Attachment 1 - Statement of Work.pdf
PDF 84 KB Posted
- Attached to
- Boiler Replacements Federal contract opportunity
- Solicitation number
- 1232SA26Q0363
About this file
This is a Statement of Work for the USDA Agricultural Research Service (ARS) San Joaquin Valley Agricultural Sciences Center in Parlier, California, for the replacement of two end-of-life boilers. The contractor must purchase and install one boiler in building 13 and one boiler in building 70, with specifications detailed in an attached minimum specification form. All work must comply with federal and industry standards, and the contractor is responsible for furnishing all equipment, materials, and supplies required for the installation. The contractor must remove old boilers, ensure new boilers are fully operational upon completion, and remove all trash and materials generated during installation. The contractor shall provide an installation schedule to the contracting officer and submit as-built documentation upon request.
Work must be performed at the San Joaquin Valley Agricultural Sciences Center located at 9611 S. Riverbend Ave, Parlier, CA 93648, during regular business hours (7:30 AM to 4:00 PM Pacific) Monday through Friday, excluding federal holidays. The performance period runs from July 1, 2026 through September 30, 2026. The contractor must comply with all security requirements, including daily sign-in with a USDA representative and adherence to local security regulations and federal, state, and local safety regulations. A site walk is highly encouraged prior to proposal submission to allow contractors to assess the facility and installation requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Photo 3.jpg | JPG image | |
| Photo 4.jpg | JPG image | |
| Photo 5.jpg | JPG image | |
| SF30 - Amendment 01.pdf | ||
| Photo 1.jpg | JPG image | |
| Site Visit Sign In Sheets.pdf | ||
| RFIs.pdf | ||
| Photo 2.jpg | JPG image | |
| Attachment 2 - Specifications.pdf | ||
| SF1442 - Solicitation Terms and Conditions.pdf | ||
| Attachment 3 - Wage Determination.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Agricultural Research Service San Joaquin Valley Agricultural Sciences Center
9611 S. Riverbend Ave, Parlier, CA 93648
Replacement of boilers in building 13 and 70 Statement of Work
1. Background: The USDA-ARS facility in Parlier, California has two boilers that have reached the end of their life cycle. This acquisition seeks obtain a contractor to purchase and install a boiler in building 13 and a boiler in building 70.
Specifications below are the minimum requirements needed to ensure that the replacement boilers provide adequate hot water for these buildings.
2. Scope: The Contractor shall provide a proposal that details the purchase and installation of a boiler in building 13 and a boiler in building 70. Site walk will be scheduled, and it is highly encouraged that contractors attend the site walk prior to submitting proposals.
3. Objectives: The objective is to obtain a contractor who is experienced with removing and installing boilers.
4. Requirements:
• Purchase two boilers per the minimum specification form (see attached).
• Remove old boilers and install new boilers in accordance with federal and industry standards.
• Ensure boilers are fully operational upon completion of installation.
• Remove trash and materials created by the installation of the new boilers.
5. Delivery: Contractor shall furnish all equipment, materials, and supplies required to achieve the quality performance standards of the work in this contract. Provide the contracting officer with an installation schedule.
6. Government-Furnished Property: Provide as-builds upon request. Area for the contractor to stage equipment and materials required, if needed.
7. Security Requirements: Contractor must sign in daily with USDA representative.
Abide by local security regulations and federal, State, local safety regulations.
8. Place of Performance: The work to be performed under this contract will be performed at the San Joaquin Valley Agricultural Sciences Center, located at 9611 S. Riverbend Ave, Parlier, CA 93648. Work will be conducted on regular business days (Monday through Friday) and during regular business hours (7:30AM to 4:00PM Pacific) excluding any federal holidays.
9. Period of Performance: Upon award of the contractor must complete work between July 1, 2026 – September 30, 2026.
| USDA Agricultural Research Service |
| San Joaquin Valley Agricultural Sciences Center |
| 9611 S. Riverbend Ave, Parlier, CA 93648 |
| Replacement of boilers in building 13 and 70 |
| Statement of Work |
File details come from the government source that posted it. Updated .