This file is a comprehensive Removal Action Specification for a Non-Time Critical Removal Action (NTCRA) at the Pinhook Bog Debris Site within Indiana Dunes National Park. The project involves excavating approximately 1,350 bank cubic yards (estimated 2,500 tons) of solid waste and contaminated soil from seven distinct debris areas located south of Michigan City, Indiana, near Interstate 80/90. The removal action objectives include characterizing and removing waste materials, transporting them to appropriate disposal facilities, collecting confirmation samples, and preparing a Removal Action Completion Report.
The solicitation (RFP #140P2125R0039) is set aside for Service-Disabled Veteran-Owned Small Business concerns, with a NAICS code of 562910 and a small business size standard of 1,000 employees. The contract will be a firm fixed-price with a combination of lump sum and unit-priced items, with an estimated project magnitude between $250,000 and $1,000,000. A group site visit is scheduled for 7/23/25, and proposals will be due approximately 30 days after the RFP is posted on SAM.gov. The government will evaluate offers on a best value basis, considering technical capability in comparison to price.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pinhook Bog Debris Site Indiana Dunes National Park
NPS Removal Action Specifications
EDL # 5MWR2220
Prepared by
Jacobs
6/25/2025
EDL # 5MWR2220 SECTION 00 01 01 - 1
6/25/2025 COVER PAGE
SIGNATORIES:
Andrea M. DePoy
Indiana Professional Engineer
License No: 10302051
Signature
6/25/2025
Date
By signing above, I attest that I meet the qualifications of an Environmental Professional as defined under 40
CFR §312.10(b) and that this document was prepared by me or under my supervision/responsible charge.
Professional Engineer/Geologist Seal
Ratified By:
Environmental Compliance and Cleanup Division
Signature Date
EDL # 5MWR2220 SECTION 00 01 10 - 1
6/25/2025 TABLE OF CONTENTS
Non-Time Critical Removal Action
SECTION 00 01 10 – TABLE OF CONTENTS
Division 0
00 01 01 Cover Page
00 01 10 Table of Contents
00 01 15 List of Drawing Sheets
Division 1
01 11 00 Summary of Work
01 26 00 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management and Coordination
01 32 16 Removal Action Schedule
01 33 00 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 29.13 Health and Safety Procedures
01 42 00 References
01 50 00 Temporary Facilities and Controls
01 57 19 Temporary Environmental Controls
01 77 00 Closeout Procedures
Division 2
02 21 01 Ecological Surveys
02 21 02 Civil Surveys
02 24 23 Chemical Sampling and Analysis of Soil
02 51 00 Physical Decontamination
02 61 13 Excavation and Handling of Contaminated Materials
02 61 29 Removal and Disposal of Contaminated Soils
Division 3
31 10 00 Site Clearing
32 90 00 Weed and Pest Control
Figures
Figure 1 – Site Location
Figure 2 – Current Conditions Map
Figure 3 – Excavation Area and Site Setup
EDL # 5MWR2220 SECTION 00 01 10 - 2
Figure 4 – Excavation Areas and Site Setup – Excavation A
Figure 5 – Excavation Areas and Site Setup – Excavation B
Figure 6 – Excavation Areas and Site Setup – Excavation C
Figure 7 – Excavation A
Figure 8 – Excavation B
Figure 9 – Excavation C
Appendices
Appendix A - Application for Permit for Archaeological Investigations
Appendix B - Class III Archeological Inventory Report and Documentation Form Standards
Appendix C - Cultural Resource Survey GIS Data Management and Deliverables
Appendix D - Removal Action Completion Report Template (Dated November 30, 2023)
Appendix E - NPS Clean Fill Protocol (Dated May 16, 2024)
Definitions
The following words, terms, and abbreviations, when used within these specifications shall have the following meanings unless the context clearly indicates otherwise.
1. Access Road: Existing and proposed roadways within the Park used to provide equipment and personnel access to Work Area, as defined in the approved
Contractor’s Removal Action Plan.
2. Action Submittals: Written, graphic information, and physical samples that require
Government’s responsive action.
3. ACM: Asbestos-containing materials.
4. AMR: Archeological Monitoring Report.
5. ARAR: Applicable or Relevant and Appropriate Requirements.
6. Archeological Monitor: Representative of Government, professional archeologist, or tribal cultural specialist, designated to oversee removal action activities that could disturb archeological resources.
7. Archeological Resources: Physical evidence of past human activity, including evidence of effects of that activity on the environment. Archeological resources represent both prehistoric and historic time periods, found above and below ground and under water.
8. Archeological Resources Protection Act (ARPA) of 1979 (Public Law (P.L.) 96-95;
93 United States Statues at Large (Stat.) 712): defines archeological resources as any material remains of past human life or activities that are of archeological interest and at least 100 years old; Section 4 of the statute describes the requirements that must be met before Federal authorities can issue a permit to excavate or remove any archeological resource on Federal or Indian lands; the curatorial requirements of artifacts, and other materials excavated or removed.
9. Archeological Site: National Register Bulletin No. 36 identifies an archeological site as “a location that contains the physical evidence of past human behavior that allows for its interpretation.”
10. Archeologically Sensitive Areas: Areas having potential to contain significant archeological resources. If National Register of Historic Places eligible or listed archeological resources could not be avoided, an appropriate mitigation strategy would be developed in consultation with state historic preservation officer and, if necessary, associated American Indian tribes.
11. ARPA: Archeological Resources Protection Act of 1979.
EDL # 5MWR2220 SECTION 00 01 10 - 3
12. Authorization to Mobilize: Written authorization issued by the CO allowing
Contractor to proceed with on-Site Work.
13. Authorized Visitor: NPS Contracting Officer (CO) and their representatives, and any representative of a regulatory or other agency having jurisdiction over the Project.
14. Bog: Pinhook Bog.
15. Borrow Material: Material from required excavations or from designated borrow areas on Site. Must meet requirements of 2006 NPS MP §4.8.2.4.
16. CAA: Clean Air Act.
17. CERCLA: Comprehensive Environmental Response, Compensation, and Liability
Act.
18. CFR: Code of Federal Regulations.
19. Civil Surveys: physical surveys that shall be conducted to document sample locations, excavation extents, and final grading of excavation areas.
20. CO: NPS Contracting Officer.
21. COC: Contaminant of Concern.
22. Common Fill: Soil, meeting the requirements of the NPS Clean Fill Protocol, for use in backfilling excavations to within 6 inches of the final ground surface
23. Completed Course: A course or layer that is ready for next layer or next phase of
Work.
24. Confirmation sample: Soil sample collected within 2 feet of the excavation sidewalls or within 6 inches of the bottom of the excavation for the purpose of demonstrating that soils remaining after completion of excavation activities do not contain COC concentrations above RGs. Confirmation samples may be collected before, during or after the completion of excavation activities.
25. COR: NPS Contracting Officer’s Representative.
26. Contract Documents: Documents comprising the contract between the Contractor and
NPS, including, the contract (SF1442 and terms) and referenced attachments, such as the Drawings and the Specifications.
27. Contractor: The firm hired by NPS to conduct the Work.
28. Contract Time: The period of performance defined in the Contract Documents.
29. Contract Sum: The Contract price defined in the Contract Documents.
30. CPM: Contractor’s Project Manager.
31. CWA: Clean Water Act.
32. DABT: Diplomate of the American Board of Toxicology.
33. DOI: Department of the Interior.
34. DOT: Department of Transportation.
35. DQO: Data Quality Objective.
36. Drawings: NPS graphical documents included along with the specifications comprising the Contract Documents.
37. Earth moving equipment: Includes, but is not limited to, excavators, skid steers, and boring equipment that may bring dirt, dust, mud, seeds, or other potential contaminants onto site.
38. Ecological Survey: Surveys that shall occur prior to potentially disruptive work during the migratory bird nesting and endangered bat roosting windows (April 1 through September 30).
39. EPA or USEPA: United States Environmental Protection Agency.
40. Excavated Waste: Buried solid waste, refuse, construction waste, and contaminated soil present prior to Contractor mobilization activities and removed as part of this non-time critical removal action. Excavated waste does not include demolition debris, EDL # 5MWR2220 SECTION 00 01 10 - 4 solid waste, refuse, construction waste, or special waste created by Contractor incidental to the Work.
41. Free Product: Free-standing petroleum or chemical liquid product present in excavation or floating on water in excavation.
42. FMCSA: Federal Motor Carrier Safety Administration.
43. HASP: Site-Specific Health and Safety Plan.
44. Haul Road: Existing and proposed roadways within the Park used for heavy truck traffic/waste transportation, as depicted in the Drawings.
45. Hazardous Soil and Debris: Material which qualifies as a hazardous or toxic waste as defined by the Resources Conservation and Recovery Act (RCRA) or the Toxic
Substances Control Act (TSCA).
46. Hazardous Waste: A waste which meets the criteria established in RCRA or specified in 40 CFR § 261.3.
47. IAC: Indiana Administrative Code.
48. IAQ: Indoor Air Quality.
49. IC: Indiana Code.
50. IDEM: Indiana Department of Environmental Management.
51. INDU: Indiana Dunes National Park.
52. Informational Submittals: Written information that does not require Government’s responsive action.
53. IPP: the federal government’s web-based Invoice Processing Platform
54. Lift: Loose (uncompacted) layer of material.
55. MUTCD: Manual on Uniform Traffic Control Devices.
56. National Historic Preservation Act: The National Historic Preservation Act (NHPA) establishes a national preservation program and a system of procedural protections, which encourage both the identification and protection of historic resources, including archeological resources. Section 106 of the NHPA requires federal agencies to consider the impact of their actions on historic properties and provide the Advisory
Council on Historic Preservation (ACHP), State Historic Preservation Officers, Tribal
Historic Preservation Officers, and local governments with an opportunity to comment on projects before implementation.
57. Native American Graves Protection and Repatriation Act: The Native American
Graves Protection and Repatriation Act of 1990 (NAGPRA) (25 USC 32) and associated regulations (43 CFR 10) governs the return of Native American remains, funerary objects, sacred objects, and objects of cultural patrimony to lineal descendants, culturally affiliated Indian Tribes, and Native Hawaiian organizations.
Through the provisions of NAGPRA, the federal government acts to treat the remains of Native ancestors and their belongings with dignity, and to return them to their communities with respect for their customs, religion, and traditions.
58. NECA: National Electrical Contractors Association.
59. NEMA: National Electrical Manufacturers Association.
60. NEPA: National Environmental Protection Act.
61. NFPA: National Fire Protection Association.
62. NIOSH: National Institute for Occupational Safety and Health.
63. Nonhazardous Soil and Debris: Material which does not qualify as a hazardous or toxic waste as defined by RCRA or TSCA and includes Excavated Waste as defined above.
64. Non-sensitive Areas: Areas with little potential of containing significant (National
Register eligible) archeological resources.
65. NPS: National Park Service.
EDL # 5MWR2220 SECTION 00 01 10 - 5
66. NPS Employee Guidance for Managing Cultural Resources: NPS Director’s Order
(DO) #28 provides that NPS will manage and protect cultural resources and comply with the DOI Secretary’s standards and guidelines. DO-28 addresses cultural resource management.
67. NRDA: Natural Resource Damage Assessment.
68. NTCRA: Non-Time Critical Removal Action.
69. OSHA: Occupational Safety and Health Administration.
70. PAHs: Polycyclic Aromatic Hydrocarbons.
71. Park: Indiana Dunes National Park.
72. PCBs: Polychlorinated Biphenyls.
73. Portable Document Format (PDF): An open standard file format licensed by Adobe
Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
74. Personal Protective Equipment (PPE): Appropriate protective clothing, gloves, eye protection, footwear, and head gear.
75. Plastic Sheeting: Polyethylene sheeting of a certain thickness as indicated.
76. Pre-Mobilization Conference: Meeting to be conducted prior to start of onsite Work with Contractor, NPS, and NPS’s representatives.
77. Prepared Ground Surface: Ground surface after completion of required clearing and grubbing.
78. Punch List: List of construction items to be completed and/or corrected, prepared by
Contractor or NPS.
79. QAPP: Quality Assurance Project Plan.
80. RCRA: Resource Conservation and Recovery Act.
81. RAO: Removal Action Objective.
82. RACR: Removal Action Completion Report.
83. Contractor’s Removal Action Plan: Planning documents prepared by the Contractor, including, but not limited to, Removal Action Schedule, construction drawings, SWPPP, Decontamination Plan, HASP, SAP, and QAPP.
84. Removal Action Schedule: Contractor’s schedule, reviewed and approved by the CO, for completing the Work.
85. RFI: Request for Information.
86. RFPP: Request for Price Proposal
87. RG: Removal Goal.
88. ROD: Record of Decision.
89. SAP: Sampling and Analysis Plan.
90. SDS: Safety Data Sheet.
91. Site: Pinhook Bog Debris Site.
92. Specifications: This package of specifications included as part of the Contract
Documents.
93. SWPPP: Stormwater Pollution Prevention Plan.
94. TSCA: Toxic Substance Control Act.
95. UL: formerly Underwriter Laboratories.
96. Wastewater: Water produced by Contractor’s operation, including groundwater removed, stormwater entering excavation pits despite controls, washdown water, used decontamination water, and other water that requires handling by Contractor to accomplish the Work. Wastewater may be hazardous or nonhazardous and shall require special handling and testing.
97. Work: the scope of work summarized in Section 01 11 00 and detailed in other specification sections and depicted on the Drawings.
EDL # 5MWR2220 SECTION 00 01 10 - 6
98. Work Area: The lateral extents of areas where on-Site work will occur, as defined in the Drawings and Specifications, plus ancillary support areas (e.g., laydown areas, stockpiles areas, access routes, etc.) to be defined in the approved Contractor’s
Removal Action Plan.
99. Work Limits: The outer extents of the Work Area, as marked by the Contractor and approved by NPS.
END OF SECTION 00 01 10
EDL # 5MWR2220 SECTION 00 01 15 - 1
6/25/2025 LIST OF DRAWING SHEETS
Non-Time Critical Removal Action
EDL # 5MWR2220
SECTION 00 01 15 – LIST OF DRAWING SHEETS
C – 1 Excavation Details
END OF SECTION 00 01 15
1ft.
1ft.
EXCAVATION
DEPTH
EXCAVATION
DEPTH
PRE-EXCAVATION
SLOPE
FINISHED
GRADE
FILL MATERIAL FROM BORROW SOURCE
CUT FROM SURROUNDING AREA
FILLED FROM SURROUNDING AREA
TYPICAL EXCAVATION
RESTORATION
EXCAVATION
DEPTH
EXCAVATION
DEPTH
EXCAVATED SOIL
TYPICAL
EXCAVATION
NATIONAL PARK SERVICE
INDIANA DUNES NATIONAL PARK PINHOOK BOG
NON-CRITICAL REMOVAL ACTION REMOVAL DESIGN
C-1 EXCAVATION DETAILS
EDL # 5MWR2220 SECTION 01 11 00 - 1
6/25/2025 SUMMARY OF WORK
Non-Time Critical Removal Action
EDL # 5MWR2220
SECTION 01 11 00 – SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of the scope of the Work, descriptions and figures depicting the areas of the Work, and general requirements.
B. Removal Action Objectives (RAO) and Removal Goals (RG)
1. RAOs define what the removal action is intended to accomplish; to that end, the specific RAOs for the Debris Site in the Pinhook Bog Unit of the Indiana Dunes
National Park (INDU) are identified in the EE/CA and Action Memorandum and include the following:
a. The selected removal action will remove or contain contaminated soil exceeding the RG and associated debris for any contaminants of concern (COC) so that the cleanup allows for unrestricted use/unrestricted exposure.
b. Follow the Voluntary Remediation Program (IC 13-25-5) Remediation Closure
Guide and State Cleanup Program (IC 13-19, 22, 25) to allow for unrestricted use/unrestricted exposure.
2. Specific RGs for the Site were also developed in the EE/CA, identified in the Action
Memorandum, and are presented in Tables 1-3 as the Confirmation Sampling Action
Levels.
3. The Work will comply with NPS Management Policies Concerning Waste
Management and Contaminant Issues:
a. 2006 NPS MP §9.1.6.1.
b. 2006 NPS MP §9.1.6.2.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Indiana Dunes National Park (INDU), Pinhook Bog Debris Site, Michigan City, IN.
B. The Work Area (Figure 3) includes:
1. Excavation A (Figure 4):
a. Area 1 (Southwest Area) includes approximately 150 cubic yards (CY) of I-beams, concrete, and guardrails. No contamination was identified at this location.
b. Area 2 (Southwest Area) includes approximately 86 CY of concrete blocks with rebar. No contamination was identified at this location.
EDL # 5MWR2220 SECTION 01 11 00 - 2
c. Area 3 (Southwest Area) includes approximately 900 CY of concrete blocks, concrete and asphalt rubble, guardrails, and tires. Soil contamination was identified and included benzo(a)pyrene, dibenz(a,h)anthracene, Aroclor 1254, Aroclor 1260, arsenic, barium, cadmium, chromium, lead, mercury, and selenium.
d. Area 4 (Southwest Area) includes approximately 10 CY of concrete rubble. No contamination was identified at this location.
2. Excavation B (Figure 5):
a. Area 5 (Central Area) includes approximately 300 CY of concrete rubble, general metal objects, surface burn piles, car parts, and appliance parts. Soil contamination was identified and included benzo(a)pyrene, dibenz(a,h)anthracene, Aroclor 1254, Aroclor 1260, arsenic, barium, cadmium, chromium, lead, mercury, and selenium.
b. Area 6 (Central Area) includes approximately 4 CY of concrete rubble, general metal objects, surface burn piles, car parts, and appliance parts. Soil contamination was identified and included arsenic, chromium, and lead.
3. Excavation C (Figure 6).
a. Area 7 (Northeast Area) includes approximately 315 CY of concrete rubble, general metal objects, surface burn piles, car parts, and appliance parts. Soil contamination was identified and included chromium and lead.
C. The Work consists of:
1. Contractor’s Removal Action Plan preparation, as defined in Section 01 31 00, to include, but not limited to:
a. Identification of key personnel and subcontractors.
b. Contractor’s construction drawings, if applicable.
c. Removal Action Schedule.
d. Decontamination Plan.
e. Waste Management Plan.
f. Site-Specific Health and Safety Plan (HASP).
g. Stormwater Pollution and Prevention Plan (SWPPP).
h. Confirmatory Sampling and Analysis Plan (SAP) and Quality Assurance Project
Plan (QAPP)
i. Fugitive Dust Mitigation Plan.
2. General phases of the Work:
a. Collect in-situ confirmation samples and in-situ waste characterization samples.
b. Install and maintain erosion and sedimentation controls in accordance with an approved SWPPP.
c. Establish support areas as required by the Specifications, defined in the approved
SWPPP, and approved by NPS.
d. Stake out horizontal extents of excavation for approval by NPS and establish vertical control necessary to achieve and verify excavation depths.
e. Clear brush and trees, as required, within excavation and support areas in accordance with Section 31 10 00. Chip clearing debris and stockpile in areas approved by NPS.
f. Excavate, load, transport, and dispose of soil and debris at an approved facility.
g. Keep the excavation open and dry until vertical and horizontal excavation limits are approved by NPS, based on results of confirmation sampling.
h. Backfill excavations in accordance with Section 31 23 23.
EDL # 5MWR2220 SECTION 01 11 00 - 3
i. Maintain erosion and sedimentation controls until vegetation is established.
Remove erosion and sedimentation controls once vegetation is established.
Vegetation will be reestablished in a separate Contract.
1.3 WORK UNDER OTHER CONTRACTS (Not Used)
1.4 NPS-FURNISHED MATERIALS
A. In case of NPS -furnished fill materials:
1. NPS will furnish fill material from a borrow source area identified by NPS located on one of the INDU National Park properties at no charge to the Contractor. NPS has identified the southwest corner of the Project Site, the golden rod field, as the likely borrow source for this Project (Figure 3). NPS will confirm the borrow source prior to mobilization.
2. Contractor is responsible for excavating from the borrow source identified by NPS, loading, transporting from the borrow source to the Work Site, unloading, handling, and placing NPS-furnished backfill at the Work Site. NPS will provide weed management details once a borrow source has been confirmed.
3. Contractor shall implement the Clean Fill Protocol for Contaminated Sites for fill material from a borrow source, including sources on NPS property.
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of Site for removal action operations. Limit use of premises to excavation areas, haul roads, and staging areas indicated on drawings. Do not disturb portions of Site beyond areas in which the Work is indicated.
B. Storage and staging of Materials: Confine storage and staging of materials to areas designated in the approved Contractor’s Removal Action Plan.
C. Parking: Confine parking to areas designated by NPS during the Pre-Mobilization Conference. Do not block Park roads.
D. Preservation of Natural Features and Cultural Resources:
1. Comply with the following:
a. NPS restrictions of public use and recreation activities to protect natural park resources: 36 CFR 2.
b. NPS restrictions of commercial and private operations in national parks, including the prohibition of nuisances: 36 CFR 5, 36 CFR 5.13.
c. 2006 NPS Management Policies: 2006 NPS MP §4.0 and §9.1.3.
d. INDU Superintendent’s Compendium (2024)
(https://www.nps.gov/indu/learn/management/compendium.htm).
2. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants outside Work Areas, at no additional expense to
NPS.
3. Avoid removing trees over 6 inches in diameter within excavation areas and when constructing the temporary haul road. It may be necessary to alter the temporary haul https://www.nps.gov/indu/learn/management/compendium.htm
EDL # 5MWR2220 SECTION 01 11 00 - 4
road path to avoid trees over 6 inches in diameter. When not possible, trees over
6 inches must be marked and a determination made by NPS Resource Management staff to approve removals.
4. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and Contracting Officer’s Representative (COR) prior to removal of roots and branches that interfere with the Work.
5. Do not fasten ropes, cables, or guys to existing trees outside Work Areas.
6. Carefully supervise trucking, equipment moving, and other removal action operations near trees, plants, and cultural resources identified by NPS outside Work Areas to prevent damage. Utilize timber mats in vehicle traffic areas to minimize ground disturbance during removal activities. Refer to Section 01 50 00 for details about temporary roads and Section 31 10 00 for details about safely clearing the Site.
E. Driveways and entrances: Keep driveways, Park roads, and entrances serving the Park clear and available to NPS employees and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule trucks and/or shipments to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment onsite.
F. Construction Camp: Establishment of a camp within the Park will not be permitted. Contractor employees may use Park campgrounds subject to the same rules as the visiting public.
G. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on Park roads are identical to Territory or State load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on Park roads may be obtained from the Office of the Park Superintendent or by searching for the Compendium at the Park’s website. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
H. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
1.6 PUBLIC USE OF SITE
A. The designated work areas will be closed to the public during removal action. The Pinhook Bog parking area and upland trails located north of the designated haul roads will remain open during removal action activities.
B. Contractor shall conduct their operations to ensure the least inconvenience to public. Parking area or trail closures may be permitted, when required, upon specific approval of CO for a maximum of 5 days. Parking area or trail closures should not include weekends or any days that work is not actively being conducted.
1.7 CONDUCT OF OPERATIONS
A. Contractor shall conduct their operations as discussed with NPS and the Park during project meetings and in conformance with rules and regulations promulgated by the Secretary of the
EDL # 5MWR2220 SECTION 01 11 00 - 5
Interior for the National Park Service, and applicable Park rules and regulations prescribed by Park Superintendent in the annual Compendium.
B. No signs or advertisements (except those specified herein) shall be displayed on the Site or within the Park unless approved by the CO.
1.8 WORK RESTRICTIONS
A. Onsite Work Hours: Work shall be generally performed during daylight hours, Monday through Friday, except when otherwise indicated. See 1.8B for work on federal holidays.
1. Work involving tree clearing (3-inch DBH or larger) may only take place between October 1 and March 31 to protect endangered bat species. See Section 31 10 00 for additional information.
B. Work on weekends or Federal holidays is discouraged and shall not be performed unless the NPS CO approves it in advance. The Contractor shall seek CO approval for weekend and/or holiday Work at least 4 workdays in advance.
C. Work during Adverse Weather: For the protection of Natural Resources, Work will not be conducted during adverse weather without prior approval from Contracting Officer. Requests to conduct onsite work during adverse weather will be made at least 4 workdays in advance.
D. Existing Utilities:
1. Prior to intrusive activities at the Site, the Contractor shall locate and mark utilities within the Work Area.
2. Existing Utilities: If utilities are observed within excavation areas, notify the CO before proceeding with excavation.
3. Contractor shall be responsible for locating and preventing damage to known utilities.
If damage occurs, repair utility at no additional expense to the NPS.
4. If damage occurs to an unknown utility, notify the CO, who may direct repair of the utility.
1.9 ENGINEERING EVALUATION/COST ANALYSIS REPORT AND ACTION
MEMORANDUM
A. The NPS Engineering Evaluation/Cost Analysis Report and Action Memorandum for the Site, detail the investigation results and the basis for developing RAOs and RGs, including an analysis of applicable or relevant and appropriate requirements (ARARs), and identify the selected removal action alternative.
B. In case of conflict between the text of either the Engineering Evaluation/Cost Analysis Report or
Action Memorandum and Drawings or Specifications herein, the Drawings and Specifications shall govern. The Contractor shall notify NPS as soon as possible after identifying any conflict.
EDL # 5MWR2220 SECTION 01 11 00 - 6
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
Res RSL ESV BTV Action Level
Maximum
Detection
Arsenic 0.68 6.8 13.39 13.39 8.2
Barium 1500 110 67.2 110 66.9
Cadmium 7.1 4 NE 4 0.14 J
Chromium (Total) 0.3 0.34 16.7 16.7 20.8
Lead 400 50 20.6 50 29.7
Mercury 1.1 0.05 0.106 0.106 0.023
Selenium 39 0.52 NE 0.52 0.088
Silver 39 2 NE 2 0.32
Acenaphthylene 1800 NE NE 1800 0.0426 U
Anthracene 1800 6.8 NE 6.8 0.12
Benzo(a)anthracene 1.1 18 NE 1.1 0.701
Benzo(a)pyrene 0.11 NE NE 0.11 0.792
Benzo(b)fluoranthene 1.1 18 NE 1.1 1.1
Benzo(g,h,i)perylene 180 NE NE 180 1
Benzo(k)fluoranthene 11 NE NE 11 0.895
Chrysene 110 NE NE 110 0.995
Dibenz(a,h)anthracene 0.11 NE NE 0.11 0.218
Fluoranthene 240 10 NE 10 1.62
Indeno(1,2,3-cd)pyrene 1.1 NE NE 1.1 0.705
Naphthalene 3.8 1 NE 1 0.0476 U
Phenanthrene 180 5.5 NE 5.5 0.352
Pyrene 180 10 NE 10 1.56
Table 1 - Confirmation Sampling Action Levels for Excavation A
Pinhoook Bog Debris Site
Maximum Detection is from 2015 SIR at sample depth 0-1 foot
Maximum Detection is greater than Action Level
U - Not detected
J - Estimated concentration above the adjusted method detection limit and below the adjusted reporting limit.
Metals (mg/kg)
PAHs (mg/kg)
Res RSL - Residential regional screening level for soil (June 2017)
ESV - National Park Service ecological screening value
BTV - Site specific background threshold value
Notes:
Res RSL ESV BTV Action Level
Maximum
Detection
Arsenic 0.68 6.8 13.39 13.39 77.0
Barium 1500 110 67.2 110 1670
Cadmium 7.1 4 NE 4 28.9
Chromium (Total) 0.3 0.34 16.7 16.7 67.6
Lead 400 50 20.6 50 2800
Mercury 1.1 0.05 0.106 0.106 8.6
Selenium 39 0.52 NE 0.52 3.6
Silver 39 2 NE 2 3.8 U,D3
Acenaphthylene 1800 NE NE 1800 0.3090
Anthracene 1800 6.8 NE 6.8 0.3100
Benzo(a)anthracene 1.1 18 NE 1.1 0.8560
Benzo(a)pyrene 0.11 NE NE 0.11 0.8590
Benzo(b)fluoranthene 1.1 18 NE 1.1 0.8450
Benzo(g,h,i)perylene 180 NE NE 180 0.7790
Benzo(k)fluoranthene 11 NE NE 11 0.3890
Chrysene 110 NE NE 110 0.9230
Dibenz(a,h)anthracene 0.11 NE NE 0.11 0.1620
Fluoranthene 240 10 NE 10 1.7400
Indeno(1,2,3-cd)pyrene 1.1 NE NE 1.1 0.3900
Naphthalene 3.8 1 NE 1 0.0507 U
Phenanthrene 180 5.5 NE 5.5 0.3900
Pyrene 180 10 NE 10 1.4100
Aroclor 1016 0.41 NE NE 0.41 0.0609 U
Aroclor 1221 0.2 NE NE 0.2 0.0609 U
Aroclor 1232 0.17 NE NE 0.17 0.0609 U
Aroclor 1242 0.23 NE NE 0.23 0.0609 U
Aroclor 1248 0.23 160 NE 0.23 0.0618 J
Aroclor 1254 0.12 NE NE 0.12 0.232
Aroclor 1260 0.24 NE NE 0.24 0.589
Table 2 - Confirmation Sampling Action Levels for Excavation B
Pinhoook Bog Debris Site
ESV - National Park Service ecological screening value
BTV - Site specific background threshold value
Notes:
Metals (mg/kg)
PAHs (mg/kg)
PCBs
Res RSL - Residential regional screening level for soil (June 2017)
Maximum Detection is from 2015 SIR at sample depth 0-1 foot
Maximum Detection is greater than Action Level
U - Not detected
D3 - Sample was diluted due to the presence of high levels of non-target analytes or other matrix interference.
J - Estimated concentration above the adjusted method detection limit and below the adjusted reporting limit.
Res RSL ESV BTV Action Level Maximum Detection
Arsenic 0.68 6.8 13.39 13.39 12.6
Barium 1500 110 67.2 110 86.2
Cadmium 7.1 4 NE 4 0.714 U
Chromium (Total) 0.3 0.34 16.7 16.7 18.4
Lead 400 50 20.6 50 65.6
Mercury 1.1 0.05 0.106 0.106 0.0303
Selenium 39 0.52 NE 0.52 2.85 U
Silver 39 2 NE 2 1.43 U
Table 3 - Confirmation Sampling Action Levels for Excavation C
Pinhoook Bog Debris Site
Maximum Detection is from 2017 Expanded SIR at sample depth 0-2 foot
Maximum Detection is greater than Action Level
Metals (mg/kg)
U - Not detected
Notes:
Res RSL - Residential regional screening level for soil (June 2017)
ESV - National Park Service ecological screening value
BTV - Site specific background threshold value
Excavation Area
Estimated Area
Contaminated Soil
(SF)
Minimum
Excavation Depth
(feet)
Estimated Soil and
Debris Removal Volume
Below Surface (CY)
Estimated Percent of Area Covered with Debris1
Average Debris
Height Above
Ground (feet)2
Estimated Debris
Removal Above
Surface (CY)
Estimated Total
Volume to be
Removed (CY)
Excavation A 5,249 1 194 70% 2 272 467
Excavation B 20,495 1 759 10% 1 76 835
Excavation C 5,999 2 444 10% 1 22 467
Totals 31,743 1,398 370 1,768
Notes:
SF - square feet Estimated excavation surface areas may increase or decrease after confirmation sampling is complete. The excavation depth is a minimum and may increase after confirmation sampling is complete.
Table 4 - Excavation Volume Estimates
Pinhoook Bog Debris Site
1Modified from EE/CA Table 4-1 2Estimated from site walk
CY - cubic yards
EDL # 5MWR2220 SECTION 01 26 01 - 1
6/25/2025 CONTRACT MODIFICATION PROCEDURES
Non-Time Critical Removal Action
EDL # 5MWR2220
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a Contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent.
2. Utilities.
3. Furnishings.
4. Office equipment.
5. Executive and management staff not exclusively assigned to the Project.
6. Support, accounting, and administrative staff.
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications.
8. Estimating and preconstruction services.
9. Mortgage costs.
10. Real estate and corporate taxes.
11. Automobile maintenance and travel costs for home office personnel.
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets.
14. Home office supplies (paper, staples, etc.).
15. Legal services.
16. Accounting and data processing.
17. Professional fees/registration.
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on
Site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating
General Conditions:
1. Project Manager (PM), Assistant Project Manager.
2. Superintendent, Assistant Superintendent.
3. Quality Control, Safety Officer, Environmental Manager, etc.
EDL # 5MWR2220 SECTION 01 26 01 - 2
4. Engineers.
5. Geologists, Archeologists, Biologists, etc.
6. Travel, lodging, and per diem (as established by Federal Travel Regulations).
7. Scheduling.
8. Field Office Trailers and associated temporary utilities.
9. Field office supplies:
a. Mailing and couriers.
b. Reproduction costs.
c. Storage.
d. Phones.
e. Computers.
f. Copiers.
10. Personal vehicles i.e., Superintendent Pickup trucks.
C. General Requirements: Costs that are directly associated with the project and that are necessary to perform the actual Work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General
Requirements:
1. Hoisting.
2. Material handling.
3. Temporary fencing.
4. Portable toilets.
5. Trash removal, dumpsters.
6. Barricades.
7. Small tools.
8. Safety supplies.
9. Daily cleaning.
10. Traffic control.
11. Temporary signage.
12. Temporary heating and power.
13. Decontamination facilities.
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the Project Site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker.
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security.
2) Medicare.
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
EDL # 5MWR2220 SECTION 01 26 01 - 3
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums.
2) Cell Phone.
3) Clothing.
4) 401K and Pensions.
5) Vehicle allowances.
6) Gas allowance.
7) Life insurance premiums.
8) Disability insurance.
9) Other Fringe Benefits required under an enforceable collective bargaining agreement.
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a Project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for an individual project based on a sliding scale related to the size of the Project. Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal shall be received in the format and within the time frame specified in the
Request for Price Proposal (RFPP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains generally the same information and level of detail as the Government’s form.
http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|
EDL # 5MWR2220 SECTION 01 26 01 - 4
3. Requests for extensions of contract time as a result of change must be justified.
Contractor’s failure to submit within the specified time frame will be construed as the
Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the CO upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification Work. Any Work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Construction Wage Rates Requirements Statute (CWRRS) as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related Work required for the modification.
C. Materials:
1. Estimated cost for materials shall be based on quotes from multiple sources, to be provided to the CO on request. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the Project must be appropriately sized for Work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating
Expense Schedule (use latest edition and applicable region).
b. Construction Blue Book.
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, EDL # 5MWR2220 SECTION 01 26 01 - 5 storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification Work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish Work of the modification.
6. Equipment not used and on the Site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform Work on the modification and will be necessary to complete additional modification Work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
7. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S.
Army Corps of Engineers Ownership and Operating Expense Schedule is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
8. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
9. Requests for compensation for equipment standby time must be justified, documented, and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this Project. Negotiated rates shall generally not exceed the following percentages for OH&P for contractor self-performed Work:
Overhead………………10%
Profit………….....……10%
2. Total aggregate limit of markup (OH&P) for Contractor and subcontractors on modification Work shall not exceed 20 percent. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3.E.1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of Work only.
EDL # 5MWR2220 SECTION 01 26 01 - 6
PART 2 - PRODUCTS – NOT USED
PART 3 - EXECUTION – NOT USED
END OF SECTION 01 26 01
EDL # 5MWR2220 SECTION 01 27 00 - 1
6/25/2025 DEFINITION OF CONTRACT LINE ITEMS
Non-Time Critical Removal Action
EDL # 5MWR2220
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item (CLIN), and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS (CLINs)
A. CLIN 1 – Project Support Tasks:
1. This item includes tasks and documentation listed herein, including preparation and submittal of the post-award planning documents defined in Section 01 31 00 and all activities not listed separately below, such as initial site visit, project management and oversight, subcontractor management, writing daily and monthly progress reports, preparing and maintaining project schedules, bonds, insurance, progress meetings, preparing excavation plan, surveying of final excavation limits and elevations as described in Section 02 21 02, surveying backfilled elevations and finished grades as described in Section 02 21 02, preparing project record drawings, preparing archeological monitoring permits and reports as defined in Section 01 35 13.22, preparing the Removal Action Completion Report, including all necessary tables, figures, appendices, and supporting documentation as defined in Section 01 77 00 paragraph 1.3A(4).
2. Costs associated with the on-site supervision of remaining CLINs shall be included in their prices, not in CLIN 1.
3. Measurement for payment will be lump sum. No separate measurement will be made.
4. Payment will be made at the contract lump sum price.
B. CLIN 2 – Pre-Characterization Plan, Sampling, and Report:
1. This item consists of all equipment, materials, expenses, and effort necessary to prepare the Pre-Characterization Sampling Plan and collect pre-characterization soil samples for the purpose of waste characterization prior to the start of excavation activities in accordance with the requirements for the Pre-Characterization Sampling
EDL # 5MWR2220 SECTION 01 27 00 - 2
Plan defined in Section 02 24 23, paragraph 1.4A. Based upon the contractor’s timing of sampling and methods for sample collection, ecological surveys or other requirements identified in the technical specifications may apply and, if needed, will be included in this line item. This item also includes the preparation of the Pre-
Characterization Sampling Report as defined in Section 02 24 23, paragraph 1.4B.
2. Measurement for payment for CLIN 2A will be lump sum for preparation of the Pre-
Characterization Plan and Report.
3. Measurement for payment for CLIN 2B will be unit rate based upon the number of unique pre-characterization samples required. The unit rate should include all costs to collect and analyze pre-characterization samples and any incremental costs associated with data validation or reporting that are affected by the number of samples collected.
Additionally, the cost to collect, analyze and report quality control samples (i.e., necessary blanks, duplicate, or matrix spike/matrix spike duplicate samples) should be included in the unit rate per unique pre-characterization sample.
4. Payment will be made at the contract lump sum price (CLIN 2A) plus price per soil sample subject to the Variation in Estimated Quantity clause (CLIN 2B).
C. CLIN 3 – Confirmation Soil Sampling:
1. This item consists of all equipment, materials, expenses, and effort necessary to prepare the Confirmation Sampling Plan and collect confirmation soil samples per the
Confirmation Sampling Plan defined in Section 02 24 23, paragraph 1.4C.
Confirmation Soil Sampling may be conducted in situ prior to excavation activities to facilitate planning and scheduling or may be collected from the open excavation.
Depending on timing of sampling and methods for sample collection, ecological surveys or other requirements identified in the technical specifications may apply and, if needed, will be included in this line item. This item also includes the preparation of the Confirmation Sampling Report as defined in Section 02 24 23, paragraph 1.4E.
2. Measurement for payment for CLIN 3A will be lump sum for the preparation of the
Confirmation Sampling Plan and Report.
3. Measurement for payment for CLIN 3B will be unit rate based upon the number of unique confirmation samples required. The unit rate should include all costs to collect and analyze confirmation samples and any incremental costs associated with data validation or reporting that are affected by the number of samples collected, including the preparation of Interim Sampling Summaries for NPS review and concurrence as defined in Section 02 24 23 paragraph 1.4D. Additionally, the cost to collect, analyze and report quality control samples (i.e., necessary blanks, duplicate, or matrix spik/matrix spike duplicate samples) should be included in the unit rate per unique confirmation sample.
4. Payment will be made at the contract lump sum price (CLIN 3A) plus price per soil sample subject to the Variation in Estimated Quantity clause (CLIN 3B).
D. CLIN 4 – Non-Removal Site Activities:
1. This item consists of all equipment, materials, expenses, and effort necessary to lay out, flag, and/or stake the excavation areas, access roads, haul roads, and staging areas, install temporary facilities and controls as defined in Section 01 50 00, install, maintain, and remove temporary environmental controls as defined in Section 01 57
19, complete site clearing per Section 31 10…
This is the start of the file's text. The full file is on GovTribe.