DEPARTMENT OF VETERANS AFFAIRS
JOHN D. DINGELL VA MEDICAL CENTER
4646 JOHN R STREET
DETROIT, MI 48201
EHRM Infrastructure Upgrades
VA Project No.: 553-21-701
BID DOCUMENTS
Prepared By:
January 31, 2023
John D. Dingell VA Medical Center
Detroit, MI
Project: 553-21-701
08-01-21
TABLE OF CONTENTS
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 05-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20
01 33 23 Shop Drawings, Product Data, and Samples 06-21
01 35 26 Safety Requirements 07-20
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 74 19 Construction Waste Management 01-21
01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
DIVISION 03 – CONCRETE
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 01-21
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 40 00 Cold-Formed Metal Framing 01-21
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
Project: 553-21-701
08-01-21
TABLE OF CONTENTS
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
08 11 13 Hollow Metal Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 31 13 Access Doors and Frames 01-21
08 71 00 Door Hardware 01-21
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 65 36.13 Static Dissipating Flooring N/A
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
DIVISION 14 – CONVEYING EQUIPEMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 02-20
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20
23 09 23 Direct-Digital Control System for HVAC 09-11
23 81 00 Decentralized Unitary HVAC Equipment 03-20
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
Project: 553-21-701
08-01-21
TABLE OF CONTENTS
00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 24 16 Panelboards 01-18
26 26 00 Power Distribution Units for Static Uninterruptible Power
Systems
01-18
26 27 26 Wiring Devices 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 33 53 Static Uninterruptible Power Supply 01-17
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 10 00 Control, Communication and Signal Wiring 06-15
27 11 00 Communications Equipment Room Fittings 06-15
27 15 00 Communications Structured Cabling 01-16
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and Security 10-18
28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-11
28 13 00 Physical Access Control System 10-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – UTILITIES
DIVISION 34 – TRANSPORTATION
DIVISION 48 – Electrical Power Generation
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
VOLUME 1
GENERAL
100-GI000 COVER SHEET VOLUME 1
100-GI001 ABBREVIATIONS AND GENERAL DETAILS
100-GI002 EXISTING CONDITIONS
100-GI003 CODE ANALYSIS
ARCHITECTURE
100-AE100 OVERALL LOWER LEVEL FLOOR PLAN
100-AD400 LOWER LEVEL DEMOLITION PLANS
100-AD400A LOWER LEVEL DEMOLITION PLANS
100-AE400 ENLARGED LOWER LEVEL FLOOR PLANS
100-AE400A ENLARGED LOWER LEVEL FLOOR PLANS
100-AE101 OVERALL FIRST FLOOR PLAN
100-AD401 FIRST FLOOR DEMOLITION PLANS
100-AD401A FIRST FLOOR DEMOLITION PLANS
100-AE401 ENLARGED FIRST FLOOR PLANS
100-AE401A ENLARGED FIRST FLOOR PLANS
100-AE102 OVERALL SECOND FLOOR PLAN
100-AD402 SECOND FLOOR DEMOLITION PLANS
100-AE402 ENLARGED SECOND FLOOR PLANS
100-AE103 OVERALL THIRD FLOOR PLAN
100-AD403 THIRD FLOOR DEMOLITION PLANS
100-AE403 ENLARGED THIRD FLOOR PLANS
100-AE104 OVERALL FOURTH FLOOR PLAN
100-AD404 FOURTH FLOOR DEMOLTION PLANS
100-AE404 ENLARGED FOURTH FLOOR PLANS
100-AE105 OVERALL FIFTH FLOOR PLAN
100-AD405 FIFTH FLOOR DEMOLITION PLANS
100-AE405 ENLARGED FIFTH FLOOR PLANS
100-AE106 OVERALL SIXTH FLOOR PLAN
100-AD406 SIXTH FLOOR DEMOLATION PLANS
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 2
100-AE406 ENLARGED SIXTH FLOOR PLANS
100-AE107 OVERALL SEVENTH FLOOR PLAN
100-AD407 SEVENTH FLOOR DEMOLITION PLANS
100-AE407 ENLARGED SEVENTH FLOOR PLANS
AE500 ARCHITECTURAL DETAILS
FIRE PROTECTION
100-FX100 FIRE PROTECTION PLAN - LOWER LEVEL FLOOR NEW
OVERALL
100-FX101 FIRE PROTECTION PLAN - FIRST FLOOR NEW OVERALL
100-FX102 FIRE PROTECTION PLAN - SECOND FLOOR NEW OVERALL
100-FX103 FIRE PROTECTION PLAN - THIRD FLOOR NEW OVERALL
100-FX104 FIRE PROTECTION PLAN - FOURTH FLOOR NEW OVERALL
100-FX105 FIRE PROTECTION PLAN - FIFTH FLOOR NEW OVERALL
100-FX106 FIRE PROTECTION PLAN - SIXTH FLOOR NEW OVERALL
100-FX107 FIRE PROTECTION PLAN - SEVENTH FLOOR NEW OVERALL
100-FX400 ENLARGED FIRE PROTECTION PLAN - LOWER LEVEL FLOOR
100-FX401 ENLARGED FIRE PROTECTION PLAN - FIRST FLOOR
100-FX402 ENLARGED FIRE PROTECTION PLAN - SECOND FLOOR
100-FX403 ENLARGED FIRE PROTECTION PLAN - THIRD FLOOR
100-FX404 ENLARGED FIRE PROTECTION PLAN - FOURTH FLOOR
100-FX405 ENLARGED FIRE PROTECTION PLAN - FIFTH FLOOR
100-FX406 ENLARGED FIRE PROTECTION PLAN - SIXTH FLOOR
100-FX407 ENLARGED FIRE PROTECTION PLAN - SEVENTH FLOOR
MECHANICAL
100-MH001 MECHANICAL COVERSHEET
100-MD100 MECHANICAL DEMOLITION PLAN - LOWER LEVEL
100-MD101 MECHANICAL DEMOLITION PLAN - FIRST FLOOR
100-MD102 MECHANICAL DEMOLITION PLAN - SECOND FLOOR
100-MD103 MECHANICAL DEMOLITION PLAN - THIRD FLOOR
100-MD104 MECHANICAL DEMOLITION PLAN - FOURTH FLOOR
100-MD105 MECHANICAL DEMOLITION PLAN - FIFTH FLOOR
100-MD106 MECHANICAL DEMOLITION PLAN - SIXTH FLOOR
100-MD107 MECHANICAL DEMOLITION PLAN - SEVENTH FLOOR
100-MD300 ENLARGED MECHANICAL DEMO PLANS - LOWER LEVEL
100-MD301 ENLARGED MECHANICAL DEMO PLANS - FIRST FLOOR
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 3
100-MD302 ENLARGED MECHANICAL DEMO PLANS - SECOND FLOOR
100-MD303 ENLARGED MECHANICAL DEMO PLANS - THIRD FLOOR
100-MD304 ENLARGED MECHANICAL DEMO PLANS - FOURTH FLOOR
100-MD305 ENLARGED MECHANICAL DEMO PLANS - FIFTH FLOOR
100-MD306 ENLARGED MECHANICAL DEMO PLANS - SIXTH FLOOR
100-MD307 ENLARGED MECHANICAL DEMO PLANS - SEVENTH FLOOR
100-MH100 MECHANICAL PLAN - LOWER LEVEL
100-MH101 MECHANICAL PLAN - FIRST FLOOR
100-MH102 MECHANICAL PLAN - SECOND FLOOR
100-MH103 MECHANICAL PLAN - THIRD FLOOR
100-MH104 MECHANICAL PLAN - FOURTH FLOOR
100-MH105 MECHANICAL PLAN - FIFTH FLOOR
100-MH106 MECHANICAL PLAN - SIXTH FLOOR
100-MH107 MECHANICAL PLAN - SEVENTH FLOOR
100-MH300A ENLARGED MECHANICAL PLANS - LOWER LEVEL
100-MH300B ENLARGED MECHANICAL PLANS - LOWER LEVEL
100-MH301 ENLARGED MECHANICAL PLANS - FIRST FLOOR
100-MH302 ENLARGED MECHANICAL PLAN - SECOND FLOOR
100-MH303 ENLARGED MECHANICAL PLAN - THIRD FLOOR
100-MH304 ENLARGED MECHANICAL PLAN - FOURTH FLOOR
100-MH305 ENLARGED MECHANICAL PLAN - FIFTH FLOOR
100-MH306 ENLARGED MECHANICAL PLAN - SIXTH FLOOR
100-MH307 ENLARGED MECHANICAL PLAN - SEVENTH FLOOR
100-MH400 MECHANICAL CONTROLS
100-MH500 MECHANICAL DETAILS
100-MH600 MECHANICAL SCHEDULES
ELECTRICAL
100-EE001 ELECTRICAL LEGEND
100-ED100 ELECTRICAL PLAN - LOWER LEVEL FLOOR OVERALL
100-ED400A ELECTRICAL DEMOLITION PLAN - LOWER LEVEL FLOOR
100-ED400B ELECTRICAL DEMOLITION PLAN - LOWER LEVEL FLOOR
100-ED101 ELECTRICAL PLAN - FIRST FLOOR OVERALL
100-ED401 ELECTRICAL DEMOLITION PLAN - FIRST FLOOR
100-ED102 ELECTRICAL PLAN - SECOND FLOOR OVERALL
100-ED402 ELECTRICAL DEMOLITION PLAN - SECOND FLOOR
100-ED103 ELECTRICAL PLAN - THIRD FLOOR OVERALL
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 4
100-ED403 ELECTRICAL DEMOLITION PLAN - THIRD FLOOR
100-ED104 ELECTRICAL PLAN - FOURTH FLOOR OVERALL
100-ED404 ELECTRICAL DEMOLITION PLAN - FOURTH FLOOR
100-ED105 ELECTRICAL PLAN - FIFTH FLOOR OVERALL
100-ED405 ELECTRICAL DEMOLITION PLAN - FIFTH FLOOR
100-ED106 ELECTRICAL PLAN - SIXTH FLOOR OVERALL
100-ED406 ELECTRICAL DEMOLITION PLAN - SIXTH FLOOR
100-ED107 ELECTRICAL PLAN - SEVENTH FLOOR OVERALL
100-ED407 ELECTRICAL DEMOLITION PLAN - SEVENTH FLOOR
100-E100 ELECTRICAL PLAN - LOWER LEVEL FLOOR NEW OVERALL
100-E200 BONDING AND GROUNDING SCHEMATIC DIAGRAM - LOWER
LEVEL FLOOR NEW OVERALL
100-E400A ENLARGED FLOOR PLANS - LOWER LEVEL
100-E400B ENLARGED ELECTRICAL PLAN - LOWER LEVEL FLOOR
100-E101 ELECTRICAL PLAN - FIRST FLOOR NEW OVERALL
100-E201 BONDING AND GROUNDING SCHEMATIC DIAGRAM - FIRST
FLOOR NEW OVERALL
100-E401A ENLARGED ELECTRICAL PLAN - FIRST FLOOR
100-E401B ENLARGED ELECTRICAL PLAN - FIRST FLOOR
100-E102 ELECTRICAL PLAN - SECOND FLOOR NEW OVERALL
100-E202 BONDING AND GROUNDING SCHEMATIC DIAGRAM - SECOND
FLOOR NEW OVERALL
100-E402 ENLARGED ELECTRICAL PLAN - SECOND FLOOR
100-E103 ELECTRICAL PLAN - THIRD FLOOR NEW OVERALL
100-E203 BONDING AND GROUNDING SCHEMATIC DIAGRAM - THIRD
FLOOR NEW OVERALL
100-E403 ENLARGED ELECTRICAL PLAN - THIRD FLOOR
100-E104 ELECTRICAL PLAN - FOURTH FLOOR NEW OVERALL
100-E204 BONDING AND GROUNDING SCHEMATIC DIAGRAM - FOURTH
FLOOR NEW OVERALL
100-E404 ENLARGED ELECTRICAL PLAN - FOURTH FLOOR
100-E105 ELECTRICAL PLAN - FIFTH FLOOR NEW OVERALL
100-E205 BONDING AND GROUNDING SCHEMATIC DIAGRAM - FIFTH
FLOOR NEW OVERALL
100-E405 ENLARGED ELECTRICAL PLAN - FIFTH FLOOR
100-E106 ELECTRICAL PLAN - SIXTH FLOOR NEW OVERALL
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 5
100-E206 BONDING AND GROUNDING SCHEMATIC DIAGRAM - SIXTH
FLOOR NEW OVERALL
100-E406 ENLARGED ELECTRICAL PLAN - SIXTH FLOOR
100-E107 ELECTRICAL PLAN - SEVENTH FLOOR NEW OVERALL
100-E207 BONDING AND GROUNDING SCHEMATIC DIAGRAM - SEVENTH
FLOOR NEW OVERALL
100-E407 ENLARGED ELECTRICAL PLAN - SEVENTH FLOOR
EE500 ELECTRICAL DETAILS
EE501 GROUNDING PLAN
EE600 PANELBOARD SCHEDULES
EE601 PANELBOARD SCHEDULES
EE602 PANELBOARD SCHEDULES
EE603 PANELBOARD SCHEDULES
EE604 PANELBOARD SCHEDULES
EE605 PANELBOARD SCHEDULES
EE606 PANELBOARD SCHEDULES
EE607 PANELBOARD SCHEDULES
EE608 PANELBOARD SCHEDULES
EE609 PANELBOARD SCHEDULES
VOLUME 2
GENERAL
100-GI004 COVER SHEET
TECHNOLOGY
T001 ABBREVIATIONS & LEGEND
100-TD100 OVERALL LOWER LEVEL PLAN - REMOVALS
100-TD100.1 LOWER LEVEL PLAN - REMOVALS - ZONE 1
100-TD100.2 LOWER LEVEL PLAN - REMOVALS - ZONE 2
100-TD100.3 LOWER LEVEL PLAN - REMOVALS - ZONE 3
100-TD100.4 LOWER LEVEL PLAN - REMOVALS - ZONE 4
100-TD100.5 LOWER LEVEL PLAN - REMOVALS - ZONE 5
100-TD100.6 LOWER LEVEL PLAN - REMOVALS - ZONE 6
100-TD100.7 LOWER LEVEL PLAN - REMOVALS - ZONE 7
100-TD100.8 LOWER LEVEL PLAN - REMOVALS - ZONE 8
100-TD100.9 LOWER LEVEL PLAN - REMOVALS - ZONE 9
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 6
100-TD100.10 LOWER LEVEL PLAN - REMOVALS - ZONE 10
100-TD100.12 LOWER LEVEL PLAN - REMOVALS - ZONE 12
100-TD100i OVERALL LOWER LEVEL INTERSTITIAL PLAN - REMOVALS
100-TD100i.1 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 1
100-TD100i.2 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 2
100-TD100i.3 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 3
100-TD100i.4 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 4
100-TD100i.5 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 5
100-TD100i.6 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 6
100-TD100i.7 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 7
100-TD100i.8 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 8
100-TD100i.9 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 9
100-TD100i.10 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 10
100-TD100i.12 LOWER LEVEL INTERSTITIAL PLAN - REMOVALS - ZONE 12
100-TD101 OVERALL FIRST FLOOR PLAN - REMOVALS
100-TD101.1 FIRST FLOOR PLAN - REMOVALS - ZONE 1
100-TD101.2 FIRST FLOOR PLAN - REMOVALS - ZONE 2
100-TD101.3 FIRST FLOOR PLAN - REMOVALS - ZONE 3
100-TD101.4 FIRST FLOOR PLAN - REMOVALS - ZONE 4
100-TD101.5 FIRST FLOOR PLAN - REMOVALS - ZONE 5
100-TD101.6 FIRST FLOOR PLAN - REMOVALS - ZONE 6
100-TD101.7 FIRST FLOOR PLAN - REMOVALS - ZONE 7
100-TD101.8 FIRST FLOOR PLAN - REMOVALS - ZONE 8
100-TD101.9 FIRST FLOOR PLAN - REMOVALS - ZONE 9
100-TD101.10 FIRST FLOOR PLAN - REMOVALS - ZONE 10
100-TD101.11 FIRST FLOOR PLAN - REMOVALS - ZONE 11
100-TD101i OVERALL FIRST FLOOR INTERSTITIAL PLAN - REMOVALS
100-TD101i.1 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 1
100-TD101i.2 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 2
100-TD101i.3 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 3
100-TD101i.4 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 4
100-TD101i.5 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 5
100-TD101i.6 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 6
100-TD101i.7 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 7
100-TD101i.8 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 8
100-TD101i.9 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 9
100-TD101i.10 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 10
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 7
100-TD101i.11 FIRST FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 11
100-TD102 OVERALL SECOND FLOOR PLAN - REMOVALS
100-TD102.1 SECOND FLOOR PLAN - REMOVALS - ZONE 1
100-TD102.2 SECOND FLOOR PLAN - REMOVALS - ZONE 2
100-TD102.3 SECOND FLOOR PLAN - REMOVALS - ZONE 3
100-TD102.4 SECOND FLOOR PLAN - REMOVALS - ZONE 4
100-TD102.5 SECOND FLOOR PLAN - REMOVALS - ZONE 5
100-TD102.6 SECOND FLOOR PLAN - REMOVALS - ZONE 6
100-TD102.7 SECOND FLOOR PLAN - REMOVALS - ZONE 7
100-TD102.8 SECOND FLOOR PLAN - REMOVALS - ZONE 8
100-TD102.9 SECOND FLOOR PLAN - REMOVALS - ZONE 9
100-TD102.10 SECOND FLOOR PLAN - REMOVALS - ZONE 10
100-TD102i OVERALL SECOND FLOOR INTERSTITIAL PLAN - REMOVALS
100-TD102i.1 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 1
100-TD102i.2 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 2
100-TD102i.3 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 3
100-TD102i.4 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 4
100-TD102i.5 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 5
100-TD102i.6 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 6
100-TD102i.7 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 7
100-TD102i.8 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 8
100-TD102i.9 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 9
100-TD102i.10 SECOND FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE
100-TD103 OVERALL THIRD FLOOR PLAN - REMOVALS
100-TD103.1 THIRD FLOOR PLAN - REMOVALS - ZONE 1
100-TD103.2 THIRD FLOOR PLAN - REMOVALS - ZONE 2
100-TD103.3 THIRD FLOOR PLAN - REMOVALS - ZONE 3
100-TD103.4 THIRD FLOOR PLAN - REMOVALS - ZONE 4
100-TD103.5 THIRD FLOOR PLAN - REMOVALS - ZONE 5
100-TD103.6 THIRD FLOOR PLAN - REMOVALS - ZONE 6
100-TD103.7 THIRD FLOOR PLAN - REMOVALS - ZONE 7
100-TD103.8 THIRD FLOOR PLAN - REMOVALS - ZONE 8
100-TD103.9 THIRD FLOOR PLAN - REMOVALS - ZONE 9
100-TD103.10 THIRD FLOOR PLAN - REMOVALS - ZONE 10
100-TD103i OVERALL THIRD FLOOR INTERSTITIAL PLAN - REMOVALS
100-TD103i.1 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 1
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 8
100-TD103i.2 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 2
100-TD103i.3 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 3
100-TD103i.4 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 4
100-TD103i.5 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 5
100-TD103i.6 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 6
100-TD103i.7 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 7
100-TD103i.8 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 8
100-TD103i.9 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 9
100-TD103i.10 THIRD FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 10
100-TD104 OVERALL FOURTH PLAN - REMOVALS
100-TD104.1 FOURTH FLOOR PLAN - REMOVALS - ZONE 1
100-TD104.2 FOURTH FLOOR PLAN - REMOVALS - ZONE 2
100-TD104.3 FOURTH FLOOR PLAN - REMOVALS - ZONE 3
100-TD104.4 FOURTH FLOOR PLAN - REMOVALS - ZONE 4
100-TD104.5 FOURTH FLOOR PLAN - REMOVALS - ZONE 5
100-TD104.6 FOURTH FLOOR PLAN - REMOVALS - ZONE 6
100-TD104.7 FOURTH FLOOR PLAN - REMOVALS - ZONE 7
100-TD104.8 FOURTH FLOOR PLAN - REMOVALS - ZONE 8
100-TD104.9 FOURTH FLOOR PLAN - REMOVALS - ZONE 9
100-TD104.10 FOURTH FLOOR PLAN - REMOVALS - ZONE 10
100-TD104i OVERALL FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS
100-TD104i.1 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 1
100-TD104i.2 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 2
100-TD104i.3 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 3
100-TD104i.4 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 4
100-TD104i.5 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 5
100-TD104i.6 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 6
100-TD104i.7 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 7
100-TD104i.8 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 8
100-TD104i.9 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 9
100-TD104i.10 FOURTH FLOOR INTERSTITIAL PLAN - REMOVALS -
ZONE 10
100-TD105 OVERALL FIFTH FLOOR PLAN - REMOVALS
100-TD105.1 FIFTH FLOOR PLAN - REMOVALS - ZONE 1
100-TD105.2 FIFTH FLOOR PLAN - REMOVALS - ZONE 2
100-TD105.3 FIFTH FLOOR PLAN - REMOVALS - ZONE 3
100-TD105.4 FIFTH FLOOR PLAN - REMOVALS - ZONE 4
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 9
100-TD105.5 FIFTH FLOOR PLAN - REMOVALS - ZONE 5
100-TD105.6 FIFTH FLOOR PLAN - REMOVALS - ZONE 6
100-TD105i OVERALL FIFTH FLOOR INTERSTITIAL PLAN - REMOVALS
100-TD105i.1 FIFTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 1
100-TD105i.2 FIFTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 2
100-TD105i.3 FIFTH FLOOR INTERSTITIAL PLAN - REMOVALS - ZONE 3
VOLUME 3
GENERAL
100-GI020 COVER SHEET
TECHNOLOGY
100-TN100i OVERALL LOWER LEVEL INTERSTITIAL PLAN - NEW WORK
100-TN100i.1 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 1
100-TN100i.2 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 2
100-TN100i.3 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 3
100-TN100i.4 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 4
100-TN100i.5 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 5
100-TN100i.6 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 6
100-TN100i.7 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 7
100-TN100i.8 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 8
100-TN100i.9 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 9
100-TN100i.10 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 10
100-TN100i.12 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 12
100-TN101 OVERALL FIRST FLOOR PLAN - NEW WORK
100-TN101.1 FIRST FLOOR PLAN - NEW WORK - ZONE 1
100-TN101.2 FIRST FLOOR PLAN - NEW WORK - ZONE 2
100-TN101.3 FIRST FLOOR PLAN - NEW WORK - ZONE 3
100-TN101.4 FIRST FLOOR PLAN - NEW WORK - ZONE 4
100-TN101.5 FIRST FLOOR PLAN - NEW WORK - ZONE 5
100-TN101.6 FIRST FLOOR PLAN - NEW WORK - ZONE 6
100-TN101.7 FIRST FLOOR PLAN - NEW WORK - ZONE 7
100-TN101.8 FIRST FLOOR PLAN - NEW WORK - ZONE 8
100-TN101.9 FIRST FLOOR PLAN - NEW WORK - ZONE 9
100-TN101.10 FIRST FLOOR PLAN - NEW WORK - ZONE 10
100-TN101.11 FIRST FLOOR PLAN - NEW WORK - ZONE 11
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 10
100-T401.1 ENLARGED DATA ROOM PLAN - RM A1026A
100-T401.2 ENLARGED DATA ROOM PLAN - RM A1115A
100-T401.3 ENLARGED DATA ROOM PLAN - RM B1230A
100-T401.4 ENLARGED DATA ROOM PLAN - RM B1340A
100-T401.5 ENLARGED DATA ROOM PLAN - RM C1772A
100-T401.6 ENLARGED DATA ROOM PLAN - RM C1864A
100-T401.7 ENLARGED DATA ROOM PLAN - RM C1514A
100-T401.8 ENLARGED DATA ROOM PLAN - RM C1671A
100-T401.9 ENLARGED DATA ROOM PLAN - RM C1999D
100-TN101i OVERALL FIRST FLOOR INTERSTITIAL PLAN - NEW WORK
100-TN101i.1 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 1
100-TN101i.2 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 2
100-TN101i.3 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 3
100-TN101i.4 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 4
100-TN101i.5 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 5
100-TN101i.6 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 6
100-TN101i.7 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 7
100-TN101i.8 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 8
100-TN101i.9 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 9
100-TN101i.10 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 10
100-TN101i.11 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 11
100-TN102 OVERALL SECOND FLOOR PLAN - NEW WORK
100-TN102.1 SECOND FLOOR PLAN - NEW WORK - ZONE 1
100-TN102.2 SECOND FLOOR PLAN - NEW WORK - ZONE 2
100-TN102.3 SECOND FLOOR PLAN - NEW WORK - ZONE 3
100-TN102.4 SECOND FLOOR PLAN - NEW WORK - ZONE 4
100-TN102.5 SECOND FLOOR PLAN - NEW WORK - ZONE 5
100-TN102.6 SECOND FLOOR PLAN - NEW WORK - ZONE 6
100-TN102.7 SECOND FLOOR PLAN - NEW WORK - ZONE 7
100-TN102.8 SECOND FLOOR PLAN - NEW WORK - ZONE 8
100-TN102.9 SECOND FLOOR PLAN - NEW WORK - ZONE 9
100-TN102.10 SECOND FLOOR PLAN - NEW WORK - ZONE 10
100-T402.1 ENLARGED DATA ROOM PLAN - RM A2031A
100-T402.2 ENLARGED DATA ROOM PLAN - RM A2140A
100-T402.3 ENLARGED DATA ROOM PLAN - RM B2239A
100-T402.4 ENLARGED DATA ROOM PLAN - RM B2359A
100-T402.5 ENLARGED DATA ROOM PLAN - RM C2981A
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 11
100-T402.6 ENLARGED DATA ROOM PLAN - RM C2741A
100-T402.7 ENLARGED DATA ROOM PLAN - RM C2571A
100-T402.8 ENLARGED DATA ROOM PLAN - RM C2465A
100-TN102i OVERALL SECOND FLOOR INTERSTITIAL PLAN - NEW WORK
100-TN102i.1 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 1
100-TN102i.2 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 2
100-TN102i.3 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 3
100-TN102i.4 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 4
100-TN102i.5 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 5
100-TN102i.6 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 6
100-TN102i.7 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 7
100-TN102i.8 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 8
100-TN102i.9 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 9
100-TN102i.10 SECOND FLOOR INTERSTITIAL PLAN - NEW WORK -
ZONE 10
100-TN103 OVERALL THIRD FLOOR PLAN - NEW WORK
100-TN103.1 THIRD FLOOR PLAN - NEW WORK - ZONE 1
100-TN103.2 THIRD FLOOR PLAN - NEW WORK - ZONE 2
100-TN103.3 THIRD FLOOR PLAN - NEW WORK - ZONE 3
100-TN103.4 THIRD FLOOR PLAN - NEW WORK - ZONE 4
100-TN103.5 THIRD FLOOR PLAN - NEW WORK - ZONE 5
100-TN103.6 THIRD FLOOR PLAN - NEW WORK - ZONE 6
100-TN103.7 THIRD FLOOR PLAN - NEW WORK - ZONE 7
100-TN103.8 THIRD FLOOR PLAN - NEW WORK - ZONE 8
100-TN103.9 THIRD FLOOR PLAN - NEW WORK - ZONE 9
100-TN103.10 THIRD FLOOR PLAN - NEW WORK - ZONE 10
100-T403.1 ENLARGED DATA ROOM PLAN - RM A3031A
100-T403.2 ENLARGED DATA ROOM PLAN - RM A3142A
100-T403.3 ENLARGED DATA ROOM PLAN - RM B3239A
100-T403.4 ENLARGED DATA ROOM PLAN - RM B3361A
100-T403.5 ENLARGED DATA ROOM PLAN - RM C3841A
100-T403.6 ENLARGED DATA ROOM PLAN - RM C3747A
100-T403.7 ENLARGED DATA ROOM PLAN - RM C3676A
100-T403.8 ENLARGED DATA ROOM PLAN - RM C3554A
100-TN103i OVERALL THIRD FLOOR INTERSTITIAL PLAN - NEW WORK
100-TN103i.1 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 1
100-TN103i.2 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 2
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 12
100-TN103i.3 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 3
100-TN103i.4 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 4
100-TN103i.5 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 5
100-TN103i.6 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 6
100-TN103i.7 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 7
100-TN103i.8 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 8
100-TN103i.9 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 9
100-TN103i.10 THIRD FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 10
100-TN104 OVERALL FOURTH FLOOR PLAN - NEW WORK
100-TN104.1 FOURTH FLOOR PLAN - NEW WORK - ZONE 1
100-TN104.2 FOURTH FLOOR PLAN - NEW WORK - ZONE 2
100-TN104.3 FOURTH FLOOR PLAN - NEW WORK - ZONE 3
100-TN104.4 FOURTH FLOOR PLAN - NEW WORK - ZONE 4
100-TN104.5 FOURTH FLOOR PLAN - NEW WORK - ZONE 5
100-TN104.6 FOURTH FLOOR PLAN - NEW WORK - ZONE 6
100-TN104.7 FOURTH FLOOR PLAN - NEW WORK - ZONE 7
100-TN104.8 FOURTH FLOOR PLAN - NEW WORK - ZONE 8
100-TN104.9 FOURTH FLOOR PLAN - NEW WORK - ZONE 9
100-TN104.10 FOURTH FLOOR PLAN - NEW WORK - ZONE 10
100-T404.1 ENLARGED DATA ROOM PLAN - RM A4075A
100-T404.2 ENLARGED DATA ROOM PLAN - RM A4144A
100-T404.3 ENLARGED DATA ROOM PLAN - RM B4223A
100-T404.4 ENLARGED DATA ROOM PLAN - RM B4355A
100-T404.5 ENLARGED DATA ROOM PLAN - RM C4967A
100-T404.6 ENLARGED DATA ROOM PLAN - RM C4763A
100-T404.7 ENLARGED DATA ROOM PLAN - RM C4654A
100-T404.8 ENLARGED DATA ROOM PLAN - RM C4483A
100-TN104i OVERALL FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK
100-TN104i.1 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 1
100-TN104i.2 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 2
100-TN104i.3 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 3
100-TN104i.4 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 4
100-TN104i.5 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 5
100-TN104i.6 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 6
100-TN104i.7 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 7
100-TN104i.8 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 8
100-TN104i.9 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 9
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 13
100-TN104i.10 FOURTH FLOOR INTERSTITIAL PLAN - NEW WORK -
ZONE 10
100-TN105 OVERALL FIFTH FLOOR PLAN - NEW WORK
100-TN105.1 FIFTH FLOOR PLAN - NEW WORK - ZONE 1
100-TN105.2 FIFTH FLOOR PLAN - NEW WORK - ZONE 2
100-TN105.3 FIFTH FLOOR PLAN - NEW WORK - ZONE 3
100-TN105.4 FIFTH FLOOR PLAN - NEW WORK - ZONE 4
100-TN105.5 FIFTH FLOOR PLAN - NEW WORK - ZONE 5
100-TN105.6 FIFTH FLOOR PLAN - NEW WORK - ZONE 6
100-T405.1 ENLARGED DATA ROOM PLAN - RM A5031A
100-T405.2 ENLARGED DATA ROOM PLAN - RM A5144A
100-T405.3 ENLARGED DATA ROOM PLAN - RMB5239A
100-T405.4 ENLARGED DATA ROOM PLAN - RM B5378A
100-TN105i OVERALL FIFTH FLOOR INTERSTITIAL PLAN - NEW WORK
100-TN105i.1 FIFTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 1
100-TN105i.2 FIFTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 2
100-TN105i.3 FIFTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 3
100-TN105i.4 FIFTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 4
100-TN105i.5 FIFTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 5
100-TN105i.6 FIFTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 6
100-TN106 OVERALL SIXTH FLOOR PLAN - NEW WORK
100-TN106.1 SIXTH FLOOR PLAN - NEW WORK - ZONE 1
100-TN106.2 SIXTH FLOOR PLAN - NEW WORK - ZONE 2
100-TN106.3 SIXTH FLOOR PLAN - NEW WORK - ZONE 3
100-TN106.4 SIXTH FLOOR PLAN - NEW WORK - ZONE 4
100-TN106.5 SIXTH FLOOR PLAN - NEW WORK - ZONE 5
100-TN106.6 SIXTH FLOOR PLAN - NEW WORK - ZONE 6
100-T406.1 ENLARGED DATA ROOM PLAN - RM A6031A
100-T406.2 ENLARGED DATA ROOM PLAN - RM A6142A
100-TN106i OVERALL SIXTH FLOOR INTERSTITIAL PLAN - NEW WORK
100-TN106i.1 SIXTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 1
100-TN106i.2 SIXTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 2
100-TN106i.3 SIXTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 3
100-TN106i.4 SIXTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 4
100-TN106i.5 SIXTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 5
100-TN106i.6 SIXTH FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 6
100-TN107 OVERALL SEVENTH FLOOR PLAN - NEW WORK
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 14
100-TN107.1 SEVENTH FLOOR PLAN - NEW WORK - ZONE 1
100-TN107.2 SEVENTH FLOOR PLAN - NEW WORK - ZONE 2
100-TN107.5 SEVENTH FLOOR PLAN - NEW WORK - ZONE 5
100-T407.1 ENLARGED DATA ROOM PLAN - RM A7031A
100-T407.2 ENLARGED DATA ROOM PLAN - RM A7142A
100-TN107i OVERALL SEVENTH FLOOR INTERSTITIAL PLAN - NEW
WORK
100-TN107i.1 SEVENTH FLOOR INTERSTITIAL PLAN - NEW WORK -
ZONE 1
100-TN107i.2 SEVENTH FLOOR INTERSTITIAL PLAN - NEW WORK -
ZONE 2
100-TN107i.5 SEVENTH FLOOR INTERSTITIAL PLAN - NEW WORK -
ZONE 5
100-TN108 OVERALL EIGHTH FLOOR PLAN - NEW WORK
100-TN108.1 EIGHTH FLOOR PLAN - NEW WORK - ZONE 1
100-TN108.5 EIGHTH FLOOR PLAN - NEW WORK - ZONE 5
103-TN100.13 LOWER LEVEL PLAN - NEW WORK - ZONE 13
103-TN100i.13 LOWER LEVEL INTERSTITIAL PLAN - NEW WORK - ZONE 13
103-TN101.13 FIRST FLOOR PLAN - NEW WORK - ZONE 13
103-TN101i.13 FIRST FLOOR INTERSTITIAL PLAN - NEW WORK - ZONE 13
T501 DETAILS
T502 DETAILS
T503 DETAILS
T504 DETAILS
T505 DETAILS
T601 SCHEDULES
T602 SCHEDULES
T603 SCHEDULES
T604 SCHEDULES
T605 SCHEDULES
100-T200 TECHNOLOGY ENLARGED PLANS
100-T400 TECHNOLOGY SCHEDULES
100-TF100 OPTICAL FIBER ROUTING PLAN - LOWER LEVEL
100-TF101 TECHNOLOGY PLAN - FIRST FLOOR
100-TF102 TECHNOLOGY PLAN - SECOND FLOOR
100-TF103 TECHNOLOGY PLAN - THIRD FLOOR
100-TF104 TECHNOLOGY PLAN - FOURTH FLOOR
Project: 553-21-701
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 15
100-TF105 TECHNOLOGY PLAN - FIFTH FLOOR
100-TF106 TECHNOLOGY PLAN - SIXTH FLOOR
100-TF107 TECHNOLOGY PLAN - SEVENTH FLOOR
TF500 OPTICAL FIBER BACKBONE RISER DIAGRAMS
- - - END - - -
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for EHRM
Infrastructure Upgrades VA Project No.: 553-21-701 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.
Offices of FFE, Inc, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the
Government without affirmations by Contracting Officer or his duly authorized representative.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items.
B. ALTERNATE NO.1: NA
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at
Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -2
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the
Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
D. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -3 information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting
Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of
Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the
VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -4
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the
Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -5 construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to
Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
All such actions shall be coordinated with the COR or Utility
Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -6
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR and Contractor, as follows:
Contractor furnish to the COR a proposed schedule of work phasing. Phasing of the work shall be limited to specific areas of each floor as to not disrupt hospital operations any more than necessary. (Example: Contractor will not be allowed to close an entire floor or a large area of the hospital at any one time).
J. All buildings will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical
Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -7 routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
K. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C
(40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -8
Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical
Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged-in ceilings, within furred spaces, in unfinished areas, Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -9 or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting
Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -10 opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -11
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by
COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
Project: 553-21-701
11-01-21
GENERAL REQUIREMENTS
01 00 00 -12
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a…