This is a Statement of Work (SOW) for the Bureau of Reclamation's Brackish Groundwater National Desalination Research Facility in Alamogordo, New Mexico. The document details urgent services needed for Well No. 2, including video inspection, equipment replacement, and cleaning. The well is producing air and has experienced performance decline, with its 7.5 hp submersible pump originally flowing at 80 gallons per minute but recently reduced to 70-72 gpm. The well is 6 inches in diameter, with the pump located 159 feet below ground surface, and is screened from 90 to 190 feet. The water is brackish, containing approximately 6,000 mg/L total dissolved solids, and the electrical supply is 480VAC/3phase.

The SOW outlines specific work components, including coordinating lock-out of pump systems, removing existing pipe insulation, pulling the pump assembly, disconnecting electrical systems, performing video inspections before and after cleaning, installing chemical cleaning agents, flushing the well, and reinstalling equipment. The contractor must comply with ASTM and AWWA standards, submit a safety plan, project schedule, and product specifications. The work is classified under NAICS code 237110 for Water and Sewer Line and Related Structures Construction. The site visit is tentatively scheduled for November 18, 2025, at 500 Lavelle Road in Alamogordo, with the facility operating from 7:30 AM to 4:30 PM MDT, Monday through Friday.

View the file

Other files

File Type Posted
Sol_140R4025Q0097_Amd_0002.pdf PDF
Sol_140R4025Q0097_Amd_0001.pdf PDF
Sol_140R4025Q0097.pdf PDF
Attachment_2_-_Price_Schedule.docx DOCX document
Attachment_3_-_DB_Act_WD_NM20250008_2_14_2025.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1

STATEMENT OF WORK

Bureau of Reclamation – Upper Colorado Region – Albuquerque Area Office

BRACKISH GROUNDWATER NATIONAL DESALINATION RESEARCH FACILITY

(Well No 2 Equipment Replacement, Cleaning, Video Inspection)

A. FOREWORD, DESCRIPTION, AND PURPOSE

The Bureau of Reclamation, Upper Colorado Region, Albuquerque Area Office, and Brackish Groundwater National Desalination Research Facility has a need for urgent services to inspect and clean existing Well No. 2.

The NAICS codes for this requirement are as follows:

237110 – Water and Sewer Line and Related Structures Construction

Project Description and Purpose. Description of work tasks is to perform a video inspection, replace equipment as necessary, and clean the existing BGNDRF Well No. 2. The well is producing air that is not bleeding off. Previous visits by a local well company have indicated there could be issues with the pump, motor, check valve, or other equipment. Well screen issues could also be present. Expected work needed includes pulling the well pump, injecting cleaning chemical, flushing the well, and performing video inspections before and after the cleaning operations. The pump, motor, check valve, and other appurtenances should be replaced. Well 2 has an estimated diameter of 6-inches and the submersible pump depth should be 159 ft below ground surface (bgs). The well is screened from 90 to 190 ft bgs and static water is around 70 ft bgs. The existing 7.5 hp pump originally flowed at 80 gallons per minute (gpm) but has recently declined to 70-72 gpm with a substantial amount of air. The electrical supply is 480VAC/3phase.

The water is brackish with approximately 6,000 mg/L total dissolved solids.

The well has not been in regular use lately but is expected to be in service more once a treatment building is built. This well is necessary for research operations and needs to be put back into service as soon as possible.

B. ABBREVIATIONS, DEFINITIONS, AND ACRONYMS

The following acronyms apply to specifications Divisions 1 through 52:

AAO Albuquerque Area Office BGNDRF Brackish Groundwater National Desalination Research Facility BOR Bureau of Reclamation CLIN Contract Line Item Number CO Contracting Officer COR Contracting Officer’s Representative.

CS Contract Specialist DOI Department of the Interior FAR Federal Acquisition Regulation GPM Gallon per Minute (gpm)

MDT Mountain Daylight Time OSHA Occupational Safety and Health Administration RSHS Reclamation Safety and Health Standards, 2014 VFD Variable Frequency Drive

C. STANDARDS AND SUBMITTALS

The following standards and generally accepted engineering principles or practices at this time and location shall govern well repairs under this action:

ASTM International (ASTM):

1. ASTM D 5978-96(11) Standard Guide for Maintenance and Rehabilitation of

Groundwater Monitoring Wells

American Water Works Association (AWWA):

1. AWWA Manual M21 Groundwater

Submit the following using English and US Customary Units for review by the Government:

1. Submit Offeror’s safety plan, project scope, and schedule.

2. Submit for each manufacturer the following: shop drawings, product description, operational/owner’s manuals, and specifications for equipment being supplied by the Offeror under this contract.

D. SAFETY AND SITE ACCESS

Contractor shall adhere to the following safety requirements:

1. Contractor shall follow the RSHS and the Service’s facility safety protocols.

The RSHS 2014 Edition is available online at:

http://www.usbr.gov/safety/RSHS/.

2. OSHA Safety and Health Standards for the Construction Industry 29 CFR Part 1926.

Site Visit: (Tentatively Scheduled) Date: Tuesday, November 18, 2025

Time: 10:30 a.m.

Location: 500 Lavelle Road

Alamogordo, New Mexico 88310

Contractor shall adhere to the following site access requirements:

1. Contractor shall follow USBR Cleaning Manual Inspection and Cleaning

Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition available online at:

http://www.usbr.gov/mussels/prevention.

2. Contractor shall use existing established access roads and work within established construction boundaries.

3. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

4. The BGNDRF access will be granted through the existing gate located along the south side of the facility. BGNDRF operational hours are from 7:30 AM MDT to 4:30 PM MDT Monday through Friday, except on federal holidays. Optional hours of operation may be granted by approval from COR. Coordinate access by contacting the facility manager:

Malynda Cappelle, Facility Manager 500 Lavelle Road Alamogordo, New Mexico 88310 Phone No.: (575) 443-6553 Email: mcappelle@usbr.gov

E. WELL REPAIRS

Offeror shall comply with all state and county codes and permits. Offeror is responsible for all permits required to pull and service water well.

Description of work tasks is to perform a video inspection, replace equipment as necessary, and clean the existing BGNDRF Well No. 2. The well is producing air that is not bleeding off.

Previous visits by a local well company have indicated there could be issues with the pump, motor, check valve, or other equipment. Well screen issues could also be present. Expected work needed includes pulling the well pump, injecting cleaning chemical, flushing the well, and performing video inspections before and after the cleaning operations. The pump, motor, check valve, and other appurtenances should be replaced. Well 2 has an estimated diameter of 6-inches and the submersible pump depth should be 159 ft below ground surface (bgs). The well is screened from 90 to 190 ft bgs and static water is around 70 ft bgs. The existing 7.5 hp pump originally flowed at 80 gallons per minute (gpm) but has recently declined to 70-72 gpm with a substantial amount of air. The electrical supply is 480VAC/3phase. The water is brackish with approximately 6,000 mg/L total dissolved solids. Any chemicals used must be compatible with well, pump, and distribution piping at the BGNDRF.

Components of Work. – The following is a short list of the principal work tasks for repairing Well No. 2:

Coordinate Tag-Out/Lock-Out of pump’s energizing systems with facility manager.

Remove existing jacketed pipe insulation and, if possible, store for reuse after repairs are completed on the well.

Pull existing motor and pump assembly for inspection and cleaning. Use existing stainless steel pipe and take caution not to damage existing airline and sound tubing.

Disconnect pump electrical systems.

Obtain video of well and provide written report documenting findings. The video must be viewable on a computer CD/DVD drive.

Install chemical for cleaning and allow to soak per manufacturer suggestions.

Flush well into BGNDRF evaporation ponds. Coordinate this work with BGNDRF staff.

Obtain video of well and provide written report documenting findings. The video must be viewable on a computer CD/DVD drive.

Install new pump, motor, and check valve. Reset well pump assembly using existing airline and sound tubing by lowering into place with new or existing stainless steel pipe.

Record depth of well.

Coordinate Tag-Out/Lock-Out to energize electrical systems to test well pump assembly.

If pump is operating correctly move to insulation step. If pump assembly is not working correctly, diagnose/troubleshoot problem and repair systems until pump is working correctly.

Reinstall jacket pipe insulation if possible. If new insulation is required, install equivalent replacement. Insulation specifications can be provided by the COR.

Clean-up area and leave project site.

F. SUBMITTALS

Submit the following for Government review or approval:

Prepare in English.

Measurement Units: US Customary Units.

Label and file name must include contract number and title including Required

Submittal Number (RSN).

Provide a unique transmittal tracking number for each submittal.

Manufacturer’s certifications shall be signed by an authorized representative.

Review of submittals:

o Time required: The Government will require a minimum of 5 working days to review each submittal or resubmittal, unless otherwise specified.

o Excess Time: Should the Government require additional review time, the CO may extend the contract completion date to allow completion of work. Time extension will be to the extent that the excess review time caused delay to contract completion.

Submit the following for Government approval or review.

o Submittal Types: A – Action requiring Government approval and

I – Informational requires Government written receipt.

o Submit to COR one electronic (eMail) copy for review.

Table A – Submittals

RSN Required Submittal and Description Due Date or Delivery Time Type

S1

Project Schedule shall include the following key milestones:

Proposed date to mobilize.

Proposed date for initial inspection and scope verification Proposed schedule of remaining activities

Within 14 days after contract award A

S2 Report confirming or modification recommended scope after inspection Within 7 days of inspection A

S3 Well 2 pump and motor, check valve, and other product specifications and installation methods

Within 14 Days after contract award. A

RSN Required Submittal and Description Due Date or Delivery Time Type

S4

Well video and corresponding report summarizing findings of initial inspection.

Report can be formal or an emailed description. Within 1 day of video completion I

S5 List and provide Safety Data Sheets (SDS) for any chemicals proposed for cleaning.

Within 14 Days after contract award. A

S6 Report confirming installation details (depth, etc.) of any new equipment or materials Within 7 days of completion I

S7

Well video and corresponding report summarizing findings of initial inspection.

Report can be formal or an emailed description. Within 1 day of video completion I

F. SITE MAP

The following map provides project location, access gate, main complex, and location of Well No. 2 on facility grounds. The facility is accessed on the southwest portion of the map. Well 2 is located on the south side of the main property west of the storage tanks and cooling tower.

Attachment 1 - SOW_ rev1.pdf
Well 2 spec sheet (motor, pump).pdf
WW02 Well Re-Development.PDF

File details come from the government source that posted it. Updated .