Attachment 1 - Statement of Work.pdf

PDF 783 KB Posted

Attached to
TBRD Water Leak Repair Phase 2
Solicitation number
127EAX26Q0045
Issued by

About this file

This is a Project Scope of Work for a water leak repair project issued by the U.S. Forest Service, Tonto National Forest, Tonto Basin Ranger District, dated May 2026.

The project involves repairing leaks in the drinking water network serving recreation campgrounds along Roosevelt Lake and Apache Lake in Arizona, with work locations including Cholla Campground (Teddy Bear, Christmas, Staghorn, and Jumping Cholla Loops), Windy Hill Campground (Chipmunk and Grapevine Goose Loops), Burnt Corral Campground, and Grapevine Group Site. The base bid work (Line Items a-f) consists of: mobilization; relocation of water hydrants at Teddy Bear and Christmas Loops closer to main water lines with abandonment of existing hydrant branches; leak repair under asphalt pavement at Chipmunk and Grapevine Goose Loops with asphalt replacement; leak repair and replacement of 80 feet of iron pipe with Schedule 40 PVC pipe at Burnt Corral Campground; and installation of priority and pressure reduction valves at Grapevine Group Campground and Cholla Campground. Five option line items (g-k) address future contingency work including hydrant relocation, leak repairs under and outside pavement, valve installation, and pipe replacement, with costs to be determined based on the contractor's proposal. The contractor is responsible for providing all personnel, equipment, tools, and materials; obtaining permits and insurance; conducting necessary site investigations; coordinating with the Contracting Officer's Representative; contacting Arizona 811 for utility locating at the Grapevine Goose location; and delivering as-built drawings upon project completion. The contractor must complete the base portion within 60 days of notice to proceed and provide an OSHA 30-HR certified safety inspector, dedicated site superintendent, and quality control representative during construction. Payment is by units as defined in the Schedule of Items. The project point of contact is Kossigan Apedjinou, Project Manager/Contracting Officer's Representative, at (602) 225-5323 or kossigan.apedjinou@usda.gov.

View the file

Other files

File Type Posted
127EAX26Q0045_Amd_0001.pdf PDF
Statement of Work_Amendment 00001.docx DOCX document
Site Visit Sign-in.pdf PDF
Attachment 6 - Wage Determination.pdf PDF
Attachment 2 - Industrial Fire Plan.pdf PDF
Attachment 4 - Drawings.pdf PDF
Attachment 3 - Directional Maps.pdf PDF
127EAX26Q0045 TBRD Leak Repair Phase 2.pdf PDF
Attachment 5 - Schedule of Items.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1/6

SOUTHWEST REGION 03

TONTO NATIONAL FOREST

TONTO BASIN RANGER DISTRICT (TBRD)

WATER LEAK REPAIR

PHASE 2

PROJECT SCOPE OF WORK

U.S. FOREST SERVICE

MAY 2026

2/6

TABLE OF CONTENTS

I. OBJECTIVE AND BACKGROUND

II. LOCATION

III. SUMMARY OF WORK

IV. CONTRACT LINE-ITEM DESCRIPTIONS

BASE BID

OPTION LINE ITEMS

V. SUBMITTAL PROCEDURES AND REQUIREMENTS

VI. PERFORMANCE PERIOD and PAYMENT

VII. PROJECT POINTS OF CONTACT 6

ATTACHMENT 6

REFERENCES 6

I. OBJECTIVE AND BACKGROUND

The Tonto National Forest - Tonto Basin Ranger District - plans to repair leaks in its drinking water network. The main objective of the project is to eliminate the known leaks, make the water network more efficient, and anticipate upcoming leak repairs that will be covered by contract modification. At the end of the project, the contractor shall provide as-built drawings of the project to the Forest Service.

The successful contractor, in addition to fixing the current issues, shall be responsible for repairing future leaks over a period of a one (1) year. There are two parts to the project:

a) The first part, called Base Bid, shall repair the known leaks that are defined in the Schedule of Items (SOI). From the Schedule of Items, those works are listed as Line-Item numbers from a to f.

b) The second part, called Option Line Items, deals with any issues the water network may have in the future. The contractor shall receive a modification detailing the requested work, and the cost shall be based on the contractor’s offer. The Schedule of Items for these works are listed as Option Line Items and are Line-Items g to k.

✓ Many of the leaks are noticed on the secondary pipes that feed 1 or 2” inch hydrant. The forest Service plans to relocate the hydrants to the main pipes by abandoning the leak pipes. The hydrants shall be furnished by the Forest Service.

✓ Some of the leaks shall be repaired under the asphalt of the loops. After backfilling the trench in accordance with the FP14 specification, the contractor must place new asphalt over the cut portion and make necessary adjustments to return the loop to its original shape.

✓ Replace an 80 feet iron pipe with a Schedule 40 PVC pipe.

3/6

✓ Install two priority valves

✓ Add pressure reduction valve

The contractor shall provide all personnel, equipment, tools, and materials to accomplish the project. The contractor is responsible for the supervision, incidentals, and services required to perform the work in strict accordance with the applicable codes and requirements and the contract document. The contractor shall also verify pipe sizing and pipe material to ensure proper materials are ordered and installed.

II. LOCATION

The project is in the Tonto Basin Ranger District (TBRD) of the Tonto National Forest. The water systems, object of the present project, are mostly situated at the Recreation Campgrounds along Roosevelt Lake and Apache Lake. The following campgrounds and loops are where the water pipes are located:

✓ Cholla Campground

• Teddy Bear Loop

• Christmas Loop

• Staghorn Loop

• Jumping Cholla Loop

✓ Windy Hill Campground

• Chipmunk Loop

• Grapevine Goose Loop

✓ Burnt Corral Campground

III. SUMMARY OF WORK

a) Teddy Bear Loop:

Relocate water hydrants closer to water main and abandon old hydrant lines.

b) Christmas Loop:

Relocate water hydrants closer to water main and abandon old hydrant lines.

c) Chipmunk Loop:

Repair water line leak under the asphalt pavement and repair asphalt.

d) Grapevine Goose Loop:

Repair water line leak under asphalt pavement and repair asphalt. Leak is near existing underground power lines and will require Blue Stake.

e) Burnt Corral Campground:

Repair ¾” PVC water line leak at hydrant.

Replace 80’ iron pipe with Schedule 40 PVC pipe.

f) Grapevine Group Site

4/6

Install pressure priority valve (valve at top of windy hill that will shut Grapevine Group Site water supply off when pressure hits below a certain point; 120psi).

Install pressure reduction valve.

g) Contingency line item for other leaks.

h) Install a pressure reduction valve for Cholla Campground

i) Future work on non-specific sites

IV. LINE-ITEM DESCRIPTIONS

BASE BID

a) Mobilization

This work involves moving personnel, equipment, materials, and incidentals to the project and performing necessary work before beginning work at the site. It also includes obtaining permits, insurance, and bonds.

b) Relocation of Hydrants at Teddy Bear and Christmas Loops

At the Teddy Bear and Christmas loops located at Cholla Campground, the contractor shall remove the hydrants from their current location and install them on the water main pipes that feed the loop. (see Drawing # 1)

The hydrants shall be placed perpendicularly at 6 feet from the loop water main lines. The water branches that were feeding the hydrants shall be abandoned in place. All work needed to reposition the 2 hydrants are considered incidental to the line Item CLIN 002.

c) Leak Repair under pavement at Chipmunk and Grapevine Goose Loops

The contractor shall repair the leak located under the loop’s pavement. These leaks shall be repaired in place by cutting the asphalt with appropriate tools, digging to the pipe, fixing the leak, back filling the trench, and replacing a new asphalt layer. The pipe diameter is supposed to be 2 inches PVC. It is recommended that the contractor conducts necessary investigations by digging and finding the pipe in order to get the appropriate material for the leak repair. (see Drawing # 2 & 3)

At Grapevine Goose, the leak is located almost under a transformer. Before starting any work on that site to repair the leak, the contractor shall contact Arizona 811 (www.arizona811.com) to investigate and mark the location of underground utilities. The contractor remains responsible for the safe conduct of the project and shall take appropriate measures to prevent damage and ensure safety.

d) Leak repair and water pipe replacement at Burnt Corral Campground

Burnt Corral Campground, the leak is located on ¾” PVC connected to the hydrant and no asphalt work is necessary. In addition to repairing the leak, the contractor shall replace the connecting iron pipe (100 feet) with a Schedule of 40 PVC. The contractor shall coordinate with the COR (Contracting Officer's Representative) to figure out the specific pipe that needs to be replaced. (see Drawing # 4) http://www.arizona811.com/

5/6

e) Installation of a priority valve and a reduction valve at Grapevine Group

Campground

To reduce the high-water pressure at Grapevine Group site, the contractor shall install a priority valve in a location designated by the COR. A reduction valve shall be added to the waterline feeding North Services. The diameter of those pipes is unknown, and the contractor may use 6 inches PVC pipe to estimate the installation cost of the two valves. (see Drawing # 5)

f) Installation of a 4” reduction valve at Cholla Campground

To reduce the high-water pressure at Cholla Campground site, the contractor shall install a pressure reduction valve in a location designated by the COR. The pressure reduction valve that shall be installed on a 4” PVC pipe. (see Drawing # 6)

g) Relocation of Hydrants

OPTION LINE ITEMS

Based on the hydrant’s relocation at Teddy Bear and at Christmas loop, the contractor shall estimate the cost to relocate hydrants in the future on the campgrounds of the Tonto Basin Ranger District.

h) Leak Repair under pavement

i) Leak Repair outside of pavement

j) Installation of valves

k) Replacement of existing water pipe with Schedule 40 PVC

V. SUBMITTAL PROCEDURES AND REQUIREMENTS

When a product, model number, part number, etc. is specified herein, it is implied a substitute product with the same performance specifications may be submitted as an Approved Equal, subject to final approval by the Contracting Officer.

Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism. Special requirements are necessary to properly close out a construction contract, such record drawings and as-built drawings.

The Contracting Officer review will be completed and returned within 14 calendar days after the date of submissions. If a submittal is marked as “Disapproved” or “Does not comply”, resubmit with appropriate corrections. No work shall proceed for this item until resubmittal is approved.

The contractor shall provide an OSHA 30-HR certified safety inspector during construction activities. The contractor shall provide a dedicated site superintendent and quality control representative during construction activities. The contractor may elect to have all safety, superintendent, and quality control duties under the supervision of one individual, so long as the individual is qualified and certified to meet the requirements.

6/6

VI. PERFORMANCE PERIOD and PAYMENT

Upon notice to proceed (NTP), the Contractor shall complete the base portion of the project in 60 days. Payment will be by units defined and determined according to the Schedule of Items for the project.

VII. PROJECT POINTS OF CONTACT

Kossigan Apedjinou – Project Manager/COR Phone: (602) 225-5323 Cell: (480) 973-0553 Email : kossigan.apedjinou@usda.gov

ATTACHMENT

- Drawing Set

- Photos Collection

- Schedule Of Items

- AZ-TNF 2024 Signed Industrial Fire Plan

- Directional Maps

REFERENCES

- The Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects (FP-14)

- Forest Service Supplemental Specifications (FSSS)

- National Uniform Plumbing Code (NUPC) mailto:kossigan.apedjinou@usda.gov