Attachment 1 - Statement of Work.pdf

PDF 217 KB Posted

Attached to
48 LRS/MUNS High Line Docks
Solicitation number
FA558726Q0052
Issued by

About this file

This is a Statement of Work (SOW) for the procurement and installation of cargo highline dock systems at Royal Air Force (RAF) Lakenheath, United Kingdom, dated September 1, 2026 (Revision 2).

The project consists of two contract line items (CLINs). CLIN 001 is the base requirement for the 48th Logistics Readiness Squadron (48 LRS) and requires procurement, delivery, demolition of the legacy dock, installation, and certification of one permanent, three-lane integrated highline cargo dock system with 18 total 463L pallet positions. CLIN 002 is an option requirement for the 48th Munitions Squadron (48 MUNS) and calls for one modular, relocatable single-lane highline cargo dock system with 6 total 463L pallet positions configured for independent relocation via 10K standard military forklifts. Both systems must interface with standard USAF 463L pallets, accommodate both 108-inch and 88-inch width orientations, and support mechanical interface with Air Mobility Command K-Loaders (Halvorsen 25K and Tunner 60K). The CLIN 001 dock must be 56 feet long with approximately 30 feet width, three parallel lanes with 6 pallet positions each, working height of 39-40 inches, minimum 10,000 lbs per pallet position safe working load, and 180,000 lbs total system structural rating. The CLIN 002 dock shares the same length and height specifications but is approximately 15 feet wide and includes adjustable leveling feet (±3 inches) for uneven surfaces; it must be modular with three bolt-together segments featuring engineered forklift pockets for relocation. Both systems require hot-dip galvanized structural steel per BS EN ISO 1461 or ASTM A123, heavy-duty sealed roller assemblies, positive mechanical pallet stops, side-loading capability, catwalks with 24-inch minimum width, OSHA/AFOSH-compliant handrails, and access stairs. The contractor must provide all equipment, tools, materials, transportation, and services necessary for assembly, dismantle the existing legacy dock, and obtain one-year comprehensive commercial warranties covering all structural elements, rollers, bearings, and hot-dip galvanization against defects and premature corrosion. Final acceptance requires on-site functional load testing using government-provided 463L pallets and K-loader interface verification supervised by the mission partner. Work hours are Monday through Friday (excluding US federal and UK bank holidays) from 0800 to 1700 local UK time. The contractor must comply with operational security (OPSEC) policies, RAF Lakenheath airfield driving regulations, foreign object damage (FOD) prevention policies, and applicable UK Standards. Shipping requirements vary by vendor location: vendors within the United Kingdom must use FOB Destination with all costs included in the purchase price, while vendors outside the United Kingdom have three options including United States Postal Service, commercial small parcel carrier, or consolidated shipping via military airlift. The government will not provide Government Furnished Property or Equipment, and the contractor is responsible for obtaining installation access passes for all personnel and maintaining proper documentation within 30 days of contract award.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

Statement of Work

(SOW)

Cargo Highline Dock at

Royal Air Force (RAF) Lakenheath

Rev. 2, 1 Sep 2026

1.0 INTRODUCTION & MISSION OBJECTIVE

1.1 Mission:

The 48th Logistics Readiness Squadron (48 LRS) Air Transportation Function (ATF) and the 48th Munitions Squadron (48 MUNS) require heavy-duty rollerized Cargo Highline Docks at RAF Lakenheath. The CLIN001 will provide a single system, three lane high-throughput cargo staging, assembly, and loading capabilities high line dock to support 48th Fighter Wing (48 FW) deployments across two Combatant Commands. CLIN002 provides an option for 48 MUNS for a one lane high line dock system, similar to CLIN001 with an off-apron, relocatable staging platform to safely build, disassemble, and transfer munitions pallet trains. CLIN002 will be a modular variant as described in the product specifications below.

1.2 Background:

Currently, RAF Lakenheath Building 1280 operates with only one functional highline dock and one legacy dock that is structurally obsolete and inoperable. Additionally at 48 Munitions, air freight staging is constrained, forcing ground-level pallet builds on wooden dunnage and multi-step forklift transfers.

Procuring 2 modern, multi-lane, rollerized highline systems expands staging capacity, enables direct pallet train assembly (T-2, T-3, T-4 configurations), and permits seamless mechanical interface with standard Air Mobility Command (AMC) K-Loaders (Halvorsen 25K and Tunner 60K).

1.3 Acquisition Scope & CLIN Structure:

• CLIN 001 (Base Requirement – 48 LRS): Procure, deliver, dismantle legacy dock, install, and certify ONE (1) Permanent, Three-Lane Integrated Highline Cargo Dock System (18 total 463L pallet positions).

• CLIN 002 (Option Requirement - 48 MUNS): Procure, deliver, assemble, and certify ONE (1) Modular, Relocatable Single-Lane Highline Cargo Dock System (6 total 463L pallet positions) configured for independent relocation via 10K standard military forklifts.

1.0 General Requirements

1.1 Business Relations: The Contractor shall successfully integrate and coordinate all activity needed to execute this requirement. The Contractor shall manage the timeliness, completeness, and quality of problem identification. The Contractor shall promptly identify issues to the Government and take timely corrective action. The Contractor shall seek to ensure mission partner satisfaction and professional and ethical behavior of all contractor personnel.

1.2 Contract Management & Administration

2.2.1 Contract Management: The Contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of resources assigned to the requirement. The Contractor must maintain continuity between the mission partner and the contractor’s corporate offices.

2.2.2 Contract Administration: The Contractor shall establish processes and assign appropriate resources to effectively administer the contract. The Contractor shall respond to the Governments requests for contractual actions in a timely fashion. The Contractor shall have a single point of contact between the Government and contractor personnel assigned to support the contract. The Contractor shall assign resources in order to maintain proper and accurate records related to this contract.

2.3 Subcontract Management: If applicable, the Contractor shall be responsible for any subcontractor and any subcontractor management necessary to integrated work executed under this contract.

2.4 Hours of Work: Work days are from Monday through Friday excluding US federal holidays and UK bank holidays. Work hours are from 0800 to 1700 local UK time.

2.0 Product Specifications & Installation Requirements

2.1 The contractor must provide all equipment, tools, materials, transportation, any other items, and services necessary to assemble the cargo Highline Dock.

3.0 Product Specifications & Installation Requirements

3.1 General System Standards (Applicable to all CLINs):

3.1.1 463L Compatibility: System must interface with standard USAF 463L Pallets (nominal dimensions 88" W x 108" L x 2.25" H) in both Aerial Delivery System (ADS / 108-inch width) and Cargo (88-inch width) orientations.

3.1.2 Corrosion & Environmental Resistance: All structural steel framing, support legs, and catwalk frameworks must be heavy-duty structural steel, Hot-Dip Galvanized (HDG) to BS EN ISO 1461 (or ASTM A123) for severe all-weather UK maritime exposure.

3.1.3 Roller Assembly: Heavy-duty, split or full-width steel conveyor rollers with sealed, weather-proof precision ball bearings.

3.1.4 Pallet Restraints & Safety Stops: Each lane must be equipped with positive mechanical pallet stops (flip-up/retractable) at transfer ends and side-loading zones to prevent accidental roll-off during loading operations.

3.1.5 Side-Loading Capability: Docks must be configured to allow direct side-loading and unloading of individual 463L pallets via standard base forklifts (10K / 25K MHE) without damaging roller assemblies.

3.2 CLIN 0001: 48 LRS Base Requirement (Permanent 3-Lane Dock System)

3.2.1 System Architecture:

- Configuration: One (1) integrated dock system consisting of three (3) parallel, continuous rollerized lanes.

- Pallet Capacity: Six (6) pallet positions per lane (Eighteen [18] total 463L pallet positions).

- Train Handling: Must support single pallets, 3x T-2 pallet trains, 2x T-3 pallet trains, or continuous outsized cargo configurations.

3.2.2 Dimensions & Heights:

- Overall Length: Approximately 56 feet (17.0 m) total run.

- Usable Lane Width: 112 inches per lane to accommodate 108-inch ADS orientation with side guide clearances.

- Overall Width: Approximately 30 feet.

- Working Height: Fixed dock elevation of 39 inches to 40 inches (990 mm to 1016 mm) from finished apron level to roller top, designed for direct level docking with 25K Halvorsen and 60K Tunner loaders.

3.2.3 Load Capacity:

- Minimum Safe Working Load (SWL): 10,000 lbs (4,536 kg) per pallet position.

- Lane Load Rating: Minimum 70,000 lbs (27,215 kg) continuous static load per lane.

- Total System Structural Rating: Minimum 180,000 lbs (81,646 kg) total static capacity.

3.2.4 Catwalks, Handrails & Personnel Access:

- Catwalks: Integrated, full-length continuous walkways positioned between adjacent roller lanes and along outer perimeters (minimum usable width 24 inches / 610 mm). Surface must be serrated, self-draining, open-grid galvanized safety grating.

- Handrails: Heavy-duty OSHA/AFOSH-compliant safety handrails (42 inches high with mid-rails and 4-inch toe boards) along all outer exposed perimeters.

- Access Stairs: One (1) heavy-duty galvanized structural steel step-ladder/stairway assembly with handrails and self-closing swing safety gates for personnel access from apron level to catwalks. Installed on Victor ramp side (North) opposite of the grass side. Coordinate with LRS Mission Partner for further instruction on stair attachment.

3.2.5 Legacy Dock Demolition & Installation:

- The Contractor shall fully dismantle, remove, and properly dispose of the existing inoperable legacy highline dock located at Victor Ramp.

- The Contractor shall anchor the new 3-lane dock system securely into the existing concrete flightline apron using heavy-duty stainless steel or galvanized wedge anchors.

3.3 CLIN 0002: 48 MUNS Option Requirement (Modular / Relocatable 1-Lane Dock)

3.3.1 System Architecture:

- Configuration: One (1) standalone, relocatable single-lane rollerized dock.

- Pallet Capacity: Six (6) total 463L pallet positions (10,000 lbs per position / 60,000 lbs total SWL).

- Modular Breakdown: Built in bolt-together modular sections (separated into three segments). Each segment must include engineered forklift pockets/slots allowing safe lifting, separation, and transport across base facilities using standard 10K forklifts.

- Height & Leveling: Equipped with heavy-duty adjustable leveling feet (+/- 3 inches) to adapt to uneven munition storage pad surfaces while maintaining standard 39"-40" K-loader interface height.

3.3.2 Dimensions & Heights:

- Overall Length: Approximately 56 feet (17.0 m) total run.

- Usable Lane Width: 112 inches per lane to accommodate 108-inch ADS orientation with side guide clearances.

- Overall Width: Approximately 15 feet.

- Working Height: Fixed dock elevation of 39 inches to 40 inches (990 mm to 1016 mm) from finished apron level to roller top, designed for direct level docking with 25K Halvorsen and 60K Tunner loaders.

3.3.3 Load Capacity:

- Minimum Safe Working Load (SWL): 10,000 lbs (4,536 kg) per pallet position.

- Lane Load Rating: Minimum 70,000 lbs (27,215 kg) continuous static load per lane.

3.3.4 Catwalks, Handrails & Personnel Access:

- Catwalks: Integrated, full-length continuous walkways positioned along outer perimeters (minimum usable width 24 inches / 610 mm). Walkways must hinge down to allow side loading of pallets. Surface must be serrated, self-draining, open-grid galvanized safety grating.

- Handrails: Heavy-duty OSHA/AFOSH-compliant removable safety handrails (42 inches high with mid-rails and 4-inch toe boards) along all outer exposed perimeters.

- Safety & Access: Includes perimeter safety stops, side loading guides, outer perimeter handrails, and one (1) removable access stair unit.

3.4 Warranty & Acceptance:

3.4.1 Commercial Warranty: The Contractor shall provide a minimum one (1) year comprehensive commercial warranty covering all structural elements, rollers, bearings, mechanical stops, and hot-dip galvanization against defects and premature corrosion for both CLIN 001 and CLIN 002.

3.4.2 Acceptance Testing: Final acceptance requires on-site functional load testing using government-provided 463L pallets and K-loader interface verification supervised by LRS or MUNS Mission Partner.

4.0 Special Requirements

4.0 Security & Safety

4.1.1 Operational Security (OPSEC): If any installation is required to take place in a

Government facility, the Contractor shall be familiar with the organizational critical information and indicators list (CIIL) and OPSEC policy of any installation they require access to. The required CIIL can be provided by the Contracting Officer.

4.1.2 Safety: The Contractor and any of its subcontractors (if applicable) shall promptly report pertinent facts regarding mishaps involving Government property damage or injury to Government/Contractor personnel that takes place on an installation. The Contractor shall notify the cognizant Contracting Officer within 24 hours of all mishaps or incidents. The Contracting Officer will in-turn notify the Safety Office. The Contractor shall cooperate in any resulting safety investigation.

4.1.3 Airfield Access & Foreign Object Damage (FOD) Prevention: Contractor personnel must adhere to RAF Lakenheath airfield driving regulations and flightline FOD prevention policies. Daily tool accountability and continuous FOD sweeps of the work area are mandatory.

4.2 Contractor Access to Installations: Access to DoD installations is limited to personnel with a valid installation access pass. Failure to submit required information to obtain required documentation will result in the exclusion of such employees from the installation until such documentation is obtained.

Contractor employees may be subject to personal and vehicle searched when entering or leaving a DoD installation. If installation access is required, the Government will provide the Contractor with the required information and documents for installation access passes upon award. Subsequently, the Contractor shall provide a list of all employees along working under this contract, along with the required documentation upon receipt of contract award, and no later than 30 days prior to the projected need for any new installation access pass requirements. The Contractor is responsible for maintaining an adequate number of personnel with active installation access passes, and adhering to the timeframes stated in this section. The cognizant mission partner is responsible for the coordination of installation access passes.

Upon termination of employment, termination or cancellation of the contract, or expiration of the contract the Contractor is responsible for collecting employee installation access passes and turning them in to the CO, or the cognizant mission partner in a timely fashion.

4.3 Shipping Instructions

4.3.1 For vendors located inside the United Kingdom.

4.3.1.1 Shipment shall be FOB Destination.

4.3.1.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either include the shipping in the costs of the items, or outline it in a separate line item).

4.3.1.3 The Government will provide the shipping address as part of the solicitation document. Additionally, the Government will provide the vendor with the point of contact at the physical destination delivery address.

4.3.2 For vendors located outside of the United Kingdom.

4.3.2.1 Option One: United States Postal Service.

4.3.2.1.1 Shipping shall be FOB Destination.

4.3.2.1.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either included the shipping in the costs of the items, or outline it in a separate line item).

4.3.2.1.3 Weight of individual shipments must not exceed 70lbs.

4.3.2.1.4 Dimensions of individual shipments must not exceed 119 inches in length, and/or 72 inches in width or height.

4.3.2.1.5 Hazardous material is not submitted.

4.3.2.1.6 The Government will provide the APO shipping address as part of the solicitation.

4.3.2.2 Option Two: Commercial small parcel carrier.

4.3.2.2.1 Shipping shall be FOB Destination.

4.3.2.2.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either included the shipping in the costs of the items, or outline it in a separate line item).

4.3.2.2.3 Weight of individual shipments must not exceed 300lbs.

4.3.2.2.4 Dimensions of individual shipments must not exceed 119 inches in length, and/or 72 inches in width or height.

4.3.2.2.5 The Contractor is responsible for arranging and performing all shipping actions from origin to final destination.

4.3.2.2.6 The Government will provide the shipping address as part of the solicitation document. Additionally, the Government will provide the vendor with the point of contact at the physical destination delivery address.

4.3.2.3 Option Three: Consolidated Shipping Point.

4.3.2.3.1 Shipping shall be FOB Destination.

4.3.2.3.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either included the shipping in the costs of the items, or outline it in a separate line item).

4.3.2.3.3 Weight of individual shipments must exceed 300lbs.

4.3.2.3.4 Dimensions of individual shipments must exceed 72 inches of any one dimensions (length, width, height).

4.3.2.3.5 Hazardous material may be shipped via this method.

4.3.2.3.6 The Contractor must complete a DD Form 1139 “XXX” to determine if the cargo can be shipped via MILAIR.

4.3.2.3.7 The Contractor shall ensure all cargo is marked “UNITED

STATES AIR FORCE” in order to ensure shipments clear customs.

4.3.2.3.8 48 FW logistics points of contact are provided for in 4.3.3.

4.3.3 Contact Information; 48th Logistical Readiness Squadron (48 LRS)

4.3.3.1 48 LRS/Inbound Customs; 48lrs.lgrddc.inboundcustoms@us.af.mil.

4.3.3.2 48 LRS/Inbound Cargo; 48lrs.inboundcargo@us.af.mil.

4.3.3.3 Commercial phone number; +44 01638 52620.

4.4 Government Furnished Material: The US Government will not provide any Government Furnished

Property (GFP) or Government Furnished Equipment (GFE) as part of this contract.

4.5 Applicable Directives: Contractor shall ensure that all products supplied, and the installation comply with all applicable UK Standards.

3 Appendix: Related Documents mailto:48lrs.lgrddc.inboundcustoms@us.af.mil mailto:48lrs.inboundcargo@us.af.mil