Attachment 1 - Statement of Work - RV1 7-01-2025.pdf

PDF 5 MB Posted

Attached to
Brainard Lake Recreation Area Deferred Maintenance Phase #1 - Recreation Site Improvements, Arapaho and Roosevelt National Forest, Colorado
Solicitation number
1240LT25R0034
Issued by

About this file

This Statement of Work (SOW) details the Brainard Lake Recreation Area Deferred Maintenance – Phase #1 Recreation Site Improvements Project for the US Department of Agriculture's Forest Service. The project focuses on renovating three high-use recreation sites near Ward, Colorado, including Niwot Picnic Ground, Arickaree Picnic Ground, and Red Rock Lake Picnic Ground. Specific renovation tasks include demolishing existing infrastructure, constructing new vault toilet structures, creating timber steps and rock retaining walls, building accessible compacted aggregate trails, renovating historic picnic sites, and revegetating disturbed areas.

The project will be conducted in the Arapaho & Roosevelt National Forests & Pawnee National Grassland, targeting a recreation area that receives approximately 250,000 visitors annually. Work is restricted to daylight hours, excluding weekends and federal holidays, with a prescribed order of site improvements: Niwot Picnic Ground first, followed by Arickaree Picnic Ground, and then Red Rock Lake Picnic Ground. The project aims to reduce deferred maintenance and improve accessibility while preserving the area's natural and historic characteristics. The estimated project magnitude ranges between $500,000 and $1,000,000, with a planned implementation date of July 1, 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e Brainard Lake Recreation Area Deferred Maintenance – Phase #1 Recreation Site Improvements Project

US Department of Agriculture (USDA)

Statement of Work (SOW) Brainard Lake Recreation Area (BLRA) Deferred Maintenance –

Phase #1 Recreation Site Improvement Project (Updated)

Arapaho & Roosevelt National Forests & Pawnee National Grassland

Boulder Ranger District – Ward, Colorado

Prepared 7/01/2025

2 | P a g e

Contents Project General Information

1.0 Background

2.0 Scope of Work

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Location

Appendix A – Project Site Locations Map Appendix B – Project Site Photos

3 | P a g e

Project Brainard Lake Recreation Area (BLRA) Deferred Maintenance – Phase #1 Recreation Site Improvements Project

General Information

1.0 Background

Brainard Lake Recreation Area (BLRA) is a unique set of developed recreation sites that are nestled up next to the Indian Peak Wilderness Area on the Boulder Ranger District near Ward, Colorado. This project covers a few of these recreation sites including Niwot Picnic Ground, Red Rock Lake Fishing Site, Arickaree Picnic Ground, and areas immediately adjacent to Brainard Lake itself. This area is a heavily utilized recreation area for the winter and summer months. There are a lot of recreation opportunities within this area, and it sees approximately one-quarter of a million visitors annually. During the summer months this entire area is filled to capacity on weekends. Hiking, fishing, picnicking, and scenic driving are all common recreation activities present at these sites.

2.0 Scope of Work

A. The proposed project’s goal is to reduce the deferred maintenance at three important and very high use recreation sites near Ward, Colorado. The reduction of deferred maintenance will be accomplished by renovating three (3) picnic grounds, which may include replacing two (2) vault toilet structures, timber steps, compacted aggregate trails, and associated sitework to improve accessibility to these recreation facilities. Sites include:

a. Niwot Picnic Ground

i. Base Items – the proposed project includes:

1. Demolishing and removing the existing timber parking barriers and retaining walls

2. Constructing timber steps

3. Constructing rock retaining walls

4. Constructing accessible compacted aggregate trails

5. Renovating existing historic picnic sites

6. Constructing new picnic sites

7. Revegetation of disturbed areas

b. Arickaree Picnic Ground

i. Base Items – the proposed project includes:

1. Demolishing and removing the existing vault toilet structure and concrete sidewalk

2. Constructing a new vault toilet structure

3. Constructing accessible compacted aggregate toilet access trail

c. Red Rock Lake Picnic Ground

i. Base Items – the proposed project includes:

1. Demolishing and removing the existing vault toilet structure and asphalt curb

2. Removing vegetation from the edge of main road.

3. Constructing timber steps

4. Constructing accessible compacted aggregate trails

5. Constructing a new vault toilet structure

ii. Optional Items – the proposed project includes:

1. Constructing new picnic sites

2. Revegetation of disturbed areas

B. Work Hours: No work shall happen on weekends or Federally recognized Holidays. Work shall be allowed during daylight hours.

a. Site Order of Work – Niwot PG, Arickaree PG, and then Red Rock PG.

4 | P a g e

C. Project Site Requirements:

a. All three (3) of these recreation sites will remain open to the public during construction. Contractor shall install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. All signs shall meet MUTCD standards.

b. Contractor may be allowed to temporarily close or block off traffic, with prior approval from the Contracting Officer, for the safety of the public.

c. Contractor shall be in compliance with current OSHA 1910 and 1926 regulations and requirements.

d. Any sub-contractors shall be under the superintendence by the Prime.

D. Inspection and Acceptance

a. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and testing at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract. See FAR Clause 52.212-4(a) contained herein. The contractor is responsible for adhering to the contract specifications and for quality control.

Contractor Requirements

3.0 Technical Requirements / Tasks

The Contractor shall furnish all management, labor, equipment, supervision, tools, materials, transportation, operating supplies, supervision, workman’s compensation, unemployment insurance and incidentals necessary to perform the work in accordance with the specification and provisions of the contract.

The project is the renovation of three (3) picnic grounds which may include the removal and replacement of two (2) stick-built toilets, accessible compacted aggregate trails, renovation of existing historic picnic sites, construction of new picnic sites, and other recreation site elements like wayfinding signs. All Contractors shall visit the project sites and acquaint themselves with current conditions prior to submitting a bid for these services. During excavation, there is a high likelihood of encountering large boulders or rock materials, especially when excavating the toilet vault holes. Large boulders or rock material shall remain on-site unless otherwise directed by the Contracting Officer.

The contractor shall be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, County, and Municipal laws, codes, and regulations applicable to the performance of the work. The contractor shall be responsible for all damages to persons or property, which occur as a result of the Contractor’s performance or negligence.

4.0 Location

A. The BLRA is located approximately 23 miles north-west of Denver, Colorado or approximately 2 miles west of the town of Ward, Colorado.

B. Site Access

a. Direction to Brainard Lake Recreation Area from Boulder: Drive approximately 10 miles north of Boulder and then turn west onto Lefthand Canyon Drive. Drive west approximately 17 miles to the town of Ward. Turn north onto Highway 72 for approximately 100 yards and then turn west onto Brainard Lake Road and travel approximately 3 miles to the project sites.

i. Red Rock Lake Picnic Ground is approximately 0.25 miles west of the main Brainard Lake Recreation Area entrance gate and fee station on NFSR 112.0.

1. Coordinates: 40° 4'58.43"N, 105°32'27.87"W

ii. Arickaree Picnic Ground is approximately 0.3 miles north of Niwot Trailhead on NFSR 112.0.

1. Coordinates: 40° 4'44.84"N, 105°34'36.48"W

5 | P a g e

iii. Niwot Trailhead is approximately 2 miles west of Red Rock Lake Picnic Ground on NFSR 112.0.

1. Coordinates: 40° 4'35.31"N, 105°34'38.38"W

Appendix A – Project Site Locations Map

6 | P a g e

Appendix B – Project Site Photos

Niwot Trailhead – Existing timber boarders, timber parking barriers, and information kiosk to be removed. Moose interpretive sign to be re-located on site.

7 | P a g e

Niwot Trailhead – Existing metal pedestal grill, fire ring, and picnic tables to be demolished and removed. Existing picnic sites to be renovated. Stone retaining walls are important and historic and will be protected during construction!

8 | P a g e

Niwot Trailhead – Existing timber bollards and barriers to be removed. Barrier rocks shall be relocated on site. Existing asphalt parking lot to remain and be protected.

9 | P a g e

Red Rock Lake Picnic Ground – Existing toilet structure to be demolished and removed.

10 | P a g e

Red Rock Lake Picnic Ground – Existing asphalt curb to be removed but asphalt parking lot to remain and be protected.

Project
General Information
1.0 Background
Brainard Lake Recreation Area (BLRA) is a unique set of developed recreation sites that are nestled up next to the Indian Peak Wilderness Area on the Boulder Ranger District near Ward, Colorado. This project covers a few of these recreation sites incl...

2.0 Scope of Work

Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Location
Appendix A – Project Site Locations Map
Appendix B – Project Site Photos