This is a Statement of Work (SOW) for the replacement of two Air Handling Units (AHU-4 and AHU-5) at the National Agricultural Library in Beltsville, Maryland. The project scope encompasses complete demolition of existing units and installation of new units with integrated controls, temporary cooling provisions during construction, VAV terminal installation in existing ductwork, and comprehensive commissioning of all systems. The facility is a 340,000-square-foot structure built in the 1960s, with the annex containing three stories (basement, ground floor, and first floor) that must remain operational throughout construction with only limited outages permitted.
The contractor is responsible for providing all labor, equipment (including cranes and rigging), materials, testing, and personal protective equipment necessary for project completion. Key deliverables include technical proposals with detailed cost estimates itemized by work task, a Critical Path Method (CPM) schedule within 14 days of award, and a Site-Specific Safety Plan within 14 days of contract award. The period of performance is 180 calendar days from Notice to Proceed, with standard work hours Monday through Friday, 7:30 a.m. to 4:30 p.m. All work must comply with specified codes and standards including IBC-2021, ASHRAE, NFPA, OSHA, and ARS Facility Design Standards. Documentation requirements include multiple submittal types (shop drawings, product data, test reports, operation and maintenance data), with a 21-day review cycle (7 days contractor response, 14 days government review). A one-year warranty on workmanship and materials is required, and a final inspection with punch list completion is mandatory prior to final payment. Key government contacts include Contracting Officer's Representative Jim Glick and Location Monitor Jermaine Winstead.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
National Agricultural Library (NAL) Cooling Tower Replacement Beltsville, MD
Jim Glick March 3, 2026
United States Department of Agriculture
Research, Education, and Economics Agricultural Research Service
USDA-ARS Facilities Division 5601 Sunnyside Ave, Beltsville, MD 20705 USDA is an Equal Opportunity Provider and Employer
Revision Date: Error! Unknown document property name. Page 2 of 9 SOW_NAL_Cooling Tower Replacement_JRG Table of Contents
| 1 | Project Information | 3 |
| 2 | Scope Statement | 3 |
| 2.1 | Background Information | 3 |
| 2.2 | Base Bid | 3 |
| 2.3 | Bid Options | 3 |
| 2.4 | Site Visit | 4 |
| 3 | Codes and Standards | 4 |
| 4 | Project Requirements | 5 |
| 5 | Contractor Responsibilities | 5 |
| 6 | Documentation Requirements | 6 |
| 6.1 | Submittals | 6 |
| 7 | Special Requirements | 7 |
| 7.1 | Permits | 7 |
| 7.2 | Quality Control | 7 |
| 8 | Safety Requirements | 7 |
| 8.1 | Housekeeping | 8 |
| 8.2 | Clean-Up | 8 |
| 9 | Project Schedule | 8 |
| 10 | Period of Performance (POP) | 9 |
| 10.1 | Work Hours | 9 |
| 11 | Warranty | 9 |
| 12 | Project Contacts | 10 |
| 13 | Attachments | 11 |
NAL Beltsville, MD – Cooling Tower Replacement
STATEMENT OF WORK
Project Information
| Title: | NAL AHU 4&5 Replace and Rezone |
| Location: | National Agricultural Library (NAL) |
| 10301 Baltimore Ave, Beltsville, MD 20705 |
Scope Statement The objective of this project is to REPLACE the two existing Air Handler Units (AHU-4 and AHU-5) entirely according to the 100% Design Package documents prepared by Summers Consultants Inc., including:
· Install new VAV terminals in existing ductwork
· Temporary cooling provisions for specific office areas
· Demolition of existing units and associated components
· New control system fully integrated into the existing BAS
· Equipment commissioning
· Training onsite personnel.
The contractor shall include all services and field labor, equipment (including cranes, rigging, and digging equipment), materials, testing and personal protective equipment necessary to perform the work.
No government equipment or services will be available for use by the contractor.
The facility will be occupied and must remain operational during construction activities. The NAL can only experience limited outages during construction.
Background Information The National Agricultural Library was built in the mid to late 1960’s. The Library approximately 340,000 square feet of space and has a fifteen-story tower and a two-story annex.
The air handling units 4 and 5 serve the annex building. They have reached the end of their useful lives and need replacement. The scope of work is to replace these air handling units.
The annex is three stories tall:
· Basement – mechanical rooms, electrical distribution, and storage
· Ground floor – data center, offices, conferences rooms, and storage
· 1st – offices, reading rooms, conference rooms, lobby, and event space Base Bid The contractor shall provide a detailed technical proposal and cost estimate for the entire project as specified in this statement of work. Vendor proposal shall be structured and itemized with details for each item including roll-up costs for items listed below. The base of the proposal shall include:
1) Demolition of AHU’s 4 and 5, and associated components
2) Replacement of AHU’s 4 and 5, pumps, fans, piping, controls, etc
3) Commissioning of AHU’s 4 and 5 Bid Options The contractor shall provide the bid options in their technical proposal and cost estimate to include the following tasks.
1) No bid options are anticipated for this project. Contractor may include options in their proposal that may be appropriate.
Site Visit There is a mandatory site visit to submit a technically acceptable quote. See solicitation for details.
Codes and Standards The following codes and standards govern the design, construction, quality control, and safety of structural work performed on this project (but not limited to the following):
· P&P 242.1M-ARS ARS Facility Design Standards
· International building code (IBC-2021), international code council (ICC).
· International existing building code (IEBC-2021), international code council (ICC).
· Minimum design loads and associated criteria for building and other structures (ASCE 7-16), American society of civil engineers.
· Specification for structural steel buildings (AISC 360-16), American institute of steel construction (aisc).
· Structural welding code-steel (AWS D1.1/D1.1M:2015), American welding society (AWS).
Other applicable Codes and Standards apply and are not limited to the following:
| · ADA - | Americans with Disabilities Act |
| · AMCA – | Air Movement and Control Association |
| · ANSI – | American National Standards Institute |
| · ASHRAE – | American Society of Heating Refrigeration and Air-Conditioning Engineers |
| · ASME – | American Society of Mechanical Engineers |
| · EPA – | Environmental Protection Agency |
| · NEC – | National Electric Code |
| · NFPA – | National Fire Protection Association |
| · OSHA – | Occupational Safety and Health Administration |
| · RCRA – | Resource Conservation and Recovery Act |
| · SMACNA - | Sheet Metal & Air Conditioning Contractors’ National Association |
Project Requirements The scope of work for this project is to replace AHU’s 4 and 5 completely, including the following:
· Install new VAV terminals in existing ductwork
· Provide and install temporary cooling provisions for specific office areas
· Demolish existing AHU’s 4 and 5 completely
· Housing, frame, piping, pumps, VFD’s, piping, controls, etc
· Supply/install new AHU’s 4 and 5 completely
· Housing, frame, piping, pumps, VFD’s, piping, controls, etc
· Integrate new AHU controls into existing BAS system
· Providing temporary cooling (as specified in the 100% Design Package)
· Commissioning new systems in coordination with A&E Commissioning Authority CxA
· and incidental related work Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer Representative a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
The contractor is responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a) Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b) Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
Commissioning is required for this project. The Contractor shall provide all services necessary to ensure commissioning is accomplished in accordance with the requirements described in section 100% Design Package. Contractor shall submit a separate CPM schedule for pre-performance testing, TAB, start-up, commissioning, and substantial completion.
Contractor Responsibilities The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.
The project work shall be performed per the following guidelines:
1. Contractor will verify all dimensions and site conditions prior to beginning work.
1. Contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.
1. Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site weekly.
1. Contractor is required to manage the project and consult with the Government prior to beginning all work phases.
1. Contractor shall perform work in a manner that minimizes the impact of daily operations of the facility and its workers. The building will be occupied and must remain functional during construction work.
1. Contractor will provide daily reports of work performed to the COR and LM, and weekly status updates to the EPM and COR.
1. Contractor must have a superintendent on the jobsite when crews are performing the installation work.
1. Contractor will provide their own restroom facility.
All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail.
Contractor shall determine where debris will be disposed of and what containers and methods will be used for handling and separating demolition debris.
The contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the contractor’s expense, to pre-damaged condition to the satisfaction of the COR and LM.
The contractor shall provide continuous noise and dust abatement as required to prevent disturbance and nuisance to the public, workers, and occupants of adjacent premises and surrounding areas. Dampen or cover areas affected by demolition operations as necessary to prevent dust nuisance.
Documentation Requirements Provide submittals to the Government well in advance of utilizing the material on the project to give enough time for review and approval. Do not purchase any material without Government approval of the submittal. Distribute product submittals to CO, COR and Location Monitor (LM) in pdf format via email attachment.
Comments and approval of the submittals by the Government shall not be construed as releasing the Contractor from compliance with the specified requirements herein or any applicable Codes.
Submittals Submittal reviews and responses to RFI’s shall be accomplished in a maximum of 7 days for the contractor AND 14 days for the Government for a total of 21 days.
Electronic files of all required documents necessary to describe the complete design intent shall be transmitted directly to the EPM/COR, LM, and CO with electronic files (typically in PDF format) unless otherwise specified by the Government.
Submittal requirements detailed in specification 01 33 00 and subsequent technical spec sections of the 100% Design Package and include:
· SD-01 Preconstruction Submittals
· SD-02 Shop Drawings
· SD-03 Product Data
· SD-04 Samples
· SD-05 Design Data
· SD-06 Test Reports
· SD-07 Certificates
· SD-08 Manufacturer's Instructions
· SD-09 Manufacturer's Field Reports
· SD-10 Operation and Maintenance Data
· SD-11 Closeout Submittals Special Requirements
Permits Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the contractor shall obtain these items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the contractor. Submit copies of demolition, hauling, and debris disposal permits and notices for record purposes. Include a description of the proposed haul routes.
Quality Control The work performed under this contract shall be subject to continuous audit by the COR and LM. Quality control is the exclusive responsibility of the contractor.
A final inspection shall be completed and documented prior to final payment and project close-out. The final inspection report must confirm the completion and successful installation of equipment, piping, electrical, and utilities according to the manufacturer’s recommended installation instructions. Final inspection report shall include a completed punch-List confirming each action item has been fully addressed to the satisfaction of the COR and LM.
Safety Requirements The contractor is responsible for complying with all local, state, and federal safety codes and laws.
The contractor will submit a Site-Specific Safety Plan (SSSP) in industry recognizable format to the CO and COR within 14 days of the contract award. The Government shall review the (SSSP) prior to the start of any construction activities.
Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor. The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel.
Housekeeping Effective housekeeping can help control or eliminate many workplace hazards. It also requires paying attention to important details such as the layout of the whole work site, work areas, walkways, storage areas, etc. Good housekeeping is also a basic part of incident and fire prevention.
Housekeeping is an ongoing task, not an ‘achievement’. Cleaning and organization must be done regularly, not just at the end of the shift. Constantly integrating housekeeping into jobsite activities can help ensure this is done properly. A good housekeeping program identifies and assigns responsibilities for the following:
· Clean up during the shift
· Day-to-Day cleanup
· Waste disposal
· Removal of unused materials
· Inspecting to ensure cleanup is complete Clean-Up The contractor shall keep the construction site clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the contractor shall remove all unused material, trash, and debris resulting from the work to the satisfaction of the COR and LM.
Project Schedule The Contractor shall provide a CPM project schedule within seven (14) calendar days after the date of receipt of award. The schedule shall show all work activities are successfully completed within the period of performance. At minimum, the schedule shall include major milestones and MEP disciplines, to include, but not be limited to:
· Notice to Proceed Date
· Permit Applications and Inspection dates
· Planned outages
· Government Review Time (2 weeks)
· Construction Start Date
· Construction End Date
· Substantial Completion
· Final Inspection/Acceptance
· Warranty Start
Contractor shall submit a separate CPM schedule for pre-performance testing, TAB, start-up, commissioning, and substantial completion.
Period of Performance (POP) The period of performance shall be 180 Calendar Days after receiving the Notice to Proceed (NTP) from the Contracting Officer.
Work Hours Generally, the contractor work hours shall be Monday - Friday, 7:30 am to 4:30 pm except on Government Holidays. Any changes to the work schedule shall be submitted to the CO and COR for written CO approval three days prior to implementing the change to the schedule.
Warranty All work shall be guaranteed for workmanship and material failures for a period of one (1) year from the date of final acceptance of the work. The contractor shall submit all product warranty documents to the COR.
Project Contacts
| Project Role: |
| Name / Location / Phone / Email |
| Contracting Officer (CO) |
| TBD |
Engineering Project Mgr (EPM) Contracting Officer’s Rep (COR) Jim Glick - USDA Beltsville, MD 443-310-0559 jamesglick@usda.gov
| Location Monitor (LM) |
| Jermaine Winstead |
Beltsville, MD
(301) 504-9817 jermaine.winstead@usda.gov
| Safety and Occupational Health Officer |
| Rachel Anderson |
Beltsville, MD
(301) 504-1250 rachel.anderson2@usda.gov
| Real Property Manager (RPM) |
| Michael Hajjar |
Beltsville, MD
(301) 922-3397 michael.hajjar@usda.gov
Attachments NAL Replace AHU 4 and 5 – 100% Drawings (IFC) NAL Replace AHU 4 and 5 – 100% Specifications (IFC)
End of doc image1.jpg image2.gif