ATTACHMENT 1 - Project Manual.pdf
PDF 7 MB Posted
- Solicitation number
- 36C77626B0013
About this file
This is a Project Manual for the Electronic Healthcare Records Management (EHRM) Infrastructure Upgrades Construction project at American Lake VA Medical Center in American Lake, Washington (Project No. 663A4-24-703). The document establishes comprehensive specifications and requirements for general construction, alterations, demolition, and infrastructure upgrades across multiple buildings and systems.
The project encompasses selective demolition of interior partitions and systems, asbestos abatement, lead-based paint removal, and installation of HVAC systems, electrical infrastructure, communications systems, and electronic safety and security systems. Key contractual requirements include: a Critical Path Method (CPM) project schedule with approximately 130 work activities; submission of a Construction Document Management Software system for hosting project communications and documentation; a comprehensive Quality Control program with three phases of control (Preparatory, Initial, and Follow-Up) for each definable feature of work; and extensive commissioning services for mechanical, electrical, communications, and security systems. The contractor must provide a Site Safety and Health Officer with minimum three years of construction safety experience, maintain temporary heating, utilities, and environmental controls, and complete pre-functional checklists and systems functional performance testing for all commissioned equipment. Additional requirements include shop drawing and product data submittals, testing and balancing services, operations and maintenance manuals, operator training, performance and payment bonds, warranty management for a minimum one-year period, and final as-built drawings. The specification sections cover general requirements, demolition, asbestos and lead abatement, safety protocols including fall protection and confined space entry, quality control procedures, special inspections by third-party inspectors, temporary environmental controls, and commissioning across multiple building systems and divisions, with comprehensive compliance requirements for OSHA, EPA, and VA regulations.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EHRM INFRASTRUCTURE UPGRADES
Final Bid Documents
PROJECT MANUAL
American Lake Veterans Affairs Medical
Center 9600 Veterans Drive, Southwest
American Lake, Washington
November 25, 2025 Project No. 663A4 -24-703
Project No. 663A4 -24-703
American Lake VA Medical Center
EHRM Infrastructure Upgrades
Project Number 663A4-24-703
CONSULTANTS DIRECTORY 000103 - 1
SECTION 000103
CONSULTANTS DIRECTORY
PART 1 - GENERAL
1.01 PROJECT LISTING
A. Architect / Physical Security
Awen Solutions Group
4196 Merchant Plaza Woodbridge, Virginia 22192
B. Fire Protection / Plumbing / Mechanical / Electrical Engineer
Coffman Engineers, Inc.
701 Corporate Center Drive, Suite 475
Raleigh, North Carolina 27607
C. Technology Engineer
Coffman Engineers, Inc.
701 Corporate Center Drive, Suite 475
Raleigh, North Carolina 27607
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
October 2, 2025
TABLE OF CONTENTS 000110 - 1
SECTION 000110
TABLE OF CONTENTS
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 03 Consultants Directory
00 01 10 Table of Contents
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements for Major Projects 05-24
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-22
01 91 00.01 Preliminary Commissioning Plan
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 41 19 Selective Demolition
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
TABLE OF CONTENTS 000110 - 2
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 31 13 Access Doors and Frames 04-22
08 71 00 Door Hardware 03-24
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 26 00 Wall and Door Protection 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 – EQUIPMENT
Not Applicable
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-21
DIVISION 14 – CONVEYING EQUIPMENT
DIVISION 20 – MECHANICAL SUPPORT
EHRM Infrastructure Upgrades
TABLE OF CONTENTS 000110 - 3
DIVISION 21 - FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
21 22 00 Clean Agent Fire Suppression Systems 05-15
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-23
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
03-23
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 03-23
23 21 13 Hydronic Piping 03-23
23 21 23 Hydronic Pumps 03-23
23 23 00 Refrigerant Piping 03-24
23 81 23 Computer-Room Air-Conditioners 03-24
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 41 Underground Electrical Construction 11-22
26 05 73 Overcurrent Protective Device Coordination Study 11-22
26 08 00 Commissioning of Electrical Systems 11-22
26 09 23 Lighting Controls 11-22
26 24 16 Panelboards 11-22
26 26 00 Power Distribution Units for Static Uninterruptible
Power Systems
11-22
26 27 26 Wiring Devices 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 33 53 Static Uninterruptible Power Supply 11-22
26 43 13 Surge Protective Devices 11-22
26 51 00 Interior Lighting 03-24
TABLE OF CONTENTS 000110 - 4
DIVISION 27 – COMMUNICATIONS
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Conduits and Backboxes for Communications Systems 10-18
27 05 36 Cable Trays for Communications Systems
27 05 53 Identification for Communications Systems
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Structural Cabling
27 11 16 Communications Cabinets, Racks, Frames, and Enclosures
27 11 19 Communications Termination Blocks and Patch Panels
27 11 26 Communications Rack Mounted Power Protection and Power
Strips
27 13 23 Communications Optical Fiber Backbone Cabling
27 13 23.13 Communications Optical Fiber Splicing and Terminations
27 15 13 Communications Copper Horizontal Cabling
27 16 19 Communications Patch Cords, Station Cords, and Cross
Connect Wire
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 13 00 Physical Access Control System 10-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 08-23
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 17 23 Pavement Markings 08-16
32 90 00 Planting 08-16
DIVISION 33 – UTILITIES
DIVISION 34 – TRANSPORTATION
EHRM Infrastructure Upgrades
TABLE OF CONTENTS 000110 - 5
DIVISION 35 – WATERWAYS AND MARINE CONSTRUCTION
DIVISION 40 – PROCESS INTERCONNECTIONS
DIVISION 41 – MATERIAL PROCESSING AND HANDLING
EQUIPMENT
DIVISION 42 - PROCESS HEATING, COOLING, AND DRYING
EQUIPMENT
DIVISION 43 – PROCESS GAS AND LIQUID HANDLING,
PURIFICATION, AND STORAGE EQUIPMENT
DIVISION 44 – POLLUTION CONTROL EQUIPMENT
DIVISION 45 – INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
DIVISION 46 – WATER AND WASTEWATER EQUIPMENT
DIVISION 48 – ELECTRICAL POWER GENERATION
List of Drawing Sheets 000115 - 1
SECTION 000115
LIST OF DRAWING SHEETS
Reference Drawings GI1001 - GI1002 for the complete List of Drawings. The drawings listed on this documentation, which accompany this Project Manual, form a part of the contract.
Drawing No. Title
BLDG 000
01-GENERAL
000-GI000 COVER SHEET
000-GI001 SHEET INDEX - GENERAL - BLDG 023
000-GI002 SHEET INDEX - BLDG 061 - BLDG 202
000-GI003 GENERAL NOTES, CODE REQUIREMENTS & SCOPE OF WORK
000-GI004 GENERAL NOTES
000-GI005 BOD SUMMARY
000-GI006 ARCHITECTURAL ABBREVIATIONS AND SYMBOLS
000-GI008 TYPICAL ADA REQUIREMENTS
000-GI014 INFECTION PREVENTION AND CONTROL PERMIT INFORMATION
000-GI015 INFECTION CONTROL RISK ASSESSMENT - CLASS IV
000-GS101 CAMPUS SITE PLAN
05-CIVIL
000-CI001 GENERAL NOTES SHEET
000-CU100 EXISTING CONDITIONS PLAN
000-CU300 OVERALL COMMUNICATIONS SITE PLAN
000-CU301 COMMUNICATIONS SITE PLAN - INSET 1
000-CU302 COMMUNICATIONS SITE PLAN - INSET 2
000-CU303 COMMUNICATIONS SITE PLAN - INSET 3
000-CU304 COMMUNICATIONS SITE PLAN - INSET 4
000-CU310 OVERALL UTILITY SITE PLAN
000-CU311 UTILITY SITE PLAN - INSET 1
000-CU312 UTILITY SITE PLAN - INSET 2
000-CU313 UTILITY SITE PLAN - INSET 3
000-CU314 UTILITY SITE PLAN - INSET 4
000-CU400 CIVIL DETAILS
000-CU401 CIVIL DETAILS
000-CU402 CIVIL DETAILS
000-CU500 FIBER OPTIC MANHOLE DETAILS
000-CU501 FIBER OPTIC MANHOLE DETAILS
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 2
000-CU502 FIBER OPTIC MANHOLE DETAILS
07-STRUCTURAL
000-S-001 GENERAL NOTES AND SPECIAL INSPECTIONS
000-S-501 TYPICAL FOUNDATION PENETRATION DETAILS
000-S-502 TYPICAL MOUNTING DETAILS
08-ARCHITECTURE
000-AE501 INTERIOR FRAMING DETAILS
000-AE502 INTERIOR FRAMING DETAILS
000-AE511 DOOR DETAILS
000-AE521 PARTITION TYPES
000-AE522 PARTITION DETAILS
000-AE531 CEILING DETAILS
11-FIRE PROTECTION
000-FA001 FIRE ALARM GENERAL NOTES AND LEGEND
000-FX001 FIRE SUPPRESSION GENERAL NOTES AND LEGEND
12-PLUMBING
000-P001 PLUMBING GENERAL NOTES & SYMBOLS LEGEND
000-P501 PLUMBING DETAILS
14-MECHANICAL
000-M001 MECHANICAL GENERAL NOTES & SYMBOLS LEGEND
000-M501 MECHANICAL DETAILS & CONTROLS
15-ELECTRICAL
000-E-001 ELECTRICAL SYMBOLS LEGEND
000-E-501 ELECTRICAL DETAILS
000-E-502 ELECTRICAL DETAILS
000-E-503 ELECTRICAL SCHEDULES
16-TELECOMMUNICATION
000-T-001 TELECOMMUNICATIONS SYMBOLS LEGEND, ABBREVIATIONS AND NOTES
000-T-002 TELECOMMUNICATIONS SCHEDULE
000-T-003 TELECOMMUNICATIONS SCHEDULE
000-T-501 TELECOMMUNICATIONS DETAILS
000-T-502 TELECOMMUNICATIONS DETAILS
000-T-503 TELECOMMUNICATIONS DETAILS
000-T-504 TELECOMMUNICATIONS DETAILS
000-T-505 TELECOMMUNICATIONS DETAILS
000-T-506 TELECOMMUNICATIONS DETAILS
000-T-601 TELECOMMUNICATIONS CAMPUS OVERALL RISER DIAGRAM
000-T-602 TELECOMMUNICATIONS CAMPUS FIBER OPTIC RISER DIAGRAM
000-T-603 TELECOMMUNICATIONS CAMPUS FIBER OPTIC RISER DIAGRAM
16.4-SECURITY
000-TY001 SECURITY NOTES, SYMBOLS & ABBREVIATIONS
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 3
BLDG 002
002-GI001 COVER SHEET
002-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
002-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
002-GI103 DIAMOND ANALYSIS PLAN - LEVEL 03
002-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 02
08-ARCHITECTURE
002-AE101 OVERALL FLOOR PLAN - LEVEL 01
002-AE102 OVERALL FLOOR PLAN - LEVEL 02
002-AE103 OVERALL FLOOR PLAN - LEVEL 03
15-ELECTRICAL
002-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 02
002-ED401 ELECTRICAL ENLARGED DEMOLITION PLANS
002-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 02
002-EP401 ELECTRICAL ENLARGED POWER PLANS
002-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
002-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
002-TN102 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 02
002-TN401 TELECOMMUNICATIONS ENLARGED PLANS
002-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
002-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
002-TN602 TELECOMMUNICATIONS RACK ELEVATIONS
16.4-SECURITY
002-TY101 SECURITY FLOOR PLAN - LEVEL 01
002-TY102 SECURITY FLOOR PLANS - LEVEL 02
002-TY103 SECURITY FLOOR PLAN - LEVEL 03
BLDG 003
003-GI001 COVER SHEET
003-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
003-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
003-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
003-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 00
08-ARCHITECTURE
003-AE100 OVERALL FLOOR PLAN - LEVEL 00
003-AE101 OVERALL FLOOR PLAN - LEVEL 01
003-AE102 OVERALL FLOOR PLAN - LEVEL 02
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 4
15-ELECTRICAL
003-ED100 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 00
003-ED401 ELECTRICAL ENLARGED DEMOLITION PLANS
003-EP100 ELECTRICAL OVERALL POWER PLAN - LEVEL 00
003-EP401 ELECTRICAL ENLARGED POWER PLANS
003-EP501 ELECTRICAL DETAILS
003-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
003-TN100 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 00
003-TN401 TELECOMMUNICATIONS ENLARGED PLANS
003-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
003-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
003-TN602 TELECOMMUNICATIONS RACK ELEVATIONS
16.4-SECURITY
003-TY101 SECURITY FLOOR PLANS
BLDG 004
004-GI001 COVER SHEET
004-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
004-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
004-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
004-GI110 EGRESS AND SEQUENCE DIAGRAM PLANS - LEVEL 00
08-ARCHITECTURE
004-AE100 OVERALL FLOOR PLAN - LEVEL 00
004-AE101 OVERALL FLOOR PLAN - LEVEL 01
004-AE102 OVERALL FLOOR PLAN - LEVEL 02
14-MECHANICAL
004-MP101 OVERALL MECHANICAL PLAN - LEVEL 01
004-MP102 OVERALL MECHANICAL PLAN - LEVEL 02
004-MP401 ENLARGED MECHANICAL PLANS
15-ELECTRICAL
004-ED100 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 00
004-EP100 ELECTRICAL OVERALL POWER PLAN - LEVEL 00
004-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
004-EP501 ELECTRICAL DETAILS
004-EP601 ONE-LINE DIAGRAM
004-EP602 ELECTRICAL SCHEDULES
16-TELECOMMUNICAITON
004-TN100 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 00
004-TN401 TELECOMMUNICATIONS ENLARGED PLANS
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 5
004-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
004-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
004-TY101 SECURITY FLOOR PLANS
BLDG 005
005-GI001 COVER SHEET
005-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
005-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
005-AE101 OVERALL FLOOR PLAN - LEVEL 01
15-ELECTRICAL
005-ED100 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
005-EP101 ELECTRICAL OVERALL POWER PLANS - LEVEL 00 AND 01
005-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
005-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
005-TN401 TELECOMMUNICATIONS ENLARGED PLANS
005-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
005-TY101 SECURITY FLOOR PLANS
BLDG 006
006-GI001 COVER SHEET
006-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
006-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
006-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
006-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
006-AE100 OVERALL FLOOR PLAN - LEVEL 00
006-AE101 OVERALL FLOOR PLAN - LEVEL 01
006-AE102 OVERALL FLOOR PLAN - LEVEL 02
15-ELECTRICAL
006-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
006-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
006-EP501 ELECTRICAL DETAILS
006-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
006-TN100 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 00
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 6
006-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
006-TN401 TELECOMMUNICATIONS ENLARGED PLANS
006-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
006-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
006-TY101 SECURITY FLOOR PLANS
BLDG 007
007-GI001 COVER SHEET
007-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
007-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
007-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
007-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 00
08-ARCHITECTURE
007-AE100 OVERALL FLOOR PLAN - LEVEL 00
007-AE101 OVERALL FLOOR PLAN - LEVEL 01
007-AE102 OVERALL FLOOR PLAN - LEVEL 02
15-ELECTRICAL
007-ED100 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 00
007-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 00
007-EP102 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
007-EP501 ELECTRICAL DETAILS
007-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
007-TN100 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 00
007-TN401 TELECOMMUNICATIONS ENLARGED PLANS
007-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
007-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
007-TY101 SECURITY FLOOR PLANS
BLDG 008
008-GI001 COVER SHEET
008-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
008-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
008-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
008-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 00
08-ARCHITECTURE
008-AE100 OVERALL FLOOR PLAN - LEVEL 00
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 7
008-AE101 OVERALL FLOOR PLAN - LEVEL 01
008-AE102 OVERALL FLOOR PLAN - LEVEL 02
008-AE401 TR 127 - ENLARGED FLOOR PLANS, RCPS AND INTERIOR ELEVATIONS
008-AE601 SCHEDULES
008-H401 TR 127 - ENLARGED ABATEMENT FLOOR PLAN AND RCP
12-PLUMBING
008-PP100 PLUMBING OVERALL PLAN - LEVEL 00
14-MECHANICAL
008-MP100 MECHANICAL OVERALL PLAN - LEVEL 00
15-ELECTRICAL
008-ED100 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 00
008-EP100 ELECTRICAL OVERALL POWER PLAN - LEVEL 00
008-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 02
008-EP501 ELECTRICAL DETAILS
008-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
008-TD100 TELECOMMUNICATIONS DEMOLITION PLAN - LEVEL 00
008-TD600 TELECOMMUNICATIONS EXISTING ELEVATIONS
008-TN100 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 00
008-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
008-TY101 SECURITY FLOOR PLANS
BLDG 009
009-GI001 COVER SHEET
009-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
009-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
009-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
009-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 02
08-ARCHITECTURE
009-AE100 OVERALL FLOOR PLAN - LEVEL 00
009-AE101 OVERALL FLOOR PLAN - LEVEL 01
009-AE102 OVERALL FLOOR PLAN - LEVEL 02
15-ELECTRICAL
009-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 02
009-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
009-EP102 ELECTRICAL OVERALL POWER PLAN - LEVEL 02
009-EP501 ELECTRICAL DETAILS
009-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 8
009-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
009-TN102 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 02
009-TN401 TELECOMMUNICATIONS ENLARGED PLANS
009-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
009-TY101 SECURITY FLOOR PLANS
BLDG 016
016-GI001 COVER SHEET
016-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
016-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
016-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 02
08-ARCHITECTURE
016-AE101 OVERALL FLOOR PLAN - LEVEL 01
016-AE102 OVERALL FLOOR PLAN - LEVEL 02
15-ELECTRICAL
016-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 02
016-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 02
016-EP501 ELECTRICAL DETAILS
016-EP601 ONE-LINE DIAGRAM AND PANEL SCHEDULES
16-TELECOMMUNICATION
016-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
016-TN102 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 02
016-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
016-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
016-TY101 SECURITY FLOOR PLANS
BLDG 017
017-GI001 COVER SHEET
017-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
017-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
017-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
017-AE101 OVERALL FLOOR PLAN - LEVEL 01
017-AE102 OVERALL FLOOR PLAN - LEVEL 02
017-AE401 TR 103 - ENLARGED FLOOR PLANS, RCPS AND INTERIOR ELEVATIONS
017-AE601 SCHEDULES
017-H401 TR 103 - ENLARGED ABATEMENT FLOOR PLAN AND RCP
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 9
15-ELECTRICAL
017-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
017-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
017-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
017-TD101 TELECOMMUNICATIONS OVERALL DEMOLITION PLAN - LEVEL 01
017-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
017-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
017-TY101 SECURITY FLOOR PLANS
BLDG 018
018-GI001 COVER SHEET
018-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
018-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
018-AE101 OVERALL FLOOR PLAN - LEVEL 01
15-ELECTRICAL
018-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
018-ED401 ELECTRICAL ENLARGED DEMOLITION PLANS
018-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
018-EP401 ELECTRICAL ENLARGED POWER PLANS
018-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
018-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
018-TN401 TELECOMMUNICATIONS ENLARGED PLANS
018-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
018-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
018-TN602 TELECOMMUNICATIONS RACK ELEVATIONS
018-TY101 SECURITY FLOOR PLANS
BLDG 019
019-GI001 COVER SHEET
019-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
019-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
019-AE101 OVERALL FLOOR PLAN - LEVEL 01
16-TELECOMMUNICATION
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 10
019-TD101 TELECOMMUNICATIONS DEMOLITION OVERALL PLAN
019-TN101 TELECOMMUNICATIONS OVERALL PLAN
019-TY101 SECURITY FLOOR PLANS
BLDG 020
020-GI001 COVER SHEET
020-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
020-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
020-AE101 OVERALL FLOOR PLAN - LEVEL 01
15-ELECTRICAL
020-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
020-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
020-EP501 ELECTRICAL DETAILS
020-EP601 ONE-LINE DIAGRAM AND PANEL SCHEDULES
16-TELECOMMUNICATION
020-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
020-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
020-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
020-TN602 TELECOMMUNICATIONS RACK ELEVATIONS
020-TY101 SECURITY FLOOR PLANS
BLDG 021
021-GI001 COVER SHEET
021-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
021-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
021-AE101 OVERALL FLOOR PLAN - LEVEL 01
021-AE401 NEW TE ENLARGED PLANS & ELEVATION
12-PLUMBING
021-PP100 PLUMBING OVERALL PLAN - LEVEL 01
14-MECHANICAL
021-MP101 MECHANICAL OVERALL PLAN - LEVEL 01
15-ELECTRICAL
021-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
021-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
021-EP601 ONE-LINE DIAGRAM AND PANEL SCHEDULES
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 11
16-TELECOMMUNICATION
021-TD101 TELECOMMUNICATIONS OVERALL DEMOLTION PLAN - LEVEL 01
021-TD600 TELECOMMUNICATIONS EXISTING ELEVATIONS
021-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
021-TN600 TELECOMMUNICATIONS RISER DIAGRAM AND RACK ELEVATIONS
021-TY101 SECURITY FLOOR PLANS
BLDG 023
023-GI001 COVER SHEET
023-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
023-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
023-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
023-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 02
08-ARCHITECTURE
023-AE100 OVERALL FLOOR PLAN - LEVEL 00
023-AE101 OVERALL FLOOR PLAN - LEVEL 01
023-AE102 OVERALL FLOOR PLAN - LEVEL 02
15-ELECTRICAL
023-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 02
023-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 02
023-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
023-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
023-TN102 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 02
023-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
023-TY100 SECURITY FLOOR PLANS
BLDG 061
061-GI001 COVER SHEET
061-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
061-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
061-GI103 DIAMOND ANALYSIS PLAN - LEVEL 03
061-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
061-GI111 EGRESS AND SEQUENCE DIAGRAM - LEVEL 02
061-GI112 EGRESS AND SEQUENCE DIAGRAM - LEVEL 03
08-ARCHITECTURE
061-AE101 OVERALL FLOOR PLAN - LEVEL 01
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 12
061-AE102 OVERALL FLOOR PLAN - LEVEL 02
061-AE103 OVERALL FLOOR PLAN - LEVEL 03
061-AE401 TR 113B - ENLARGED FLOOR PLANS, RCPS AND INTERIOR ELEVATIONS
061-AE402 TR 214B - ENLARGED FLOOR PLANS, RCPS AND INTERIOR ELEVATIONS
061-AE601 SCHEDULES
061-H401 TR 113B & TR 214B - ENLARGED ABATEMENT FLOOR PLAN AND RCP
11-FIRE PROTECTION
061-FX101 FIRE PROTECTION OVERALL PLAN - LEVEL 1
061-FX102 FIRE PROTECTION OVERALL PLAN - LEVEL 2
12-PLUMBING
061-PD401 PLUMBING ENLARGED DEMOLITION PLANS
061-PP101 PLUMBING OVERALL PLAN - LEVEL 01
061-PP102 PLUMBING OVERALL PLAN - LEVEL 02
061-PP401 PLUMBING ENLARGED PLANS
14-MECHANICAL
061-MD401 ENLARGED MECHANICAL DEMOLITION PLANS
061-MP101 MECHANICAL OVERALL PLAN - LEVEL 01
061-MP102 MECHANICAL OVERALL PLAN - LEVEL 02
061-MP401 MECHANCIAL ENLARGED PLANS
061-MP601 MECHANICAL SCHEDULES
15-ELECTRICAL
061-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
061-ED102 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 02
061-ED103 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 03
061-ED401 ELECTRICAL ENLARGED DEMOLITION PLANS
061-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
061-EP102 ELECTRICAL OVERALL POWER PLAN - LEVEL 02
061-EP103 ELECTRICAL OVERALL POWER PLAN - LEVEL 03
061-EP401 ELECTRICAL ENLARGED POWER PLANS
061-EP501 ELECTRICAL DETAILS
061-EP601 ONE-LINE DIAGRAM
061-EP602 PANEL SCHEDULES
16-TELECOMMUNICATION
061-TD101 TELECOMMUNICATIONS OVERALL DEMOLITION PLAN - LEVEL 01
061-TD102 TELECOMMUNICATIONS OVERALL DEMOLITION PLAN - LEVEL 02
061-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
061-TN102 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 02
061-TN103 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 03
061-TN401 TELECOMMUNICATIONS ENLARGED PLANS
061-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
061-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 13
061-TN602 TELECOMMUNICATIONS RACK ELEVATIONS
16.4-SECURITY
061-TY101 SECURITY FLOOR PLANS - LEVEL 01
061-TY102 SECURITY FLOOR PLANS - LEVEL 02
061-TY103 SECURITY FLOOR PLANS - LEVEL 03
BLDG 062
062-GI001 COVER SHEET
062-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
062-GI110 EGRESS & SEQUENCE DIAGRAMS
08-ARCHITECTURE
062-AE101 OVERALL FLOOR PLAN - LEVEL 01
15-ELECTRICAL
062-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
062-ED401 ELECTRICAL ENLARGED DEMOLITION PLANS
062-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
062-EP401 ELECTRICAL ENLARGED POWER PLANS
062-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
062-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
062-TN401 TELECOMMUNICATIONS ENLARGED PLANS
062-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
062-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
062-TY101 SECURITY FLOOR PLANS - LEVEL 01
BLDG 071
071-GI001 COVER SHEET
071-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
071-GI110 EGRESS & SEQUENCE DIAGRAMS - LEVEL 01
08-ARCHITECTURE
071-AE101 OVERALL FLOOR PLAN - LEVEL 01
16-TELECOMMUNICATION
071-TD101 TELECOMMUNICATIONS DEMOLITION PLAN - LEVEL 01
071-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
BLDG 072
072-GI001 COVER SHEET
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 14
072-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
072-GI110 EGRESS & SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
072-AE101 OVERALL FLOOR PLAN - LEVEL 01
16-TELECOMMUNICATION
072-TD101 TELECOMMUNICATIONS DEMOLITION PLAN - LEVEL 01
072-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
BLDG 081
081-GI001 COVER SHEET
081-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
081-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
081-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
081-GI103 DIAMOND ANALYSIS PLAN - LEVEL 03
081-GI104 DIAMOND ANALYSIS PLAN - LEVEL 04
081-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 00
081-GI111 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
081-GI112 EGRESS AND SEQUENCE DIAGRAM - LEVEL 03
08-ARCHITECTURE
081-AE100 OVERALL FLOOR PLAN - LEVEL 00
081-AE101 OVERALL FLOOR PLAN - LEVEL 01
081-AE102 OVERALL FLOOR PLAN - LEVEL 02
081-AE103 OVERALL FLOOR PLAN - LEVEL 03
081-AE104 OVERALL FLOOR PLAN - LEVEL 04
15-ELECTRICAL
081-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 00
081-ED102 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
081-ED103 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 03
081-ED401 ELECTRICAL ENLARGED DEMOLITION PLANS
081-EP101 ELECTRICAL OVERALL POWER - LEVEL 00
081-EP102 ELECTRICAL OVERALL POWER - LEVEL 01
081-EP103 ELECTRICAL OVERALL POWER - LEVEL 03
081-EP401 ELECTRICAL ENLARGED POWER PLANS
081-EP402 ELECTRICAL ENLARGED POWER PLANS
081-EP501 ELECTRICAL DETAILS
081-EP502 ELECTRICAL DETAILS
081-EP601 ONE-LINE DIAGRAM
081-EP701 PANEL SCHEDULES
16-TELECOMMUNICATION
081-TN100 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 00
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 15
081-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
081-TN103 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 03
081-TN401 TELECOMMUNICATIONS ENLARGED PLANS
081-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
081-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
081-TN602 TELECOMMUNICATIONS RACK ELEVATIONS
081-TN603 TELECOMMUNICATIONS RACK ELEVATIONS
081-TN604 TELECOMMUNICATIONS RACK ELEVATIONS
16.4-SECURITY
081-TY100 SECURITY FLOOR PLANS - LEVEL 00
081-TY101 SECURITY FLOOR PLANS - LEVEL 01
081-TY102 SECURITY FLOOR PLAN - LEVEL 02
081-TY103 SECURITY FLOOR PLANS - LEVEL 03
081-TY104 SECURITY FLOOR PLAN - LEVEL 04
BLDG 085
085-GI001 COVER SHEET
085-GI100 DIAMOND ANALYSIS PLAN - LEVEL 00
085-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
085-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
085-GI103 DIAMOND ANALYSIS PLAN - LEVEL 03
085-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 02
08-ARCHITECTURE
085-AE100 OVERALL FLOOR PLAN - LEVEL 00
085-AE101 OVERALL FLOOR PLAN - LEVEL 01
085-AE102 OVERALL FLOOR PLAN - LEVEL 02
085-AE103 OVERALL FLOOR PLAN - LEVEL 03
15-ELECTRICAL
085-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 02
085-ED401 ELECTRICAL ENLARGED DEMOLITION PLAN
085-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 02
085-EP401 ELECTRICAL ENLARGED POWER PLAN
085-EP501 ELECTRICAL DETAILS
085-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
085-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
085-TN102 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 02
085-TN401 TELECOMMUNICATIONS ENLARGED PLANS
085-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
085-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 16
085-TY101 SECURITY FLOOR PLANS
BLDG 111
111-GI001 COVER SHEET
111-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
111-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
111-AE101 OVERALL FLOOR PLAN - LEVEL 01
111-AE401 TE 103 - ENLARGED FLOOR PLANS AND INTERIOR ELEVATION
15-ELECTRICAL
111-EP101 ELECTRICAL POWER OVERALL PLAN - LEVEL 01
111-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
111-TD101 TELECOMMUNICATIONS OVERALL DEMOLITION PLAN - LEVEL 01
111-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
111-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
111-TY101 SECURITY FLOOR PLANS - LEVEL 01
BLDG 143
143-GI001 COVER SHEET
143-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
143-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
143-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
143-AE101 OVERALL FLOOR PLAN - LEVEL 01
143-AE102 OVERALL FLOOR PLAN - LEVEL 02
15-ELECTRICAL
143-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
143-ED401 ELECTRICAL ENLARGED DEMOLITION PLAN
143-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
143-EP401 ELECTRICAL ENLARGED POWER PLAN
143-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
143-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
143-TN401 TELECOMMUNICATIONS ENLARGED PLANS
143-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
16.4-SECURITY
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 17
143-TY101 SECURITY FLOOR PLANS
BLDG 148
148-GI001 COVER SHEET
148-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
148-GI102 DIAMOND ANALYSIS PLAN - LEVEL 02
148-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
148-AE101 OVERALL FLOOR PLAN - LEVEL 01
148-AE102 OVERALL FLOOR PLAN - LEVEL 02
148-AE401 TR 146A - ENLARGED FLOOR PLANS, RCPS AND INTERIOR ELEVATIONS
148-AE601 SCHEDULES
148-H401 TR 146A & TR 131- ENLARGED ABATEMENT FLOOR PLAN AND RCP
11-FIRE PROTECTION
148-FX101 FIRE PROTECTION OVERALL PLANS - LEVEL 01
12-PLUMBING
148-PD401 PLUMBING ENLARGED DEMOLITION PLANS
148-PP101 PLUMBING OVERALL PLAN - LEVEL 01
148-PP401 PLUMBING ENLARGED PLANS
14 - MECHANICAL
148-MD401 MECHANICAL ENLARGED DEMOLITION PLANS
148-MP101 MECHANICAL OVERALL PLAN - LEVEL 01
148-MP401 MECHANICAL ENLARGED PLANS
148-MP601 MECHANICAL SCHEDULES
15-ELECTRICAL
148-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
148-ED401 ELECTRICAL ENLARGED DEMOLITION PLAN
148-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
148-EP401 ELECTRICAL ENLARGED POWER PLAN
148-EP601 ONE-LINE DIAGRAM AND PANEL SCHEDULES
16-TELECOMMUNICATION
148-TD101 TELECOMMUNICATIONS OVERALL DEMOLITION PLAN - LEVEL 01
148-TD600 TELECOMMUNICATIONS EXISTING ELEVATIONS
148-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
148-TN401 TELECOMMUNICATIONS ENLARGED PLANS
148-TN600 TELECOMMUNICATIONS RISER DIAGRAMS RACK ELEVATIONS
148-TY101 SECURITY FLOOR PLANS
BLDG 199
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 18
199-GI001 COVER SHEET
199-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
199-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
199-AE101 OVERALL FLOOR PLAN - LEVEL 01
11-FIRE PROTECTION
199-FA101 FIRE ALARM OVERALL PLAN - LEVEL 01
199-FX101 CLEAN AGENT OVERALL PLAN - LEVEL 01
15-ELECTRICAL
199-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
199-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
199-EP501 ELECTRICAL DETAILS
199-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
199-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
199-TN401 TELECOMMUNICATIONS ENLARGED PLANS
199-TN402 TELECOMMUNICATIONS ENLARGED PLANS
199-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
199-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
199-TY101 SECURITY FLOOR PLANS
BLDG 200
200-GI001 COVER SHEET
200-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
200-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
200-AE101 OVERALL FLOOR PLAN - LEVEL 01
200-AE401 ENLARGED FLOOR PLANS
15-ELECTRICAL
200-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
200-ED401 ELECTRICAL ENLARGED DEMOLITION PLANS
200-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
200-EP401 ELECTRICAL ENLARGED POWER PLANS
200-EP402 ELECTRICAL ENLARGED POWER PLANS
200-EP501 ELECTRICAL DETAILS
200-EP601 ONE-LINE DIAGRAM
200-EP602 PANEL SCHEDULES
200-EP603 PANEL SCHEDULES
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 19
200-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
200-TN401 TELECOMMUNICATIONS ENLARGED PLANS
200-TN600 TELECOMMUNICATIONS RISER DIAGRAMS
200-TN601 TELECOMMUNICATIONS RACK ELEVATIONS
200-TN602 TELECOMMUNICATIONS RACK ELEVATIONS
200-TN603 TELECOMMUNICATIONS RACK ELEVATIONS
200-TN604 TELECOMMUNICATIONS RACK ELEVATIONS
200-TY101 SECURITY FLOOR PLANS
BLDG 202
202-GI001 COVER SHEET
202-GI100 DIAMOND ANALYSIS PLAN - LEVEL 01
202-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
202-AE101 OVERALL FLOOR PLAN - LEVEL 01
15-ELECTRICAL
202-ED101 ELECTRICAL OVERALL DEMOLITION PLAN - LEVEL 01
202-ED401 ELECTRICAL ENLARGED DEMOLITION PLAN
202-EP101 ELECTRICAL OVERALL POWER PLAN - LEVEL 01
202-EP401 ELECTRICAL ENLARGED POWER PLAN
202-EP501 ELECTRICAL DETAILS
202-EP601 ONE-LINE DIAGRAM
16-TELECOMMUNICATION
202-TN101 TELECOMMUNICATIONS OVERALL PLAN - LEVEL 01
202-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
202-TY101 SECURITY FLOOR PLANS
BLDG MRI
MRI-GI001 COVER SHEET
MRI-GI101 DIAMOND ANALYSIS PLAN - LEVEL 01
MRI-GI110 EGRESS AND SEQUENCE DIAGRAM - LEVEL 01
08-ARCHITECTURE
MRI-AE101 NEW TE - FLOOR PLAN, ENLARGED PLAND AND INTERIOR ELEVATION
15-ELECTRICAL
MRI-EP100 ELECTRICAL OVERALL POWER PLAN - LEVEL 1
MRI-EP600 ONE-LINE DIAGRAM
American Lake VA Medical Center
EHRM Infrastructure Upgrades
List of Drawing Sheets 000115 - 20
MRI-TN100 TELECOMMUNICATIONS FLOOR PLAN - LEVEL 1
MRI-TN600 TELECOMMUNICATIONS RISER DIAGRAMS AND RACK ELEVATIONS
MRI-TY101 SECURITY FLOOR PLANS
TOTAL NUMBER OF
SHEETS: 560
--- END ---
EHRM Infrastructure Upgrades
Project Number 663A4-24-703
October 2, 2025
GENERAL REQUIREMENTS 010000 - 1
SECTION 010000
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 013526, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing construction, and furnish labor and materials and perform work for American Lake VA Medical
Center, EHRM Infrastructure Upgrades, as required by drawings and specifications.
B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting
Officer.
C. Offices of Awen Solutions Group, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by General Contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, necessary removal of existing structures and construction. All work shall be performed in accordance with contract drawings and specifications.
American Lake VA Medical Center
EHRM Infrastructure Upgrades
Project Number 663A4-24-703
October 2, 2025
GENERAL REQUIREMENTS 010000 - 2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION DOCUMENT MANAGEMENT SOFTWARE SYSTEM.
A. Provide, administer, and use construction document management software system for purposes of hosting and managing Project communication and documentation in electronic form until final completion.
1. Construction document management software system shall include, at a minimum, the following features:
a. Compilation of Project Contract Documents, Project communications required in individual Specification Sections, including, but not limited to, substitution requests, RFIs, submittals, construction schedule, COR’s Supplemental Instructions, Change Order
Proposals, and Change Orders, Applications and Certifications for
Payment, meeting minutes, Drawings, Specifications, coordination drawings, and list of incomplete and deficient Work.
b. Compilation of Project data for each entity involved in Project, including Contractor, subcontractors, Architect, Architect's consultants, and COR. Include names of individuals and contact information.
c. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents.
d. Document workflow planning, allowing customization of workflow between project entities.
e. Creation, logging, tracking, and notification for Project communications required in individual Specification Sections, including, but not limited to, substitution request, RFIs, submittals, COR’s Supplemental Instructions, , Proposal Requests, Change Order Proposals, and Change Orders.
f. Track status of each Project communication in real time, and log time and date when responses are provided.
g. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.
American Lake VA Medical Center
EHRM Infrastructure Upgrades
GENERAL REQUIREMENTS 010000 - 3
h. Processing and tracking of payment applications.
i. Processing and tracking of contract modifications.
j. Creating and distributing meeting minutes.
k. Document management for Drawings, Specifications, and coordination drawings, including revision control.
l. Creating, distributing, tracking, and updating list of incomplete items (punch list).
m. Mobile device compatibility, including smartphones and tablets.
n. Construction document management software system tutorials, training videos, and user support.
2. Provide free user licenses for use by COR, Architect, and their consultants.
3. At completion of Project, provide digital archive of documents generated or stored within construction document management software system in format acceptable to Owner and Architect. Provide data in locked format to prevent further changes.
4. Products: Provide [one of] the following:
a. Autodesk Inc.; Construction Cloud.
b. Corecon Technologies, Inc.; Corecon.
c. Trimble Inc.; Prolog or ProjectSight.
d. Newforma, Inc.; ConstructEx.
e. Oracle; Primavera Submittal Exchange.
f. Procore Technologies, Inc.; Procore.
1.6 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can
American Lake VA Medical Center
EHRM Infrastructure Upgrades
GENERAL REQUIREMENTS 010000 - 4
be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project, and to take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 087100, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
American Lake VA Medical Center
EHRM Infrastructure Upgrades
GENERAL REQUIREMENTS 010000 - 5
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. An unlimited number of permits shall be issued for General
Contractor and its employees for parking in designated areas only.
Contractor to coordinate with VA Medical Center Facility Manager.
1.7 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
American Lake VA Medical Center
EHRM Infrastructure Upgrades
GENERAL REQUIREMENTS 010000 - 6
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence
American Lake VA Medical Center
EHRM Infrastructure Upgrades
GENERAL REQUIREMENTS 010000 - 7
of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR, and
Contractor.
3. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
American Lake VA Medical Center
EHRM Infrastructure Upgrades
GENERAL REQUIREMENTS 010000 - 8
Veterans Affairs so that Medical Center operations will continue during the construction period.
4. Immediate areas of alterations not noted will be temporarily vacated while alterations are performed.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 1.83 m (six feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned…
This is the start of the file's text. The full file is on GovTribe.