This is a Statement of Work for diesel fuel testing and tank cleaning services at Fort Harrison VA Medical Center in Fort Harrison, Montana.
The contractor shall provide annual fuel quality testing on seven diesel fuel storage tanks using ASTM-approved methods, with tests including flash point, water and sediment, distillation, viscosity, sulfur, cetane index, cloud point, density/API gravity, thermal stability, pour point, free water, trace metals, microbial analysis, and visual appearance. The seven tanks range in capacity from 500 to 10,000 gallons. As-needed fuel remediation must be performed when test results fall outside acceptable ASTM D975 standards, utilizing a High Velocity Recirculation & Filtration System to remove water bottom, sediment, gums, microbes, and oxidized fuel, with biocide dosing calculated on-site and subject to approval by the Fort Harrison maintenance supervisor or VAMC Point of Contact. Up to three additional fuel quality tests per calendar year shall be conducted for remediated fuel at 90-day intervals or until analysis is acceptable. All testing must follow specific ASTM standards (D4057, D7464, D2709, D4176, D7220) and NFPA 110 requirements. Reports must be delivered within 30 days of testing or remediation and shall include laboratory identification, lab results compared to acceptable levels, tank conditions assessment, remediation activities performed, and biocide/additive quantities. All work must be coordinated with the VAMC Point of Contact, comply with VAMC regulations and OSHA requirements, and any exposure to protected health information must be immediately reported.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25926Q0712 0003_1.docx | DOCX document | |
| 36C25926Q0712 0003.docx | DOCX document | |
| S06 - 36C25926Q0712 0002.docx | DOCX document | |
| 36C25926Q0712 0002_1.docx | DOCX document | |
| Attachment 4 - Questions and Answers - RFQ 36C25926Q0712.pdf | ||
| S06 - 36C25926Q0494 0001.docx | DOCX document | |
| 36C25926Q0712 0001_1.docx | DOCX document | |
| Attachment 3 - Questions and Answers - Previous Solicitation.pdf | ||
| Attachment 2 - Wage Determinations.pdf | ||
| 36C25926Q0712_1.docx | DOCX document | |
| RFQ 36C25926Q0712.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Fuel Testing and Tank Cleaning
1. Overview The contractor shall provide all services, materials, labor, supervision, safety planning, certification, expertise, tools, and equipment to perform diesel fuel testing and tank cleaning.
Testing and cleaning services shall be performed in accordance with National Fire Protection Association (NFPA) 110. The place of performance is the Fort Harrison VA Medical Center (VAMC), located at 3687 Veterans Drive, Fort Harrison, MT 59636.
2. Required Services A. Annual Fuel Quality Testing: Testing shall be performed on seven diesel fuel storage tanks using applicable Advancing Standards Transforming Markets (ASTM) standards. Fuel tests must include the following:
1) Flash Point
2) Water and Sediment
3) Distillation
4) Viscosity
5) Sulfur
6) Cetane Index
7) Cloud Point
8) Density / API Gravity
9) Thermal Stability
10) Pour Point
11) Free Water
12) Trace Metals
13) Microbial
14) Visual Appearance
B. As Needed Fuel Remediation: Where test results show fuel is outside of the acceptable range, perform fuel remediation for diesel fuel tanks to meet fuel quality standards defined by ASTM D975.
1) Tank 144B 800 gal
2) Tank 155 525 gal
3) Tank 158 3750 gal
4) Tank 169 500 gal
5) Tank MV 5430 gal
6) Tank 141B 8000 gal
7) Tank 171 10000 gal
8) Clean tank with High Velocity Recirculation & Filtration System.
9) Remove contamination in the tank including but not limited to:
a) Water bottom
b) Sediment
c) Gums
d) Microbes
e) Oxidized Fuel
10) Add Biocides when required – dosing to be calculated and determined on site. All additives must be approved by the Fort Harrison maintenance supervisor or VAMC Point of Contact (POC) before introduction.
C. As Needed Additional Fuel Quality Tests: Where annual fuel testing has revealed the need for remediation, after remediation is performed, perform up to three additional fuel quality tests per calendar year for the remediated fuel. The tests should occur every 90 days or until analysis is acceptable.
3. Fuel Tank List Fuel Tank Fuel Capacity
[gal]
Generator 144B 800
Generator 155 525
Generator 158 3750
Generator 169 500
Generator MV 5430
Boiler 141B 8000
Boiler/Generator
10000
4. Fuel Quality Test Requirements A. All testing should be performed using ASTM-approved test methods such as, but not limited to
1) ASTM D4057, Standard Practice for Manual Sampling of Petroleum and Petroleum Products, for fuel quality;
2) ASTM D7464. Standard Practice for Manual Sampling of Liquid Fuels, Associated Materials and Fuel System Components for Microbiological Testing, for microbial contamination;
3) ASTM D2709, Standard Test Method for Water and Sediment in Middle Distillate Fuels by Centrifuge, for water and sediment;
4) ASTM D4176, Standard Test Method for Free Water and Particulate Contamination in Distillate Fuels (Visual Inspection Procedures), for appearance-distillate;
5) ASTM D7220, Standard Test Method for Sulfur in Automotive, Heating, and Jet Fuels by Monochromatic Energy Dispersive X-ray Fluorescence Spectrometry, for sulfur (ppm), and meet engine manufacturer requirements.
(NFPA 110-2025, A.8.3.7)
5. Reporting Below are the minimum requirements to be included in reports. Reports are to be provided within 30 days of testing or remediation.
A. Fuel Test Report
1) Laboratory performing the tests.
2) Lab results, comparing measured levels with acceptable levels.
3) Fuel tank conditions, including caps, gaskets, fittings, and vents.
B. Fuel Remediation Report
1) Remediation activity performed.
2) Test criteria to determine successful remediation and the results.
3) Biocides or other additives, including quantities added.
6. Work Schedule, Site, and Privacy All work shall be scheduled and coordinated with the VAMC POC. The Contractor shall adhere to all VAMC regulations while on VA premises. The Contractor shall be liable for any damages that occur to any Government facilities or property and is responsible for all worksite safety measures and compliance with Occupation Safety and Health Administration (OSHA) requirements. Any incidental exposure to protected health information shall be immediately reported to the VAMC POC.
| 1. Overview |
| 2. Required Services |
| 3. Fuel Tank List |
| 4. Fuel Quality Test Requirements |
| 5. Reporting |
| A. Fuel Test Report |
| B. Fuel Remediation Report |
6. Work Schedule, Site, and Privacy