Attachment 1 - PWS Repair Concrete Basewide.pdf
PDF 1 MB Posted
- Attached to
- Repair Concrete Base-wide, 126 ARW, Scott AFB
- Solicitation number
- W50S7S26Q0013
- Issued by
-
Department of the Army National Guard
About this file
This is a Performance Work Statement (PWS) for concrete repair and site improvement work at Scott Air Force Base, Illinois, under VDYD 262008, dated 29 May 2026.
The project encompasses five contract line items (CLINs): (1) sidewalk repairs involving removal and replacement of 350 square yards of cracked concrete sidewalk across multiple areas; (2) replacement of seven trench drains with damaged grates and surrounding cracked concrete at Building 5006, including flow testing and installation of Neenah Foundry R-4996-A1 grated cover trench drains or approved equal; (3) removal and replacement of a damaged concrete pad at POL Building 5036 with compaction testing, dowel bars, and ADA-compliant slopes; (4) removal of a vehicle ramp, installation of a new concrete foundation designed to support 50,000 lbs live load, and ramp reinstallation at Building 5006; and (5) construction of an ADA-compliant ramp and sidewalk at the parking lot north of Building 5010, including 4-inch minimum concrete thickness with 4,000 PSI strength, #4 rebar reinforcement, 1:12 maximum running slope, 36-inch minimum width, and detectable warning surface. All concrete work requires non-slip broom finish, expansion joints where applicable, and slump testing prior to placement. The contractor must conduct site verification, coordinate utility locates and dig permits, perform compressive strength testing at 7 and 28 days, and maintain as-built documentation. Work is restricted to standard hours (7:30 A.M. to 4:30 P.M., Monday through Friday, excluding federal holidays), with coordination required through 126th Civil Engineer Squadron. The contractor must submit a proposed performance period for government negotiation, provide detailed construction milestones and 2-week look-ahead schedules, and comply with UFC, NFPA, NEC, and local/federal regulations including OSHA requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FOR
Repair, Concrete Basewide
VDYD 262008
SCOTT AIR FORCE BASE, ILLINOIS
29 May 2026
1. REQUIREMENT:
a. BACKGROUND: There are several locations on the grounds where concrete sidewalks are cracked to an extent requiring removal and replacement. In the Vehicle Refueling Building 5006, there are seven (7) trench drains that have damaged grates and cracked and spalling concrete surrounding them. Additionally, in front of the POL Building 5036, the concrete pad has damage from heaving resulting in a full depth crack across its width.
At the Vehicle Refueling Building 5006, the vehicle ramp immediately north of thebuilding, has been pressed into the asphalt pavement from regular use bearing the weight of vehicles during maintenance work,. There are four 2 IN to 3 IN deep impressions where the 1FT X 1FT plates supporting the four stands bracing the level section of the ramp have pressed into the pavement. Lastly, north of Building 5010 an ADA Ramp is needed to transition between the parking lot to the adjacent sidewalk.
b. OBJECTIVES: The project objectives are as follows:
i. Correct existing cracked and failing concrete walkway paths by replacing damaged concrete panels.
ii. Replace damaged trench drains with new approved trench drain systems connecting to the existing drain piping.
iii. Replace concrete pad in front of Building 5036.
iv. Place new concrete foundation for the vehicle ramp immediately north of the Vehicle
Refueling Building 5006.
v. ADA Ramp added to parking lot north of Building 5010.
c. PROJECT LOCATION: All work will be within the 126th Air Refueling Wing (area).
Specific buildings where work will take place under this scope are Buildings 5006, 5008, 5010 and 5036 at Scott AFB, Illinois.
2. PROJECT ADMINISTRATION:
a. SITE VISIT: Contractor is responsible to verify all measurements and conditions pre-bid.
The Government intends to only hold one official site visit. Requests for additional site access must go through the 126th Contracting Squadron (126 CONS) point of contact (POC) listed in the Request for Proposal (RFP) letter. Any additional site access will be made available to all Contractors solicited for this project.
b. MEETINGS
i. Kick-Off Meeting/Project Schedule – Kick-off meeting to occur within one week of NTP. Overall project schedule with milestone markers and 2-week look-ahead to be completed at kick-off meeting.
ii. Contractor shall coordinate with the 126th Contracting Squadron (126 CONS) on bi-weekly meetings once the construction phase begins. This meeting shall include the review of an updated 2-week look ahead schedule. Contractor shall provide meeting minutes within 24 hours of each meeting and allow the Government up to 24 hours to accept or request changes to the minutes.
3. PROJECT SCOPE:
a. BASE BID CLIN 001: Sidewalk Repairs i.
ii. Contractor shall break and remove 350 SY total of concrete sidewalk. See highlighted images above and table of estimated areas of sidewalk to be replaced and repaired below.
Sidewalk Restoration
Area
Area (SF) Area (SY)
1 93 0 4-0 85 9 4-1 85 9 4-2 275 31 4-3 317 35 4-4 75 8 4-5 175 19 4-6 108 12 4-8 76 8 4-9 231 26
12-5 441 49 13 324 36 14 74 8
iii. Sidewalk removal to include removal of existing base rock.
iv. The contractor shall prepare the subgrade to ensure a stable and compacted base suitable for new concrete placement.
v. Contractor shall place base rock on subgrade. Ensure there are no soft spots, frozen areas, or standing water. Contractor to place base rock so that the surface of the rock is level providing positive drainage away from building structures. Add and compact a minimum 4” aggregate base course (or match existing thickness if greater).
vi. Contractor to install expansion joint material between existing concrete and newly placed concrete.
vii. The contractor shall form, place, and finish new cast-in-place concrete sidewalk butting up to the existing sidewalk. The completed work shall meet the following requirements:
(a) Concrete: All new concrete shall have a minimum thickness of 4 inches and a minimum 28-day compressive strength of 4,000 PSI. The surface shall have a non-slip broom finish.
viii. Apply/spray concrete cure.
ix. Site Restoration
(1) Upon completion of the concrete work and after the required curing period, the contractor shall remove all forms and construction materials. The contractor shall restore all adjacent areas disturbed by construction activities to their original condition. This includes, but is not limited to, grading and seeding any damaged landscape areas.
b. (CLIN 002): Replace Trench Drains and Surrounding Cracked Concrete
i. Conduct site inspection to verify site conditions. Contractor to coordinate all utility locates and dig permits. See the marked-up plan sheet A9.1 Floor Pattern and Equipment Plan in Exhibit A7.
ii. Contractor to perform flow test from trench drain connections to downstream observation points including Oil and Gas or Paint separators to verify the discharge pipes function properly prior to start of construction.
iii. Contractor shall sawcut at 1 ft offset from the perimeter of the trench drains.
iv. Contractor will remove the existing 8” thick concrete pavement around the trench drains leaving the rebar in place
v. Contractor will remove the trench drain walls and floors as well as the anchors and angle brackets for the existing trench drain grates.
vi. Existing drain pipes and hardware/fittings from the trench drains shall be protected and repaired/replaced to maintain their function.
vii. Contractor shall be responsible for disposal of construction debris.
viii. Install new Neenah Foundry R-4996-A1 grated cover trench drains or approved equal. Ensure the drains are sloped for proper drainage to existing discharge pipe locations.
ix. Place the concrete for the removed pavement. Concrete shall be 4000 psi ILDOT mix with a finish matching the existing concrete pavement.
x. Contractor shall perform a slump test on the mix before pouring concrete.
xi. Contractor will provide compressive strength testing of two cores. One at seven (7) days and one at twenty-eight (28) days.
xii. Contractor shall perform a close-out flow test to show the newly installed trench drains and connecting discharge pipes function properly.
c. CLIN 003: Remove and Replace Concrete Sidewalk at POL Building:
i. At the west entrance to the POL Building 5036, contractor to cleanly saw-cut the full depth of the concrete joints bordering the cracked concrete panel to ensure a neat butt joint with existing pavements. Demolish and remove the damaged concrete panels (typically 4” thick). Ensure all debris is hauled away utilizing contractor-supplied dumpsters positioned at locations approved by Civil Engineering (CE).
ii. Excavate and grade the exposed subgrade to ensure a uniform foundation and positive drainage away from building structures.
iii. Contractor shall place base rock on subgrade. Ensure there are no soft spots, frozen areas, or standing water. Contractor to place base rock so that the surface of the rock is level providing positive drainage away from building structures. Add and compact a minimum 4” aggregate base course (or match existing thickness if greater).
iv. **Compaction Testing & Proof Rolling:** Perform proof rolling or density testing on the subgrade and aggregate base to identify and remediate any weak or pumping areas prior to placing forms. Moisture condition the subgrade as necessary to ensure uniform support.
v. Contractor to install smooth steel dowel bars by drilling into the building’s foundation wall to ensure long-term slab stability and prevent differential shifting.
Contractor to inject approved epoxy or use other approved means to secure dowel bars in the foundation concrete.
vi. Install rigid forms ensuring a minimum finished concrete thickness of 4”. Concrete must be poured to maintain an ADA-compliant cross-slope (maximum 1:50 or 2%) and a longitudinal slope matching the existing accessible route (maximum 1:20, or up to 1:12 if structured as an adjusted ramp). Install joint filler material between existing foundation wall and new sidewalk concrete. Apply dowel-bar-lubricant to dowel bars.
vii. Place the concrete and trowel edges. Broom finish the surface. Concrete shall be 4000 PSI IL DOT mix.
viii. Apply/spray approved concrete cure at manufacturer’s required rates.
ix. Contractor to strip and remove forms as well as all construction material and debris from the project site.
x. Contractor shall repair any ruts in the construction area with clean topsoil and replant disturbed grassy areas with IDOT seed mix class 1B with mulch method 2.
d. CLIN 004: Remove Vehicle Ramp, Install Foundation Concrete and Reinstall Ramp:
i. Contractor to inspect existing ramp and pavement below north of Vehicle Refueling Building 5006.
ii. Provide a foundation design structural slab/mat or spread footing, etc. to support the ramp structure and the maximum Live Load weight of vehicles positioned on it of 50,000 lbs.
iii. Contractor to sawcut, demolish, and remove pavement, subbase and subgrade for installation of ramp foundation.
iv. Contractor shall place base rock on subgrade per approved design. Ensure there are no soft spots, frozen areas, or standing water. Contractor to place base rock so that the surface of the rock is level providing positive drainage away from building structures.
v. Contractor to install rebar per approved design.
vi. Contractor to place concrete. Broom finish the surface as called out in approved design.
vii. Apply/spray concrete cure.
viii. Following concrete cure period, Contractor shall set the vehicle ramp on the new concrete foundation.
ix. Site Restoration
(1) Upon completion of the concrete work and after the required curing period, the contractor shall remove all forms and construction materials. The contractor shall restore all adjacent areas disturbed by construction activities to their original condition. This includes, but is not limited to, grading and seeding any
e. CLIN 005: ADA Compliant Ramp and Sidewalk Installation
i. Site Demolition and Preparation
(1) The contractor shall demolish and remove the existing concrete sidewalk and curb as required to construct the new ramp. The area of demolition will be approximately 60 SF of sidewalk and 10 LF of curb. All demolition debris shall be legally disposed of off-site.
(2) The contractor shall prepare the subgrade to ensure a stable and compacted base suitable for new concrete placement.
(3) The contractor shall form, place, and finish a new cast-in-place concrete ramp that connects to the existing sidewalk. The completed work shall meet the following requirements:
(a) Concrete: All new concrete shall have a minimum thickness of 4 inches and a minimum 28-day compressive strength of 4,000 PSI. The surface shall have a non-slip broom finish.
(b) Reinforcement: All new concrete shall be reinforced with #4 rebar at 18 inches on-center each way. The rebar grid should be placed in the middle of the concrete slab's depth (~2”).
(c) Ramp Slope: The running slope of the ramp shall not exceed a 1:12 ratio.
The cross-slope shall not exceed a 1:48 ratio.
(d) Dimensions: The ramp shall have a minimum clear width of 36 inches.
(e) Landings: A level landing shall be provided at the top and bottom of the ramp. Each landing shall be a minimum of 60 inches by 60 inches.
(f) Flares: Side flares shall have a slope no greater than 10%.
(g) Detectable Warning Surface: The contractor shall install a red detectable warning surface at the base of the ramp where it meets the vehicular way.
The surface shall be a minimum of 24 inches deep and 48 inches wide.
ii. Site Restoration
(1) Upon completion of the concrete work and after the required curing period, the contractor shall remove all forms and construction materials. The contractor shall restore all adjacent areas disturbed by construction activities to their original condition. This includes, but is not limited to, grading and seeding any
4. DELIVERABLES: Contractor shall provide all material submittals to the contracting office for review using the Air Force Form 3000 (AF3000).
5. SCHEDULE:
a. Performance period: The period of performance (PoP) for this project shall be proposed by the contractor and negotiated with the government from the date that Notice to Proceed (NTP) is issued. All work must be scheduled to be complete within this timeframe. Any modifications or extensions must be requested through the 126th Civil Engineer Squadron
(126 CES) and the Contracting Officer for review and discussion. Contractor must provide construction milestones to 126 CES and the Contracting Officer.
b. Prior to beginning construction, Contractor shall provide to the CO and 126 CES construction milestones in sufficient detail to accurately identify all phases/disciplines of work to be performed.
c. Contractor shall provide general construction schedule, showing, at a minimum, the critical path items.
d. Contractor will be required to provide 2-week look ahead at each meeting described above.
e. Construction may be authorized by the Contracting Officer upon acceptance and approval of the schedule and equipment/material submittal approvals.
6. SPECIFICATIONS:
a. All work performed shall comply with all applicable UFC, NFPA, NEC and other local and federal regulations and code. This includes but is not limited to:
i. Unified Facilities Criteria (UFC) 1-200-01 General Building Requirements
ii. UFC 3-250-01 Pavement Design for Roads and Parking Areas
iii. Air Force Corporate Facilities Standards
iv. UFC 3-120-01 Design Sign Standards
v. Scott Air force Base Architectural Compatibility Guidelines
7. GENERAL CONDITIONS:
a. An alternate method can be proposed for any of the above tasks and will be reviewed.
Any alternate methods or deviations from the requested work shall be called out or highlighted in the Contractor’s proposal in a manner that is clearly identifiable. Any approved alternate methods will result in a SOW modification prior to the commencement of work. The Government will assume any additional design or construction costs associated with the approved alternatives but will not assume any costs associated with the Contractor processing this required modification.
b. A phased approach is to be used in the construction of these projects to minimize disruptions.
c. Contractor must ensure that all accesses to the building be left clear of construction materials when not on the worksite. Ensure material/tools/equipment do not hamper operations during operating hours.
d. Contractor shall supply any dumpsters required to properly dispose of any construction materials.
e. Contractor shall coordinate with CE for enter/exit points to access job site, for this facility. Contractor to coordinate with CE for location of dumpster.
f. Contractor shall site verify all dimensions and/or existing site conditions prior to the commencement of work. Commencement of work shall begin within ten (10) calendar days upon the receipt of the NTP issued by the Contracting Officer.
g. Contractor shall be completed within the agreed upon PoP as stated within the contract issued by the Contracting Officer.
h. Contractor shall be required to apply for and submit to the Contracting Officer an AF Form 103, Work Clearance Request, for all work to be accomplished under this delivery order five (5) days prior to the commencement of work. The AF Form 103 can be obtained from and approved by 126CES.
i. Contractor shall brief all Sub-Contractors on all safety and fire prevention regulations, emphasizing the requirement to obtain a daily AF Form 592, Welding, Cutting, and Brazing Permit, when welding, cutting, or brazing operations are to occur under this delivery order. The AF Form 592 can be obtained from and approved by 126CES.
j. Contractor shall complete and submit the appropriate DD Form 1354, Transfer and Acceptance of DoD Real Property to the 126CES for records. The DD Form 1354 can be obtained from 126 CES.
k. Contractor shall provide an inventory, utilizing Microsoft Excel, of all removed systems to ASTM-E1557-09 Uniformat II, Level 4 system detail. Detail data includes Facility Number, ID Number (if available); Equipment Type; Equipment Make;
Serial Number; Model; Capacity; Manufacturer; and Location. Contractor shall provide the government two copies of CD/DVD media with an electronic copy of the removed systems inventory as part of the final close out document package.
l. Contractor shall provide an inventory, utilizing Microsoft Excel, of newly installed systems to ASTM-E1557-09 Uniformat II, Level 4 system detail. Since section detail data can be recorded for equipment and non-equipment section types, some of the data elements may not apply to component-sections. The Contractor must provide section detail data for those data elements that do apply (see Attachment 4).
i. Section detail data includes Facility Number; Level 2 Group Element (System) Description; Level 3 Individual Element (Component) Description; Level 4 Sub-Element (Section) Description; Sub-Element Description; Equipment Type; Equipment Make; Serial Number; Model; Capacity; Manufacturer;
Warranty Company; Warranty Expiration Date; Location; Date Manufactured; Control Type/Make and Year Installed.
ii. Contractor shall provide the government two copies of CD/DVD media with an electronic copy of the installed systems inventory as part of the final close out document package.
m. Contractor shall provide an electronic draft copy of the installed systems inventory for review and issuance of the applicable inventory ID Number and bar-code labels at least 30 days prior to O&M handover walk-through (conducted prior to contract close out).
n. Contractor shall, during construction, keep an accurate electronic record of as-built conditions, all variations from the contract drawings (that have been approved by the contracting officer or COR in writing in advance of any such variations - including those made because of the selection of optional materials), shall be clearly indicated.
These variations shall be shown in the same general detail utilized in the initial contract drawings. The as-built drawings shall be maintained in a current condition during construction. The as-built drawings shall be furnished to the Contracting Officer and 126 CES not later than ten workdays after the final inspection date. As part of the as-built drawings a separate set of plans shall be marked-up showing areas found/known to contain asbestos.
o. Contractor shall install bar-code labels on all newly installed systems, as required.
Bar-code labels must match applicable component-sections standardized on the Base.
p. All documents related to the disposal of hazardous material must be supplied to 375 CONS and 126 CES. The Contractor must obtain the proper documents from 126 CES to ensure all materials leaving Scott Air Force Base can be tracked and accounted for, in accordance with all governing laws.
q. Under the 1992 Clean Air Act, all products used in executing this project must not be related to the Class I Ozone Depleting Chemicals (ODCs) identified in Air Force Policy. The following products are considered Class I ODCs: CFC-11, CFC-12, CFC- 113, CFC-114, CFC-115, Halon 1211, Halon 1301, Halon 2402, CFC-13, CFC-111, CFC-112, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, CFC-217, Carbon tetrachloride, and Methyl Chloroform.
r. Respondents are encouraged to prioritize the utilization of utility company energy savings incentives as a key funding mechanism for the implementation of proposed projects. These incentives should be thoroughly explored and integrated into the proposed plan to maximize cost-effectiveness and ensure alignment with energy savings measures. Demonstrating a proactive approach to leveraging these incentives will be viewed favorably during the evaluation process.
s. The awardee of this solicitation will need to determine if any components of this project are eligible for the local utility companies' energy efficiency rebate/incentive program. The awardee will be responsible for preparing and submitting the application to the utilities program. New Construction/Custom applications require a preapproval from the local utility's energy efficiency program prior to placing an order for material with a vendor. The awardee is responsible for the general rules and requirements of the local utility's EE application.
8. FIELD CONDITIONS:
The Contractor shall be responsible for all field measurements to accomplish work.
Quantity and sizes of materials shall be determined from site visits and drawings. The
Contractor shall carefully examine the entire site and building and shall make all necessary investigations to become thoroughly aware of the existing conditions and all difficulties involved in the completion of the work in accordance with the contract documents.
9. ACCOMPLISHMENT OF WORK:
The work areas of the existing building will be in occupied and unoccupied areas. The Contractor must ensure that all access to the existing building always remains clear for occupants and emergency access during the construction period. All temporary closures, barriers, and protective procedures shall be coordinated with the Contracting Officer. All work shall be accomplished during the standard 8-hour day, 5-day week, Monday through Friday, between the hours of 7:30 A.M. and 4:30 P.M. local time, excluding Federal Legal holidays and nonwork days resulting from holidays occurring on weekends.
However, power outages shall be accomplished on weekends or 126ARW down days (calendar provided). The 126ARW has a compressed schedule and does have roughly two down days per month, typically on Fridays. Please reference the 126ARW calendar to coordinate the construction schedule to not work on scheduled down days unless required.
10. WORK CONDITIONS:
The Contractor shall coordinate work with the Contracting Officer, in conjunction with the User and 126 CES. The Contractor shall notify the Contracting Officer or the 126 CES inspection representative the day before he/she moves onto the work site to commence work.
The Contractor shall again provide notification the day he moves back to the work site after an interruption of work of two or more days in duration. The Contractor shall also provide an original work schedule and updates if required. This schedule shall describe major work items and projected completion dates.
11. PROTECTION OF BUILDING PROPERTY:
The Contractor shall protect from damage all building property located in or adjacent to the building and shall repair, replace, or otherwise be held liable for all such damage. Building properties include but are not limited to, furniture, vehicles, or items of supplies. Exercise control measures of all dust and toxic fumes associated with construction operations, to prevent hazards or illness to base and Contractor personnel.
12. CLEANUP:
The Contractor shall cleanup each work site at the end of each workday to the satisfaction of the Contracting Officer. Upon completion of the work, all construction equipment and debris shall be removed from the site and the area shall be left in a neat and completely acceptable condition as required by the General Provisions. Contractor must always recycle materials, such as, but not limited to cardboard and paper. The Contractor will use whatever means necessary to store all recyclable materials and is responsible for turning in recyclable materials to the Base Recycling Center.
13. PATCHING AND REPAIRING:
After the work has been completed, holes, cuts, and damages made in the finished surfaces of the work site and adjacent areas shall be properly repaired and restored to match the existing finishes. Any abrasion or disfigurement of the finish work or any portion of the building where any such abrasion or disfigurement is caused by the activities of the Contractor shall be repaired and neatly refinished to match the adjacent work to the satisfaction of the Contracting Officer. Contractor shall maintain integrity of all fire walls/barriers.
14. PRODUCTS:
All products shall conform to their respective manufacturing and performance publications.
All materials and equipment used in the work area shall be the products of manufacturers regularly engaged in the manufacture of construction products.
15. SUBMITTALS:
The Contractor shall submit for approval all items as required by other parts of these specifications. The Contracting Officer may request submittals in addition to those required by the other parts of this Statement of Work when deemed necessary to adequately describe the work. Submittals shall be made to the Contracting Officer in five (5) copies using AF Form 3000, Material Approval Submittal. In general, submittals shall be provided a minimum of thirty (30) calendar days in advance of scheduled installation to allow satisfactory time for Government review. Additionally, unless stated otherwise submissions on test results and other submissions of a similar nature shall be made within fourteen (14) calendar days after the work or test is performed. Each submittal shall be complete and in sufficient detail for ready determination of compliance with contract requirements.
Submittals shall include such items as Contractor’s or manufacturer’s shop drawings, descriptive literature, catalog cuts, samples, certifications, installation procedures and recommendations, templates, and other descriptive literature as may be required by the Contracting Officer. Catalog cuts and other descriptive data which may have more than one model or type shall be clearly marked to show the model, type, size, and all optional or accessory equipment the Contractor proposes to install. Submittals on component items forming a system or interrelated items shall be submitted at one time as a single submittal to demonstrate that the items have been properly coordinated and will function as a unit.
Approval of submittals will not relieve the Contractor of compliance with the project drawings and specifications. Submittal items that are disapproved will be promptly corrected and resubmitted by the Contractor. No materials shall be installed until submittals are approved by the Contracting Officer. All submittals involving color selections, patterns, and other decorative architectural features shall be submitted at the same time for both interior and exterior materials.
16. SPECIFICATIONS:
Work shall be performed in strict accordance with these contract general specifications, as well as all applicable local, state, and national Building and Life Safety Codes, American Society for Testing and Materials (ASTM) specifications. Safety plans and procedures issues must adhere to all applicable Occupational Safety and Health Act (OSHA) regulations.
17. PROJECT POINTS OF CONTACT:
The project points of contact for this project are:
Contracting Specialist/Officer MSgt Jonathan Middleton 126th Contracting Office P: 618-222-5112 Email:
jonathan.middleton.5@us.af.mil
Project Manager Capt Brett Luithly 126th Civil Engineer Squadron P: 618-222-4886 Cell: 260-615-5492 Email: brett.luithly@us.af.mil
Construction Inspector/Manager Mr. Larry Fuller 126th Civil Engineer Squadron P: 618-222-4889 Cell: 217-313-1023 Email: larry.fuller@us.af.mil
Real Property Manager Mr. Eric Bennett 126th Civil Engineer Squadron P: 618-222-4890 Email: eric.bennett.11@us.af.mil