This is a Performance Work Statement for repacking a Peerless 5AEF11G 1000 GPM Fire Pump at Jesse Brown VA Medical Center in Chicago, Illinois. The contractor must replace failing packing around the main fire pump in the Bed Tower to comply with local fire codes and regulatory requirements. Work must commence within 14 calendar days of contract award and be completed within 14 calendar days of start, with all labor, tools, materials, and travel supplied by the contractor.
The detailed scope includes removing existing packing, inspecting the stuffing box, gland, and shaft sleeve for wear, furnishing and installing a replacement shaft sleeve if required (with costs included in the quote), thoroughly cleaning the stuffing box, repacking using like or approved materials, visually inspecting the unit, manually rotating the shaft to ensure free rotation, performing all work during regular business hours (7 a.m. to 5 p.m.), conducting daily cleanup, and enabling pump operation with final visual inspection to verify no leaks or issues. The contractor must comply with NFPA 99, OSHA, Joint Commission, VA, UL, NEC, state and local regulations, and manufacturer standards. Personnel must meet qualifications under NFPA 20, NFPA 25, and NFPA 72 for fire pump and fire prevention system work. Additional requirements include coordinating the schedule with the facility's Electric Shop supervisor, checking in at the hospital front desk, obtaining written approval from the Contracting Officer Representative to modify work hours, performing disruptive work between 6 p.m. and 6 a.m., requesting system shutdowns at least 14 calendar days in advance, and avoiding work on national and federal holidays. Final inspection and checkout with the Contracting Officer Representative is required upon completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| 36C25226Q0689 0001 SAM.gov.pdf | ||
| Attachment 2 Peerless Pump Image.pdf | ||
| Attachment 3 Name Plate Image.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
for Repacking Fire Pump
Place of Performance:
Jesse Brown VA Medical Center 820 S. Damen Ave Chicago, IL 60612
Project Objective: The purpose of this project is to perform a repack on the Peerless 5AEF11G 1000 GPM Fire Pump in the main fire pump room of the Bed Tower as required by local fire codes and regulatory authorities to ensure the fire system functions properly in event of an emergency. Contractor shall supply all labor, tools, materials and travel to and from worksite.
Current Conditions/Background: The packing around the fire pump is failing. This packing prevents leaking and helps maintain proper pressure and flow rate to the pump. It provides cooling by carrying heat away that’s generated by friction between the shaft and seal and prevents the pump from overheating.
Proper packing allows for controlled leakage which keeps the shaft seal and packing gland lubricated, reducing wear and extending life of the seal.
Part 1: Project Scope of Work Overview:
Contractor shall replace the packing around the main fire pump at Jesse Brown VA Medical Center.
Part 2: Period of Performance (POP) and Project Construction Cost Magnitude:
Contractor shall commence work within 14 calendar days after contract award and complete work within 14 calendar days of commencement.
Part 3: Detailed Project Scope of Work:
1. Remove existing packing, as required.
2. Inspect stuffing box, gland, and shaft sleeve surface for excessive wear. If the shaft sleeve is determined to require replacement, the Contractor shall furnish and install a replacement shaft sleeve as part of the work required under this contract. The cost of any required shaft sleeve replacement shall be included in the Contractor’s quote.
3. Clean stuffing box thoroughly.
4. Repack fire pump using like or approved materials.
5. Visually inspect unit.
6. Manually rotate shaft to ensure free rotation prior to restoring to service.
7. Perform all work during regular business hours – 7a-5p.
8. Perform daily clean-up of work areas.
9. Enable pump operation and conduct visual inspection to ensure no leaks or issues.
Part 4: Applicable Performance Standards/Contractor Qualifications Contractor shall ensure that the equipment functions in conformance with the latest published edition of NFPA 99, OSHA, Joint Commission, VA, UL, NEC, state and local regulations. The equipment covered under this contract shall be maintained in accordance with the manufacturer's standards/specifications. Contractor must be qualified to perform work on the fire pump/fire prevention system per NFPA 72. Personnel must meet qualification requirements under NFPA 20 and NFPA 25 in addition to any relevant signaling interfaces.
Part 5: Jesse Brown VAMC Additional Requirements Comply with all Jesse Brown VAMC site specific requirements and Standard Operating Procedures including and not limited to: Key Policy, Badging Policy, Rules of Behavior, Lockout tag out, and Smoking Policy.
a. Schedule should be coordinated prior to arrival with Electric Shop supervisor or Chief, Maintenance and Operations.
b. Contractor shall check in at hospital front desk and notify contract POC prior to start of work.
c. Normal work hours can be modified only by written approval of the Contracting Officer
Representative (COR).
d. Any work including and not limited to: noise, vibration, dust, odors, core drilling, hammer drilling, saw cutting, equipment moving in public corridors, soil compaction shall performed between 6:00 pm through midnight concluding by 6:00 am on the following day.
e. Request system shutdowns not less than 14 calendar days in advance.
f. Government Furnished Property: Main fire pump in Bed Tower Fire Pump Room
g. Recognized Holidays: Contractor performs on no national or federal holidays.
h. Facility Check-in and Out/Inspection: Contractor shall check out with COR once work is completed for final inspection.
| Part 1: Project Scope of Work Overview: |
| Part 2: Period of Performance (POP) and Project Construction Cost Magnitude: |
| Part 3: Detailed Project Scope of Work: |