This is a Price Schedule for dam area mowing and trimming services at Fort Peck, Montana, issued by the US Army Corps of Engineers. The contract covers a base year from May 1, 2026 through April 30, 2027, with four optional one-year extensions through April 30, 2031. Active service periods run from May 1 through September 30 of each year, with inactive periods from October 1 through April 30 when the contractor is not required to perform services.

The scope of work is divided into five contract line items (CLINs) representing distinct geographic tracts: CLIN 0001 covers the Shaft Area Buildings & Overlook; CLIN 0002 covers the Spillway Building Area & Overlook; CLIN 0003 covers Yellowstone Road, Jefferson Road, Dam Crest, and Middle Road; CLIN 0004 covers the Relief Well Area & Toe Road; and CLIN 0005 covers Dam Coulee Roads & Instrumentation. The base year specifies maximum quantities of 8 mowings for CLINs 0001-0004 and 4 mowings for CLIN 0005, measured in each (EA). Option Years 1-4 reduce the quantities to 6 mowings for CLINs 0001-0004 while maintaining 4 mowings for CLIN 0005. The price schedule contains blank columns for unit cost and annual maximum cost, to be filled in by offerors during the solicitation process. Actual quantities may vary based on Performance Work Statement (PWS) requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

DAM AREA MOWING/ TRIMMING

FORT PECK, MONTANA

US ARMY CORPS OF ENGINEERS

Base Year: 01 May 2026 through 30 April 2027

• Active period of performance: 01 May 2026 through 30 September 2026

• Inactive period of performance: 01 October 2026 through 30 April 2027

*Note: The Contractor is not required to perform any services during the inactive period of performance.

DESCRIPTION MAX

QTY

UNIT UNIT

COST $

ANNUAL MAX

COST $

CLIN 0001- TRACT #1 – SHAFT AREA

BUILDINGS & OVERLOOK

8 EA

CLIN 0002- TRACT #2 -SPILLWAY

BUILDING AREA & OVERLOOK

8 EA

CLIN 0003- TRACT #3 -YELLOWSTONE

ROAD, JEFFERSON ROAD, DAM CREST,

MIDDLE ROAD

8 EA

CLIN 0004- TRACT #4 -RELIEF WELL AREA

& TOE ROAD

8 EA

CLIN 0005- TRACT #5 -DAM COULEE

ROADS & INSTRUMENTATION

4 EA

Note: Quantities listed are the maximum number of mowings. Actual quantities may vary per PWS requirements.

Option Year 1: 01 May 2027 through 30 April 2028

• Active period of performance: 01 May 2027 through 30 September 2027

• Inactive period of performance: 01 October 2027 through 30 April 2028

UNIT UNIT

COST $

ANNUAL MAX

COST $

CLIN 0001- TRACT #1 – SHAFT AREA

BUILDINGS & OVERLOOK

6 EA

CLIN 0002- TRACT #2 -SPILLWAY

BUILDING AREA & OVERLOOK

6 EA

CLIN 0003- TRACT #3 -YELLOWSTONE

ROAD, JEFFERSON ROAD, DAM CREST,

MIDDLE ROAD

6 EA

CLIN 0004- TRACT #4 -RELIEF WELL AREA

& TOE ROAD

6 EA

CLIN 0005- TRACT #5 -DAM COULEE

Option Year 2: 01 May 2028 through 30 April 2029

• Active period of performance: 01 May 2028 through 30 September 2028

• Inactive period of performance: 01 October 2028 through 30 April 2029

UNIT UNIT

COST $

ANNUAL MAX

COST $

CLIN 0001- TRACT #1 – SHAFT AREA

BUILDINGS & OVERLOOK

6 EA

CLIN 0002- TRACT #2 -SPILLWAY

BUILDING AREA & OVERLOOK

6 EA

CLIN 0003- TRACT #3 -YELLOWSTONE

ROAD, JEFFERSON ROAD, DAM CREST,

MIDDLE ROAD

6 EA

CLIN 0004- TRACT #4 -RELIEF WELL AREA

& TOE ROAD

6 EA

CLIN 0005- TRACT #5 -DAM COULEE

Option Year 3: 01 May 2029 through 30 April 2030

• Active period of performance: 01 May 2029 through 30 September 2029

• Inactive period of performance: 01 October 2029 through 30 April 2030

UNIT UNIT

COST $

ANNUAL MAX

COST $

CLIN 0001- TRACT #1 – SHAFT AREA

BUILDINGS & OVERLOOK

6 EA

CLIN 0002- TRACT #2 -SPILLWAY

BUILDING AREA & OVERLOOK

6 EA

CLIN 0003- TRACT #3 -YELLOWSTONE

ROAD, JEFFERSON ROAD, DAM CREST,

MIDDLE ROAD

6 EA

CLIN 0004- TRACT #4 -RELIEF WELL AREA

& TOE ROAD

6 EA

CLIN 0005- TRACT #5 -DAM COULEE

Option Year 4: 01 May 2030 through 30 April 2031

• Active period of performance: 01 May 2030 through 30 September 2030

• Inactive period of performance: 01 October 2030 through 30 April 2031

UNIT UNIT

COST $

ANNUAL MAX

COST $

CLIN 0001- TRACT #1 – SHAFT AREA

BUILDINGS & OVERLOOK

6 EA

CLIN 0002- TRACT #2 -SPILLWAY

BUILDING AREA & OVERLOOK

6 EA

CLIN 0003- TRACT #3 -YELLOWSTONE

ROAD, JEFFERSON ROAD, DAM CREST,

MIDDLE ROAD

6 EA

CLIN 0004- TRACT #4 -RELIEF WELL AREA

& TOE ROAD

6 EA

CLIN 0005- TRACT #5 -DAM COULEE