Attachment 1 SOW Updated.docx
DOCX document 25 KB Posted
- Solicitation number
- 36C26020Q0177
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 RFI List 20200826.docx | DOCX document | |
| 36C26020Q0177 0004.docx | DOCX document | |
| Attachment 2 Revised Price Schedule.docx | DOCX document | |
| 36C26020Q0177 0003.docx | DOCX document | |
| Attachment 1 RFI List as of 20200820.docx | DOCX document | |
| Attachment 2 EMR Change.docx | DOCX document | |
| Attachment 1 RFI List-2.docx | DOCX document | |
| Attachment 2 Yurt Grade.png | PNG image | |
| Attachment 3 Sign-in sheet 8-8-2020.pdf | ||
| 36C26020Q0177 0002.docx | DOCX document | |
| 36C26020Q0177 0001.docx | DOCX document | |
| Attachment 1 RFI List.docx | DOCX document | |
| Attachment 4 Drawings As-Builts.pdf | ||
| Attachment 3 Drawings Updated.pdf | ||
| Attachment 2 Specs.pdf | ||
| 36C26020Q0177_3.docx | DOCX document | |
| Attachment 5 Wage Determination.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Reuse CT Trailer for Yurt Area Project: 692-20-115
The contractor will provide all material, labor, equipment, and supervision necessary to complete the below items.
1. Move the CT structure from its current location to the Yurt area. Disconnect the weld plates and utilities from the existing foundation before moving. Saw cutting of sidewalk and minor excavation will be needed to reach the weld plates. See attached Structural As-Builts for locations of lifting lugs.
2. Welding
a. Provide the embeds needed for the footings
b. Weld the CT structure to the new foundation
3. Excavation and compaction of subgrade for the new concrete footings including
a. Excavating a 41’ x 14’ area up to 3’ in depth
b. Compacting the base layer of earth
c. Infilling with ¾” rock and compacting to a depth of 18”
d. Overlaying the compacted rock with 2” of sand
e. Framing and pouring of concrete
4. New Sewer
a. Excavation and installation of a new sewer with 4” PVC to be run back to the new site of the trailer
b. The sewer will require trenching down to a depth of 6’-10’ requiring the use of shoring or trench boxing per OSHA
c. Sewer to have a minimum depth of 3’
d. Sewer will have a run of approximately 175’
5. New water
a. Excavation and installation of new 2” PVC water to be run to the CT trailer
b. Will require removing the old backflow and installing a new one closer to the CT Trailer
c. Water to have a minimum depth of 3’
d. Water will have a run of approximately 600’
Refer to drawings and specifications for additional details.
BASE BID: Items 1, 2, & 3
Work will be completed in 56 calendar days from Notice To Proceed.
OPTION 1: Item 4
Work will be completed in 21 calendar days
OPTION 2: Item 5
Work will be completed in 21 calendar days