Attachment 1-PWS. MCC RENO -FINAL.pdf

PDF 914 KB Posted

Attached to
MCC RENOVATION Federal contract opportunity
Solicitation number
FA557520QBB01
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

View the file

Other files for this federal contract opportunity

Other files attached to MCC RENOVATION, newest first.
File Type Posted
Attachment 4-Questions and Answers.pdf PDF
Attachment 2-ROT. MCC. RENO -FINAL.pdf PDF
Combined Synopsis Solicitation.docx DOCX document
Attachment 3 MCC Reno - Price Schedule.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

(PWS)

FOR

MCC RENO

WO: 20261

CIVIL ENGINEERING 496 ABS/CENDP

(26-06-2020)

PERFORMANCE WORK STATEMENT (PWS)

TABLE OF CONTENTS

SECTION PAGE

1. DESCRIPTION OF SERVICES 5/6

2. SERVICES SUMMARY 7

3. GOVERNMENT FURNISHED PROPERTY AND SERVICES 7

4. GENERAL INFORMATION 7/8/9

5. APPENDIX 10

1. DESCRIPTION OF SERVICES. The contractor will provide all the management, material, tools, supplies, equipment and labor needed, to accomplish the works for modify/repair the existing areas/offices from bldg.: 1411 and create new MCC RENO areas offices, see Requirements Floor plan.

1.1. Description of Work. The works includes, but is not limited to, the following items:

The Civil Work will consist:

- Repair/Update existing doors (1,2,3,4,), with new locks/panic hardware’s devices.

- Demolish existing door (7).

- Remove/Re-place existing door (6) in the space from demolished door (7).

- Install/Place new door (5), (like to existing ones) and new lock/panic hardware devices.

- Install/Place acoustic tiles(thickness:35mm²) on walls(Approx.:190m²) & low ceilings

(Approx.:110m²).

- Install/Place gypsum board(finished) on walls(Approx.:190m²).

- Repair/Paint all areas affected by the works.

- Coordinate the works with BCE & CE.

The Electrical Work will consist:

- Install/Connect new main breaker(80A) in the existing PC1 electrical panel.

- Install/Connect new power supply (conduit, wire, etc..) from new breaker to new MCC electrical panel.

- Install/Connect new MCC electrical panel (inside room 111).

- Modify existing light fixtures & new aluminum raceways installations.

- Install/connect new conduits, aluminum raceways (electrical/communications) junction boxes, etc…

- Install/Connect new wires(2.5mm²) and wires(4mm²) “in the kitchen area receptacles”.

- Install/Connect new two duplex receptacles(NEMA5-20R) by each work desk(14ea).

- Install/Connect new one duplex receptacles(NEMA5-20R) by each TVs(2ea) & by each projector(3ea).

- Install/Connect new one duplex receptacle GFCI(20A) and two duplex receptacles

(NEMA5-20R) at kitchen area.

- Install/Connect new accesses control (next to new door (5) /cameras/key-board/interior-exterior interphone/monitor.

o With interior monitor for four cameras.

o Control of the doors1, 2, 3 & 4, from interior side.

o 3 Cameras in the corridors and other one, in exterior interphone.

o 4 control key-boards form exterior side.

o 4 heavy duty lock with key & panic-hardware.

- Coordinate the works with BCE & CE.

The Communication Work will consist:

- Install/Connect new aluminum raceways(electrical/communications)/service

Colum(NIPR)(2ea).

- Install/Connect new aluminum raceways(communications)/service Colum(SIPR)(2ea).

- Install/Connect new communication cables(CAT6/shielded).

- Install/Connect new one duplex outlet(RJ45) by each work desk(14ea).

- Install/Connect new one duplex outlet(RJ45) for existing projectors (main room 2ea & conference room 1ea) (2ea).

- Install/Connect new one duplex outlet(RJ45) by each work desk for SIPR(10ea).

- Coordinate the work with BCE, CE & SCOO/SCX.

The Work/Supply Furniture’s will consist:

- Supply/Place office Furniture’s:

o 1 work desk (L) + 1 office chair.

o 12 work desks (1.6x0.8mts) + 12 office chairs.

o 1 work desk (1.2x0.8mts) + 1 office chair.

o 1 conference table (1.6x3.2mts).

o 12 chairs.

o 4 whiteboards(3x1mts).

o 2 shelving(1.23x2.4mts).

o 14 hangers/accessories for work desks.

o 3 projectors screen(2x2mts).

- Install/Connect new water supply and drain at kitchen area (pipes, valves, etc….).

- Supply/Install sink (2 bowl) with faucets & countertop.

- Supply/Place microwave & refrigerator.

- Move existing safe box from main room (111) to room (110).

- Move existing thermostat (room 107),” if it necessary”.

- Move existing projector screens (room 111).

- Coordinate the works with BCE, CE.

1.2. Brand Names:

Names indicated for materials are for the purpose of establishing a standard selection only.

Other manufacturers' materials are acceptable provided they conform to all specified requirements. Names indicated for the quality of model, give the quality standard to be achieved. Other manufacturer's materials are acceptable if it is equal to the quality and function of the suggested model. All selected material is subject to the approval of Contracting Officer and Civil Engineering.

1.3. Final Cleaning.

Final cleaning of installations affected by this contract.

The items mentioned and the list of main tasks do not limit in any way the responsibility of the contractor to perform all work required by the contract to provide a complete and operational installation.

1.4. Period of Performance. The period of performance for this contract is 60 days (Sixty days) at the site. The contractor shall provide its execution time with their proposal.

2. SERVICES SUMMARY.

Performance Objective SOW Performance Threshold The Electrical/Communication installations will be accordance to NEC, REBT.

Par 1.1 100%

3. GOVERNMENT FURNISHED PROPERTY AND SERVICES.

3.1. Use of Base Utilities: Base utilities are available to the Contactor at no additional expense to the Contractor. The following utilities shall be available from the existing Base utility connections in reasonable quantities:

a. Electricity 120/208 volts, 60 Hz.

b. Water.

All of the equipment, materials and labor required to accomplish the aforementioned connections to existing utilities lines shall be supplied by the Contractor, as part of this contract.

4. GENERAL INFORMATION.

4.1. Security Requirements. The contractor will request installation access through 496

ABS/CE

4.2. Physical Security. The contractor shall be responsible for safeguarding all government property provided for contractor use. At the close of each work period, government facilities, property, and materials shall be secured.

4.3. Hours of Operation.

4.3.1. Normal Hours of Operation. The contractor shall perform the services required under this contract during the following hours: Monday to Friday, 08:00-17:00. The contractor may work, with prior approval of the Contracting Officer, extended hours to ensure timely completion of work at no additional cost to the Government.

4.3.2. Recognized Holidays. The contractor is not required to provide service on the following days: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Days, Thanksgiving Day and Christmas Day. If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.

4.4. Conservation of Utilities. The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:

4.4.1. Lights shall be used only in areas where and when work is actually being performed.

4.4.2. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.

4.4.3. Water faucets or valves shall be turned off after the required use has been accomplished.

4.4.4. Government telephones shall be used only for official government business.

4.5. Records. The contractor shall be responsible for creating, maintaining, and disposing of only those governments required records that are specifically cited in this SOW.

4.6. Environmental Controls:

4.6.1. Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the Contracting Officer pursuant to notice requirements and negotiate a modification to the contract.

4.6.2. Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to Moron AB Fire Dept at 117. The liability for the spill or release of such substances rests solely with the contractor and its agent.

4.6.3. Material Storage and Use. The contractor shall follow manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. This includes hazardous materials.

4.7. Government Observations: Government personnel, other than contracting officers (Cos) and quality assurance personnel (QAPs), may from time-to-time, with CO coordination, observe contractor operations. However, these personnel may not interfere with contractor performance or make any changes to the contract.

4.8. Safety Requirements. In performing work under this contract, the contractor shall:

4.8.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

4.8.2. Take such additional immediate precautions as the contracting officer may reasonably require for safety and mishap prevention purposes.

4.8.3. Develop and provide at the start of the orientation period or the start of the first operational performance period (if there is no orientation period) a safety plan for the protection of government facilities and property and to provide a safe work environment for contractor personnel.

4.8.4. Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the contractor.

4.8.5. Include a clause in all subcontracts to require subcontractors to comply with the safety provisions of this contract as applicable.

4.8.6. Record and report promptly (within one hour) to the contracting officer or designated government representative (GR), all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.

4.8.7. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer.

4.8.8. If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.

4.8.9. Include a clause in each applicable subcontract requiring the subcontractor’s cooperation and assistance in accident reporting and investigation.

4.9. Special Qualifications. The Contractor shall submit any commercial certifications and a reference of past performance on similar works performance to the existing as means to verify experience in this work field.

4.10. Continuation of Essential DOD Contractor Services during Crisis IAW DoDI 3020.37.

IAW AFI 63-124, para 2.7.1, and DODI 3020.37 this requirement is not considered mission essential.

4.11. Contract Restriction: In accordance with the Agreement of Defense and Cooperation between the Kingdom of Spain and the United States of America, any contract resulting from this notice/solicitation can only be entered into with companies authorized to carry out these activities in Spain under Spanish law. Companies must meet the requirements established by Spanish legislation for execution of Government works. In addition, in accordance with the Office of Defense Cooperation Policy Directive 400- 5 "(4) Spanish material, labor, and equipment must be used if permitted by the requirements of the contract specifications."

5. APPENDIXES:

A. Location (Bldg.:1411):

B. Interior Floor Plan:

C. Dimensions Works Areas:

D. Electrical Requirements Floor Plan E. Communications Requirements Floor Plan:

F. Detail (Electrical /Communication) Type:

G. Detail (Acoustic tile) Type:

H. Detail (Existing Doors) & Safe Box:

I. Detail (Furniture’s) Type:

A. Location (Bldg.:1411):

B. Interior Floor Plan:

C. Dimensions Works Areas:

D. Electrical Requirements Floor Plan:

E. Communications Requirements Floor Plan:

F. Detail (Electrical /Communication) Type:

G. Detail (Acoustic tile) type:

H. Detail (Existing Doors) & Safe Box:

I. Detail (Furniture’s) type: