MLO facility is clearly visible from Saddle Road and efforts should be made to reduce this visibility on the north side of the facility.

5.0 ROOM REQUIREMENTS

Climate Zone: Temperate (summer-dry cool)

STATEMENT OF WORK / PROJECT PROGRAM - Page 9

Conference room

Space Characteristics

Function/adjacencies: Conference room with large windows.

Special Dimensions:

Ideal Plan Dimensions: Flexible ~380 sq ft.

Minimum Ceiling Height: Flexible

Acoustics: N/A

Access: Shall be located adjacent to the main entrance on the east end of the facility. Exterior door should be locking.

Number of Occupants: <18

Other/Special Requirements: This room should be located in the northeast corner of the building to allow for easy access into the conference and to best capture the dramatic views from the site to the east and north. Large conference room windows on the east and north walls.

Uniformat Section

Description Qty Size Specific Requirements

C3020 Floor Durable, non-slip, material. Concrete or vinyl.

D5020 Lighting Dimmable LED ceiling lighting with switch at the door.

C10 Interior doors Double door access into the corridor to the science laboratories. Single door access into the bathroom. Single door (fire rated) access into the loading dock area.

C10 Exterior doors Main entrance double doors to access the facility from the east. Doors should be locking.

D50 Power One 20-A circuit for the room for outlets.

B2020 Windows

Provide non-opening windows on east and north walls.

Bottom of window height is flexible and can range from 0”- 36” off the finished floor. Windows should include window treatments (roller shades) or similar to darken the room as needed for meetings/presentations.

C1030 Conference Table and chairs

1 table, 18 chairs

Provide a conference table to seat a minimum of 10 staff and additional seating to accommodate 18 staff total.

D5030 Data Provide 2 (ea) quad outlets (total of 8 lines)

Science Laboratory Areas

Space Characteristics

Function/adjacencies: Main science laboratory areas.

Special Dimensions:

Ideal Plan Dimensions: Flexible – ~240 sq ft. per room. 6-8 total rooms.

Minimum Ceiling Height: Flexible

Acoustics: Noise reducing materials required to minimize acoustics from running instrumentation.

STATEMENT OF WORK / PROJECT PROGRAM - Page 10

Access: Must be located along the main corridor of the facility. Access to adjacent lab to create larger science areas by merging two adjacent rooms into one larger space is required.

Number of Occupants: <4

Other/Special Requirements: Rooms must include power around the perimeter in a racetrack at bench height. Lab benches (~15 linear ft) per room and one storage cabinet is required. Hanging wire cable trays are required around each room above lab benches. Cable trays should interconnect between all of the laboratories and also extend into the mechanical room to access the IT server rack.

Uniformat Section

Description Qty Size Specific Requirements

C3020 Floor Durable, non-slip. Concrete or vinyl. Anti-static material should also be considered.

D5020 Lighting Dimmable LED ceiling lighting (3-way) with switches.

C1020 Interior doors

Door(s) must be locking and accessible from corridor.

Double doors between lab spaces should be the largest opening possible. Double doors into corridors (where applicable) should be full 6’ width available to move cargo in the facility.

D50 Power

One 20-A circuit for each laboratory bench in the room.

Approximately 4 circuits total in each room. Each bench should be on an independent breaker. Power in raceways 18 inches above bench tops.

C1030 Lab benches Approx 15 lf

36” standard width

Lab benches distributed in each room along full north-south walls and on each side of double doors into adjacent lab. Lab benches should include storage under each benchtop surface and have wooden tops. Benches to be provided as part of this design/build project.

B2020 Windows Each room shall have a minimum of one exterior window for ambient lighting. Windows must have blinds or ability to block sunlight as needed.

C1030 Shelving/Cabinets

Minimum of 1 heavy-duty shelving/cabinets unit with doors to store spare parts in each room. Shelving units shall be >12” depth and match (paint color) the benches.

Shelving/Cabinets to be provided as part of this design/build project.

Cable Trays Approx 60 lf per room

Minimum of 6” standard width and 4” depth.

Hanging cable tray (wire mesh) from the ceiling should pass through all the science rooms (continuous through walls) and also access the mechanical room to route IT cables back to the server rack. Hanging cable trays will also be used to route data and sample lines around rooms and to the roof deck.

B30 Roof Hatch 3’x3’ or 4’x4’

Opening

One roof hatch is required above one science laboratory.

Location is flexible. Interior laboratory space should extend up into the chimney needed to support the roof hatch and be accessible with a ladder within the laboratory space.

D30 HVAC heating cooling equipment

Heating should be electric baseboard on thermostat. No AC units should be used. (Refrigerants used for cooling are measured at the site at one part per trillion, so CFCs, HFCs, etc. are banned at MLO.) Individual rooms may have large instrument loads that warm the room. Design system to

STATEMENT OF WORK / PROJECT PROGRAM - Page 11 bring cooler external air into the room and vent warmer exhaust air into the corridor. Then, design ventilation for the corridor to be able to exhaust this additional heat, as needed.

The system (fans, dampeners, louvers, etc.) should all be controlled via thermostats and be able to hold temperatures in any given room +/- 5 degrees F. Consider variable speed (RPM) fans that can turn on/off and increase speed as needed to control temps.

E1020 Flammable Storage

Small benchtop-sized flammable storage cabinet in each room. Actual dimensions to be determined during the design phase

D5030 Data Provide 2 (ea) quad outlets above each 8’ of bench. Data can also be in a separate racetrack around the lab.

Loading Dock Area

Function/adjacencies: Loading/unloading of equipment and supplies for the facility. Storage for facility supplies and short-term staging area .

Special Dimensions:

Ideal Plan Dimensions: Flexible – ~450 sq ft.

Minimum Ceiling Height: Flexible

Acoustics: N/A

Access: Must be located on the east end of the facility to allow vehicles to drive up to the loading bay. Overhead garage door entrance. Concrete ramp from grade to finished-floor height also required.

Number of Occupants: <4

Other/Special Requirements: This room should have double door access into the corridor to facilitate moving larger cargo from the loading bay into one of the scientific labs.

Uniformat Section

Description Qty Size Specific Requirements

C3020 Floor Durable, non-slip, material. Concrete.

D5020 Lighting Dimmable LED ceiling lighting (3-way) with switches near each door.

C1020 Interior doors Doors must be fire rated.

D50 Power One 20-A circuit with multiple outlets in the loading bay.

One 40-A (220v) circuit. One EV charging station on exterior of building (just outside of loading dock).

C1030

Work bench Approx

8 LF

TBD

Approximately 2-3 lab benches distributed throughout space for instrumentation. Some must be located along eastern wall.

D30 Soldering hood Soldering hood located above one bench to vent solder fumes.

STATEMENT OF WORK / PROJECT PROGRAM - Page 12

B2020 Windows TBD Space shall have a minimum of one exterior window for ambient lighting. Window must have blinds or ability to block sunlight as needed.

C1030 Shelving Minimum of 4 heavy duty and adjustable height shelving units to store spare parts.

E1020 Flammable Storage Large flammable storage cabinet. Actual dimensions to be determined during the design phase

E1020 Cylinder storage Space and racks to securely store up to 10 standard “K” size cylinders in the room.

D5030 Data Provide 1 quad outlet above the work bench.

Storage/Janitorial Closet

Function/adjacencies: Storage/janitorial closet.

Special Dimensions:

Ideal Plan Dimensions: Flexible Minimum Ceiling Height: Flexible

Acoustics: =N/A

Access: Janitorial closet and storage locations flexible, but must be accessible from either the corridor or the loading bay.

Number of Occupants: N/A

Other/Special Requirements: Door to keep supplies out of sight.

Uniformat Section

Description Qty Size Specific Requirements

C3020 Floor Durable, non-slip, material. Concrete or vinyl.

D5020 Lighting LED ceiling lighting with switch inside door.

Janitorial closet Location flexible, shall be accessed by corridor or loading bay. Shelving on one wall.

Kitchenette Area

Function/adjacencies: Break/lunch area for facility.

Special Dimensions:

Ideal Plan Dimensions: Flexible Minimum Ceiling Height: Flexible

Acoustics: N/A

STATEMENT OF WORK / PROJECT PROGRAM - Page 13

Access: Room should be adjacent to the conference room or part of the same open floor plan as the conference room. The mechanical room should be relatively close to minimize pipe lengths inside the facility.

Number of Occupants: 4

Other/Special Requirements: Non-potable water in sink for handwashing only. Provide drinking water dispensing machine with both cold and hot water options.

Description Qty Size Specific Requirements

C3020 Floor Durable, non-slip, material. Concrete or vinyl.

D5020 Lighting Dimmable LED ceiling lighting. With switch and lighting provided above the countertop area.

E10 Appliances Typical kitchenette with sink, small stove/oven, microwave, and refrigerator. No dishwasher.

D20 Water system Water system (interior holding tank in mechanical) to service restroom (sink and toilet).

D20 Sanitary Sewage system Tie into existing septic on site or build dedicated for this facility.

C1030 Kitchen cabinets and countertop

Cabinets to store food/drink supplies. Counterspace to allow food preparation and outlets to power toaster, coffee maker, etc.

D20 Sink On-demand hot water heater under sink to allow for hot water to wash hands and dishes.

E20 Lunch table/seating Include a table (standard or bar height) with four chairs.

Restroom

Function/adjacencies: Lavatory for facility.

Special Dimensions:

Ideal Plan Dimensions: Flexible Minimum Ceiling Height: Flexible

Acoustics: N/A

Access: Room should be accessible from the conference room and kitchenette area. Shouldt be adjacent to the mechanical room to minimize pipe lengths inside the facility. Must have a locking door.

Number of Occupants: 1

Other/Special Requirements: Meet ADA requirements.

STATEMENT OF WORK / PROJECT PROGRAM - Page 14

Uniformat Section

Description Qty Size Specific Requirements

C2030 Floor Durable, non-slip, material. Concrete or vinyl.

D5020 Lighting Dimmable LED ceiling lighting with switch inside door.

C1010 Walls Additional wall thickness to insulate room (noise) from the rest of the facility.

D20 Water system Water system (interior holding tank in mechanical) to service restroom (sink and toilet).

D20 Sewage system Tie into existing septic on site or build dedicated for this facility.

C1020 Door Locking interior door.

D2010 Toilet High-efficiency (low flow) toilet.

D2010 Urinal Water-less urinal, if space allows.

D2010 Sink with vanity Sink with on-demand hot water heater below in cabinet.

Mirror above sink. High-efficiency (low-flow) water faucet.

C1030 Storage cabinets Cabinets to store bathroom supplies, if space allows..

D30 Ceiling/exhaust fan Exhaust fan installed in ceiling.

Mechanical Room

Function/adjacencies: Primary mechanical room for water/electrical distribution to facility.

Special Dimensions: Ensure proper clearance around all equipment per code and size mechanical room accordingly.

Ideal Plan Dimensions: Flexible Minimum Ceiling Height: Flexible

Acoustics: N/A

Access: Should be accessible from the corridor and not from the conference room area directly. Must have a locking door.

Number of Occupants: N/A

Other/Special Requirements: Include space and power for one IT server rack. If water holding tank co-located in the mechanical with the IT, build IT rack onto 4” concrete curb to elevate rack (and power) above floor in case of leaks.

Description Qty Size Specific Requirements

C3020 Floor Durable, non-slip, material. Concrete. See note above regarding elevating IT server rack, as needed.

STATEMENT OF WORK / PROJECT PROGRAM - Page 15

D5020 Lighting LED ceiling lighting with switch inside door.

C1020 Door 1 Door must be fire rated.

C1010 Walls Additional insulation or wall thickness to insulate room (temp) and to minimize noise from mechanical from rest of facility.

C1030 Shelving 2 10” x 48” x 60”

Shelving built against one wall for storage of spare gear.

Units on wheels would be preferred.

D20 Water system

Water system (small interior holding tank) to service restroom and kitchenette. Main water storage tank should be exterior to the facility (west side) and capture rainwater from gutters. If an internal tank is not necessary and internal plumbing can run directly from the exterior holding tank, that is also acceptable.

MUST BE ABLE TO PUMP TO THE EXTERIOR

HOLDING TANK FROM THE PARKING LOT

ADJACENT (SOUTH) OF THE BUILDING.

D20 Sewage system

Tie into existing septic on site or build dedicated for this facility.

MUST BE ABLE TO ACCESS THE SEPTIC TANK

FROM THE PARKING LOT ON EITHER SOUTH OR

EAST SIDE OF THE BUILDING.

D30 Equipment dampening Provide structural vibration isolation between mechanical room equipment and the rest of the facility.

IT Server Rack (full height)

Per IT requirements listed in Part 6 - Attachments. Include integrated UPS system. Cable trays as required.

D50 Power One IT server rack

For the IT Server rack: typically, one rack unit requires ~4kW. Rack shall have two dedicated circuits.

Cable Trays Approx 12 lf

Minimum of 6” standard width and 4” depth.

Hanging cable tray (wire mesh) from the ceiling should pass through all the science rooms (continuous through walls) and also access the mechanical room to route IT cables back to the server rack.

D30 HVAC heating cooling

Per design requirements.

Corridor / Hallway

Function/adjacencies: Access to all science laboratories, the loading bay, and conference room/kitchenette/bathroom area. Should have double doors on the east end and a single door exterior exit on the west end..

Special Dimensions:

Ideal Plan Dimensions: Flexible Minimum Ceiling Height: Flexible

Acoustics:

Access: Immediately interior of west entrance entrance. Adjacent to the conference/kitchenette area and main front doors on the east. .

STATEMENT OF WORK / PROJECT PROGRAM - Page 16

Number of Occupants:

Other/Special Requirements: East double doors should have the ability to be held open, if needed.

Description Qty Size Specific Requirements

C3020 Floor Durable, non-slip, material. Concrete or vinyl.

D50 Lighting Dimmable LED ceiling lighting (3-way) with switches near exit doors.

D2020 Eyewash Locate one eyewash station for the facility. Location flexible but should be accessible from all rooms.

C1020 Exterior doors Exterior door on west end of corridor should be locking and extra-wide (48”) single door. Door should swing outward and to the north.

C1020 Interior doors

Double doors into corridor from loading bay should be full 6’width available to move cargo in the facility. Double doors for access between the corridor and the conference room area can be slightly narrower width if needed.

D30 HVAC heating cooling

Individual science rooms may have large instrument loads that warm the room. Design system to bring cooler external air into the room and vent warmer exhaust air into the corridor. Then, design ventilation for the corridor to be able to exhaust this additional heat, as needed. The system (fans, dampeners, louvers, etc.) should all be controlled via thermostats and be able to hold temperatures in any given room +/- 5 degrees F. Consider variable speed (RPM) fans that can turn on/off and increase speed as needed to control temps. Include ventilation from Conference/Kitchenette area into corridor.

Walls Protect lower 36-48” of walls with durable material so that equipment moving does not damage drywall.

Educational materials display - Poster frames

8 36”x48” Poster snap frames. Location flexible, but required, to hang facility/safety information and display science.

STATEMENT OF WORK / PROJECT PROGRAM - Page 17

6.0 ENGINEERING SYSTEMS REQUIREMENTS (ESR)

A10 Foundations A20 Basement Construction B10 Superstructure B20 Exterior Closure B30 Roofing C10 Interior Construction C20 Stairs C30 Interior Finishes D10 Conveying Systems D20 Plumbing

D30 HVAC

D40 Fire Protection Systems D50 Electrical Power and Lighting E10 Equipment E20 Furnishings F10 Special Construction F20 Selective Building Demo G10 Site Preparations G20 Site Improvements G30 Site Civil/Mechanical Utilities G40 Site Electrical Utilities

A10 FOUNDATION

Provide a concrete slab foundation. See alternative option for a conductive concrete slab also.

Slab should be extended in each direction to provide walkways and scientific staging areas around the building. The walkway should be nominally 4’ wide on the south and west side, 8’ wide on the north side, and 20’ wide on the east. The concrete apron on each side should have the appropriate slope to drain rainwater AWAY from the building, but also be usable as a walkway and scientific staging area.

B10 SUPERSTRUCTURE

The structural system must be designed using the following parameters:

International Building Code (IBC) Risk Category II

Live loads: In accordance with UFC 3-301-01, Structural Engineering. Determine the design wind speed, ground snow load, and seismic parameters from UFC 3-301-01, Structural Engineering. Determine the wind exposure category from IBC Paragraph

1609.4. Determine the snow exposure category from American Society of Civil Engineers (ASCE) 7-10 Table 7-2.

STATEMENT OF WORK / PROJECT PROGRAM - Page 18

B20 EXTERIOR ENCLOSURE

Insulation as appropriate for the elevation of MLO.

B2010 EXTERIOR WALLS

Vapor Retarder, Air Barrier and Insulation Provide continuous insulation, vapor retarder and air barrier to exceed requirements of UFC 3-101-01 Architecture and the American Society for Heating, Refrigerating, and Air- Conditioning Engineers (ASHRAE) 90.1 per the project's energy savings requirements.

Confirm building envelope thermal performance with infrared thermography testing described in Part 4.

Confirm air barrier compliance with air barrier performance testing described in Part 4.

Exterior Louvers & Screens Provide exterior louvers and screens, where required, that match the finish of the windows and are detailed to integrate with the architecture of the building, as appropriate to the design of the building.

Balcony Walls & Handrails Provide complete metal balcony walls and non-corrosive metal railing systems including anchors and attachment sleeves and fasteners.

Exterior Coatings Provide field applied exterior coatings for all items that are not prefinished, and to prefinished items when required to provide a color other than a standard prefinished color.

All paint must be in accordance with the Master Painter Institute (MPI) standards for the exterior architectural surface being finished.

Joint Sealants Provide exterior application of joint sealants to seal joints and prepare for finish material installation. Ensure all sealants comply with the Banned Compounds List.

B2020 EXTERIOR WINDOWS

As much as practical, windows must be provided in each area of the building that is regularly occupied, with a goal of enhancing the working environment without compromising visual acuity and comfort. Windows can provide for natural lighting in the spaces and reduce the need for lighting to be used. Provide windows meeting thermal performance required by Part 4 - General Specifications.

Windows Provide a mockup of one typical combination window unit for the project. North-facing

STATEMENT OF WORK / PROJECT PROGRAM - Page 19 laboratory spaces should have windows that can open for maximum scientific flexibility.

Exterior Glazing Glazing must be clear, laminated, insulating glass units.

B2030 EXTERIOR DOORS

Exterior doors: Exterior doors shall have the following minimum characteristics:

- Locking

- Outward opening

- Weather stripping

- Metal, glass, or a combination of each.

- Provide exterior drip edge (wall, flashing, or other system) to keep water from dripping down the front door and jamb.

Thermal performance: At minimum, doors (including access hatches) shall meet thermal performance required by Part 4 - General Specifications.

B30 ROOFING

Provide an insulated roof system design and construction including all necessary ancillary and incidental work necessary for a complete and watertight roof system installation.

One roof hatch 3’x3’ or 4’x4’ is required above a science lab space. Exact location is flexible and can either be above a laboratory space where the roof deck is, or, where the roof deck is not located. If the laboratory is below the roof deck, the hatch chimney (interior space) should extend up and through the roof deck with the hatch terminating ~24” above the roof deck height. If the hatch is located in a room without the roof deck overheard, the hatch should terminate ~24” above the height of the roof decking. The hatch should be able to open, mounted level, and flashed and sealed to be a water-tight component of the roofing system.

B3010 ROOF COVERINGS

Provide insulation, roof membrane, membrane flashing, sheet metal flashing materials, and accessories and incidental work necessary for a complete and watertight roof system installation.

Insulation system should be no less than that required by ASHRAE 90.1, Chapter 5 for the project climate zone.

Exposed sheet metal items must be of the same material. Consider the following as exposed sheet metal: gutters, including hangers; downspouts; gravel stops and fascias; cap, valley, steeped, base, and eave flashings and related accessories.

STATEMENT OF WORK / PROJECT PROGRAM - Page 20

B3020 PERFORMANCE REQUIREMENTS

The installed roof system must be watertight; free of defects in materials and workmanship; free of damage, including blisters, delaminations, cuts, scratches, abrasions, and patchwork; provide for positive drainage of the roof surface area; and suitable for the climatic and service conditions of the installation.

Provide roof system with solar reflectance, thermal emittance and total thermal performance as prescribed by ASHRAE 90.1, Chapter 5 for project climate zone and as required by other project sustainability goals.

B3030 WIND UPLIFT AND FIRE RESISTANCE REQUIREMENTS

The roof system must be designed and attached to resist wind uplift pressures calculated in accordance with ASCE 7. Uplift resistance must be validated by applicable Factory Mutual (FM) uplift testing, or calculations based on standard engineering practice and applicable recommendations of FM.

Sheet metal perimeter and flashing components must be designed, attached, and installed to provide for wind resistance equivalent to or greater than that required for the roof membrane system, and in accordance with FM, National Roofing Contractors Association (NRCA), or other applicable industry standard recommendations. Gravel stops and fascia on low slope built-up, modified bitumen, and single-ply roofs less than 2:12 in slope must conform to the requirements of ANSI/SPRI ES-1.

The roof system must provide Class A or Class B fire resistance, as tested by standard American Standard Testing and Materials (ASTM), FM, or Underwriters Laboratories (UL) procedures.

B3040 ROOF WARRANTY

Provide a manufacturer no-dollar-limit 20-year watertightness warranty for the total roof system, including flashings, in accordance with referenced requirements of Standard Design-Build Template PTS B30.

Manufacturer's warranty must provide for full removal and replacement of failed, defective, and damaged roof system materials or installation workmanship in the event of water intrusion into or through the roof system, and repair of defects such as blistering, delamination, open seams, cracking, splitting, and excessive weathering. Warranty for corrective action must not be limited in dollar value.

Provide minimum two-year contractor warranty against defects in installation workmanship in accordance with referenced requirements of Standard Design-Build Template PTS B30. Contractor warranty must provide for full removal and replacement of failed or defective workmanship and damaged materials, including sheet metal flashings.

STATEMENT OF WORK / PROJECT PROGRAM - Page 21

B3050 ROOF SPECIFICATION AND DETAILING

All work, materials, installation and details must be in accordance with Standard Design- Build Template PTS B30 and comply with all applicable UFGS materials and installation requirements. UFGS's are referenced in PTS B30 and are available at www.wbdg.org/ccb/browse_cat.php?c=3 . Provide for complete rough carpentry, roof insulation, roof covering, sheet metal flashing, and other components necessary to complete the installation.

Utilize the applicable UFGS for development of the roof membrane specification. Edit for application to the specific project and compliance with the RFP. Provide complete rough carpentry, roof insulation, and sheet metal flashing specification sections coordinated and compatible with the membrane specification.

All details must be in accordance with recommendations and guidelines of the NRCA Roofing and Waterproofing Manual and Construction Details and as required by the Request for Proposal (RFP).

The roof system must comply with the applicable requirements of the IBC. Refer to UFC 3-110-03, Roofing, and UFC 3-101-01, Architecture for additional technical requirements for the roof system to be installed.

B3060 ROOF DESIGNER REQUIREMENTS

Provide materials specification, installation requirements, and system detailing to include all flashings, penetrations, closures, corners, intersections, terminations, transitions, interfaces, joint, and lap conditions to provide for a watertight installation.

The Contractor must utilize the services of a Registered Roof Consultant (RRC) certified by the Roof Consultants Institute, or a Registered Professional Architect or Professional Engineer either of which is knowledgeable and experienced in roof investigation, inspection, and design and specializes in roof design and roof consulting services. The consultant must be thoroughly familiar with the field conditions and prepare the design or provide design review and approval prior to design acceptance by the Contracting Officer.

The consultant must validate in writing familiarity with field conditions and that the design for the project is complete, in accordance with the current edition of NRCA Roofing and Waterproofing Manual, UFC's, RFP, and standard industry practices and building codes, and provides for a complete and effective roof system solution and design.

B3070 QUALITY CONTROL PROGRAM

Contractor must establish a quality control program to assure adherence to the contract design and construction requirements and to report on the installation quality.

STATEMENT OF WORK / PROJECT PROGRAM - Page 22

C10 INTERIOR CONSTRUCTION

Interior Construction The scientific laboratory spaces require separation from the adjacent spaces. The partitions for the Loading Bay, Restroom, and Mechanical should incorporate additional insulation and separation from adjacent spaces.

C1010 PARTITIONS

Fixed Partitions Provide fixed interior partitions, except where demountable or retractable partitions are specifically required. Sound-rated partition assemblies must have a minimum Sound Transmission Coefficient (STC) of 50 in accordance with ASTM E 90 or ASTM E 413 for frequency data.

C1020 INTERIOR DOORS

Provide metal doors with hollow metal door frames.

Provide vision glazing in doors where it is required by this RFP, or it is deemed advantageous to be able to see through the door, either for safety of pedestrian traffic, or other functional reason.

C1030 SPECIALTIES

Toilet and Bath Accessories Contractor to confirm toilet and bath accessories conform to facility/client requirements and janitorial contracts.

Provide toilet and bath accessories including toilet paper holder, soap dispenser, trash receptacle/paper towel dispenser: convertible automatic universal, roll paper towel dispenser and 12-gallon waste receptacle module.

Marker Boards and Tack Boards Provide one marker boards in each science lab. Provide one marker board in the conference room. Provide one tack board in the Kitchenette area.

Signage All interior doors must have an identifying device per UFC 3-120-10, Sign Standards.

Shelving Provide steel utility shelving in the loading bay as specified in Chapter 5 above.

STATEMENT OF WORK / PROJECT PROGRAM - Page 23

Fire Extinguisher Cabinets and Fire Extinguishers Provide fire extinguisher cabinets and fire extinguishers where required by UFC 3-600-01, Fire Protection Engineering for Facilities, and the building / fire codes. Coordinate size and Class of fire extinguishers with the local Fire Department.

Counters Provide solid countertops and backsplashes in Kitchenette.

Cabinets Provide cabinetry and millwork items with associated accessories and hardware. Cabinetry must be AWI premium grade and have concealed hinges with adjustable standards for shelves. All exposed surfaces will be covered with high pressure plastic laminate clad, or hardwood veneer with exposed edges of solid hardwood.

Casework Lab benches (workbenches): Provide pre-manufactured metal cabinetry with epoxy or wooden tops for spaces identified in Chapter 5 above.

Firestopping Penetrations Provide all sleeves, caulking, and flashing for firestopping penetrations, as required.

Entrance Floor Grilles and Mats Provide recessed pan floor mats at all building entrances.

Other Interior Specialties Provide one, full-height, IT server rack (locking) in the mechanical room and dedicated power circuits (two) as identified in Chapter 5 above.

C30 INTERIOR FINISHES

C3010 WALL FINISHES

Unless noted otherwise, all interior gypsum board wall partitions and interior concrete masonry partitions must be painted.

Provide ceramic tile wainscot in all toilet rooms to a height of 6 feet.

Provide acoustical sound absorbing materials to walls as indicated in room requirements sheets in chapter 5.

STATEMENT OF WORK / PROJECT PROGRAM - Page 24

C3020 FLOOR FINISHES

Provide slip resistant commercial grade resilient flooring materials. If concrete flooring is used, provide finished interior grade and sealed surface.

Consider providing anti-static floor in scientific laboratory spaces identified in Chapter 5 as an alterative.

C3030 CEILING FINISHES

Finished ceiling is required. Ceiling system must allow easy access to all above ceiling equipment. If design incorporates open ceiling above any room area, all installed conduit, HVAC, structural supports, etc. must be painted.

D10 CONVEYING SYSTEMS

Not used

D20 PLUMBING

This project will include the design of a self-contained plumbing system for a water supply (rainwater catchment and cistern(s)) and wastewater (septic). There are no water or sanitary services provided to the site.

Provide heat-trace and insulation on all water and sewer piping

Provide secondary containment for internal water storage tank, if used.

D2010 PLUMBING FIXTURES

Provide quantity and type of plumbing fixtures required for the occupancy, use, and functions described for this facility and in accordance with the plumbing code. Provide handicapped fixtures in accordance with the referenced criteria.

Provide low flow fixtures at all locations.

Water Closets Provide floor mounted flush tank type water closets in private restroom spaces.

Urinals Provide non water use type urinals in all public restroom spaces, if included.

STATEMENT OF WORK / PROJECT PROGRAM - Page 25

Lavatories Provide undermount countertop sink in lavatory.

Sinks Provide undermount stainless steel kitchen sink.

D2020 DOMESTIC WATER EQUIPMENT

Provide instantaneous electric water heaters (under sink) to support the kitchen and bathroom sinks.

Provide emergency eyewash station in the main space.

Other Domestic Water Supply Provide piping supports in accordance with the IPC. Provide inspections, disinfection, and testing in accordance with the IPC.

D2030 SANITARY WASTE

Provide connection to existing site septic system, if possible. Location of existing septic (distance and elevation) may not make this possible.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .