Attachment 1 - Scope of Work.pdf

PDF 1 MB Posted

Attached to
Flat roof waterproofing and insulation replacement in a U. S Government Property located in Boulogne-Billancourt
Solicitation number
19FR6325Q0041
Issued by

About this file

This Statement of Work (SOW) details a flat roof waterproofing and insulation replacement project for Building 1 at the Embassy of the United States of America in Boulogne-Billancourt, Paris. The project involves completely removing the existing failed waterproofing membrane and underlying insulation, and installing a new high-performance waterproofing system and thermal insulation that meets French building regulations (RT 2020). Key requirements include using a waterproofing membrane with a specified lifespan, achieving enhanced energy efficiency, ensuring proper detailing at roof penetrations and facades, and minimizing disruption to building occupants through the use of a temporary external lift for material and worker access. The contractor must be a reputable roofing specialist with Qualibat qualification 32 ETANCHEITE, provide qualified personnel, and comply with French health and safety regulations throughout the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

UNCLASSIFIED

STATEMENT OF WORK FOR

Flat roof waterproofing and insulation replacement

Location:

Building 1

Boulogne-Billancourt

Client:

Embassy of the United States of America in Paris

SENSITIVE BUT UNCLASSIFIED

Statement of Work (SOW)

1. ADMINISTRATIVE

1.1. PROJECT OVERVIEW:

1.2. PROJECT OBJECTIVES:

1.3. RESPONSABILITIES & CONTRACTOR DUE DILIGENCE

3. SCOPE OF WORKS:

3.1 PREPARATORY WORKS:

3.2 REMOVAL AND DISPOSAL:

3.3 INSTALLATION OF NEW THERMAL INSULATION:

3.4 INSTALLATION OF NEW WATERPROOFING SYSTEM:

3.5 ROOF PENETRATIONS AND UPSTANDS:

3.6 TEMPORARY EXTERNAL LIFT FOR ROOF ACCESS:

3.7 SAFETY WORKS:

3.8 QUALITY CONTROL AND INSPECTIONS:

3.9 WASTE MANAGEMENT:

3.10 HEALTH AND SAFETY:

3.11 PROJECT COMPLETION AND HANDOVER:

4. CONTRACTOR REQUIREMENTS:

SENSITIVE BUT UNCLASSIFIED

1. ADMINISTRATIVE

1.1. PROJECT OVERVIEW:

This scope of works outlines the requirements for the complete replacement of the exis�ng waterproofing membrane and thermal insula�on on the flat roof of apartment building 01, located in Boulogne- Billancourt.

The three exis�ng buildings on the site were originally built in the mid-1950s, and with some par�al renova�ons of the roofs having already been carried out, the condi�on of the exis�ng roof finish has now reached a state in which it needs overhaul. The exis�ng area of each roo�op is approximately 645 sq.m., which a plant room of approximately 90sq.m.

The project involves the concep�on, removal of the exis�ng and replacement of the roof’s waterproofing and thermal complex up to and including the exis�ng perimeter where it meets the building facades.

A key requirement is also the provision and u�liza�on of a temporary external li� for material and worker access to the roof, to minimize disrup�on to building occupants and reducing internal access to a minimum, and if possible zero access to the interior.

SENSITIVE BUT UNCLASSIFIED

An inves�ga�on of the exis�ng roof complex make-up was carried out in April 2025, from which the following photos were taken:

Photo of existing plant room roof access ladder, ducting and plant room finishes

1.2. PROJECT OBJECTIVES:

To completely remove the exis�ng failed waterproofing membrane and underlying insula�on.

To install a new, high-performance waterproofing system with a specified lifespan.

To install new thermal insula�on under the new waterproofing system that meets or exceeds current French building regula�ons, which include the RT 2020 or equivalent and provides enhanced energy efficiency.

To ensure proper detailing and waterproofing at all roof penetra�ons, upstands, and where the roof meets the building facades.

To provide a durable and weather-�ght roof structure that protects the building from water ingress and improves thermal comfort for residents.

To minimize disrup�on to building occupants during the execu�on of the works, via a temporary external li�, avoiding internal building access.

To ensure all works are carried out in accordance with relevant French building codes, regula�ons, and best prac�ces.

1.3. RESPONSABILITIES & CONTRACTOR DUE DILIGENCE

Due to the specific needs and unique nature of the roof works, the contractor is responsible for establishing a health and safety plan, which shall be coordinated with the following:

• Embassy representa�ve,

• COR,

• Security services, The property will be occupied during the works and the contractor shall take all necessary measures to avoid disturbances and nuisances to occupants.

The working hours should be from 8:00 to 12:00 and from 13:00 to 17:00 Monday to Friday. The persons carrying out the work shall be always accompanied by an “escort”, who will be provided by the Embassy.

During American and French holidays, the property will be closed. All access and deliveries shall be coordinated around these periods, and any special access request must be requested via the COR representa�ve. This request will not necessarily obtain authoriza�on.

All work shall be performed in accordance with:

I. The safety requirements of the EM-385-1-1 htp://www.publica�ons.usace.army.mil/Portals/76/Publica�ons/EngineerManuals/EM_385-1-1.pdf;

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

II. The safety requirements within the Occupa�onal Safety and Health Standards htps://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_toc_level=1&p_part_numb er=1910;

III. Local French occupa�onal safety and health requirement laws and regula�ons.

IV. When there is a difference with the minimum requirements the more stringent requirement shall be followed.

The Contractor will submit, prior to any work, a detailed schedule and execu�on plans for COR’s approval.

The Contractor shall also submit for COR approval all manufacturer’s data.

https://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_toc_level=1&p_part_number=1910 https://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_toc_level=1&p_part_number=1910

SENSITIVE BUT UNCLASSIFIED

3. SCOPE OF WORKS:

3.1 PREPARATORY WORKS:

Site Survey and Condi�on Assessment:

The contractor shall provide a detailed survey of the exis�ng roof area, including measurements, iden�fica�on of exis�ng penetra�ons (vents, pipes, etc.), and assessment of the condi�on of the exis�ng waterproofing, insula�on, and substrate.

• Photographic documenta�on of the exis�ng roof condi�on.

• Iden�fica�on of any poten�al hazards or access restric�ons.

Vehicle and traffic management Plan:

To access the site, the contractor shall provide with the submission a traffic management plan for the delivery and removal of materials, including the posi�oning and opera�on of the temporary external li�.

The contractor shall coordinate with local authori�es regarding any necessary permits or no�fica�ons for traffic management.

A circula�on plan shall be provided and agreed with the COR

Building 1 Site access

SENSITIVE BUT UNCLASSIFIED

Protec�on of Adjacent Areas:

The contractor shall provide all measures to protect surrounding areas, including landscaping, walkways, trees and plan�ng, landscaped areas and parked vehicles, from damage during the works.

Resident Communica�on:

The Contractor shall work with the Client to develop and implement a plan to inform staff residents about the project �meline, poten�al disrup�ons, and safety measures.

3.2 REMOVAL AND DISPOSAL:

Safe Removal of Exis�ng Waterproofing:

Careful and safe removal of the exis�ng waterproofing membrane, ensuring no damage to the underlying substrate.

Proper handling and disposal of all removed materials in accordance with local regula�ons and best environmental prac�ces.

Safe Removal of Exis�ng Insula�on:

Removal of the exis�ng roof insula�on down to the structural deck (concrete screed).

Inspec�on of the structural deck for any signs of damage or deteriora�on. Any necessary repairs to the structural deck will be addressed under a separate instruc�on and varia�on order if not already iden�fied.

Proper handling and disposal of all removed insula�on materials in accordance with local regula�ons and environmental best prac�ces.

Cleaning of the Substrate:

Thorough cleaning of the exposed roof substrate to ensure a clean and sound surface for the installa�on of the new insula�on and waterproofing.

The building’s roof area is approximately 645 sq.m. of which 90sq.m is plant area.

SENSITIVE BUT UNCLASSIFIED

3.3 INSTALLATION OF NEW THERMAL INSULATION:

Supply and Installa�on of New Insula�on:

Supply and install new thermal insula�on boards of a specified type and thickness to achieve the required thermal performance.

Thermal Proper�es: The new insula�on shall have a minimum thermal resistance R ≥ 5 of and a maximum thermal conduc�vity of 0.20 W/m².K. The specific type and thickness of insula�on will be subject to Client approval based on calcula�ons demonstra�ng compliance with current French building regula�ons, RT 2020 and project energy efficiency goals. Op�ons to be considered with relevant thermal proper�es, and proposed to COR.

Installa�on shall be carried out in accordance with the manufacturer's instruc�ons and relevant best prac�ces, ensuring a con�nuous layer of insula�on with minimal thermal bridges.

3.4 INSTALLATION OF NEW WATERPROOFING SYSTEM:

Supply and Installa�on of New Waterproofing Membrane:

Supply and installa�on of a new, high-performance flat roof waterproofing system. The specific type of membrane, TPO and bituminous membrane and system build-up will be subject to Client approval based on factors such as durability, lifespan, cost-effec�veness, and compa�bility with the insula�on.

Installa�on shall be carried out by cer�fied installers in strict accordance with the manufacturer's instruc�ons and relevant industry standards.

This includes proper detailing at all laps, seams, penetra�ons (vents, pipes, ducts.), upstands, and termina�on points.

Installa�on of Drainage System Components:

Inspec�on and cleaning of exis�ng roof drains.

Replacement of any damaged or inadequate drainage components (drain outlets, leaf guards) as required and agreed with the Client.

Ensuring proper integra�on of the drainage system with the new waterproofing membrane.

Perimeter Detailing at Facades:

Careful detailing where the new waterproofing system meets the building facades. This shall include:

Ensuring a water�ght seal between the roof membrane and the facades of the roof plant rooms.

Considera�on of appropriate upstands and termina�on methods to prevent water ingress into the building structure.

SENSITIVE BUT UNCLASSIFIED

Coordina�on with the facade materials and construc�on details to ensure compa�bility and a durable finish.

Within the requirements of the DTU and updated renova�on methods, retain the aspect and detailing of the exis�ng roof to address each point of contact with walls, facades, steps, duc�ng, drainage points, cabling and safety atachments, (see annex 01 exis�ng roof details and roof plan).

Installa�on of Protec�on Layers:

Installa�on of any necessary protec�on layers gravel ballast, specified for the chosen waterproofing system.

3.5 ROOF PENETRATIONS AND UPSTANDS:

Waterproofing of Penetra�ons:

Proper waterproofing around all exis�ng and any new roof penetra�ons (exhaust vents, HVAC extrac�on and intake pipes, skylights, upstands) using appropriate collars, sleeves, or other approved methods to ensure a water�ght seal.

Treatment of Upstands:

Ensuring adequate height and proper waterproofing of all upstands around parapet walls, equipment bases, and other ver�cal elements on the roof.

3.6 TEMPORARY EXTERNAL LIFT FOR ROOF ACCESS:

Provision and Installa�on of Temporary External Li�:

The Contractor shall be responsible for the supply, installa�on, and safe opera�on of a temporary external li� capable of transpor�ng materials and personnel to and from the roof level.

The li� shall have sufficient capacity to handle the largest and heaviest materials required for the project, and respect all security requirements & fire-safety cer�fica�on and

The loca�on of the li� shall be agreed upon with the Client, taking into considera�on site access, ground condi�ons, and minimizing disrup�on to residents and pedestrian traffic.

All necessary permits and approvals for the installa�on and opera�on of the li� shall be obtained by the Contractor.

Safe Opera�on and Maintenance of the Li�:

The Contractor shall ensure the safe opera�on and regular maintenance of the temporary external li� in accordance with relevant safety regula�ons and manufacturer's guidelines.

Only trained and authorized personnel shall be permited to operate the li�.

Appropriate safety barriers and signage shall be installed around the li� at ground level to prevent unauthorized access.

Removal of Temporary External Li�:

Upon comple�on of the roof works, the Contractor shall be responsible for the safe dismantling and removal of the temporary external li� and the reinstatement of any affected areas.

3.7 SAFETY WORKS:

Note: Weighted handrails are for collec�ve protec�on on exis�ng structures where permanent fixed handrails are not technically possible and do not meet the requirements of Ar�cle R 4323-66 of the French Labor Code (“Code du travail - Article R4323-66”) as they must be dismantled for waterproofing work. They are not suitable for new installa�ons or roof waterproofing refurbishments. Please make provision for this during and a�er the installa�on to ensure all safety codes are respected.

Removal of Exis�ng Handrails:

Removal of exis�ng handrails ("garde-corps") which are located at the perimeter of the building. These handrails are weighted.

Removal of Exis�ng Caged Ladder:

Removal of exis�ng caged ladder ("échelle à crénoline").

Installa�on of New Handrails ("garde-corps"):

Installa�on of new handrails for compliance with NF E85-015 standard of July 2019 - VECTACO sabot D type, or similar.

Installa�on of New Caged Ladder:

Installa�on of a compliant caged ladder ("échelle à crénoline"), in the same loca�on as the exis�ng ladder.

SENSITIVE BUT UNCLASSIFIED

3.8 QUALITY CONTROL AND INSPECTIONS:

Regular Inspec�ons:

The Contractor shall conduct regular internal quality control checks throughout the project.

Client Inspec�ons:

The Client or their appointed representa�ve shall have the right to inspect the works at various construc�on stages, including:

• Upon comple�on of the removal of exis�ng materials.

• Upon comple�on of the installa�on of the new insula�on.

• Upon comple�on of the installa�on of the waterproofing membrane (prior to any overlaying protec�on layers).

• Upon comple�on of all works.

Water Tes�ng:

Depending on the chosen waterproofing system, flood tes�ng or other appropriate water tes�ng methods shall be required to verify the integrity of the installed membrane.

3.9 WASTE MANAGEMENT:

Responsible Waste Disposal:

The Contractor shall be responsible for the proper segrega�on, storage, and disposal of all waste materials generated during the project in accordance with local regula�ons and environmental best prac�ces.

Provision of appropriate skips and containers for waste collec�on.

Documenta�on of waste disposal methods and quan��es may be required.

3.10 HEALTH AND SAFETY:

Compliance with Safety Regula�ons:

The Contractor shall be fully responsible for ensuring that all works are carried out in a safe manner and in compliance with all relevant French health and safety regula�ons. As stated earlier, Provision and use of appropriate personal protec�ve equipment (PPE) for all workers.

Implementa�on of safe working prac�ces for working at height, handling materials, and opera�ng equipment, including the temporary external li�.

Provision of necessary safety signage and barriers.

Development and implementa�on of a site-specific health and safety plan.

SENSITIVE BUT UNCLASSIFIED

3.11 PROJECT COMPLETION AND HANDOVER:

Final Inspec�on:

A joint final inspec�on of the completed roof works shall be carried out by the Contractor and the Client or their representa�ve.

Snagging List:

o Any defects or incomplete items iden�fied during the final inspec�on shall be documented in a snagging list and rec�fied by the Contractor in a �mely manner.

Handover Documenta�on:

The Contractor shall provide the Client with the following handover documenta�on:

Manufacturer's warran�es for the new waterproofing membrane and insula�on.

Installa�on cer�ficates for the waterproofing system.

Test results (if applicable).

As-built drawings showing the layout of the new waterproofing and insula�on.

Opera�on and maintenance manual for the new roof system (if applicable).

Documenta�on related to the temporary external li� (inspec�on records, etc.).

Waste disposal records.

4. CONTRACTOR REQUIREMENTS:

The Contractor shall be a reputable and experienced roofing contractor with a proven track record in similar flat roof replacement projects, par�cularly in urban environments.

The Contractor shall possess all necessary licenses, permits, and insurance coverage to carry out the works in Boulogne-Billancourt including Qualibat qualifica�on 32 ETANCHEITE.

The Contractor shall provide qualified and experienced personnel for all aspects of the project.

The Contractor shall be commited to minimizing disrup�on to building occupants and maintaining a clean and safe working environment.

SENSITIVE BUT UNCLASSIFIED

5. CLIENT RESPONSIBILITIES:

Provide the Contractor with access to the building and roof area for inspec�on before the site works are to begin.

Facilitate communica�on with building residents regarding the project.

Review and approve material samples and specifica�ons.

Carry out inspec�ons at agreed stages of the works within the planning of the works.

Provide �mely payment in accordance with the agreed contract terms.

6. TIMELINE:

A detailed project �meline, including start and comple�on dates, will be agreed upon between the Client and the Contractor prior to the commencement of works.

***END OF STATEMENT OF WORK***

1. ADMINISTRATIVE
1.1. Project Overview:
1.2. Project Objectives:
1.3. RESPONSABILITIES & CONTRACTOR due diligence
3. Scope of Works:
3.1 Preparatory Works:
Site Survey and Condition Assessment:
Vehicle and traffic management Plan:
Protection of Adjacent Areas:
Resident Communication:
3.2 Removal and Disposal:
Safe Removal of Existing Waterproofing:
Safe Removal of Existing Insulation:
Cleaning of the Substrate:
3.3 Installation of New Thermal Insulation:
Supply and Installation of New Insulation:
3.4 Installation of New Waterproofing System:
Supply and Installation of New Waterproofing Membrane:
Installation of Drainage System Components:
Perimeter Detailing at Facades:
Installation of Protection Layers:
3.5 Roof Penetrations and Upstands:
Waterproofing of Penetrations:
Treatment of Upstands:
3.6 Temporary External Lift for Roof Access:
Provision and Installation of Temporary External Lift:
Safe Operation and Maintenance of the Lift:
Removal of Temporary External Lift:
3.7 Safety Works:
Removal of Existing Handrails:
Removal of Existing Caged Ladder:
Installation of New Handrails ("garde-corps"):
Installation of New Caged Ladder:
3.8 Quality Control and Inspections:
Regular Inspections:
Client Inspections:
Water Testing:
3.9 Waste Management:
Responsible Waste Disposal:
3.10 Health and Safety:
Compliance with Safety Regulations:
3.11 Project Completion and Handover:
Final Inspection:
Snagging List:
Handover Documentation:

4. Contractor Requirements: