This is a Statement of Work (SOW) for the U.S. Forest Service, Southwestern Region 03, Prescott National Forest, issued on May 12, 2026 (Revision 2).

The SOW covers two primary projects: NFSR 373 Aggregate Hauling and NFSR 360 Cattle Guard Replacement. For the aggregate hauling project, the contractor must load and haul approximately 2,500 cubic yards of government-furnished MAG (M.A.G.) ABC aggregate from the Willow Work Center stockpile in Yavapai County, Arizona to NFSR 373 (Thumb Butte Loop), located approximately 8.5 miles from the stockpile. The contractor must also purchase and haul an additional 600 cubic yards (1,050 tons) of MAG ABC or surface course material from a commercial source. Base bid line items include mobilization/demobilization, loader with operator (minimum 5-cubic yard bucket), three dump trucks (10-12 cubic yard capacity) with operators, a vibratory smooth drum roller with operator (minimum 50-inch compaction width), a water tender with operator (2,000-3,000 gallon capacity), and the commercial aggregate purchase and delivery. An optional line item includes a road grader with operator for spreading, grading, and shaping aggregate. The performance period is 60 calendar days from Notice to Proceed. The government will furnish aggregate material, roadbed preparation, and road grading (unless the road grader option is awarded). For the optional NFSR 360 Cattle Guard Replacement work, the contractor must remove and dispose of an existing damaged cattle guard and install two new 8-foot by 8-foot concrete bases with steel grids, wings, warning signs (30" x 30"), and Type 3 object markers. The contractor is responsible for coordinating with Arizona 811 prior to excavation, managing backfill compaction in 6-inch lifts, and installing road closure signage at intersecting roads approximately one-quarter mile away. The Contracting Officer's Representative is Sergio Montanez (sergio.montanez@usda.gov, 928-765-5502). Payment terms are based on hourly operating rates for equipment and materials, with weight tickets required to support billing for hauling activities. Aggregate material specifications reference Table 1, FP-24 standards for surface course characteristics, and compaction must comply with specified AASHTO standards detailed in Attachment K.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

SOUTHWESTERN REGION 03

PRESCOTT NATIONAL FOREST

NFSR 373 AGGREGATE HAULING

NFSR 360 CATTLE GUARD REPLACEMENT

STATEMENT OF WORK

U.S. FOREST SERVICE

05/12/2026_Revision2

2 | P a g e

TABLE OF CONTENTS

1.0 GENERAL INFORMATION

1.1 WORK SUMMARY

1.2 PROJECT LOCATION

1.2.1 NFSR 373 MATERIAL HAULING

1.2.2 NFSR 360 CATTLE GUARD REPLACEMENT

1.3 PERFORMANCE PERIOD & WORK RESTRICTIONS

1.4 POINTS OF CONTACT

1.5 CONTRACTOR STAGING & STORAGE AREAS

1.6 UTILITIES & SANITATION SERVICES

1.7 USE OF PREMISES

1.8 GOVERNMENT FURNISHED ITEMS AND MATERIALS

1.9 PROTECTION OF NATURAL RESOURCES

1.10 COORDINATION OF RESOURCES

1.11 SUBMITTALS

2.0 PROJECT SCOPE

2.1 SCOPE

2.2 BASE BID LINE ITEMS

2.2.1 MOBILIZATION AND DEMOBILIZATION

2.2.2 LOADER WITH OPERATOR

2.2.3 DUMP TRUCK WITH OPERATOR

2.2.4 VIBRATORY SMOOTH DRUM ROLLER WITH OPERATOR

2.2.5 WATER TENDER WITH OPERATOR

2.2.6 AGGREGATE MATERIAL PURCHASE

Table 1, FP-24, Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, Section 703.05 Subbase, Base, and Surface Course Aggregate

2.2.7 AGGREGATE MATERIAL HAULING AND DELIVERY

2.3 OPTION BID LINE ITEMS

2.3.1 ROAD GRADER WITH OPERATOR

2.3.2 NFSR 360 CATTLE GUARD REPLACEMENT

2.4 SCOPE ATTACHMENTS

ATTACHMENT A – PROJECT MAP, NFSR 373 AND STOCKPILE LOCATION

ATTACHMENT B – PROJECT MAP, STOCKPILE LOCATION, WILLOW WORK CENTER

3 | P a g e

ATTACHMENT C – AGGREGATE STOCKPILE PICTURES

ATTACHMENT D – PROJECT MAP, NFSR 360 CATTLE GUARD & VERDE RANGER STATION

ATTACHMENT E – PROJECT MAP, NFSR 360 CATTLE GUARD

ATTACHMENT F – EXISTING CATTLE GUARD PICTURES

ATTACHMENT G – GOVERNMENT-FURNISHED CATTLE GUARD SUPPLIES

ATTACHMENT H – WARNING SIGN INSTALLATION GUIDELINES

ATTACHMENT I – TYPE 3 OBJECT MARKER INSTALLATION GUIDELINES

ATTACHMENT J – TYPICAL ROADWAY SECTIONS, AGGREGATE SURFACED

ATTACHMENT K – COMPACTION SPECIFICATIONS, FP-24

4 | P a g e

1.0 GENERAL INFORMATION

1.1 WORK SUMMARY

Load and haul MAG ABC aggregate from Prescott National Forest stockpile location at Willow Work Center to National Forest System Road (NFSR) 373, Thumb Butte Road.

1.2 PROJECT LOCATION

1.2.1 NFSR 373 MATERIAL HAULING

The existing stockpile is located at LAT 34.594533° / LONG -112.511707° at the Willow Work Center in Yavapai County, Arizona, within Prescott city limits.

From the Bradshaw Office (344 S. Cortez, Prescott, AZ, 86303), drive west on Aubrey Street, then turn right on S. Montezuma Road. Drive 1.5 miles, then the road turns curves to form Whipple Street. Drive 0.7 miles, then continue straight through the intersection, where the road turns into W. Iron Springs Road. Drive 1.4 miles, then turn right onto Williamson Valley Road. Continue 1.5 miles, then turn left onto Burnt Ranch Drive. Take the first right onto Hozoni Road, then turn left onto Katahn Drive. Continue 0.7 miles, then arrive at the aggregate stockpile location on the south side of the road.

The haul location will be NFSR 373, Thumb Butte Loop. The beginning of the road is 8.5 miles away from the stockpile location, approximately thirty (30) minute drive time. The northernmost point on the road is located at LAT 34.543362° / LONG -112.548144°. NFSR 373 is a Maintenance Level 2 (ML-2) road, recommended for high-clearance vehicles only.

From the stockpile location, drive 0.7 miles on Katahn Drive, then turn right onto Hozoni Road.

Drive 0.1 miles, then turn left onto Burnt Ranch Drive. Turn right into N. Williamson Valley Road and drive 1.5 miles. Turn left onto Iron Springs Road, then continue 0.9 miles. Turn right onto Gail Gardner Way and drive 1.3 miles. Turn right onto Oregon Avenue, drive 0.6 miles, then continue on Idylwild Road. Drive 0.7 miles, then turn right onto Thumb Butte Road. Drive 2.5 miles, then arrive at northern most point of NFSR 373, Thumb Butte Road.

1.2.2 NFSR 360 CATTLE GUARD REPLACEMENT

The existing damaged cattle guard is located at LAT 34.660696° / LONG -111.972764° in Yavapai County, Arizona, within Cottonwood town limits.

From the Verde Ranger Station (300 East AZ-260, Camp Verde, AZ, 86322), drive west on AZ- 260 for 11.0 miles, passing through numerous traffic circles. At the traffic circle with Thousand Trails Rod to the north and Camina Real to the south, take the 3rd exit onto Camino Real. Drive

0.7 miles, then arrive at the damaged cattle guard location.

5 | P a g e

1.3 PERFORMANCE PERIOD & WORK RESTRICTIONS

The performance is sixty (60) calendar days from Notice to Proceed.

1.4 POINTS OF CONTACT

Contracting Officer’s Representative:

Sergio Montanez, sergio.montanez@usda.gov, 928-765-5502

1.5 CONTRACTOR STAGING & STORAGE AREAS

The Contractor may stage equipment at the stockpile and project location. The stockpile is behind a gate with a key code.

1.6 UTILITIES & SANITATION SERVICES

There are no sanitation or utilities available at the site.

1.7 USE OF PREMISES

Driveways, Walkways, and Entrances: Keep driveways, walkways and entrances serving clear premises and available to emergency vehicles and pedestrians. Do not use these areas for parking or storage of materials, unless approved by the COR.

Smoking is not permitted within any government building, or within 25 feet of any entrance or window.

Provide adequate signage and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.

Secure equipment and contract work against theft and vandalism. The Government is not responsible for the theft and/or vandalism of any materials or equipment left at the project site.

1.8 GOVERNMENT FURNISHED ITEMS AND MATERIALS

For the NFSR 373 Aggregate Hauling work, the Government will furnish:

- Aggregate Material, approximately 3500 tons (2500 cubic yards)

- Roadbed preparation

- Road grading activities, unless option item 2.3.1 is awarded.

For the NFSR 360 Cattle Guard Replacement work, the Government will furnish:

- Cattle guard concrete base, 8’ x 8’, two (2) each mailto:sergio.montanez@usda.gov

6 | P a g e

- Cattle guard steel grid, two (2) each

- Cattle guard wing, two (2) each

- Cattle guard warning sign, 30” x 30”, two (2) each

- Type 3 Object Marker, two (2) each

- Sign installation hardware

- U-channel posts

1.9 PROTECTION OF NATURAL RESOURCES

Confine all operations to work limits of the project. Prevent damage to natural surroundings.

Restore damaged areas, and repair or replace damaged trees and plants, at no additional expense to the Government. Provide temporary barriers to protect existing trees and plants and root zones. Do not remove, injure, or destroy trees or other plants without prior approval.

Consult with COR and remove agreed-on roots and branches that interfere with construction.

Do not fasten ropes, cables, or guys to existing trees.

1.10 COORDINATION OF RESOURCES

The Contracting Officer’s Representative (COR) will coordinate Government-provided resources, including stockpile access and roadbed preparation activities. The COR will determine where aggregate placement will occur along NFSR 373, and aggregate thickness.

1.11 SUBMITTALS

Submit the following items for review and approval, prior to the start of the work:

- M.A.G. ABC Material Specification / Gradation Sheets, or substitute surface course material as described in Section 2.2.6.

7 | P a g e

2.0 PROJECT SCOPE

2.1 SCOPE

The Contractor shall furnish all supervision, materials, equipment and vehicles, tools, parts, labor, transportation, lodging, and miscellaneous items to load and haul approximately 2500 cubic yards of Government-Furnished MAG spec. ABC, and purchase/haul from a commercial source additional MAG spec. ABC, to NFSR 373, with an optional item to replace a cattle guard along NFSR 360, in accordance with the drawings, specifications, and other attachments referenced and contained herein.

No changes to the specifications, terms, or conditions of this statement of work shall be made without the prior approval of the Contracting Officer, in writing.

2.2 BASE BID LINE ITEMS

2.2.1 MOBILIZATION AND DEMOBILIZATION

Mobilize and demobilize to and from the Willow Work Center stockpile location and NFSR 373 Thumb Butte Loop with all required loading and hauling equipment, personnel, and all other contractual requirements.

2.2.2 LOADER WITH OPERATOR

Provide a loader with a minimum five (5) cubic yard bucket, with operator, to load haul trucks at the stockpile location. Pay unit is loading operating hour (HR), and shall be reimbursed for actual operating time loading haul vehicles. Down time due to mechanical breakdown and hauling activities will not be reimbursed. Consider having the loader operator also drive a haul vehicle to increase efficiency.

2.2.3 DUMP TRUCK WITH OPERATOR

Provide three (3) dump trucks, ten to twelve (10 – 12) cubic yard capacity, with operator, to haul aggregate material to NFSR 373 Thumb Butte Loop. Pay unit is operating hour (HR), and shall be reimbursed for actual operating and hauling time to and from the delivery location.

Down time due to mechanical breakdown and hauling activities will not be reimbursed. Provide weight tickets and/or a log of all hauling activities in support of final billing.

2.2.4 VIBRATORY SMOOTH DRUM ROLLER WITH OPERATOR

Provide one (1) vibratory smooth single-drum roller, minimum 50-inch compaction width, with operator, to compact aggregate at NFSR 373 Thumb Butte Loop, after the Government spreads, grades, and shapes aggregate material. Pay unit is operating hour (HR), and shall be reimbursed

8 | P a g e for actual operating time compacting aggregate. Down time due to mechanical breakdown and hauling activities will not be reimbursed. Compact in accordance with Attachment K.

2.2.5 WATER TENDER WITH OPERATOR

Provide one (1) water tender with 2000 – 3000 gallon capacity, with operator, to support aggregate reshaping and compaction activities on NFSR 373 Thumb Butte Loop. Pay unit is operating hour (HR), and shall be reimbursed for actual operating time. Down time due to mechanical breakdowns will not be reimbursed. Hourly rate includes the cost of the non-potable construction water and driving to and from the water source. Water source must be within thirty (30) minutes of the project site.

2.2.6 AGGREGATE MATERIAL PURCHASE

Purchase 600 cubic yards, or 1050 ton, of M.A.G. Aggregate Base Course (ABC) spec material from a local commercial source. A substitute material is preferred that meets surface coarse characteristics, such as asphalt millings. The material will be used as a surface course for the road, and surface coarse specifications are preferred due to the increase in plasticity and binder for withstanding road wear. Surface coarse specifications are below:

9 | P a g e

Table 1, FP-24, Standard Specifications for Construction of Roads and Bridges on Federal

Highway Projects, Section 703.05 Subbase, Base, and Surface Course Aggregate

2.2.7 AGGREGATE MATERIAL HAULING AND DELIVERY

Load, haul, and delivery 600 cubic yards, or 1050 ton of aggregate material (purchased under Section 2.2.6) to the road work area. Provide weight tickets and/or a log of all hauling activities in support of final billing.

10 | P a g e

2.3 OPTION BID LINE ITEMS

2.3.1 ROAD GRADER WITH OPERATOR

Provide a road grader (blade) with operator, for:

- Aggregate spreading

- Aggregate rough and fine grading

- Aggregate shaping

Pay unit is loading operating hour (HR), and shall be reimbursed for actual operating time.

Down time due to mechanical breakdown and hauling activities will not be reimbursed.

The COR will determine and provide the standard roadway section, as shown in Attachment J, and the final compacted aggregate surface coarse, that may be three (3) inches or more in compacted depth.

2.3.2 NFSR 360 CATTLE GUARD REPLACEMENT

The Contactor is responsible for coordinating and contacting Arizona 811 prior to all excavation activities, http://www.arizona811.com/.

Remove and dispose of the existing cattle guard concrete base and steel grids at the specified NFSR 360 location. The existing location contains a concrete base approximately 8-feet by 21-feet, and three (3) steel grids.

Load, haul, deliver, and install two (2) 8-feet by 8-feet concrete cattle guard bases, two (2) steel grids, and two (2) cattle guard wings at the existing location. Re-wire fence to the cattle guard wings. The new road width at this location will be sixteen (16) feet in lieu of twenty-one (21) feet. Regrade the surrounding area to natural grades, including the voids left from the larger footprint where the old cattle guard base sat. Center the new cattle guard to the center of the road. Final location shall be approved by the Contracting Officer’s Representative.

Excavate unsuitable material if encountered at foundation grade. Prepare subgrade for new cattle guard installation. Provide a firm earthen foundation of uniform density throughout its length and width. Place backfill lifts evenly on all sides of the structure. Extend each lift to the limits of the excavation or natural ground. Place backfill in compacted lifts no more than 6 inches in thickness.

Install new cattle guard warning signs, two (2) each, 30” x 30”, and two (2) Type 3 object markers, at the new cattle guard location, per the sign installation guidelines attached herein.

U-Channel posts, sign hardware, and signs will be Government-Furnished.

The Contractor is responsible for installing road closure signage where NFSR 360 intersects with NFSR 9604D to the north and NFSR 361 to the south, both locations approximately 1/4-mile away from the cattle guard location.

http://www.arizona811.com/

11 | P a g e

2.4 SCOPE ATTACHMENTS

ATTACHMENT A – PROJECT MAP, NFSR 373 AND STOCKPILE LOCATION

ATTACHMENT B – PROJECT MAP, STOCKPILE LOCATION, WILLOW WORK CENTER

ATTACHMENT C – AGGREGATE STOCKPILE PICTURES

ATTACHMENT D – PROJECT MAP, NFSR 360 CATTLE GUARD & VERDE RANGER STATION

ATTACHMENT E – PROJECT MAP, NFSR 360 CATTLE GUARD

ATTACHMENT F – EXISTING CATTLE GUARD PICTURES

ATTACHMENT G – GOVERNMENT-FURNISHED CATTLE GUARD SUPPLIES

ATTACHMENT H – WARNING SIGN INSTALLATION GUIDELINES

ATTACHMENT I – TYPE 3 OBJECT MARKER INSTALLATION GUIDELINES

ATTACHMENT J –TYPICAL ROADWAY SECTIONS, AGGREGATE SURFACE

12 | P a g e

ATTACHMENT A – PROJECT MAP, NFSR 373 AND STOCKPILE LOCATION

13 | P a g e

ATTACHMENT B – PROJECT MAP, STOCKPILE LOCATION, WILLOW WORK CENTER

14 | P a g e

ATTACHMENT C – AGGREGATE STOCKPILE PICTURES

15 | P a g e

ATTACHMENT D – PROJECT MAP, NFSR 360 CATTLE GUARD & VERDE RANGER STATION

16 | P a g e

ATTACHMENT E – PROJECT MAP, NFSR 360 CATTLE GUARD

17 | P a g e

ATTACHMENT F – EXISTING CATTLE GUARD PICTURES

18 | P a g e

19 | P a g e

ATTACHMENT G – GOVERNMENT-FURNISHED CATTLE GUARD SUPPLIES

20 | P a g e

21 | P a g e

ATTACHMENT H – WARNING SIGN INSTALLATION GUIDELINES

22 | P a g e

23 | P a g e

24 | P a g e

ATTACHMENT I – TYPE 3 OBJECT MARKER INSTALLATION GUIDELINES

25 | P a g e

ATTACHMENT J – TYPICAL ROADWAY SECTIONS, AGGREGATE SURFACED

26 | P a g e

ATTACHMENT K – COMPACTION SPECIFICATIONS, FP-24

27 | P a g e

1.0 GENERAL INFORMATION
1.1 WORK SUMMARY
1.2 PROJECT LOCATION
1.2.1 NFSR 373 MATERIAL HAULING
1.2.2 NFSR 360 CATTLE GUARD REPLACEMENT
1.3 PERFORMANCE PERIOD & WORK RESTRICTIONS
1.4 POINTS OF CONTACT
1.5 CONTRACTOR STAGING & STORAGE AREAS
1.6 UTILITIES & SANITATION SERVICES
1.7 USE OF PREMISES
1.8 GOVERNMENT FURNISHED ITEMS AND MATERIALS
1.9 PROTECTION OF NATURAL RESOURCES
1.10 COORDINATION OF RESOURCES
1.11 SUBMITTALS
2.0 PROJECT SCOPE
2.1 SCOPE
2.2 BASE BID LINE ITEMS
2.2.1 MOBILIZATION AND DEMOBILIZATION
2.2.2 LOADER WITH OPERATOR
2.2.3 DUMP TRUCK WITH OPERATOR
2.2.4 VIBRATORY SMOOTH DRUM ROLLER WITH OPERATOR
2.2.5 WATER TENDER WITH OPERATOR
2.2.6 AGGREGATE MATERIAL PURCHASE
Table 1, FP-24, Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, Section 703.05 Subbase, Base, and Surface Course Aggregate
2.2.7 AGGREGATE MATERIAL HAULING AND DELIVERY
2.3 OPTION BID LINE ITEMS
2.3.1 ROAD GRADER WITH OPERATOR
2.3.2 NFSR 360 CATTLE GUARD REPLACEMENT

2.4 SCOPE ATTACHMENTS

ATTACHMENT A – PROJECT MAP, NFSR 373 AND STOCKPILE LOCATION
ATTACHMENT B – PROJECT MAP, STOCKPILE LOCATION, WILLOW WORK CENTER
ATTACHMENT C – AGGREGATE STOCKPILE PICTURES
ATTACHMENT D – PROJECT MAP, NFSR 360 CATTLE GUARD & VERDE RANGER STATION
ATTACHMENT E – PROJECT MAP, NFSR 360 CATTLE GUARD
ATTACHMENT F – EXISTING CATTLE GUARD PICTURES
ATTACHMENT G – GOVERNMENT-FURNISHED CATTLE GUARD SUPPLIES
ATTACHMENT H – WARNING SIGN INSTALLATION GUIDELINES
ATTACHMENT I – TYPE 3 OBJECT MARKER INSTALLATION GUIDELINES
ATTACHMENT J – TYPICAL ROADWAY SECTIONS, AGGREGATE SURFACED
ATTACHMENT K – COMPACTION SPECIFICATIONS, FP-24

File details come from the government source that posted it. Updated .