Attachment 1 SOW LoneMountainMaterialSourceSite_042926.docx
DOCX document 22 KB Posted
- Attached to
- Lone Mt. Material Site Development & Stockpile, Coronado NF Federal contract opportunity
- Solicitation number
- 127EAX26Q0021
- Issued by
- Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the development and operation of the Lone Mountain Quarry located on the Sierra Vista Ranger District of the Coronado National Forest in Arizona. The contractor must perform rock blasting, excavation, crushing, and stockpiling operations to produce road surfacing aggregate in "G" grading per Federal Highway Project specifications and Forest Service Supplemental Specifications. All work must comply with Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), and the contractor bears full responsibility for obtaining equipment, supplies, labor, and all required permits from the Arizona Department of Environmental Quality. The project site is accessible via NFSR 4768 at coordinates 31.368855°N, 110.401489°W, with no existing water or utility infrastructure available.
The base contract requires clearing and grubbing, topsoil stripping and stockpiling, and crushing and stockpiling of 11,000 cubic yards of surface course aggregate. Four additive bid items are available for an additional 2,200; 1,200; 1,200; and 1,000 cubic yards respectively of the same aggregate material. The total contract performance period is not to exceed 60 days from Notice to Proceed, with a mandatory pre-construction field meeting required within 14 days of award. Contractor deliverables due before Notice to Proceed include a project schedule, blasting operation plan, crushing and stockpiling plan, spill plan, quality control qualifications and plan, and erosion control plan or SWPPP, with a 14-day review period allowed. This solicitation (127EAX26Q0021) is issued as a Request for Quotation for a Total Small Business Set-Aside under NAICS 237310 (Highway, Street, and Bridge Construction) with a $45 million small business size standard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend 0001 127EAX26Q0021.pdf | ||
| RFI Log 127EAX26Q0021 RFI 01-07.docx | DOCX document | |
| Attachment 3 Map LoneMountainMaterialSourceSite_Map.pdf | ||
| Attachment 7 General Decision No. AZ20260055.pdf | ||
| Attachment 4 Table 703-3.pdf | ||
| 127EAX26Q0021 SF1442.pdf | ||
| Attachment 2 SOI LoneMountainMaterialSourceSite_SOI0126.xlsx | XLSX spreadsheet | |
| Attachment 5 FSSS LoneMountainMaterialSourceSite_FSSS.docx | DOCX document | |
| Attachment 6 Fire Plan Guidelines 170515.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LONE MOUNTAIN MATERIAL SOURCE SITE DEVELOPMENT & STOCKPILING
Coronado National Forest, Sierra Vista Ranger District Statement of Work 03/19/2026
Scope of Work The scope of this project is to develop the Lone Mountain Quarry for road surfacing aggregate production. Lone Mountain Quarry is located on previously undisturbed land within on the Sierra Vista Ranger District of the Coronado National Forest. Work consists of rock blasting and excavating, rock crushing and stockpiling. All work must comply with the Standard Specifications For Construction of Roads and Bridges on Federal Highway Projects (FP-14) and Forest Service Supplemental Specifications (FSSS). The surface course aggregate gradation to be produced is the “G” grading shown in Table 703-3 (See FSSS). The contractor is responsible for providing all equipment, supplies, labor, and incidentals to perform the work described herein. The contractor shall be responsible to obtain all permits as required by Arizona Department of Environmental Quality for the contractor’s operation methods. There is no water or any other utilities within the quarry boundary.
Bid Items (SOI) Base bid items:
1) Clearing and grubbing of area needed for the bid aggregate quantity
2) Topsoil stripping and stockpiling of area needed for the bid aggregate quantity
3) Crush and stockpile 11,000 CY of surface course aggregate (“G” grading) Additive bid items:
1) Crush and stockpile an additional 2,200 CY of surface course aggregate (“G” grading)
2) Crush and stockpile an additional 1,200 CY of surface course aggregate (“G” grading)
3) Crush and stockpile an additional 1,200 CY of surface course aggregate (“G” grading)
4) Crush and stockpile an additional 1,000 CY of surface course aggregate (“G” grading)
Travel From Tucson, AZ take Interstate 10 E 23 miles to AZ-83 S (Sonoita Mountain View Highway) towards Sonoita/Patagonia. Travel south for 53 miles. Turn left onto W Coronado Trail proceed for 5.3 miles. Turn right onto W Lochiel Road for 0.1 mile then slight left onto Lone Mountain Ranch Road proceed 0.1 miles. Turn right onto NFSR 4768 and travel south for 0.6 miles, entrance to the newly constructed quarry access road is on the west side of the road. The coordinates of the intersection of NFSR 4768 and the quarry access road is Latitude: 31.368855° Longitude: -110.401489° (See Map).
Deliverables/Schedule Total contact time from Notice to Proceed to completion shall be no more than 60 days A pre-construction meeting in the field is required within 14 days of contract award. Notice to Proceed for construction operations will be given once all required deliverables are received. Allow 14 days for the review of deliverables, bringing these items to the pre-construction meeting will help in expediting the Notice to Proceed. Deliverables include, but are not limited to the following:
· Project Schedule
· Blasting operation plan
· Crushing and stockpiling plan
· Spill Plan
· Quality control qualifications and plan
· Erosion control plan or SWPPP