Attachment 1_Statement of Work.docx
DOCX document 432 KB Posted
- Attached to
- Installation of roof sealant
- Solicitation number
- 12639526Q0209
About this file
This is a Statement of Work (SOW) for roof rehabilitation services at the USDA Moore Air Base in Edinburg, Texas. The project involves coating and sealing the entire roof of Building 6017 (the Citrus Health Response Program facility) with a quality elastomeric reflective roof coating and repairing any roof leaks beyond the scope of coating alone. The building roof measures approximately 115 feet long by 75 feet wide. The contractor must attend a mandatory site visit to acquire precise roof repair and seal measurements before proposal submission. Work specifications include power soft washing the roof to remove dirt and grime, repairing areas with extensive damage causing water leaks prior to coating application, and applying a minimum of two coats of heavy-duty elastomeric reflective roof coating using either a 3/4-inch nap exterior paint roller or professional airless sprayer. The coating must be applied on clear, warm, sunny days with temperatures above 55°F for 24 hours and not exceeding 110°F, with one hour cure time between coats and perpendicular application of the second coat. The contractor is responsible for site preparation and protection, cleanup, prevention of paint overspray and spillage, and compliance with all EPA, state, and local environmental and safety regulations.
Work must be performed Monday through Friday during normal business hours (7:00 AM to 3:30 PM), with any work outside these times requiring written approval from the Facilities Maintenance Manager. Moore Air Base is a restricted facility requiring all contractor employees to possess valid picture identification and maintain proper vehicle insurance and registration. All contractors must remain on-site under supervision of a qualified job site superintendent, and portable restroom facilities must be provided for projects exceeding three working days. All work shall be performed by EPA-certified technicians in a professional manner, with all equipment and materials being new and unused unless otherwise specified. Contractors must provide Material Safety Data Sheets for all products used and strictly comply with manufacturers' instructions and all applicable federal, state, and local codes and regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFIs and Responses.docx | DOCX document | |
| 6017 Roof Sealant Installation Sign-In Sheet.pdf | ||
| 12639526Q0209.docx | DOCX document | |
| 12639526Q0209.docx | DOCX document | |
| Attachment 2_Federal Construction Wage Rates_Hidalgo County.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12639526Q0209, Attachment 1 Statement of Work For 6017 CHRP Roof Rehab June 2026
1.0 CONTRACT PROJECT: 6017 CHRP Roof Rehab
2.0 LOCATION: USDA Moore Air Base (MAB)
| APHIS PPQ FO CHRP |
| (Citrus Health Response Program) |
| Building 6017 |
| 22675 N. Moorefield Rd. |
| Moore Air Base |
| Edinburg, TX 78541 |
3.0 PROJECT BACKGROUND: USDA, APHIS, PPQ, FO, CHRP collaborate with State departments of agriculture and the citrus industry to safeguard the American citrus industry. The goals of the Citrus Health Response Program (CHRP) are to sustain the U.S. citrus industry, maintain grower access to export markets, and safeguard citrus-producing areas against exotic citrus diseases and pests.
To achieve these goals, CHRP performs multi-pest surveys in commercial and residential citrus areas to identify early infestations of exotic citrus pests for eradication, and to ensure that quarantine boundaries accurately reflect infested areas. CHRP protects the American consumer’s access to domestically produced citrus fruit and nursery trees with regulations that limit the spread of pests to un-infested areas.
Citrus-producing regions in the United States are at high risk for the introduction and establishment of exotic pests and diseases because of their proximity to international air and maritime ports and favorable climatic conditions.
Five exotic citrus pests and diseases are established in the United States and have the potential to harm every acre of citrus if they were allowed to spread. They include huanglongbing, also known as citrus greening; Asian citrus psyllid; citrus canker; citrus black spot; and sweet orange scab.
The current MAB CHRP building 6017 has roof leaks and needs a new roof coating to mitigate the leaks entering the building offices.
4.0 DESCRIPTION: Coat and seal the entire building 6017 roof with a quality elastomeric reflective roof coating and repair any roof leaks present that are beyond the ability to be just coated and cause future leaks.
4.0.1 Roof Coating Seal/Repair Specifications:
1. Contractors must attend a solicitation site visit to acquire all roof repair/seal measurements and specifics. The rough roof measurements are: 115’ L X 75’ W.
2. Provide labor and materials to apply elastomeric reflective roof coating to the Greening Building.
3. Roof shall be power soft wash to remove excess dirt and grime for proper adhesion to the existing metal roof. Includes planning, equipment, and material acquisition, area preparation and protection, setup and cleanup.
4. Repair all areas with extensive roof damage causing water leaks into the building before new roof coat sealant is applied.
5. Install new heavy duty elastomeric reflective roof coating.
6. The new coating shall be applied on a clear, warm sunny day. Temperatures must be above 55°F (12°C) for 24 hours and rise, but not above 110°F (43°C). Apply with a 3/4” nap exterior paint roller or professional airless sprayer. First, apply one coat over all seems and joints and allow to cure for one hour or until dry. Then, apply two uniform coats, avoiding excessive rolling or spraying. Two coats are mandatory for all applications. Apply second coat perpendicular to first coat.
7. Minimum of two coats shall be applied to the roof allowing proper dry time between coats.
8. Communicate and protect the building surroundings from paint overspray or excess paint spillage. Any material over spray or material spillage will be the responsibility of the contractor to clean and make right/compensate.
9. Keep construction site clean and leave the surrounding area clean after project completion.
The Contractor shall ensure that all solutions/products shall be used in strict conformance with the product's Environmental Protection Agency (EPA) and state requirements. All manufacturers' instructions and recommendations for the use of the solutions shall be strictly followed. In addition, the contractor shall comply with all federal, state, or local laws and regulations concerning the use, storage, and disposal of hazardous materials.
Contractor will provide Material Safety Data Sheets (MSDS) as specified in this contract and keep the sheets current for any product that is used in this contract.
Contractors must comply with applicable codes, environmental regulations in the State of Texas and local ordinances.
· All work shall be performed in accordance with all applicable State and Local codes and standards.
· All work to be performed by EPA certified technicians and executed in a professional workman like manner.
· All equipment and material installed on this project shall be new and unused unless otherwise noted.
· All work to be performed during normal business hours, Monday through Friday, unless otherwise noted.
5.0 Facility Security and Safety Requirements:
In addition to this SOW, Moore Air Base is a restricted facility.
· Work Hours are Monday through Friday from 7:00 AM to 3:30 PM. All work outside of the mentioned days and hours shall be approved by the Facilities Maintenance manager in writing, prior to entering the facility. This includes work during Federal holidays.
· Some of this work will be required after 3:30. The Contractor is to provide a schedule for those days to coordinate with the Maintenance Mechanic Supervisor.
· All Contractor employees shall have a valid picture identification such as a driver’s license or a State identification card.
· All vehicles shall have proper insurance and registration for entering the facility.
· All Contractors working at the facility shall remain in the project site under the supervision of a qualified job site superintendent. Anyone found outside of the determined construction area will be removed from the facility and not allowed to return.
· All Contractors shall provide temporary and portable restroom facilities for their employees if the project has a duration of over three working days.
image3.jpeg image1.png image2.jpeg
File details come from the government source that posted it. Updated .