This Statement of Work (SOW) details the Bay Furnace Campground Repaving Project for the USDA Forest Service in Munising, Michigan. The project involves full depth reclamation (FDR) and repaving approximately 130,000 square feet of asphalt at the Hiawatha National Forest's Bay Furnace Campground, including parking lots and roadways. Key requirements include installing two 1.5" lifts of Type II asphalt concrete, preparing existing gravel parking spurs, adding base aggregate, applying tack coat, and painting parking area markings in white and blue.
The project is scheduled to commence after Labor Day 2026, with work limited to weekday hours between 8:00 am and 5:00 pm. The Contracting Officer Representative is Greg Gardner, and the contractor must provide a project schedule within 4 weeks of award, comply with all safety requirements, minimize construction impacts, and ensure quality control. Final payment will be contingent upon submission of certified payroll and a contract release form, with a thorough final inspection requiring complete site cleanup and restoration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BAY FURNACE CAMPGROUND REPAVING PROJECT
HIAWATHA NATIONAL FOREST
MUNISING RANGER DISTRICT
ALGER COUNTY, MI
1.0 PROJECT INTRODUCTION
Project Name: Bay Furnace Campground Repaving Project
1.1 Scope
In accordance with the terms and conditions of the Contract, the Contractor shall perform the work of this Statement of Work (SOW) for the USDA-Forest Service (FS) as described below.
The Contractor shall perform inspection, and construction services in accordance with the requirements within the contract. The Contractor shall provide all equipment, labor, supervision, transportation, materials, tools and other incidentals and execute all work necessary to perform the full depth reclamation (FDR) and install two 1.5” lifts of Type II concrete of the Bay Furnace Campground Road. The contractor shall also prepare the existing gravel parking spurs for asphalt and then apply two 1.5” lifts of Type II concrete in accordance with specification and exhibits in this contract, and current industry standards. Contractor is responsible for ensuring all equipment meets State, Federal, and Local Laws.
The Contractor shall perform all services necessary to produce a complete and usable project in accordance with the project goals and design intent stated herein.
1.2 Location
The project is located at the Hiawatha National Forest Munising District Bay Furnace Campground at Bay Furnace Rd, M-28, Munising, MI 49862. From the Munising District Office turn left onto E. Munising Ave., at the traffic circle take the 1st exit onto M-28 W, travel 5.1 miles along M-28 W and turn right onto Bay Furnace Road. Coordinates:46.438315, -86.708335
1.3 Contact Information
Contracting Officer Representative (COR): Greg Gardner, Phone: 906-280-4132. E-mail:
Gregory.gardner1@usda.gov
2.0 GENERAL REQUIREMENTS
2.1 Scope of Work Summary
The project will consist of improving the parking lots and roadway at the campground based on the attached drawings set. The work covered by these plans shall conform to the FP-14 Standard Specifications for Construction Roads and Bridge on Federal Highway Projects and the Forest Service Supplemental Specifications. The project will include these major tasks, but not be limited to, the construction of the following major items of work:
1. Mobilize for the project.
2. Install temporary traffic control signs before starting construction. See Section 635 – Temporary Traffic Control. This shall be maintained for the duration of the project.
Signage shall comply with Manual on Uniform Traffic Control Devices (MUTCD).
3. Complete FDR of the entire paved area. See Section 306 – Full Depth Reclamation with Asphalt.
4. Add base aggregate for FDR as needed to meet FP-14 Section 306 Full Depth Reclamation.
Also add base aggregate to parking spurs to meet 6-inch minimum gravel depth. See Section 703.05 Subbase, Base, and Surface Course Aggregate.
5. After the FDR and parking spur preparation is complete, clean the existing surface of loose material, dirt, and other materials. Apply tack coat to the cleaned surface. See Section 412
- Asphalt Tack Coat.
6. Apply two 1.5” compacted thickness lifts of Type II asphalt concrete. The mix shall be placed according to Section 403 – Asphalt Concrete.
7. All bituminous mixtures shall be transported by a truck which shall have tight, clean, smooth metal beds. Each truck shall be covered with a canvas or other suitable material of such size that will protect the mixture from the weather. See Section 401.11- Hauling.
8. Bituminous materials shall be placed, finished, and compacted according to Section 403 Asphalt Concrete. See Section 401.07- Weather Limitations.
9. Seal joints at the interface between the new asphalt the existing drainage structures, sidewalks, and pavement. See Section 414- Asphalt Pavement Crack Sealing and Filling.
10. Day Use Area and Overflow parking lots shall be painted according to attached drawing set.
• Painting shall be performed only when pavement surface is dry and clean, when the outside temperature is above 40 degrees F, and when the weather is not excessively windy, dusty, or foggy.
• The mechanical equipment shall be an approved atomizing spray-type marking machine, suitable for application of traffic paint. Shall produce an even and uniform film thickness for required coverage.
• Paint shall meet TT-P-1952D for water based paint.
• Film thickness shall be no less than 3 mills.
• Application rate would be 100 to 105 square feet per gallon of paint.
• Use contractor grade acrylic, striping paint, four (4) inch width, Sherwin
Williams Setfast Acrylic Modified Alkyd Traffic Marking Paint or approved equivalent.
• Follow Manufacturer’s recommendation for applying paint.
• Paint Color:
• White paint shall be used for parking stall markers, directional arrows, and no parking zone hatching.
• Blue paint shall be used for handicap parking designation markers.
11. On all disturbed areas, spread approved seed mix. See Section 625- Turf Establishment.
Verification of Dimensions The contractor shall be responsible for the conditions and proper relation of their work to the site conditions and will familiarize themselves with all details of the work and working conditions. The contractor shall verify all dimensions in the field and generate their own quantities for work provided. Any and all incidental items not specifically listed in this contract are to be included by the contractor, to provide the government a complete and usable end product.
2.2 Project Meetings
2.2.1 Pre-Construction Meeting
The COR shall setup a pre-construction meeting with the contractor after award. Payrolls and other construction administration documentation shall be required to be prepared by the Contractor and submitted to the COR.
2.3 Contractor’s Project Schedule
General: The Contractor shall provide a Project schedule for the entire contract period within 4 weeks after award. Work will only be performed after Labor Day, 9/7/2026.
2.4 Submittals
2.4.1 Submittal Register
Submittals for this contract shall be emailed to the COR.
Manufacturer’s recommended installation procedures and Manufacturer’s Industry Standard shall be the basis of how products and materials are installed in addition to accessibility codes.
The contractor will provide the manufacturer’s recommended installation instruction or manual for each submittal and process.
2.4.2 Submittals Distribution and Format
B. Construction Submittals:
1. All construction submittals shall be e-mailed to the COR. Other formats may be approved by the COR.
2.4.3 Submittal Procedures
The COR shall have 10 days to review and return submittals to the Contractor.
The CO/COR oversight is for quality assurance only and compliance with contract requirements. The Contractor is fully responsible and liable for construction applications, technical considerations, and use of products for the intended application.
3.0 GENERAL REQUIREMENTS BY WORK ITEM
3.1 Asphalt Replacement
FDR and overlay approximately 130,000 square feet of asphalt as shown on the attached plans.
Contractor shall ensure FDR grade drains to the drainage ditch. Ensure that the final base is sufficient in compaction and quality to support delivery traffic. Slope to drain and provide a smooth transition between the parking lot and driveway.
4.0 SPECIFIC CONSTRUCTION REQUIREMENTS
4.1 Safety
The Contractor shall comply with all Federal and State safety requirements for the type of work to be performed. Refer to the Occupation Safety and Health Standards (OSHA) for details of these and other safety requirements.
4.2 Closure of Site
The site will remain closed for the duration of the construction.
Upon commencement of work, it shall be the contractor’s responsible to supply and maintain traffic control devices during the duration of work and all associated dry times. Signage shall be in compliance with FP-14 Section 635 – Temporary Traffic Control and MUTCD.
4.3 Advertisement/Company Logo
The Contractor shall not place any form of advertisement or company logo, in any form, on the pavement or anywhere on Federal Lands.
4.4 Project Limits along Roadways
The limits of work along Federal, State, County, or Local roads include all pavement “drive apron” or deceleration/ acceleration lanes associated with that road or site.
4.5 Construction specifications (FP-14)
The Forest Service, US Department of Agriculture has adopted the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14, U.S. Customary Units (FP-14) for construction of National Forest System Roads and other projects.
The full provisions of FP-14 shall apply as applicable on this contract, unless modified by the Forest Service Supplemental Specifications, attached.
5.0 ADDITIONAL REQUIREMENTS
5.1 Temporary Facilities
The contractor shall provide bathroom facilities (i.e port-a-potty).
5.2 Work Hour Restrictions
All work and deliveries shall be limited to the weekday hours of 8:00 am to 5:00 pm unless otherwise approved by the COR. No work shall occur on Federal holidays or weekends without prior approval.
5.3 Quality Control
The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings. Failure to provide adequate quality control will result in retention and other contract actions.
5.4 Hazard Control
Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.
5.4.1 Smoking
Smoking is allowed on Forest Service land, but cigarette butts shall not be discarded on the ground.
5.5 Minimizing Construction Impacts
The Contractor shall take all precautions necessary to minimize and restore all construction impacts. All existing work and conditions impacted or modified by the contractor shall be replaced with like kind at the contractor’s expense.
5.6 Project Closeout
Payment:
The quantities shall be paid for as lump sum quantities or by other methods of measure as listed in the SCHEDULE OF ITEMS. Such payment shall be considered full compensation for constructing the complete project in accordance with the plans and specifications. The availability of progress payments shall be determined by the CO. The invoice must be inputted into the IPP System.
Additional Documents required to be prior to final invoice processing are:
Certified Payroll Contract Release Form
Final payment will not be processed until all documents have been received by the CO/
COR.
5.7 Final Inspection
Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Pick up and remove all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.
| 1.0 PROJECT INTRODUCTION |
| 1.1 Scope |
| 1.2 Location |
| The project is located at the Hiawatha National Forest Munising District Bay Furnace Campground at Bay Furnace Rd, M-28, Munising, MI 49862. From the Munising District Office turn left onto E. Munising Ave., at the traffic circle take the 1st exit ont... |
| 1.3 Contact Information |
| 2.0 GENERAL REQUIREMENTS |
| Verification of Dimensions |
| 2.2 Project Meetings |
| 2.3 Contractor’s Project Schedule |
| 2.4 Submittals |
| 2.4.2 Submittals Distribution and Format |
| 2.4.3 Submittal Procedures |
| 3.0 GENERAL REQUIREMENTS BY WORK ITEM |
| 4.0 SPECIFIC CONSTRUCTION REQUIREMENTS |
| 4.2 Closure of Site |
| 4.3 Advertisement/Company Logo |
| 4.4 Project Limits along Roadways |
| 4.5 Construction specifications (FP-14) |
| 5.0 ADDITIONAL REQUIREMENTS |
| 5.2 Work Hour Restrictions |
| 5.3 Quality Control |
| 5.4 Hazard Control |
| 5.4.1 Smoking |
| 5.5 Minimizing Construction Impacts |
| 5.6 Project Closeout |
| 5.7 Final Inspection |