About this file
This document is a Performance Work Statement (PWS) for a federal contract opportunity to provide drain repair services for four barrier autoclaves located at the National Bio and Agro-Defense Facility (NBAF) in Manhattan, Kansas. The contractor is required to cut and remove old leaking stainless steel fittings, weld in new fittings, test for leaks, and passivate all repaired piping. The work must adhere to various federal, state, and local codes and standards, and the contractor must comply with strict site security requirements, including completing safety orientation training and obtaining site access badges. Key deliverables include submitting a detailed cost proposal, service schedule, and passivation method, as well as providing daily work reports and close-out documents. The contract duration is 240 calendar days from the Notice to Proceed. The related federal contract opportunity, Solicitation Number 12805B24Q0239, is for a firm fixed-price purchase order for the barrier autoclave drain repair services, with quotes due by 2:30 PM Central Time on May 23, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1 - 12805B24Q0239.pdf | ||
| RFQ - 12805B24Q0239 Clauses and Provisions.pdf | ||
| Attachment 2 - SCA Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
PERFORMANCE WORK STATEMENT
Barrier Autoclave Drain Repair.
National Bio and Agro-Defense Facility (NBAF) USDA-ARS, Manhattan, KS
3/19/2024
Contents Project General Information
1.0 Scope of Work
2.0 Background
3.0 Contractor Requirements
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment
Project Barrier Autoclave Drain Repairs.
General Information
1.0 Scope of Work
The contractor is to provide drain repairs on four (4) barrier autoclaves located on the NBAF campus. Work includes cutting and removing old leaking stainless fittings and welding in new fittings. The contractor shall test fittings for leaks and passivate all sections of repaired piping.
2.0 Background
The National Bio and Agro-Defense Facility (NBAF) is seeking a company with extensive knowledge and expertise servicing/repairing 316L Stainless steel lab waste drains. NBAF is designed to contain bio safety level BSL-2 through BSL-4 research studies. Contractors associated with maintenance of the facility should fully understand the construction types and maintenance methods associated with these facilities. The equipment is in a non containment portion of the facility, in the NBAF campus at Downtime of the equipment during the service shall be kept to a minimum.
3.0 Contractor Requirements
3.1 Work Restrictions & Conditions
3.1.1 Site Security Access: Access to the site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/subcontractor employees shall sign-in and out at the main entrance gate and always wear a contractor/visitor identification badge while on the site. The ID badges will be turned in at the end of the workday. A current government-issued identification with a picture ID is required for entry. See 8.0 for additional security information.
3.1.2 All persons accessing the site must complete the approximate two hour, NBAF Site Security and Safety Orientation. Site specific bio agent training is currently being developed. If development is completed during the duration of this contract the training may be required for all persons accessing the site.
3.1.3 Limited number of vehicles will be allowed access on the premises; contractor employee’s personal vehicles shall be parked in the facilities main parking lot.
3.1.4 Work shall be confined to the areas the service resides. Unless accompanied by a USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.
3.1.5 Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.
3.1.6 Work Hours: Regular work hours for the site are 8:00 am to 4:00 pm, Monday through Friday, excluding Government holidays.
3.1.7 Federal Holidays are listed below:
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day
Memorial Day Thanksgiving Day Independence Day Christmas Day Juneteenth Independence Day
3.1.8 Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires Security approval in advance. Make application thru the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.
3.2 General Requirements / Tasks
3.2.1 The Contractor shall furnish a detailed cost proposal, including all prime and sub pricing showing labor cost, material cost, OH and Profit and estimated service times including crew size, to provide material and services as specified in the scope of work. Proposal shall indicate how many site visits are anticipated to complete the work and any associated travel costs. Proposal must be in whole dollars, no cents. Otherwise, bids will be rounded to the nearest dollar.
3.2.2 The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.
3.2.3 Bid or performance bonds may be required per the Contracting Officer’s bid package.
Obtaining and the cost of these bonds is the responsibility of the Contractor. Proof of Insurance will also be required.
3.2.4 Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
3.2.5 The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All services shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e.:
UBC, NFPA, UL, ACI, ANSI, FCC, ASTM, NEC, NEMA, etc.) and health and safety codes, in effect at the time of award, or as determined by the authority having jurisdiction.
3.2.6 All work must meet ARS 242.1M P&P titled “ARS Facilities Design Standards” found at https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf, in addition to meeting all Local, State and Federal codes, and latest IBC codes.
3.2.7 N/A
3.2.8 There should be no need for a service trailer at the jobsite. Contractor may store equipment tools, materials onsite as needed for the project in a contractor provided, locked job-box, if requested.
https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf
3.2.9 The Contractor shall work with Facility personnel to ensure project is accomplished in a timely manner.
3.3 Pre-Service/Repair Requirements / Tasks
3.3.1 Prior to Services Notice to Proceed (NTP) the following submittals must be submitted to the Contracting Officer (CO) for approval, unless otherwise determined by the CO that submittals may be provided after NTP. Documents shall be submitted in PDF that can be easily read when printed on 8-1/2 x 11 or 11 x 17 sheets. Contractor is responsible for any costs incurred for equipment ordered without prior approval:
3.3.1.1 Product Data, Shop Drawings, and Installation instructions for all material used on this project, that are a different make/model than those currently installed. SDS for all chemicals that will be used shall be provided prior to being brought onsite. Submittals shall be annotated/highlighted to show products’ conformance with SOW requirements. If multiple items are listed on a submittal, the specific items being submitted for use shall be annotated/highlighted for clarity.
3.3.1.2 As a deliverable the contractor shall provide passivation method to be used for all drain repairs to include Chemicals, MSDA Sheets, solution concentration, time and temperature. If entire drain leg is to be passivated marked drawings shall be provided to USDA showing circuits and connection points for points of contractor’s equipment.
3.3.1.3 Service schedule indicating work hours, include the daily starting and stopping time, and days of the week the Contractor proposes to carry out the work. Schedule shall cover the anticipated duration of work to complete the project.
3.3.1.4 Quality Control Plan is NOT required on this service.
3.3.1.5 Individual Environmental Protection Plan is NOT required on this service.
3.3.1.6 The Contractor shall provide to the CO a list of personnel of the general and subcontractors, who will be emergency contacts, including address, and telephone numbers for use in an emergency. The Contractor shall update and submit the list monthly with invoices.
3.4 Service/Repair Requirements / Tasks
3.4.1 The contractor shall demo existing facility 316L schedule 40 stainless steel drain bushing and elbow 1 each on four (4) barrier autoclaves to repair leaks and allow for uniform/matching fittings. This work will be performed within the autoclave housing requiring the contractor to work around existing piping, pumps and electrical which can restrict visibility and ease of access to the focus point of the work.
3.4.2 The contractor shall install new welded 316L stainless steel bushing with threaded female center and replace elbow to match existing size in accordance with GMP-3 22 71 00 SPEC on four (4) barrier autoclaves. Waste pipe/fittings shall be stainless steel, seamless, 316L, schedule 40 passivated. Any traps shall be schedule 80 passivated. New fittings shall be installed and welded by a certified pressure vessel welder with current certifications required by ASME B31.1 or B31.9.
3.4.3 The contractor shall inspect and hydrostatically test all repaired gravity drains to 5-psi pressure while maintaining 5-psi for 2 hours without leakage.
3.4.4 After successful testing, clean and flush piping system to eliminate debris in drainage system.
3.4.5 The contractor shall passivate and flush all repaired sections of stainless-steel waste and vent piping after installation and testing has been completed. As per 3.3.1.2 Contractor shall provide as a deliverable passivation testing method for 316L Stainless steel to be used for all piping repairs.
3.4.6 Provide a daily report indicating assets serviced and results or efforts. The report shall indicate any issues or components that need to be repaired/replaced beyond those identified in the scope of work.
3.4.7 Existing Installations / Demolition
3.4.7.1 All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disconnecting equipment that might jeopardize on-going research.
3.4.7.2 Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations.
Contractor shall legally dispose all equipment / materials removed that will not be retained.
3.4.8 Building will be occupied while service is ongoing. Contractor shall schedule work with location to allow location to meet current research needs. Contractor shall always maintain at minimum one fully functioning autoclave throughout duration of the project.
3.4.9 Shutoff of utilities, if required, shall be scheduled no less than five (5) working days in advance.
3.4.10 The Contractor shall protect the work, the site, and all existing property and structures within the limits of the service activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.
3.4.11 The work performed under this contract shall be subject to continuous audit by the
CO/COR/LM. Escorting subcontractors is exclusively the contractor’s responsibility’s, Quality control is the exclusive responsibility of the Contractor.
3.4.12 Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, confined space entry plan, safety plan or take other precautions as may be required by law or local authorities of the protection and security.
3.4.13 The contractor shall follow the site lock-out/Tag-out policy and coordinate implementation of LOTO with the facility as needed.
3.4.14 The material and equipment to be furnished under project shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
3.4.15 All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies, and Contractor before during and after shipment in a manner to prevent warping, twisting, breaking, chipping, rusting and any injury, theft, or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be new and subject to inspection and approval by the CO/COR.
3.4.16 Submit to the CO/COR documentation of hazardous materials/waste disposed or recycled.
3.4.17 The work site shall always be kept clean and free of debris. Disposal of the old material or equipment is required. Restore disturbed areas to original like appearance and conditions. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
3.4.18 Contractor to provide standard warranty from deficiencies and defects. Warranty information shall include the warranty period (dates), and warranty contacts with names, addresses and telephone numbers.
3.4.19 Prior to submitting final payment, the following documents shall be submitted:
a. General contractors’ warranty on work.
b. USDA approval on completed work.
c. Update any NBAF engineering drawings if you change anything on current set.
d. Invoice
4.0 Government Furnished
4.1 The Government shall be afforded 14 calendar days review periods for submittals requiring approval and 7 calendar days for information only submittals.
4.2 Please follow FAR 52.247-5 when using government furnished equipment with or without operators.
4.3 The Government will furnish a reasonable amount of electricity and water if requested. Access to a toilet facility will be provided by the Government. The Government can provide minimal craft labor assistance when needed.
5.0 Deliverables / Schedule
The Contract duration for this project is 240 calendar days from Notice to Proceed issued by Contracting Officer.
Key Deliverables
Item No.
Deliverable / Item Title
Description Frequency Reference Delivery Format
Due By
2 Submittals Passivation Method, Product data sheets, shop drawings, installation instructions, SDS
Once per product
Ref. SOW, Section 3.3.1.1/3.3.1.2
PDF to COR Prior to Service/Repair NTP
3 Emergency Contact List
Emergency contact info for persons working onsite
Preservice and monthly
Ref. SOW, Section 3.3.1.5
PDF to COR Prior to Service/Repair NTP & with each invoice
4 Repair Recommendation Report
Material and Labor cost report needed to fix chiller
Once Ref. SOW, Section 3.4
PDF to COR Within 7 calendar days of troubleshooting effort
5 Daily Reports Document and photo describing daily activities
Each day of work
Ref. SOW, Section 3.4.4
PDF to COR Within 24 hrs. after the date(s) covered by the report
6 Service Schedule Schedule indicating work hours and days planned to work
Preservice & at a minimum with each invoice
Ref. SOW, Section 3.3.1.2
PDF to COR Prior to Service/Repair NTP & with each invoice
7 Closeout Documents
Warranty/Final Pyament
Once Ref. SOW, Section 3.4.18/3.4.19
PDF to CO/COR Prior to final payment
6.0 Travel
There are no anticipated travel requirements. If travel costs, flights and per diem, are needed to get technicians to the facility for services they shall be reflected on a separate cost line.
7.0 Contractor’s Key Personnel
Service Repair Technicians shall be certified pressure vessel welders with current certifications required as per ASME B31.1 or B31.9.
8.0 Security Requirements
8.1 Personnel employed by the Contractor or any representative of, or agent of the Contractor, entering this facility shall conform to the facility security regulations. The Contractor shall provide all information required for background checks to meet facility access requirements as performed by the facility security office. Contractor personnel shall comply with all personal identity verification requirements as directed by USDA-ARS Security office. Each person accessing the site will be required to provide personal details, (full name, DOB, SSN, DL#) and will undergo a routine background check, such as a National Agency Check with additional inquiries, which may include a criminal and credit check. Details required for the check should be submitted the security office NLT 5 days prior to the visit. Results of this check may return earlier. However, it should not be planned to have results earlier than 5 days. If, while on site the contractor/vendor will have access to sensitive information, they must complete a National Disclosure Agreement (NDA), along with the required training. This training will most likely be completed by reviewing a series of slides covering the topics of the definition of controlled unclassified information (CUI), access, handling, distribution, storage, and destruction of CUI. Each person will acknowledge receiving and understanding the training on the NDA. The process should not exceed two hours. Acknowledgement and completion of the NDA will be turned in with the form required for the background check. Results will be returned through the Contracting Officer or Contracting Officer Representative. Contractors needs to follow Title 41, Code of Federal Regulations, Part 102- 74, Subpart C Rules, and Regulation Governing Conduct on Federal Property.
8.2 Contractor Personnel, Contract Vehicles, Tools, Equipment, Material Deliveries & Shipments. The Service Entry Control Point (ECP)/Guard Post serves as the initial screening point for vehicles and visitors.
8.2.1 All Vehicles, equipment, and personnel will be confirmed for NBAF access. Upon confirmation, all vehicles and equipment will be thoroughly searched at the Service ECP.
Once cleared, visitors may be thoroughly screened by Security at the Service ECP or will be directed to park in the North Transshipping (TSSG) Parking Lot to undergo Security Screening within the Transshipping Building.
8.2.2 Following screening, visitors without a Long-Term Visitor Badge (LTVB) will be issued a short short-term visitor’s badge.
8.2.3 Escorted by either Contractor staff with a Local Badge/PIV or an authorized USDA Escort, visitors, vehicles, tools, equipment, and materials will enter NBAF through Gate 2, and travel to the designated delivery entry point(s).
8.2.4 Escort coordinates to meet an authorized USDA member at the designated delivery entry point(s). This coordination will need to be done through the contract COR.
8.2.5 Escorts must always maintain line of sight of visitors and a 5:1 escort ratio.
8.2.6 Leaving the designated delivery entry points, escorted visitors will drive out of Gate 2.
Vehicles, equipment, and personnel are subject to additional Security Screening and egress procedures pending campus status.
8.2.7 Visitors without LTVBs will either be directed to park in the North TSSG parking lot to return their badge within Transshipping or will be directed to turn in their badge at the Service ECP. Once the Visitor Badge is returned, the visitor will then exit the respective area and leave the NBAF premises. Those with LTVB’s will leave the premises upon exiting Gate 2.
8.2.8 Visitors that are part of the delivery crew, but whom are not in the delivery vehicle will be subject to standard site access requirements utilizing the main Entry Control Point off Denison Avenue and screening by Security at the Visitors Center. Visitors will then be escorted from the Visitors Center, by a Contractor staff with a Local Badge/PIV or an authorized USDA Escort, to join the rest of the crew.
8.2.9 Escort will enter PIN at the access control reader and escort visitors through the designated delivery entry point(s) into the work area. Additional instruction pertaining to containment is as follows:
8.2.9.1 Access/Egress of containment loading areas and activities within containment are subject to additional limitations, requirements and restrictions that will be determined, evaluated, and approved on a case-by-case basis.
8.2.9.2 All personnel, tools, equipment, and materials are subject to additional Security Screening and ingress/egress procedures pending campus status.
8.2.9.3 At no time can a direct path from outside the facility into containment occur.
8.2.9.4 Within containment, the containment cafeteria is the only authorized place to eat and drink. Food and Drink are only allowed to enter containment through the cafeteria pass through box via the warming kitchen.
8.2.9.5 All Contractor Staff and Visitors will be required to check their phones into a locker outside of containment prior to entering containment.
8.2.9.6 Radios can be signed out for communication within containment. The radios must stay within containment.
8.3 Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.
8.4 The Contractor shall safeguard all USDA-ARS equipment, information and property provided for Contractor use. At the close of each work period, USDA-ARS facilities, equipment, and materials shall be secured.
9.0 Data Rights
Not Applicable
10.0 Section 508 – Electronic and Information Technology Standards Not Applicable
Attachment Not Applicable
| United States Department of Agriculture |
| Agricultural Research Service |
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| 3.0 Contractor Requirements |
| 3.1 Work Restrictions & Conditions |
| 3.2.1 The Contractor shall furnish a detailed cost proposal, including all prime and sub pricing showing labor cost, material cost, OH and Profit and estimated service times including crew size, to provide material and services as specified in the sco... |
| 3.2.6 All work must meet ARS 242.1M P&P titled “ARS Facilities Design Standards” found at https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf, in addition to meeting all Local, State and Federal codes, and latest IBC codes. |
| 4.0 Government Furnished |
| 4.1 The Government shall be afforded 14 calendar days review periods for submittals requiring approval and 7 calendar days for information only submittals. |
| 4.2 Please follow FAR 52.247-5 when using government furnished equipment with or without operators. |
| 4.3 The Government will furnish a reasonable amount of electricity and water if requested. Access to a toilet facility will be provided by the Government. The Government can provide minimal craft labor assistance when needed. |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 8.1 Personnel employed by the Contractor or any representative of, or agent of the Contractor, entering this facility shall conform to the facility security regulations. The Contractor shall provide all information required for background checks to me... |
| 8.4 The Contractor shall safeguard all USDA-ARS equipment, information and property provided for Contractor use. At the close of each work period, USDA-ARS facilities, equipment, and materials shall be secured. |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| Attachment |