This statement of work outlines the requirements for a nuclear, biological, chemical component test stand for the Anniston Army Depot. Key requirements include designing, fabricating, and installing a test stand capable of testing five NBC system components according to test specification DMWR 9-4800-206. The test stand must include software to dynamically display test parameters, record and store data, and allow manual or automatic test procedures. Hardware must include components that will be supported for at least ten years. The physical test stand footprint cannot exceed six by twelve feet and must allow easy maintenance and calibration. The contractor must provide training, warranty, calibration and maintenance documentation, and spare parts for two years of operation. The contractor will have one year to complete the work after award of the contract under solicitation number W911KF-23-Q-0025 from the Department of the Army Materiel Command Contracting Command Detroit Arsenal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for NBC Component Test Stand
1.0 Scope:
This specification establishes the requirements for design, delivery, and install of one NBC Component Test Stand. Test Stand shall be capable of testing five (5) components of the M1 NBC system according to test specification in DMWR 9-4800-206 including: prioritization regulating valve, pressure regulating valve, anti-ice valve, temperature valve, and anti-ice servo valve.
1.1 Scope Change Statement:
The Contractor shall not proceed with any change(s) in scope of work from sources other than those listed as the Contracting Officer Representative (COR) section of the contract and without written confirmation, signed by the Contracting Officer (KO).
2.0 Applicable Documents:
AMERICAN NATIONAL STANDARD RDS INSTITUTE (ANSI)
| ANSI AS35411 | Fittings & Lubrication | |
| ANSI B93.114M | Pneumatic Fluid Power Systems - Standard for Industrial | Equipment and Machine Tool Applications |
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
| IEEE C2 | (2002) National Electrical Safety Code |
| IEEE Std 142 | (1992) Recommended Practice for Grounding of Industrial and Commercial Power Systems - Green Book |
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
| ISO 4414: 1998 | Pneumatic Fluid Power - General Rules |
| Relating to Systems |
NATIONAL FLUID POWER ASSOCIATION (NFLPA)
| NFPA T2.25.1R2 200x | Pneumatic Fluid Power - Systems Standards For Industrial | Machinery - Supplement to ISO 4414:1998 |
| NFPA / JIC T2.24, 1R1 | Hydraulic Fluid Power - Systems standard for stationary | industrial machinery |
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
| NEMA MG 1 | Motors and Generators (DOD adopted) |
| NEMA ICS 1 | Industrial Control and Systems: General Requirements |
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
| NFPA 70 (2017) | National Electrical Code | |
| NFPA 79 | Electrical Standard for Industrial Machinery (DOD adopted) | General Industry, OSHA Safety and Health Standards |
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
| ANSI S3.41 | (1990; R 2001) Audible Emergency Evacuation Signal (ASA 96) FM | GLOBAL (FM) |
| FM P7825a | (2003) Approval Guide Fire Protection |
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C62.41 (1991; R 1995) Surge Voltages in Low-Voltage AC Power Circuits
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
| NFPA 1221 | (2002) Installation, Maintenance and Use of Emergency | Services Communications Systems | |
| NFPA 70 | (2017) National Electrical Code | ||
| NFPA 72 | (2002) National Fire Alarm Code | ||
| NFPA 90A | (2002) Installation of Air Conditioning and Ventilating | ||
| Systems | |||
| NFPA 2001 | (2004) Clean Agent Fire Extinguishing Systems |
UNDERWRITERS LABORATORIES (UL)
| UL 1242 | (2000; Rev thru May 2003) Electrical Intermediate Metal | Conduit -- Steel | |||||
| UL 1971 | (2002) Signaling Devices for the Hearing Impaired | ||||||
| UL 228 | (1997; Rev Jan 1999) Door Closers-Holders, With or Without | Integral Smoke Detectors | |||||
| UL 268 | (1996; Rev thru Apr 2003) Smoke Detectors for Fire Protective | Signaling Systems | |||||
| UL 268A | (1998; Rev thru Apr 2003) Smoke Detectors for Duct | Application | |||||
| UL 38 | (1999; Rev thru Jun 2001) Manual Signaling Boxes for Fire | Alarm Systems | |||||
| UL 464 | (2003) Audible Signal Appliances | ||||||
| UL 521 | (1999; Rev thru Oct 2002) Heat Detectors for Fire | ||||||
| Protective Signaling Systems | |||||||
| UL 6 | (2000; Rev thru May 2003) Rigid Metal Conduit | ||||||
| UL 797 | (2000; Rev thru May 2003) Electrical Metallic Tubing – | ||||||
| Steel | |||||||
| UL 864 | (1996; Rev thru Aug 2001) Control Units for Fire Protective | Signaling Systems |
Government Documents: The following documents form a part of this specification to the extent specified herein. Unless otherwise indicated, the issue in effect on date of request for proposal shall apply.
· DMWR 9-4800-206, Depot Maintenance Work Requirement for Nuclear, Biological, Chemical System
3.0 Safety and Environmental Practices and Guidelines:
The Contractor shall conform to all federal OSHA standards applicable to the work performed and all safety practices and guidelines contained within this Statement of Work. Contractor shall strictly adhere to the contract clause entitled "Accident Prevention", Army Material Command (AMC) Regulation (R) 385-100, Safety and Occupational Health Regulation ANADR 385-1, Engineering Manual (EM) 385-1-1, 29 Code of Federal Regulations (CFR) 1926/1910, other related Department of Transportation (DOT) Regulations (49 CFR), and all local policies.
If a contractor employee is observed performing an activity in a manner inconsistent with any of the above cited regulations or is engaged in any activity that is dangerous to life, limb, or government property, the ANAD Safety Representative shall have the authority to notify the employee and/or the contractor’s on-site supervisor of the hazardous activity and require correction of the hazardous activity. This authority does not preclude the Safety Representative from notifying the Contracting Officer’s Representative of the hazardous condition or safety violation in appropriate situations.
If necessary, the ANAD Safety Representative shall have the authority on behalf of the Contracting Officer to require the contractor and/or its employee to stop the hazardous activity until corrective action is taken to eliminate a hazardous condition or safety violation. Said action shall not be considered to be the basis of a claim and shall be at no cost to the Government.
Contractor will notify ANAD Safety Office immediately of Reports of Inspections and/or Notices of Violation or other enforcement actions (including warning letters) received from by local, State, and Federal Regulators in which the violation is attributed to the action of the contractor or its subcontractors while working or providing services on ANAD installation. Contractor will provide ANAD with a copy of the Inspection Report, Notice of Violation or other enforcement action, and all supporting documentation.
Contractor shall comply will all national, state, and local Environmental Laws and Regulations. Contractor shall comply with Green Procurement Requirements. Verification will be made to ensure adherence to National Environmental Policy Act Documentation. Contractor shall conform with Environmental Management System and have an assigned Environmental Compliance Officer Point of Contact (ECOPC). All contractor employee on site will be trained on generation of solid waste, generation of hazardous waste, use of hazardous materials, protection of worksite resources, prevention of spills, corrective action for noncompliance, noise, mercury materials, universal waste, and pollution prevention.
4.0 Responsibilities:
4.1 Contractor:
Contractor shall be responsible for the design, fabrication, and installation of all equipment and upgrades listed in contract on one NBC Component Test Stand located at ANAD building 133. Contractor shall ensure all employees needing access to ANAD can pass a criminal background check and meet residency requirements to gain access to ANAD. Contractor shall provide training to ANAD employees on proper operation of all software, equipment operation, equipment maintenance, and calibration. This training shall include a minimum of two test stand operators, one maintenance specialist, one engineer and one calibration employee trained on location at ANA. All work shall be complete within one year of contract award.
4.2 Government:
Government will provide all test documents and one each component to be tested. Government will provide all utilities required for proper operation of test stands.
5.0 Install Verification:
Upon installation of all parts and software contractor shall verify all items are operational by conducting 3 consecutive tests on each part without failure. Tests include calibration and acceptance test.
6.0 Warranty:
Contractor shall provide a warranty on all parts and software for a term of no less than one year. Contractor shall respond within 48 hours of notification in event test stand is not operational.
7.0 NBC Stand Requirements:
7.1 Software
The application software shall be an advanced package which has the capability to dynamically display every acquired and calculated parameter within the test system listed in NMSR test requirements. During test runs, Data shall be displayed in predefined pages which can be designed to show all data pertinent to the test. All display pages shall be cycled for display at the touch of a key. Any other page shall be called up as needed with just a few keystrokes. The data displays shall be updated at a configuration file defined rate with a minimum of four times a second to maximize view ability. During Test Mode, a list of operator-selectable test procedures shall be displayed in a pop up window. A procedure shall be initiated by selecting it from the list. A manual command line text entry shall also allow running each test procedure. The software shall allow real-time recording, operator-initiated snapshots, and flexible storage of all specified data records. The software shall store all specified data on its hard disk during Run Mode. When a run is complete, the operator (or an automatic sequence) may specify that the data shall be printed or plotted in a report, and save data to hard drive by serial number and unique run identifier for each test. Test procedure shall be designed to be user friendly and intuitive to operate in both manual and automatic modes. All software and hardware shall be capable of operating without network connection.
7.2 Controller Hardware requirements
Unit shall have a minimum 1 terabyte hard drive Drive to burn physical media such as DVD or CD Minimum 2 USB ports for removable media in addition to any USB ports needed for operation Standard PC optical scroll mouse and keyboard Laser printer designed to withstand test environment Minimum 24” Flat Panel monitor An uninterruptible power supply for backup power Processor and Operating System so as to not be obsolete for minimum of 5 years Unit shall use National Instrument and Allen Bradley components that are commercially available and will be supported for a minimum of 10 years
7.3 Part Mounting
Stand shall be designed to utilize quick fittings to minimize part change over time.
7.4 Physical Requirement
Stand shall fit in footprint no more than six (6) feet by twelve (12) feet. Design shall allow for ease of accessibility for maintenance and calibration. Stand shall be configured for maximum ergonomic flexibility with operator in mind. Stand shall have safety enclosure to protect operator in case of part or equipment failure.
7.5 Calibration
Contractor shall provide calibration procedures with required material needed for calibration of all flow and electrical equipment.
7.6 Utilities
Stand shall operate on standard United States three phase voltage. Stand shall operate with compressed air no more than ninety (90) psi or have an internal compressor.
7.7 Spare Parts
Contractor shall supply adequate spare parts for twenty-four months continuous operation.
7.8 Manuals and Drawings
Contractor shall provide three count paper and three count digital CD Rom copies of the following:
Installation Instructions Operator Manual Maintenance Manual Fabrication Drawings Calibration Manual Spare Parts List
7.9 Training
The contractor shall provide at a minimum training to the following type of personnel on-site at ANAD:
Operators and Technicians – 5 days Maintenance and/or Engineering Personnel – 3 Days