Attachment 1 - Statement of Work.pdf
PDF 843 KB Posted
- Attached to
- FY25 High Voltage Switch Repair
- Solicitation number
- FA462025QA956
About this file
This Statement of Work (SOW) details the repair requirements for a Cooper High Voltage Switch (Serial #CP572004691) at Fairchild Air Force Base (FAFB) in Washington. The contractor must provide labor, tools, equipment, and materials to repair a critical switch with a burned 600-amp bushing, including tasks such as removing the main tank cover, draining and filtering oil, replacing the damaged bushing, inspecting internal components, and performing vacuum/pressure and continuity tests. The project is part of the Department of the Air Force Air Mobility Command's FY25 maintenance efforts, with a performance period of 60 days after contract award and work to be completed during standard business hours (0700-1630 Monday through Friday), with potential flexibility for alternative work times approved by the Contracting Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25QA956 Combo (Rev. 06).pdf | ||
| Amendment 0008.pdf | ||
| 25QA956 Combo (Rev. 05).pdf | ||
| Amendment 0007.pdf | ||
| 25QA956 Combo (Rev. 04).pdf | ||
| Amednment 0006.pdf | ||
| Amendment 0005.pdf | ||
| 25QA956 Combo (Rev. 03).pdf | ||
| 25QA956 Combo (Rev. 02).pdf | ||
| Amendment 0004.pdf | ||
| 25QA956 Combo (Rev. 01).pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Attachment 2 - Wage Determination 2015-5537 (Rev. 24).pdf | ||
| 25QA956 Combo.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
FY25 High Voltage Switch Repair
March 2025
FA462025QA956
Attachment 1 - Statement of Work
Statement of Work (SOW) For
FY25 High Voltage Switch Repair
Fairchild AFB, WA
1. BACKGROUND: Cooper VFI Switch Serial #CP 572004691 suffered a critical failure with a burned up 600-amp bushing, making this until unusable and must be repaired to restore full electrical capacity to
FAFB.
2. SCOPE OF WORK: Contractor shall provide all necessary labor, tools, equipment, and materials to make necessary repairs to a Cooper High Voltage switch serial number CP572004691. Will be required to Unbolt and remove main tank cover; drain and filter all oil into new clean containers; remove and replace burned 600-amp bushing; clean and inspect all remaining bushings; check all internal connections; Re-filter oil back into unit; reseal amin tank cover; perform vacuum/pressure test; compete continuity test and clean unit. Upon completion the contractor will provide fully repaired and operational Cooper VFI switch as described in this Statement of Work and verified by Fairchild AFB 92d CES Electric Shop. All work shall be performed in accordance with all Federal, State, local laws and regulations, manufacturer’s recommendations and requirements set forth in this Statement of Work
(SOW).
3. OBJECTIVES: To provide a fully a fully repaired and operational Cooper VFI switch that functions in accordance with all Federal, State, local laws, regulation, manufacturers recommendations and requirements set forth in this SOW.
4. REQUIREMENTS:
i. Coordinate delivery of switch from FAFB to contractor’s workplace with 92 CES Electric Shop point of contact Mr. Jon Dolar at 247-2984
ii. Provide personnel to unload switch at contractors work location.
iii. Unbolt and remove Main tank cover.
iv. Drain and filter all oil into clean containers.
v. Remove and replace burned 600-Amp bushing with new 600 Amp 15/25 KV deadbreak bushing.
vi. Clean and inspect remaining bushings and replace if necessary.
vii. Check all internal connections for security and signs of damage.
viii. Re-Filter oil back into the unit and Re-seal main tank cover.
ix. Perform Vacuum/Pressure test.
x. Complete continuity test on unit
5. SECURITY REQUIREMENTS: All personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering the government installation, shall abide by all Fairchild Air Force Base security regulations.
6. PLACE OF PERFORMANCE: Work will be performed at Contractors workplace
7. PERIOD OF PERFORMANCE: Project to be completed within 60 days after award of contract
8. HOURS OF OPERATION: Hours of operation are 0700-1630 Monday through Friday, excluding Federal Holidays and any other designated down day. Work can be done at other than the normal hours of operation with the approval of the Contracting Officer. The contractor shall coordinate in advance all hours of work and any service interruptions with 92 Civil Engineer Squadron points of contact.