This is a Performance Work Statement (PWS) for Aerospace Ground Equipment (AGE) Corrosion Prevention and Paint Services at Joint Base Charleston, South Carolina. The contract requires surface preparation and painting services for 368 pieces of various AGE items over a 60-month period consisting of a base period from June 1, 2026 through September 30, 2026, followed by four one-year option periods and a final option period from October 1, 2030 through May 30, 2031. The estimated workload is 6-7 assets per month, with work to be completed within two weeks (14 calendar days) of equipment pickup.

The contractor must provide all labor, materials, transportation, and facilities to complete surface preparation including washing, degreasing, sanding, and masking; apply one coat of primer (MIL-PRF-23377, Type I, Class N) and one coat of finish paint (SAE-AMS-STD-595, gray number 26173, MIL-PRF-85285 Type IV); and apply protective bed liner coating to Generator Sets and -95 Gas Turbine Cart units and black safety striping to oil, hydraulic, and fuel bowsers. The contractor must provide a transport vehicle with a minimum 15,000-pound winch capacity, pick up and return equipment at Building 548 (308 N Graves Avenue, Charleston AFB, SC 29404), and notify the Government 24 hours prior to delivery. Equipment pickup and drop-off occur during base hours (7:00 AM to 5:00 PM, Monday through Friday), with base access requiring contractor access forms submitted 72 hours in advance. The contractor assumes full liability for equipment while in possession and must maintain compliance with all federal, state, and local safety and environmental regulations, including proper disposal of hazardous materials.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JOINT BASE CHARLESTON

Performance Work Statement (PWS)

Aerospace Ground Equipment (AGE) Corrosion Prevention and Paint Services

1.0 Introduction

This Performance Work Statement (PWS) defines the requirements for the surface preparation and painting services of 368 pieces of various AGE items belonging to the AGE Flight at Joint Base Charleston (JB CHS) SC, in accordance with DAFI 21-101. The Contractor shall provide all labor, materials (including paint conforming to Air Force Mil Spec SAE-AMS-STD-595, gray number 26173, MIL-PRF-85285 Type IV, topcoat), facilities, equipment, and transportation necessary to perform the work described herein in accordance with all applicable federal, state, and local regulations, as well as the specifications outlined in this document. This Requirements contract will span a 60-month period in 1-year option increments with an estimated workload of 6-7 assets per month.

Workload will be defined via the issuance of task orders.

2.0 Scope of Work

The Contractor shall provide all necessary services to prepare, paint, and return the AGE listed in Attachment 1- AGE INVENTORY to a like-new condition. This includes but is not limited to:

2.1 Equipment Pickup and Transportation: The Contractor shall be responsible for picking up all AGE requiring painting from the designated pickup area at the back side of Bldg 548, JB CHS, SC. The Contractor shall provide a suitable transport vehicle equipped with a winch (minimum 15,000 lbs capacity) for loading and unloading equipment. The Government will assist with the loading and unloading of forklift-able equipment at Bldg 548.

2.2 Surface Preparation: The Contractor shall thoroughly prepare all surfaces to be painted. This includes:

2.2.1 Washing and degreasing all surfaces.

2.2.2 Sanding or scuffing existing paint to ensure proper adhesion of the new coating.

2.2.3 Masking off all areas not to be painted, including but not limited to tires, windows, lights, placards, and delicate components.

2.2.4 For Generator Sets and -95 Gas Turbine Cart (GTC) units, the Contractor shall prepare the cable/hose compartments for the application of a protective bed liner coating.

2.3 Priming and Painting:

2.3.1 The Contractor shall provide and apply one coat of primer and one coat of finish paint, conforming to Air Force Mil Spec (MIL-PRF-23377, Type I, Class N – primer SAE-AMS-STD-595, gray number 26173, MIL-PRF-85285 Type IV -topcoat), to all equipment listed in Attachment 1.

2.3.2 All painting shall be performed IAW military specifications and applicable technical orders.

2.3.3 All inside doors, control panels, and readily accessible interior areas shall also be sanded/scuffed, masked, primed, and painted.

2.3.4 Generator Sets and -95 GTC units shall have their cable/hose compartments coated with a durable bed liner material to prevent premature paint wear.

2.3.5 All oil, hydraulic, and fuel bowsers will have their required safety striping applied using black paint provided by the Contractor.

2.4 Quality Inspection and Acceptance:

2.4.1 Upon completion of painting, the Contractor shall notify the Government POC by phone at 843-963-4758/4725 to schedule delivery back to Bldg 548.

2.4.2 An authorized Government representative will inspect the painted equipment at Bldg 548 upon delivery to verify compliance with all requirements and identify any deficiencies.

2.4.3 Any equipment requiring rework will be returned to the Contractor's facility for correction. The Contractor shall bear all costs associated with transporting equipment back to their facility for rework. The Government will assist with loading and unloading the equipment at Bldg 548.

2.4.4 Once the rework is completed, the Contractor shall notify the Government POC to schedule a final inspection and acceptance at Bldg 548.

2.5 Equipment Return and Delivery:

2.5.1 Following successful inspection and acceptance, the painted equipment will be formally accepted at the designated drop-off area at the back side of Bldg 548, JB CHS, SC.

2.5.2 The Contractor shall notify the Government 24 hours prior to delivery to coordinate equipment receipt and offloading.

3.0 Period of Performance

The base period of performance for this contract is 1 June 2026- 30 September 2026, followed by four (4) one-year option periods, and a final option period for 1 October – 30 May 2031 for a total potential period of performance of 60 months. Upon receipt of the equipment, the contractor shall complete all work specified in this PWS within two (2) weeks (14 calendar days) from the date of pick up to return of the equipment, unless otherwise specified by the Contracting Officer or Contracting Officer’s Representative (COR).

4.0 Government Furnished Property (GFP)

4.1 The Government will provide AGE to be refurbished under this contract.

4.2 The Government will assist with the loading and unloading of forklift-able equipment at

Bldg 548.

5.0 Contractor Furnished Property (CFP)

The Contractor shall provide all labor, tools, equipment, transportation, facilities, and materials (including paint as specified in Note 1) required to perform the work outlined in this PWS. This includes, but is not limited to:

5.1 Transportation vehicles with a minimum 15,000 lbs winch capacity for loading and unloading.

5.2 Sanding and surface preparation equipment.

5.3 Painting equipment and supplies (e.g., spray guns, respirators, masking materials).

5.4 Bed liner material for Generator Sets and -95 GTC units.

5.5 Black paint for striping oil, hydraulic, and fuel bowsers.

5.6 All materials and labor necessary to comply with environmental regulations for the disposal of excess paint and hazardous materials.

6.0 Quality Assurance

6.1 The Contractor shall implement a quality control plan to ensure all work performed meets or exceeds the requirements of this PWS.

6.2 The Contractor shall comply with all applicable safety data sheets (SDS) for all materials used.

6.3 The Government will conduct a final inspection of the painted equipment at the Contractor's facility before acceptance.

6.4 Any work deemed unacceptable by the Government shall be corrected by the Contractor at no additional cost to the Government.

7.0 Safety and Environmental

7.1 The Contractor shall comply with all applicable federal, state, and local safety and environmental regulations.

7.2 The Contractor shall be solely responsible for the safety of its employees and agents performing work under this contract.

7.3 The Contractor shall dispose of all excess paint and hazardous materials in accordance with all applicable regulations.

8.0 General Information

8.1 The Pick-up & Drop Off Location for this requirement will be the AGE Flight in building 548 located at;

308 N Graves Ave Charleston AFB, SC 29404 843-963-4758/ 4725 The main points of contact for scheduling with be the Contracting Officer’s Representative (COR) or AGE Flight Chief or delegate within the AGE flight as necessary.

8.2 Base Hours of Operation & Scheduling: 7:00AM to 5:00 PM, Monday through Friday.

The contractor is not required to provide services on Federal holidays. Pick up and Drop Off scheduling can be done anytime during Base Operating hours and will be scheduled with Contract POC’s as defined in 2.1 & 2.4.1. Any work outside of regular hours of operation requires a request for approval to the POC for approval 96 hours prior to work outside of regular hours. Work scheduled but not accomplished because of base closure due to weather, exercises or actual alert will be accomplished as soon as possible after reopening the base.

8.3 Base Access - The COR is responsible for turning the contractor access form into the respective visitor center a minimum of 72 hours prior to the start of each project/period of performance. Failure to do so may delay entry for personnel and delay project performance. The 628 SFS will conduct a fitness determination prior to a base credential being issued for base access. Failure to fully comply with all federal and state law on/off Joint Base Charleston, may result in federal or local citations or prosecution or denial of access to JB CHS. Please note transport vehicles will be subject to inspection at the Rivers Avenue Gate in order to gain base access, so plan for time accordingly.

9.0 Accountability and Responsibility

9.1 The Contractor shall sign an AF Form 1297, Temporary Issue Receipt, at the time of equipment pickup. By signing this document, the Contractor assumes full responsibility for the equipment listed while it is in their possession and is liable for any loss or damage.

9.2 Any existing damage to the equipment shall be annotated on the AF Form 1297 before the Contractor takes possession.

9.3 The completion/return date will be documented on the AF Form 1297.

9.4 In the event of unforeseen delays (weather, supply chain issues, etc.), a mutually agreeable completion/return date will be established between the Government and the Contractor.

10.0 Attachments

• Attachment 1: AGE Inventory.