Attachment 1 - SOW Renovation of BLDG 10 for CLC at Waco.pdf

PDF 275 KB Posted

Attached to
Renovate BLDG. 10 for CLC | Doris Miller VAMC
Solicitation number
36C25725R0062
Issued by

About this file

This Statement of Work (SOW) details the renovation of Building 10 at the Doris Miller Veterans Medical Center in Waco, Texas. The project involves transforming the existing 53,000 square foot building into a modern, fully accessible multi-story space to consolidate Community Living Center and rehabilitative functions. The anticipated performance period is 360 days from the Notice to Proceed, with the contractor responsible for providing all necessary construction services, materials, and personnel to complete the renovation in compliance with the latest International Building Code.

Key requirements include submitting a comprehensive safety plan, obtaining all necessary permits, providing O&M manuals and As-Built drawings, and coordinating with VA representatives. The contractor must conduct a mandatory site visit prior to bidding, verify all quantities and dimensions, and ensure professional conduct throughout the project. The renovation will require strict adherence to OSHA, VHA, and DOD regulations, with weekly safety inspections by the VA. Contractors must have experience with construction projects between $10-20 million and be certified as a Service-Disabled Veteran-Owned Small Business (SDVOSB) or Veteran-Owned Small Business (VOSB).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

RENOVATION OF BUILDING 10 FOR CLC

PROJECT NO.: 674A4-21-105

PROJECT OVERVIEW

PURPOSE:

The purpose of this project is to renovate the existing Building 10 (53,000 GSF) into a modern and fully accessible multi-story space to consolidate Community Living Center and rehabilitative functions. Included will be other ancillary support spaces as budget allows.

This project will be conducted within the buildings previously mentioned, at Doris Miller Veterans Medical Center at 4800 Memorial Drive, Waco TX 76701.

SCOPE OF WORK

The construction contractor shall provide all necessary construction services, equipment, materials, and personnel as required to adequately construct the project as per the A/E firm’s contract drawings, specifications, technical reports, and cost estimates for the project. All materials and workmanship shall meet or exceed the latest edition of the International Building Code. Upon acceptance of the work by the Government, the Contractor will provide a One (1) year warranty on all materials and workmanship furnished in the installation of the building.

The scope of this project is to renovate the existing Building 10 (53,000 GSF) into a modern and fully accessible multi-story space to consolidate Community Living Center and rehabilitative functions, located at the Doris Miller Veterans Medical Center at 4800 Memorial Drive, Waco TX 76701. Anticipated period of performance is 360 days from issuance of Task Order Notice To Proceed.

A site visit is required prior to bidding, so that the contractor will be fully acquainted with existing site conditions and scope of work.

It is the responsibility of the contractor to verify all quantities, amounts, and dimensions. If there are any discrepancies or any changes in condition affecting work shall be brought to the attention of the VA Contracting Officer Representative before proceeding with the work.

The Contractor shall be responsible for obtaining and coordinating the services of all third-party Contractors performing other services on site and other entities as part of the contract to ensure the expected quality, timely delivery, and documented final product.

The Contractor shall be responsible for generating and providing all O&M Manuals, As Built (redline) drawings in CAD and PDF, obtain all applicable permits, installation, testing, and commissioning as required.

Performance Period: 365 days after issuance of the notice to proceed.

Performance and Payment bonds: Due 10 days after award.

Proof of Insurance: Due 10 days after award.

A. Points of Contact:

1. The Contracting Officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.

2. The Contracting Officer Representative (COR) is responsible for the inspection, technical supervision, and acceptance of the work called for in the contract schedule, including related specifications and contract terms regarding onsite work requirements. Pursuant to the Delegation of Authority

(by separate memo), he or she does not have the authority to make changes to the contract in quantity, dollar amount, or time.

3. Coordinate with VA COR before the start of work. See information below:

B. Government Holidays:

1. The Government hereby provides notice and Contractor hereby acknowledges receipt that Government personnel observe the listed days as holidays:

New Year's Day January 1st

Martin Luther King's Birthday Third Monday in January

Washington’s Birthday Third Monday in February

Memorial Day Last Monday in May

Juneteenth June 19th

Independence Day July 4th

Labor Day First Monday in

September

Columbus Day Second Monday in

October

Veterans Day November 11th

Thanksgiving Day Fourth Thursday in

November

Christmas December 25th

C. In addition to the days designated as holidays, the Government observes the following days:

1. Any other day designated by Federal Statute

2. Any other day designated by Executive Order

3. Any other day designated by the President’s Proclamation

• It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel shall not otherwise be a reason for an additional period of performance, or entitlement of compensation. In the event the Contractor's personnel work during the holiday, they may be reimbursed by the Contractor, however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked.

D. Submit the proper documentation and reports to receive payment on this service. See information below:

1. Invoices and Payment

a) Payment to be made monthly, in arrears, following satisfactory performance by

Contractor’s personnel and upon receipt of a properly prepared invoice.

b) Contractor shall be required to invoice through the Tungsten System at http://www.tungsten-network.com/us/en/veterans-affairs/. Additional information regarding Tungsten shall be provided upon award.

c) The contract shall have current registration in the System for Award Management

(SAM) for this solicitation; URL: www.sam.gov.

d) The invoice MUST be itemized to include the following information. Any information listed below, and not provided on an invoice, will render that invoice incomplete and the invoice will be returned for immediate correction.

i. Time period being invoiced for

ii. Description of services performed.

iii. Unit Cost billed.

iv. Extended amount due.

v. Invoice number, date, and

vi. Contract and obligation numbers.

Other Considerations

• The contractor will be required to submit a safety plan for VA review and approval prior to the performing work.

• It is the contractor’s responsibility to provide adequate documentation verifying that any equipment and/or materials proposed will meet or exceed all federal government requirements.

• Work shall be performed during normal working hours unless otherwise noted by the COR or PM. Working hours are 0700 – 1630, Monday – Friday.

• The contractor’s supervisor shall always be available to address any needs the

VA COR may have during the period of performance. All employees or sub-contractors shall be accountable solely to the Contractor, not the Government.

http://www.tungsten-network.com/us/en/veterans-affairs/ http://www.tungsten-network.com/us/en/veterans-affairs/ http://www.tungsten-network.com/us/en/veterans-affairs/ http://www.tungsten-network.com/us/en/veterans-affairs/ http://www.tungsten-network.com/us/en/veterans-affairs/ http://www.tungsten-network.com/us/en/veterans-affairs/ http://www.sam.gov/ http://www.sam.gov/ http://www.sam.gov/

• The contractor shall be required to coordinate work activities and shutdowns with VA COR and Project Manager.

• The contractor shall thoroughly clean inside and outside of project site daily with contractor’s own equipment, including vacuums, mops, buckets, wash rags, dust mops, etc.

• The Government will not provide facilities or staging area for the Contractor’s use to support this contract. The contractor is responsible for all shipping, receiving, storage and security of any materials or equipment for the duration of this project.

• The Government will provide water and electrical utilities. All utilities in the facility will be available for the Contractor’s use in performance of tasks outlined in this SOW. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.

• Contractor personnel’s conduct shall not reflect discredit upon the

Government. The Contractor shall ensure that personnel present a professional appearance. The Contractor’s employees shall observe and comply with all local policies and procedures concerning fire, safety, environmental protection, sanitation, security, and possession of firearms or other lethal or illegal weapons or substance. The Contractor is responsible for ensuring that any Contractor employees providing services under this contract conduct themselves and perform services in a professional, safe, and responsible manner. The Contractor shall remove from the job site any employee for reasons of misconduct or security. The Contractor shall ensure no contractor employees conduct political related activities or events on VA

Facilities.

• The Contractor shall notify the COR or Government representative of any accidents requiring medical treatment. Emergency medical treatment and services for Contractor personnel is the responsibility of the Contractor.

Codes and Standards

• The project shall be in accordance with the latest Uniform Building Code (UBC), National Fire Protection Associate (NFPA) standard, Uniform Federal Accessibility

Standard (UFAS), Inspectors Manual, VA Specifications and Standards, and local facility requirements. In the event there is a conflict between any of the standards/codes, the more stringent standard/code shall apply.

• The contractor shall provide all applicable safety signage and barricades applicable to

OSHA, VHA and DOD regulations. Contractor shall comply with VHA DIRECTIVE

2004-012 and all VA Center Policy Memorandums, including but not limited to the following:

(a) Protection of patients, visitors, and employees from traumatic injury, as well as occupational and facility–associated infections.

(b) Compliance with OSHA and State construction safety regulations. Construction contracts require that the general contractor’s on-site “competent person” have completed the OSHA 30-hour construction worker course and that all other general and sub-contractor’s workers have completed the OSHA 10-hour construction worker course or other relevant competency training. The determination for training is based on the project hazards and complexity, State and Federal regulations and VA requirements. Verification of completion of training will be required prior to performing work.

(c) Compliance with EPA and State environmental regulations.

SAFETY PLAN REQUIREMENTS

Prior to performing any work, the contractor will be required to submit a safety plan in accordance with OSHA and VA Regulations. The safety plan shall include, but not limited to the following:

A. Safety and Health Policy (i.e. company policy)

B. Safety and Health Objectives (i.e. company goals, procedures, etc.)

C. Job Site Inspections (i.e. safety inspection/potential hazards/prevention, etc.)

D. Contractor Safety Administrator (i.e. competent person/safety officer)

E. Personal Protective Equipment (i.e. head, hearing, and eye protection, footwear, clothing, gloves, etc.)

F. Safety Rules (i.e. rules applicable to the work/task being performed, equipment, ladders, confined spaces, open flame, etc.)

G. Job Safety Training (i.e. OSHA, safety meetings, etc.)

H. 30 Hour OSHA Construction Safety Course – competent person

I. 10 Hour OSHA Construction Safety Course – all others

J. Safety Discipline (i.e. correction of violations, etc.)

K. Hot Work Permit (i.e. responsibilities, procedures, etc.)

L. Emergency Procedures (i.e. responsibilities, procedures, etc.)

M. Written Hazard Communication Program (i.e. responsibilities, procedures, list of hazards, MSDS, etc)

SAFETY INSPECTIONS

On a weekly basis, the VA will conduct a safety inspection of the work area. This inspection includes, but is not limited to the following:

A. Means of Egress

• Fire/Smoke Doors unlocked, free of obstructions.

• Means of Egress (includes Exits) free of obstructions and clearly marked.

B. Fire Alarm, Fire Detection, and Fire Suppression Systems.

• Fire Alarm Pull Stations are unobstructed.

• Smoke Detector smoke caps in use or removed at end of the day.

• Hot Work Permits are current, in use.

• Sprinkler Heads are unobstructed.

C. Housekeeping and Traffic Control

• Trash and debris are removed promptly and transported outside the construction area.

• Floor mats and dust tack mats are located at the entrance to construction area.

• Tools and equipment are properly stored.

• Signs installed to restrict patient access (doors locked as needed)

• Dust control measures are in place.

• Barriers are in place and properly sealed.

D. Hazardous Chemicals/Conditions

• Appropriate storage of hazardous chemicals.

• MSDS sheets are readily available on-site.

• Lock out/tag out procedures are in place.

• Hot work permit is current and posted.

E. Clothing

• PPE is available and properly worn.

• Clothing is relatively dust free with the construction area and patient areas.