Attachment 1 RFP SOW Pier and Pavilion Repair.pdf
PDF 1 MB Posted
- Attached to
- Consolidated Lake Piers Projects
- Solicitation number
- FA481922R0024
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4819-22-R0024
29 Mar 22
REQUEST FOR PROPOSAL
For
PQM Lake, Felix Lake and Horseshoe Lake
Pier and Pavilion Repairs
TYNDALL AFB FLORIDA
Project Numbers: XLWU 22-8115
XLWU 22-8116
XLWU 22-8118
29 Mar 2022
Contents
1.0 SCOPE
1.1 GENERAL REQUIREMENTS
2.0 APPLICABLE DOCUMENTS
3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION,
EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)
4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
4.0 A TABLE 1 - TABLE OF DELIVERABLES
4.1 WORK BREAKDOWN STRUCTURE (WBS)
4.2 SCHEDULE AND PLANNING REQUIREMENTS
4.2.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)
4.2.2 Integrated Master Schedule (IMS)
4.2.2.1 CONTRACT PROGRESS SCHEDULE (AF 3064)
4.3 STATUS REPORTING
4.3.1 Reporting Requirements for Firm Fixed Price (FFP)
4.4 MEETING AND CONFERENCE REQUIREMENTS
4.4.1 Meeting/Teleconference Support
4.4.2 Red Zone Meeting
4.4.3 Senior Advisory Group (SAG) and Senior Executive Review Group (SERG)
4.5 CONTRACTOR DOCUMENTATION
4.6 NOTIFICATION REQUIREMENTS
4.7 PERMITS
4.8 PHOTO DOCUMENTATION
4.10 SITE ACCESS BADGES
4.11 WORKSITE ACTIVITIES AND COORDINATION
4.11.1 Coordination of Activities
4.11.2 Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting
4.11.3 Recording and Preserving Historical and Archaeological Finds
4.12 PROJECT DATA/PROJECT DELIVERABLES
4.12.1 Protecting Unclassified DoD Data
4.12.2 Security Breach Notification
4.12.3 Data Collaboration Site
4.13 HEALTH AND SAFETY PLAN (HSP) OR (APP)
4.14 QUALITY SYSTEM PLAN (QSP)
4.15 TECHNICAL PLANS AND REPORTS
4.15.1 Construction Work Plan
4.15.2 Technical Reports
4.15.3 Environmental Protection Plan (EPP)
5.0 PROSECUTING THE WORK
5.1 SITE WORK
5.1.1 Conservation
5.1.2 Site Preparation
5.1.3 Demolition
5.2 CONSTRUCTION OPERATION SERVICES
5.2.1 Construction
5.2.2 Inspections
5.3 DEMOBILIZATION
5.4 EMERGENCY RESPONSE
5.5 MAINTENANCE AND REPAIR
5.6 ORDNANCE REMOVAL AND SUPPORT
5.7 SECURITY REQUIREMENTS
5.8 GENERAL SAFETY REQUIREMENTS
5.9 GENERATED REFUSE
6.0 FACILITY CONSTRUCTION PROJECT DELIVERY METHODS
6.1 DESIGN BUILD (D-B)
6.1.1 Designers of Record (DOR)/Design Project Manager (PM)
6.1.2 Contractor Design Requirements after Award
6.1.3 User Requirements Design Meeting
6.1.4 Geotechnical/Hazardous Material Survey Requirements and Responsibilities
6.1.4.1 Soil Survey Requirements and Responsibilities for Contractor
6.1.5 General Design Requirements
6.1.6 Design Review
6.2 DESIGN-BID-BUILD (D-B-B)
7.0 ADDITIONAL REQUIREMENTS
7.1 TYPES OF PROJECTS/WORK
7.1.1 Military Family Housing
7.1.2 Fueling System Projects
7.1.3 Range Construction
7.1.4 Pavement Systems (Airfield and Non-airfield)
7.1.5 Renovations (including historic buildings)
7.1.6 Construction of Classified or Highly Secure Facilities
7.2 AS-BUILT DOCUMENTATION
POINTS OF CONTACT (POCS)
Attachments
Appendix A Description of Work Felix Lake XLWU 22-8115
Appendix B Description of Work Horseshoe Lake XLWU 22-8116
Appendix C Description of Work PQM Lake XLWU 22-8118
1.0 SCOPE
A. This is a Design-Build project to demo, repair and restore exterior elements of multiple lake piers. The project is comprised of repairing and/or replacing existing piers and pavilions at Felix Lake, Horseshoe Lake and PQM Lake on Tyndall AFB. The related disciplines of work as specific tasks in Scope of Work (Appendix A, B, C). The Design-
Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW).
B. The Contractor shall be responsible for all professional services, A/E design, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the tasks defined by the SOW, including the disposal of all resulting waste materials and project clean up. The performed tasks shall be based on the project description, other data furnished in this SOW, and information covered during kick-off meeting.
C. Ancillary items: Providing necessary support to the primary activities or operation of an organization, institution, industry, or system. An example of ancillary item: Lighting controls, but is not limited to the following: switches, motions sensors, and dimmers, ballasts, emergency backup controls, etc. An incompatible dimmer or electronic equipment replacement to support a conversion from fluorescent to LEDS lights would fit the ancillary item description. Another example is Pump controls but is not limited to the following: Starters, on and off switches, logic controllers. This is all support equipment to ensure the task is completed. Roofs: All required items required by regulations code to complete the installation of a roof system such as detection, fire protections, etc. All of these items must result in a complete and usable product at completion of the project to ensure all the previous functionality was provided in the new design.
D. This SOW sets forth the requirements for Design/Build (DB) contract site-specific design and construction effort to remove, repair and restore exterior elements and related infrastructure within a building on Tyndall AFB, Florida.
E. See Appendix D for Supporting Documentation.
1.1 General Requirements
A. Applicable provisions of the Contract Clauses in the contract will govern work under each section of the specifications.
B. This project has an estimated period of performance from Notification to Proceed (NTP) through completion and turnover of the facility back to the Government for mission operations of 180 calendar days.
C. Proposal Documents: The contractor shall complete the proposal schedule included in the solicitation and include the completed schedule with the submitted proposal documents.
D. Measurements: The GC is required to validate dimensions and quantities. The quantities are listed as approximations and GC field measurements and quaintly verification should be used for bidding package.
E. Field Changes:
a. Field Changes: The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the CO prior to execution. Only the CO may authorize field changes or deviations from the SOW.
b. No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether or not acting within the limits of his authority, or any other representatives of the Government, shall constitute a change order under the “Changes” clause of this contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting Officer.
F. Job Start Meeting: A job start meeting shall be accomplished with the Contractor, Contracting Officer, CE, and user upon acceptance of the 35%, 65%, or 95% design submission. The meeting objective is to review project details, determine design delivery dates and anticipated construction start date, security procedures for site, dumpster locations, and any applicable requirements during construction. The Contractor shall visit the job site to verify location, conditions, and dimensions prior to starting work.
G. Pre-Construction Meeting: A preconstruction meeting shall be held when all the design has reached the Issued For Construction (IFC) stage and all preconstruction submittals have been approved. The contractor Quality Control Manager, Site Safety Officer, and
Superintendent shall be required to attend. This meeting will address all items specific to the project to include access, safety, and environmental needs.
H. Facility Occupancy: The facility covered by this contract is currently not occupied and not functional. During performance of this contract, non-work areas will remain functional to normal base activities. The Contractor is responsible for diverting and restricting pedestrian and vehicle traffic if required for any reason for the duration of the performance period.
I. Bulletin Board: Immediately upon mobilization, the Contractor shall provide a bulletin board not less than 36 by 48 inches (915 by 1220 mm) in size for displaying various documents required within the contract. The bulletin board shall be located at the project site in a conspicuous place easily accessible to all employees. All documents posted shall be legible and replaced as needed when unreadable. The board shall be displayed until the work is completed whereby the Contractor shall remove the board and remain the property of the Contractor. The contents of the board shall include, but not limited to, the following:
a. Contractor’s company name
b. Project name
c. MPLS number
d. Superintendent’s name and a 24 hour available response phone number
e. Equal Employment Opportunity poster
f. Wage determination
g. Wage Rate Information poster.
h. Other documents as needed or required.
J. Employee Parking: Contractor employees shall park privately owned vehicles in an area designated by CES and approved by the CO.
K. Job Site Tools and Equipment: All hand tools and equipment shall be maintained in good working conditions and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.
L. Field Measurements: The Contractor shall be required to make his/her own field investigations to verify existing conditions, dimensions and other information shown on
Government available non-verified furnished reference drawings, solicitation documents and construction documents. Deviations, errors, or omissions in the government supplied reference materials or the design team’s construction documents shall be identified and addressed by the contractor during the design phase of the contract. They shall be annotated on the respective contract documents as well as on a consolidated register that will be made available to the government for simplified identification and review.
M. Notification Requirements: The Contractor shall notify the Government a minimum of ten
(10) days in advance of each mobilization. The Contractor is required to notify the CO and
Government Project Manager of critical issues that may affect the contract performance and/or human health and the environment. For critical issues pertaining to human health and the environment, the Contractor shall immediately notify the CO and stop work. Work shall only resume at the direction of the CO following resolution of the issue.
N. On-Site Field Oversight: The Contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of the construction period for the contract. It is the responsibility of the
Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.
O. Federal Holidays:
a. The standard Federal legal holidays are observed:
1. New Year’s Day
2. Birthday of Martin Luther King, Jr.
3. Washington’s Birthday
4. Memorial Day
5. Independence Day
6. Labor Day
7. Columbus Day
8. Veterans Day
9. Thanksgiving Day
10. Christmas Day
11. Juneteenth:
b. Any of the holidays falling on Saturday will be observed on preceding Friday;
holidays falling on Sunday will be observed on the following Monday. In addition, the Government may dictate the work day before or the work day after an observed holiday as a “Family Day.”
c. The Contractor should not perform work on observed holidays, Wing Down Days, Wing Safety Days or Family Days unless authorized by the Contracting Officer for the TO. In the event work is authorized on observed holidays, the Contractor shall pay all applicable overtime and/or holiday pay rates required by law.
P. Working Hours: The normal duty hours of the facility are from 7:00 AM to 5:00 PM, Monday thru Friday excluding Federal Holidays. All work shall be performed during normal duty hours. All other hours to include weekend and holidays shall be requested through the CO for approval. This request shall be submitted no less than three (3) workdays prior to the time requested.
Q. Availability and Use of Utility Services: The contractor should plan on having an offsite office location. The government does not guarantee office space will be provided. The
Government does not guarantee utilities will be provided for office space. The use of a generator and porta toilets may be required of office space is provided. To install and office space and laydown yard will require an 813 permit determination and could take up to 60 days to obtain the permit.
R. Sanitation: The Contractor shall provide and maintain within the construction area minimum field-type sanitary facilities approved by the CO. Government toilet facilities will not be available to Contractor's personnel.
S. Clean Up: At the end of each working day the Contractor shall clean up the work site by the removal of all construction debris, waste materials, packaging material and the like. If the before mentioned items could become airborne they shall be placed in refuse containers immediately. Clean up of the work site shall include the construction area(s), construction office area(s), material storage area (s), parking and eating area(s), and any other area(s) affected by the construction process. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily. Materials resulting from demolition activities which are salvageable shall be stored within the work area or at a supplemental storage area. Stored material not in trailers, whether new or salvaged, shall be neatly stacked when stored in an approved location.
T. Contractor’s Management and Use of Electromagnetic Emission Devices on Base:
(Electromagnetic emission devices include: Radio/Radar Transmitters; Navigational
Aids/Instrumentations; Signaling, Intrusion Detecting, and Identification Devices; Mobile and Fixed Business Radio Communications Equipment; and MARS, CBs, and Amateur
Radio Stations.) The Contractor shall comply with the Air Force Military Training Center
(AFMTC) Regulation 700-14, Jul 89.
U. Preparation of Progress Schedules and Reports: The reports contemplated by FAR Clause, 52.236-15, Schedules for Construction Contracts, shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and
AF Form 3065, Contract Progress Report. Contract Schedules and Reports shall run from
Monday through Sunday and be submitted to the CO per table of deliverables located in
4.0A Table 1 - Table of Deliverables.
V. Deteriorated Construction And Finish
a. Authority: The QA Inspector will be the governing authority in determining if existing construction and finishes are deteriorated and require repair and/or replacement.
W. Contractor Storage/Staging Area
a. Operations and Storage Approval: Notwithstanding Contract FAR Clause, FAR
52.236-10, Operations and Storage Areas, subject to approval by the CO and in turn, availability and need, a storage/staging area may be provided at the subject project site.
If project site space is not available, then offsite storage may be required.
b. Utility ‘tie-ins’, where available, are the Contractor’s responsibility. See 1.1 General
Requirements, Q. Availability and Use of Utility Services for additional information.
c. Storage Area Clean Up: Weekly discard trash and debris in the Contractor’s containers (dumpsters). Do not allow debris to accumulate. At work completion, clean the storage area. This area must be free of any materials, trash or debris before receipt of final payment.
d. In areas of high visibility, the job site construction fence shall have a screen fabric material applied to the fence fabric in order to block the view during the construction phase. The CO will make the determination at the pre-construction meeting if the subject project will require a screened fence or not. Remove fence upon completion.
Rehabilitate disturbed turfs and grass and if reseeding is required use Bermuda grass.
X. Hazardous component abatement for materials such as asbestos, lead-based paint, PCBs, and other hazardous materials shall be the responsibility of the Contractor. Abatement of mold resulting from water damaged materials shall be the responsibility of the Contractor.
Y. The duration of days is considered calendar days unless otherwise noted.
Z. COVID-19 Requirements - During the COVID-19 pandemic it is vital to Tyndall AFB’s
Mission that the Contractor adhere to all Tyndall AFB Covid-19 directives to mitigate virus transmission. The contractor shall be responsible for the following: follow CDC guide lines, setting up teleconference meetings, wearing mask and social distancing when entering a government facility, the screening of their employees, and reporting COVID-19 cases to the 325th CONS and 325th CES project manage (PM). As Covid-19 directives are living documents, it is the Contractor’s responsibility to be informed and follow the most recent published directive.
AA. Project Signage: As required per the FAR.
a. As required, a job sign shall be required at the project site. The CO or the Government
Inspector will make a determination based on cost and visibility. The sign shall indicate the Contractor’s company name, project name and MPLS number, superintendent’s name and a 24 hour available response phone number. The size of the sign shall be 4’ x 8’ x ¾” thick plywood board mounted to a 2x4 wood frame and diagonal braces. The wood frame shall be supported on 4x4 wood supports and be mounted to the ground in concrete footings. Background color shall be in accordance with Federal Standard
White (Gloss). The color of the lettering shall be Black (gloss) with Helvetica font.
2.0 APPLICABLE DOCUMENTS
A. The Contractor shall identify and comply with all applicable federal, state, and local laws;
statutes; Executive Orders; Department of Defense/Air Force manuals, handbooks, regulations, guidance, and policies. The contractor shall comply with the National Institute of Building Sciences’ Whole Building Design Guide Construction Criteria Base (CCB)
Unified Facility Criteria (UFC) 3-600-01 and all of the related libraries. The primary criteria are the Air Force Criteria from the Documents Library, but other agency criteria may be directed for use, depending on the customer agency for a particular TO. The
Unified Facilities Guide Specifications (UFGS) is the mandatory starting point for all specifications, and shall not be deleted, materially modified, or made less stringent without
Government approval. It is the contractor’s responsibility to identify and comply with all applicable requirements. It shall be the contractor’s responsibility as the Designer of
Record (DOR) to identify any design/construction criteria waivers that are warranted for the Project and to accomplish all necessary coordination activities necessary to obtain approval of these proposed waivers through the Contracting Officer (CO), and/or Project
Manager (PM).
B. In addition, the contractor shall refer to and comply with the current versions of the
Department of Defense Policy and Guidelines for Acquisitions Involving Environmental
Sampling or Testing and The United States Air Force Construction Management
Implementation Guide as well as the latest version of The USAF Project Manager’s Guide to Design and Construction. Base-specific documents are identified in the attached appendices.
C. The Contractor and Design Team shall adhere to the following guidance during design and construction phase(s) of this project: Those sections of the Southern Standard Building
Codes not incorporated in the UBC/International Building Code (IBC) for our respective area, International Concrete Repair Institute (ICRI) Guidelines, Air Force Standards, Department of Defense (DOD) Directives, Florida State Statutes, and the Tyndall AFB
Facility Excellence Plan (Base Regulations), Occupational Safety and Health
Administration (OSHA) Requirements, Department of Environmental Protection (DEP)
Regulations, Environmental Protection Agency (EPA) Regulations, and ABA
Accessibility Compliance Requirements.
D. The Contractor shall design and construct new facilities and related sitework to meet the requirements of UFC 1-200-02 and to achieve Third Party certification under GBCI
Guiding Principles Assessment or GBI Guiding Principles Compliance. Refer to Part 18
SUSTAINABLE DESIGN of this specification for specific requirements and criteria.
E. In addition to adhering to the previous guidance, the Contractor shall review and adhere to the most recent version of the following code criteria as applicable at start of the design phase:
a. UFC 1-200-01 The DoD Building Code
b. UFC 1-200-02 High Performance and Sustainable Building Requirements
c. UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Standard
d. UFC 1-300-07A Design Build Technical Requirements
e. UFC 1-300-08 Criteria for Transfer and Acceptance of DoD Real Property
f. UFC 3-101-01 Architecture
g. UFC 3-110-03 Roofing
h. UFC 3-110-04 Roofing Maintenance and Repair
i. UFC 3-120-01 Design: Sign Standards
j. UFC 3-120-10 Interior Design
k. UFC 3-190-06 Protective Coatings and Paints
l. UFC 3-201-01 Civil Engineering
m. UFC 3-201-02 Landscape Architecture https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-300-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-300-08 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-101-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-110-03 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-110-04 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-190-06 https://www.wbdg.org/FFC/DOD/UFC/ufc_3_201_01_2018_c5.pdf
n. UFC 3-210-10 Low Impact Development
o. UFC 3-220-01 Geotechnical Engineering
p. UFC 3-220-05 Dewatering and Groundwater Control
q. UFC 3-230-01 Water Storage and Distribution
r. UFC 3-230-10A Water Supply, Water Distribution
s. UFC 3-240-01 Wastewater Collection and Treatment
t. UFC 3-250-01 Pavement Design for Roads and Parking Areas
u. UFC 3-250-03 Standard Practice Manual for Flexible Pavements
v. UFC 3-250-04 Standard Practice for Concrete Pavements
w. UFC 3-250-08FA Sealing Joints and Cracks
x. UFC 3-250-11 Soil Stabilization for Pavements
y. UFC 3-260-02 Pavement Design for Roads, Streets, Walks, and Open Storage Areas
z. UFC 3-300-07A Design Build Technical Requirements
aa. UFC 3-301-01 Structural Engineering
bb. UFC 3-310-04 Seismic Design for Buildings
cc. UFC 3-400-02 Design: Engineering Weather Data
dd. UFC 3-401-01 Mechanical Engineering
ee. UFC 3-410-01 Heating, Ventilating, and Air Conditioning
ff. UFC 3-410-02 Direct Digital Control for HVAC
gg. UFC 3-410-04 Industrial Ventilation
hh. UFC 3-420-01 Plumbing Systems
ii. UFC 3-420-02FA Compressed Air
jj. UFC 3-430-09 Exterior Mechanical Utility Distribution
kk. UFC 3-450-01 Noise and Vibration Control
ll. UFC 3-501-01 Electrical Engineering
mm. UFC 3-520-01 Interior Electrical Systems
nn. UFC 3-530-01 Interior and Exterior Lighting and Controls
oo. UFC 3-540-01 Engine-Driven Generator Systems for Prime and Standby
Power Applications, with Change 2
pp. UFC 3-550-01 Exterior Electrical Power Distribution
qq. UFC 3-560-01 Electrical Safety O&M
rr. UFC 3-570-01 Cathodic Protection
ss. UFC 3-570-06 Operation and Maintenance: Cathodic Protection Systems
tt. UFC 3-575-01 Lightning and Static Electricity Protection
uu. UFC 3-580-01 Telecommunications Interior Infrastructure
vv. UFC 3-600-01 Fire Protection Engineering for Facilities
ww. UFC 3-701-01 DoD Facilities Pricing Guide, with Change 2; 2019
xx. UFC 3-730-01 Programming Cost Estimates for Military Construction
yy. UFC 3-740-05 Handbook: Construction Cost Estimating
zz. UFC 4-010-01 DOD Minimum Antiterrorism Standards for Buildings aaa. UFC 4-010-05 Sensitive Compartmented Information Facilities bbb. UFC 4-010-06 Cybersecurity of Facility-Related Control Systems ccc. UFC 4-020-01 DoD Security Engineering Facilities Planning Manual ddd. UFC 4-021-01 Mass Notification Systems https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-250-08fa https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-301-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-310-04 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-400-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-401-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-410-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-410-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-410-04 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-420-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-430-01fa https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-450-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-501-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-520-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-530-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-540-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-540-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-550-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-560-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-570-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-575-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-580-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-600-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-021-01 eee. UFC 4-021-02 Electronic Security Systems fff. UFC 4-211-01 Aircraft Maintenance Hangars ggg. UFC 4-214-03 Central Vehicle Wash Facilities hhh. USAF BIM Minimum Requirements Version 2.1
iii. AASHTO A Policy on Geometric Design of Highways and Streets jjj. ABAS Architectural Barriers Act Standards; The ABA may be found at https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards kkk. AFDS Air Force Design Guide lll. AFGM 2018-32-01 Civil Engineer Control Systems Cybersecurity mmm. AFI 32-1020 Planning And Programming Built Infrastructure Projects nnn. AFI 32-1024 Standard Facility Requirements ooo. AFI 32-1063 Electrical Power Systems ppp. AFI 32-1064 Electrical Safe Practices qqq. AFI 32-1065 Grounding System www.wbdg.org › FFC › AFI › afi_32_1065_2017 rrr. AFI 32-1067 Water Systems sss. AFI 32-1068 Heating Systems and Unfired Pressure Vessels ttt. AFI 32-1069 Gas Supply and Distribution uuu. AFMAN 91-203 Air Force Occupational Safety, Fire and Health Standards
vvv. AFMAN 32-1084 Facility Requirements Standards www. ANSI C2 National Electric Safety Code
xxx. ASCE 7-10 Wind Loads yyy. ASHRAE 55 Thermal Environmental Conditions for Human Occupancy zzz. ASHRAE 62.1 Ventilation for Acceptable Indoor Air Quality aaaa. ASHRAE 90.1 Energy Standard for Bldgs. Except Low-Rise Residential bbbb. ASHRAE 100 Energy Conservation in Existing Buildings cccc. ASHRAE 111 Testing, Adjusting, and Balancing of Building HVAC
Systems dddd. ASHRAE 180 Inspection & Maintenance Commercial Bldg. HVAC
Systems eeee. ASHRAE 189.1 Standard for the Design of High-Performance Green
Buildings ffff. ASHRAE 202 Commissioning Process for Buildings and Systems gggg. ASHRAE Guide 4Prep of Operating and Maintenance Documentation hhhh. ECB 2018-11 Control System Cybersecurity Coordination Requirement
iiii. EISA Energy Independence and Security Act of 2007 jjjj. EM 385-1-1 USACE Safety and Health Requirements Manual kkkk. EPAct 2005 Energy Policy Act of 2005 llll. FC 4-218-03F Air Force Criteria for Precision Measurement Equipment
Laboratory Design and Construction mmmm. FAR Federal Acquisition Regulations nnnn. FS 553 Florida Building Code oooo. IBC International Building Code https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-021-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-211-01 http://www.wbdg.org/FFC/AF/AFBIM/AF_Minimum_BIM_Requirements_V2.1.pdf http://www.access-board.gov/guidelines-http://www.wbdg.org/ http://www/ https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf pppp. IES Illuminating Engineering Society Lighting Handbook qqqq. IFGS International Fuel Gas Code rrrr. IMC International Mechanical Code ssss. IPC International Plumbing Code tttt. MIL-HDBK-1190 MILITARY HANDBOOK: FACILITY PLANNING AND
DESIGN GUIDE
uuuu. NACE SP-0169
vvvv. NACE SP-0185 wwww. NACE SP-0286
xxxx. NBIMS US V3 National BIM Standard US Version 3 yyyy. NEBB Standards for Whole Building Systems Commissioning zzzz. NEC National Electrical Code, current edition aaaaa. NEMA National Electrical Manufacturer's Association bbbbb. NESC National Electrical Safety Code current edition ccccc. NFPA 13 Standard for the Installation of Sprinkler Systems ddddd. NFPA 24 Installation of Private Fire Service Mains and Their
Appurtenances eeeee. NFPA 70 National Electric Code fffff. NFPA 72 National Fire Alarm Code ggggg. NFPA 90A Standard for the Installation of Heating and Air
Conditioning Systems hhhhh. NFPA 101 Life Safety Code
iiiii. NFPA 1141 Standard for Fire Protection Infrastructure for Land
Development in Wildland, Rural, and Suburban Areas jjjjj. NPDES National Pollutant Discharge Elimination System http://www.dep.state.fl.us/water/stormwater/npdes/construction3.htm kkkkk. SMACNA Guides
Sheet Metal & Air Conditioning
Contractors’ National Assoc.
lllll. TAFB FEP TAFB Facility Excellence Plan mmmmm. TAFB IFS TAFB Installation Facility Standard https://www.tyndallifs.com/ nnnnn. TM 5-683 Facilities Engineering Electrical Interior Facilities ooooo. TM 5-684 Facilities Engineering - Electrical Exterior ppppp. USAF BIM Minimum Requirements Version 2.1 qqqqq. UFAS Uniform Federal Accessibility Standards rrrrr. UFGS 23 09 00 Instrumentation and Control for HVAC sssss. UFGS 23 09 13 Instrumentation and Control Devices for HVAC ttttt. UFGS 23 09 23.02
BACnet Direct Digital Control for HVAC and Other
Building Control Systems uuuuu. UFGS 23 09 93 Sequences of Operations for HVAC Controls
vvvvv. UFGS 25 05 11 Cybersecurity for Facility-Related Control Systems wwwww. UFGS 23 08 10 Utility Monitoring and Control System Testing
xxxxx. UFGS 25 10 10 Utility Monitoring and Control System (UMCS) Front End http://www/ https://www.nationalbimstandard.org/files/NBIMS-US_V3_4.2_COBie.pdf http://www.dep.state.fl.us/water/stormwater/npdes/construction3.htm http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/tyndall-afb-ifs http://www.tyndallifs.com/ http://www.tyndallifs.com/ http://www.wbdg.org/FFC/AF/AFBIM/AF_Minimum_BIM_Requirements_V2.1.pdf http://www/ and Integration
F. Miscellaneous
a. AFCEC AGRAM 17-01 Change to AF New Construction and Major Renovation
Certification Requirements
b. Air Force Pamphlet 91-210 (Contract Safety)
c. Air Force Systems Security Instruction 7700 - Communications and Information -
Emission Security
d. Air Force Systems Security Instruction 7702 - Communications and Information
- Emission Security
e. Air Force Sustainable Design and Development (SDD) Implementation Guidance
f. Tyndall Mass Notification System Messages
g. Tyndall Rebuild Facility Related Control Systems (FRCS) Technology Summary
–Appendix L –22 Sept 2021
h. Memorandum For ALMAJCOM-FOA-DRU, Mandatory Use Policy for Air
Force Carpet Acquisitions within the Contiguous U.S.
i. Draft Rule Amendments of the Environmental Resource Permitting (ERP)
Program in the Northwest District, Applicant's Handbook Volume I & II, http://www.dep.state.fl.us/water/wetlands/erp/rules/draft nw.htm.
j. Recommended Standards for Wastewater Facilities (Ten States Standards)
k. Chapter 62-555 FAC General Permit of Construction of Water Main Extension for
Public Water System
l. Chapter 62-600 of the Florida Administrative Code, Public Drinking Water
Distribution System and Domestic Wastewater Facilities
m. Chapter 62-604 FAC Collection Systems and Transmission Facilities of the Florida
Administrative Code, Domestic Wastewater Facilities and the Wastewater Permit checklist.
n. Manual of Practice No. FD-4 Design of Wastewater and Stormwater Pumping
Stations.
o. Manual of Practice No. FD-5 Gravity Sanitary Sewer Design and Construction.
p. USACE ETL 1110-3-466 Selection and Design of Oil/Water Separators at Army
Facilities, August 1994
q. USACE Designing Coalescing Oil/Water Separators for Use at Army Washracks, December 2000
r. GCEC MANUAL OF STANDARDS AND SPECIFICATIONS FOR WATER
MAIN CONSTRUCTION FOR TYNDALL AFB SYSTEM
s. Guiding Principles for Sustainable Federal Buildings and Associated Installations
t. Illuminating Engineering Society of North America (Handbook)
u. Florida Fish and Wildlife Commission; Sea Turtle Lighting Guidelines - Chapter
62B-55 Model Lighting Ordinance for Marine Turtle Protection.
v. E.O. 13834 Efficient Federal Operations http://www.dep.state.fl.us/water/wetlands/erp/rules/draft%20nw.htm
G. Lightning Protection Requirement: Lightning Protection System (LPS) shall be designed and installed IAW the following references:
a. AFI 32-1065 Grounding System www.wbdg.org › FFC › AFI › afi_32_1065_2017
b. NFPA 70 National Electric Code
c. NFPA 780 Standard for the installation of Lightning Protection System
d. UFC 3-575-01 Lightning and Static Electricity Protection System
e. UL 96 Lightning Protection Components
f. UL 96A Installation Requirements for Lightning Protection System
g. UL 467 Grounding and Bonding Equipment
F. Security Requirements:
a. MIL-HDBK-1013: DOD Military Handbook Design Guidelines for Physical
Security of Facilities
b. AFI 31-101: Air Force Instruction 31-101: The Air Force Installation
Security Program
c. DOD 5200.1.R Department of Defense 5200.1.R: Information Security
Program Construction Standards.
d. ICD-ICS-705 Tech Spec
e. UFC 4-010-01 Unified Facilities Criteria Antiterrorism Standards for New and Existing Facilities
f. UFC 4-010-05 Sensitive Compartmented Information Facilities
g. UFC 4-010-06 Cybersecurity of Facility-Related Control Systems
G. FAR Case No. 92-54 requires the Solicitation Package for all construction projects to reflect the government's preference for "acquisition of environmentally sound and energy efficient products and services, and an affirmative procurement program favoring items containing the maximum practicable content of recovered materials".
H. DOD Information
a. Department of Defense Manual 5200.01, Volume 1; DoD Information Security
Program: Overview, Classification, and Declassification; 2012
b. Department of Defense Manual 5200.01, Volume 2; DoD Information Security
Program: Marking of Classified Information; 2013
c. Department of Defense Manual 5200.01, Volume 3; DoD Information Security
Program: Protection of Classified Information; 2013
d. Department of Defense Manual 5200.01, Volume 4; DoD Information Security
Program: Controlled Unclassified Information (CUI); with Change 1 2018
I. DOD Information
J. Facilities Department of
K. Federal Green Construction Guide for specifiers. This guide can be found at:
http://www.wbdg.org/design/greenspec.php http://www.wbdg.org/ http://www.wbdg.org/design/greenspec.php
L. Non-ERP Soil Management Guidelines, May 2020
M. The Contractor shall perform all work IAW with AFI, ETL, UFC and industry standards.
Compliance with AF UFCs is mandatory unless the IFS has more stringent requirements.
If the Contractor determines that the work cannot be performed and/or included in the SOW
IAW with ETL’s/UFCs or industry standards, the Contractor shall notify the Tyndall AFB
POC listed in this document in writing immediately before award of the contract.
Otherwise, the Contractor shall be responsible for the required work.
N. All work shall be in compliance with all Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DODI), Department of Defense Directives (DODD), or other higher authority documents as applicable. Many applicable compliance documents are authorized by DoD MIL-STD-3007F, and are available through the Government-sponsored Whole Building Design Guide located at https://www.wbdg.org.
O. If there is a conflict between these codes, regulations specifications, and/or guidance documents, the most stringent requirements shall apply, as determined by the CO through the Request for Information (RFI) process. These listed documents do not relieve the
Contractor from complying with other required regulatory documents not listed.
P. The government may take up to 30 days to review design documents. The contractor schedule activity for less days will be overridden by this time frame and will not be considered a delay by the government. The contractor schedule shall reflect the 30 day review time.
3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED
INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)
A. Historical architectural and structural construction documents may be available for review, however field verification and documentation of existing conditions and configurations prior to construction is essential. The government takes no responsibility for errors and omissions contained in the reference material and field verification shall be performed by the contractor.
4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
A. Design submittals, 95%, and 100%, will be routed with an AF Form 3000 and will be reviewed and approved/disapproved within 30 calendar days.
B. No delay damages or time extensions will be allowed for time lost in late or lost submittals.
Government review times may take up to 30 days and is not considered a delay for design reviews. The contractor’s schedule shall include time for these 30 day reviews. The official review time starts when the CO acknowledges the receipt of the submittal.
https://www.wbdg.org/FFC/FEDMIL/std3007f.pdf https://www.wbdg.org/
C. Submittals pertaining to environmental issues may take up to 30-45 days for review and approval. Wetland permits may take greater than 60 days to process. Environmental 813 submittals shall include drawings, locates for utilities with depth, size of lines, length of runs, underground or above ground routing, spatial coordinates, duration of the laydown yard or temporary trailer, number of personnel, location of temporary porta toilets, etc.
Delays greater than the anticipated days listed herein do not constitute a governmental delay. Contractor will be allotted a no-cost PoP extension for days over and above those listed herein.
D. All other submittals should be reviewed and approved/disapproved within 10 work days.
Submittals will be reviewed for accuracy and relevance to the project and specifications.
Material Submittal documents shall be submitted with AF Form 3000, Material Approval
Submittal.
E. Submittal documents shall include required forms, reports, drawings, samples, pictures, media recordings, manufacturer data, certifications, test reports, equipment warranty information, and the like. Submittal documents shall be submitted by the Contractor to the by CO for approval. All submitted documentation shall become the complete property of the Government. The Contractor shall not purchase, install, or construct any equipment or facility component, for which a submittal is required, without first obtaining an approved signed submittal from the CO. Required submittals shall be listed on AF Form 66, Schedule of Material Submittals, and/or a Submittal Register approved by the CO.
F. Table of Deliverables: Project deliverables shall be as shown in the following 4.0A Table
1 - Table of Deliverables. The dates in the table are hard dates not to be exceeded without
CO approval. The deliverables and scheduled activities may be provided or completed early.
G. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The
Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.
H. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the
Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but have been omitted from the register or marked "N/A."
I. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.
J. Contracting Officer Review will be completed within 30 calendar working days after the date of submission for submittals requiring Government approval.
4.0A Table 1 - Table of Deliverables
Document
Copies
Max Delivery Timeframe 3
C E
S
C
O N le ct ro n ic
H a rd C o p y ct ro rd C o
Standard Meetings and Reports
Meeting Minutes 1 0 1 0 3 calendar days after each meeting
Progress Schedule(AF 3064 or approved equivalent) 1 0 1 0
5 calendar days after NTP or modification to extend PoP
Progress Report (AF 3065 or approved equivalent) 1 0 1 0
Weekly
3-week Look Ahead report 1 0 1 0 Weekly w/ Progress Report
Daily Logs - Form 1477 or equiv. 1 0 1 0 NLT 0900 the day following - Daily
HAZMAT Forms 81 and 82 1 1 1 1 10 Days prior to preconstruction meeting
Work Clearance Request (AF Form 103A) 1 1 1 1 10 Days prior to preconstruction meeting
Material Approval (AF Form 3000) 1 0 1 0 At the 100% Final Design
Construction Material Testing Reports 1 0 1 0 As required
Welding/Burn Permit 1 0 1 0 10 Days prior to requirement
Production or Delivery Problem Report 1 1 1 1 At time of identification
Draft DD1354 1 0 1 0 When request for final inspection is submitted
Work Activities
IMS, WBS and AF 3064/3065 1 0 1 0 15 Days Prior to NTP
Kickoff meeting with all stakeholders 1 0 1 0 5 Days Prior to NTP
Health and Safety Plan (HSP) or (APP) 1 0 1 0 Prior to site visits
NTP 1 0 1 0 As assigned by CO
Contractor Site Investigation 1 0 1 0 5 Days from NTP
Design Quality Plan (DQCP) or (DQSP) 1 0 1 0 Prior to Design Starting
Quality Control Pan (QCP) or (QSP) 1 0 1 0 Prior to construction activities
Construction Work Plan (CWP) 1 0 1 0 Prior to construction activities
C
C
O ct ro rd C o ct ro rd C o
Site Investigation Memorandum 1 0 1 0 10 Days from Contractor Site Investigation
Charrette Meeting N/A
Charrette Meeting Minutes Acceptance and
Approval 1 0 1 0
N/A
The 35% and 65% design may be waived for small projects
N/A
35% Design w/ AF Form 3000 1* 0 1* 0 N/A
35% Design Review and Meeting 1 0 1 0 N/A
35% Design Resubmittal if submittal was disapproved 1 0 1 0
N/A
35% Design Final Submittal and Approval 1 0 1 0 N/A
65% Design w/ AF Form 3000 1* 0 1* 0 N/A
65% Design Review and Meeting 1 0 1 0 N/A
65% Design Resubmittal if submittal was disapproved 1 0 1 0
N/A
65% Design Final Submittal and Approval 1 0 1 0 N/A
95% Design w/ AF Form 3000 0 0 0 0 30 Days from NTP
95% Design Review and Meeting 1 0 1 0 30 Days from 95% Design Submittal
95% Design Resubmittal if submittal was disapproved 1 0 1 0
10 Days from 95% Design Disapproval
95% Design Final Submittal and Approval 1 0 1 0
10 Days from 95% Design Re-
Submittal
100% Design w/ AF Form 3000 1* 0 1* 0 20 Days from 95% Final Design
100% Design Review and Meeting 1 0 1 0 30 Days from 100% Design Submittal
100% Design Resubmittal if submittal was disapproved 1 0 1 0
10 Days from 100% Design
Disapproval
100% Design Final Submittal and Approval 1 0 1 0
10 Days from 100% Design Re-
Submittal
All Material Submittals
At 100% Design Approval or 30 Days from design Approval with CO approval.
Demolition Plan when demolition activities 1 0 1 0 Prior to 100% Design Approval
Environmental Plan (EPP) 1 0 1 0 Prior to 100% Design Approval
Storm Water Pollution Protection Plan
(SWPPP)
1 0 1 0 Provided as part of the EPP
C
C
O ct ro rd C o ct ro rd C o
Red Line drawings Submitted 1 0 1 0 15 Days prior to Start Work
Draft Phasing Plan 1 0 1 0 N/A
Final Phasing Plan 1 0 1 0 N/A
Mobilization of Contractor 0 0 0 0 After 100% Design Approval or before with CO approval
Contractor Base Access Request 1 0 1 0 15 Days prior to contractor mobilization
Job Start Meeting 1 0 1 0 After 100% Design Approval or before with CO approval
Implementation of the Design 90-120 Days
Red Zone Meeting 1 0 1 0 45 Days prior to end of POP
Pre-Final Inspection 1 0 1 0 At end of Implementation
Pre-Final Inspection Report 1 0 1 0 5 Days after Pre-Final Inspection
Operations & Maintenance Manuals 1 1 1 1 N/A
HAZMAT Form 83 1 0 1 0 Prior to Final Inspection
Final Inspection 1 0 1 0 15 Days after Pre-Inspection
Final Inspection Report 1 0 1 0 5 Days After Final Inspection
O&M’s Review 1* 1 1* 0 N/A
As-Built Design Documents 1 0 1 0 5 Days After Final Inspection
As-Built Design Drawings 1* 0 1* 0 5 Days After Final Inspection
As Built Review Meeting 1 1 1 1 10 Days After Final Inspection
As Built Review Comments 1 0 1 0 15 Days After Final Inspection
O&M’s Acceptance 1* 1 1* 0 N/A
As Built Comments Acceptance 1 0 1 0 20 Days After Final Inspection
As Built Approval 1 0 1 0 20 Days After Final Inspection
Transfer & Acceptance of Military Real
Property (DD 1354) 1 1 1 0 5 Days after Final Design Approval
O&M’s to user 1 0 1 0 N/A
User training 1* 1 1* 0 N/A
*Both Autodesk AutoCAD and Adobe Acrobat versions of drawings are required
K. Electronic copies of all design deliverable documents shall be provided on CD or DVD discs, formatted for use by the latest software version, and compatible with the
Government’s version of Microsoft Word, Excel, PowerPoint, Access, Outlook, the Adobe family of products, the Autodesk family of applications, the ANSYS family of applications, or other software platform as appropriate and as determined and directed by the CO.
Whenever possible, the electronic files given to the Government should be compatible with at least one software program application listed on the Air Force Evaluated Products List
(EPL) or the Defense Information Systems Agency (DISA) Approved Products List (APL).
For any submitted documents converted to one of the above formats from another software program, the Contractor shall also submit the electronic document file from the software program originally creating it, along with a statement describing what creating software program and version was used, as well as any programs used to convert files from one format to another. Submitted electronic files shall be unlocked and fully editable.
L. Builder Template
a. A builder template will be provided to the contractor to complete for real property items that were installed per the scope of work.
4.1 Work Breakdown Structure (WBS)
E. A 3064 or equivalent spreadsheet is used for the WBS. The task number, start and stop dates, Value for the task will be provided.
4.2
Schedule and Planning Requirements
A. See Section General Requirements
4.2.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)
A. Provided as needed.
4.2.2 Integrated Master Schedule (IMS)
4.2.2.1 Contract Progress Schedule (AF 3064)
A. The Contractor shall submit a signed AF 3064, Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance as described in the 4.0A Table 1 - Table of Deliverables. The line items, associated project percentages, and dates shall accurately depict the planned work to be performed.
B. A template spreadsheet may be provided by the government to use for progress reporting.
C. The progress schedule shall be signed by CE recommending approval and approved by the
CO.
4.2.2.2 Contract Progress Report (AF 3065)
A. The Contractor shall submit AF 3065 as described in 4.0A Table 1 - Table of Deliverables.
This report shall be signed by the Contractor’s on-site representative in the Remarks section of the AF 3065. The work elements and percentages of the total job identified on the AF
3065 shall be identical to the work elements and percentages on the AF 3064. The
Contractor shall obtain either the QA Inspector or the Government contract inspector’s acceptance by signature of the actual reported progress prior to submission to the CO.
Additionally, the Contractor shall submit the updated AF 3064 as an attachment to the AF
3065.
4.2.2.3 Submitting Schedules and Reports
A. Contract Progress Report. Contract Schedules and Reports shall run from Monday through
Sunday and be submitted to the CO by Tuesday of the following week. Contractor will prepare reports covering activities for days work and give one to the Government Inspector for each week of work even if there was no work accomplished that week. The weekly report may be turned in for each week at the end of the week when construction begins.
B. A 3064/3064/schedule spreadsheet may be used to coordinate progress reporting. A example spreadsheet can be provided.
4.3 Status Reporting
4.3.1 Reporting Requirements for Firm Fixed Price (FFP)
4.3.1.1 Contractor’s Progress, Status, and Management Report (CPSMR)
A. A 3064 is used for this project.
4.4 Meeting and Conference Requirements
A. Upon award the Contractor shall attend the following meetings at a minimum: Project
Start and Pre-Construction Job Start, 35%, 65%, and/or 95% Design Review, 100% Design
Review, Corrected Design Review, Incremental Site Inspection (as needed), Test and
Balance (as needed), Commissioning (as needed), Pre-Final Inspection, Final Inspection, and other meetings (as needed).
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .