Summary
This is a pricing template for a Blanket Purchase Agreement (BPA) solicitation for handyman, maintenance, repair, and minor construction services to be performed on a task order basis. The contractor shall provide all labor, materials, supervision, equipment, and incidental services necessary to complete approximately 200–300 task orders annually, with most individual task orders valued under $15,000 and all work generally under the Simplified Acquisition Threshold (SAT). Pricing shall be submitted in U.S. dollars and include all direct and indirect costs unless otherwise specified.
The contractor must provide fully burdened hourly labor rates for 17 distinct labor categories ranging from General Laborer to Control Technician/Specialist, with estimated annual hours ranging from 2,080 to 4,160 hours per category. Rates must include all wages, fringe benefits, administrative expenses, incidentals, and consumables; only overhead and profit may be applied as additional markups to labor. Labor rates are subject to Davis-Bacon Act (DBA) wage determinations for construction work above $2,000 and Service Contract Labor Standards (SCLA) for maintenance services above $2,500. Materials are reimbursed at actual invoice cost with no overhead or profit allowed, though a material handling/markup rate (not to exceed a specified percentage) may be applied. The contractor shall provide overhead and profit percentages as ceiling rates; the Contracting Officer retains the right to negotiate lower rates at the call level. Emergency/after-hours service premiums (after hours, weekend/holiday, and emergency response) may be applied to labor only with pre-approval. The BPA term is five years, with annual reviews to ensure fair and reasonable pricing and continued performance. Contractors may request labor rate adjustments within 30 days of updated wage determinations, subject to Contracting Officer approval.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Handyman BPA Synopsis (UPDATED).pdf | ||
| Attachment 4-Handyman Past Performance Questionnaire.docx | DOCX document | |
| Attachment 3-DBA Wage Determiantion.pdf | ||
| Attachment 2-SCLA Wage determination.pdf | ||
| Handyman BPA Synopsis 5 14 26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL
The Contractor shall provide all labor, materials, supervision, equipment, and incidental services necessary to perform handyman, maintenance, repair, and minor construction services on a task order basis.
Work will consist of approximately 200–300 task orders annually, generally under the Simplified Acquisition Threshold (SAT), with most individual task orders valued under $15,000.
All prices shall be in U.S. dollars and shall include all direct and indirect costs unless otherwise specified.
LABOR RATES (FULLY BURDENED)
The Contractor shall provide fully burdened hourly labor rates for each labor category listed below. Rates shall include all wages, fringe benefits, administrative expenses, incidentals and consumables expenses.
Only additional markups that can be applied to labor is overhead and profit.
CLIN Labor Category Unit Estimated Hours (Annual)
Unit Price ($/Hr)
Total Price
0001 General Laborer (DBA) Hr 4160 $_______ $________
0001 General Maintenance Worker (SCLA) Hr 4160 $_______ $________
0002 Carpenter (DBA) Hr 4160 $_______ $________ 0002a Carpenter, Maintenance (SCLA) Hr 4160 $_______ $________ 0003 Electrician (DBA) Hr 2080 $_______ $________ 0003a Electrician Apprentice (DBA) Hr 2080 $_______ $________ 0003b Electrician, Maintenance (SCLA) Hr 2080 $_______ $________ 0004 Plumber (DBA) Hr 2080 $_______ $________ 0004a Plumber, Maintenance (DBA) 0004b Plumber Maintenance (SCLA) Hr 2080 $_______ $________ 0005 HVAC Technician (DBA) Hr 2080 $_______ $________ 0005a HVAC apprentice (DBA) 0005b HVAC, Maintenance (SCLA) Hr 2080 $______ $________ 0006 Painter (DBA) Hr 4160 $______ $________ 0006a Painter, Maintenance (SCLA) Hr 4160 $______ $________ 0007 Maintenance Mechanic (SCLA) Hr 2080 $______ $________ 0008 Supervisor/Foreman Hr 2080 $_____ $________ 0009 Locksmith (SCLA) Hr 2080 $_____ $________ 0010 Control Technician/Specialist Hr 2080 $______ $________
0011 Welder (DBA) Hr 2080 $______ $________ 0011a Welder, Maintenance (SCLA) Hr 2080 $______ $________ 0012 Pipe Fitter (DBA) Hr 2080 $______ $________ 0012a Pipe Fitter, Maintenance (SCLA) Hr 2080 $______ $________ 0013 Sheet-Metal Worker (DBA) Hr 2080 $______ $________ 0013a Sheet-Metal Worker (SCLA) Hr 2080 $______ $________ 0014 Furniture Handler (SCLA) Hr 4160 $______ $________ 0015 Carpet Layer (DBA) Hr 4160 $______ $________ 0015a Carpet Layer (SCLA) Hr 4160 $______ $________ 0016 Rigger (SCLA) Hr 2080 $______ $________
0017 Drywall Spackling, Taping, & Finishing (DBA) Hr 2080 $______ $________
If you are a specialized contractor that provides only certain services (e.g., electrical, mechanical), complete only the portions of the pricing table applicable to your trade(s). If you are capable of providing all required services (or most), please complete the entire pricing table accordingly.
NOTES:
1. DBA applies to projects considered to be construction above $2,000, the General Wage Determination issued under the Davis-Bacon and Related Acts (DBRA) by the U.S.
Department of Labor.
2. SCLA applies to service, to include maintenance services, above $2,500 for which the McNamara-O’Hara Service Contract Labor Standards statute (formerly the Service Contract Act (SCA)) by the U.S. Department of Labor.
Other trades will be negotiated on a case-by-case requirement as dictated by the type of work to be performed.
Estimated hours are for evaluation purposes only and do not guarantee quantities.
MATERIALS
Materials shall be reimbursed at the Contractor’s actual invoice cost. No additional overhead or profit will be allowed on materials.
The Contractor may apply a material handling/markup rate not to exceed ___%.
CLIN Description Unit Estimated Amount Markup % Total Price 0010 Materials (Reimbursable) Lot $75,000 ___% $____.__
Requirements:
• Supporting invoices shall be provided upon request
• No markup shall be applied to sales tax, shipping, or pass-through costs.
• All discounts, rebates, or credits shall be passed to the Government
INCIDENTALS AND CONSUMABLES
All minor tools, consumables, fasteners, and standard supplies (e.g., screws, sealants, adhesives, PPE) shall be included in the labor rates and shall not be billed separately.
OVERHEAD AND PROFIT
Overhead: ___% Profit: ___%
The above percentages represent the maximum allowable indirect cost and profit rates applicable to this contract. These rates shall be considered ceilings and shall not be automatically applied to all calls. Ordering Officials (Contracting Officer or authorized COR, as applicable) retain the right to negotiate lower overhead and/or profit rates at the call level based on the scope, complexity, risk, and competitive conditions of the requirement. Nothing in this section shall be construed as guaranteeing application of the maximum rates.
CALL PRICING
Each task order shall be priced as follows:
Total Task Order Price = (Labor Hours × Contract Labor Rates) x Applicable Overhead and Profit + (Material Costs × Approved Material Handling/Markup Rate (overhead and profit will not be added to material cost))
The Contractor shall provide a detailed estimate for call, including:
• Labor categories and hours
• Material quantities and costs
• Total Not-to-Exceed (NTE) price
EMERGENCY / AFTER-HOURS SERVICES
CLIN Service Type Adjustment 0011 After Hours +___% 0012 Weekend/Holiday +___% 0013 Emergency Response +___%
Premiums shall apply to labor only and must be pre-approved by the Contracting Officer or
COR.
PRICE CEILING / ORDER LIMITATIONS
Individual task orders shall not exceed the Simplified Acquisition Threshold unless otherwise authorized by the contracting officer. No calls above $15,000 can be processed via the Government Purchase Card. Calls above $15,000 shall be processed by a contracting officer.
TOTAL EVALUATED PRICE
The Total Evaluated Price shall be the sum of all CLINs for the base period (and option periods, if applicable
BPA TERM AND ANNUAL REVIEW
The Blanket Purchase Agreements (BPAs) established under this solicitation shall have a five (5) year ordering period.
In accordance with FAR Part 13, the Government will conduct an annual review of each BPA to ensure pricing remains fair and reasonable, and that performance continues to meet the Government’s needs.
As part of the annual review, the Government will provide updated Davis-Bacon Wage Determinations and Service Contract Labor Standards (SCLS), as applicable. Upon issuance of updated wage determinations, the Contractor may request adjustments to labor rates.
Any request for labor rate adjustments shall be submitted in writing within thirty (30) calendar days of the Government’s issuance of the updated wage determinations. The request shall include sufficient supporting documentation to justify the proposed changes. Adjustments are not automatic and are subject to review, negotiation, and approval by the Contracting Officer.
| GENERAL |
| LABOR RATES (FULLY BURDENED) |
| MATERIALS |
| INCIDENTALS AND CONSUMABLES |
| OVERHEAD AND PROFIT |
| CALL PRICING |
| EMERGENCY / AFTER-HOURS SERVICES |
| PRICE CEILING / ORDER LIMITATIONS |
| TOTAL EVALUATED PRICE |
| The Total Evaluated Price shall be the sum of all CLINs for the base period (and option periods, if applicable |
| BPA TERM AND ANNUAL REVIEW |