Attachment 1 - Performance Work Statement.pdf
PDF 349 KB Posted
- Solicitation number
- W50S7S26Q0035
- Issued by
-
Department of the Army National Guard
About this file
This is a Performance Work Statement (PWS) for landscape planter bed repair and restoration at Scott Air Force Base, Illinois, with contract number VDYD262015, dated 03 September 2026.
The project involves comprehensive restoration of approximately 1,664 linear feet of metal edging and 14,511 square feet of planter bed areas across 18 locations at the 126th Air Refueling Wing. The scope consists of six primary tasks: (1) removal of deteriorated metal lining and anchor stakes; (2) removal of existing decorative rock and weed barrier using non-destructive methods to protect plant root systems; (3) removal of deteriorated weed barrier fabric; (4) installation of heavy-duty, needle-punched non-woven polypropylene geotextile fabric meeting minimum specifications of 4.5 oz/sq. yd material weight, 115 lbs grab tensile strength, and 300 lbs CBR puncture strength; (5) installation of new commercial-grade steel planter bed liners (1/8" thick by 8" high) with corrosion-resistant polyester powder-coat finish or hot-dip galvanized; and (6) placement of new matching decorative river gravel or granite stone (1" to 4" diameter) to achieve a uniform 3-inch average depth. The contractor must retain all existing landscaped plants, including shrubs, flowers, trees, and bushes, working carefully around root systems and maintaining a 2-inch buffer zone around plant collars to prevent crown rot. Work must be completed within a contractor-proposed performance period from Notice to Proceed, with construction scheduled during standard business hours (7:30 A.M. to 4:30 P.M., Monday through Friday), excluding federal holidays and scheduled base down days. The contractor is responsible for all field measurements, site verification, obtaining required Air Force forms (AF Form 103, AF Form 3000, DD Form 1354, AF Form 592 if applicable), providing detailed construction schedules with milestones, conducting bi-weekly coordination meetings with 126th Contracting Squadron and 126th Civil Engineer Squadron, and delivering comprehensive submittals and as-built documentation upon project completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FOR
REPAIR Planter Beds Various Locations
VDYD262015
SCOTT AIR FORCE BASE, ILLINOIS
03 September 2026
1. REQUIREMENT:
a. BACKGROUND: There are numerous planter areas on the 126 ARW’s property alongside entrances to Wing buildings and along walking paths. These planters have a typical design of a weed barrier laid over subgrade. Decorative rock fill of rocks between
1” to 4” in diameter is placed on top of the weed barrier to an averaged depth of 3”.
Bordering the decorative rock fill is a 1/8” thick X 8” high metal barrier. The metal barrier is installed only where the planter areas border grassed areas. The weed barriers in the planters have not been replaced since their installation and grass, weeds, trees, and other plants are growing from the rock beds where they were not planted or planned to grow.
Because of this, a significant amount of time and resources are spent manually removing the wild plants from the landscaped beds and trimming them. The metal barriers lining the planter beds are rusted in various locations presenting hazardous jagged lengths of metal which could trip and cut working crew members near them.
b. OBJECTIVES: The objective of this project is to restore the planter beds to their original condition free of tears, weeds, grass, and other unplanned plants growing through the underlying weed barrier as well as replacing the deteriorated metal lining with new functioning liners. The existing landscaped plants, including shrubs, flowers, trees, bushes, etc. shall be retained, worked around and beneath, and protected from damage during the scope of this project. Key objectives include:
i. Remove approximately 1664 LF of metal lining from the borders of the planter beds.
ii. Remove approximately 14511 SF of decorative rock and underlying weed barrier from the various planter beds on the 126 ARW property.
iii. Where existing shrubs and plants are to be retained the existing decorative rock and weed barrier shall be removed in a manner to prevent the damage to the existing root system.
iv. Install new weed barrier on top of subgrade.
v. Install new bed liners replacing the removed metal lining.
vi. Place decorative rock to provide an average depth of 3”. In areas where plants are retained, the rock depth may be feathered out as necessary as it approaches the trunk/stem of the plant.
c. PROJECT LOCATION: All work will be at the 126th Air Refueling Wing, Scott AFB, Illinois.
2. PROJECT ADMINISTRATION:
a. SITE VISIT: Contractor is responsible for verifying all measurements and conditions pre-bid. The Government intends to only hold one official site visit. Requests for additional site access must go through the 126th Contracting Squadron (126 CONS) point of contact (POC) listed in the Request for Proposal (RFP) letter. Any additional site access will be made available to all Contractors solicited for this project.
b. MEETINGS
i. Kick-Off Meeting/Project Schedule – Kick-off meeting to occur within one week of NTP. Overall project schedule with milestone markers and 2-week look-ahead to be completed at kick-off meeting.
ii. Contractor shall coordinate with the 126th Contracting Squadron (126 CONS) on bi-weekly meetings once the construction phase begins. This meeting shall include the review of an updated 2-week look ahead schedule. Contractor shall provide meeting minutes within 24 hours of each meeting and allow the Government up to 24 hours to accept or request changes to the minutes.
3. PROJECT SCOPE:
a. The contractor shall address the known issues identified in this scope. To the maximum extent possible, contractors should identify defects or discrepancies not noted below by submitting a Request for Information (RFI) prior to bid submission. Approximate total quantities to be replaced under this CLIN are 1,664 LF of edging/bed lining and 14,511 SF of weed barrier and decorative rock.
b. Planter Areas – Reinstall
i. Task 1: Metal Lining Removal
(1) 1.1 Contractor shall cleanly excavate, remove, and dispose of approximately 1,664
LF of existing rusted and deteriorated metal lining bordering the planter beds at each building and location per the reference set of plans titled “Repair Landscape
Basewide VDYD 112012”.
(2) 1.2 Removal shall include extracting all associated anchor stakes, splices, and broken metal fragments. The Contractor shall avoid damaging adjacent turf, sidewalks, structures, or the root systems of existing plants. All removed metal lining shall be legally disposed of off base property.
ii. Task 2: Decorative Rock Removal
(1) 2.1 Contractor shall remove the existing decorative rock from within the 14,511 SF of planter beds.
(2) 2.2 The existing decorative rock and weed barrier shall be removed using non-destructive methods (such as hand tools or industrial landscape vacuums) to prevent damage to the trunks, bark, limbs, or existing root systems of remaining plants.
(3) 2.3 Contractor shall screen and wash the removed decorative rock to eliminate accumulated soil, organic matter, and weed seeds. Washed rock shall be stored on heavy-duty tarps or other approved impermeable barriers in a location designated by Civil Engineering (CE) to avoid ground contamination or turf damage.
iii. Task 3: Remove Weed Barrier
(1) 3.1 Contractor shall remove the existing deteriorated weed barrier fabric from within the 14,511 SF of planter beds, ensuring no residual scraps remain in the subgrade.
(2) 3.2 Removal around the root zones of retained plants shall be done carefully by hand to prevent root tear or plant displacement.
(3) 3.3 Following removal, the Contractor shall hand-weed and grub the exposed subgrade to extract remaining weed roots and wild sapling root systems.
(4) 3.4 Contractor shall collect and dispose of all removed weed barrier fabric off base property in accordance with federal, state, and local regulations.
iv. Task 4: Install New Weed Barrier
(1) 4.1 Contractor shall level and rake the exposed subgrade, removing any sharp stones, roots, or debris that could puncture the new barrier. Subgrade must be graded to maintain positive drainage away from building foundations and walkways.
(2) 4.2 Contractor shall supply and install heavy-duty non-woven geotextile weed barrier fabric over the prepared subgrade.
(3) 4.3 Weed Barrier Technical Specifications:
(a) Material Type: Heavy-duty, needle-punched non-woven polypropylene geotextile fabric. Woven landscape fabrics are strictly prohibited due to reduced permeability and potential for water pooling.
(b) Material Weight: Minimum 4.5 oz/sq. yd (conforming to ASTM D5261) to withstand the weight of decorative rock and prevent weed breakthrough.
(c) Grab Tensile Strength: Minimum 115 lbs (conforming to ASTM D4632).
(d) CBR Puncture Strength: Minimum 300 lbs (conforming to ASTM D6241) to resist puncture during angular rock placement.
(e) Water Flow Rate: Minimum 100 gpm/sq. ft (conforming to ASTM D4491) to ensure rapid drainage and prevent root rot.
(f) UV Resistance: Minimum 70% strength retention after 500 hours of xenon-arc exposure (conforming to ASTM D4355).
(4) 4.4 Installation Requirements:
(a) The geotextile fabric shall be rolled out flat, free of wrinkles or folds.
(b) Adjacent rolls of fabric must overlap by a minimum of 6 inches (12 inches along joints and bed boundaries).
(c) Fabric shall be pinned to the subgrade using 6-inch long by 1-inch wide, 11-gauge steel landscape staples driven flush with the ground. Staple spacing shall be a maximum of 3 feet on center along all seams, borders, and overlaps, and 4 feet on center in the field.
(d) For retained plantings, the Contractor shall make neat, precise "X" or "U" shaped incisions in the fabric. The resulting flaps shall be folded under to expose only the plant base/root collar, ensuring no constriction of the trunk or stem occurs.
v. Task 5: Install New Planter Bed Liners
(1) 5.1 Contractor shall supply and install new commercial-grade steel planter bed liners along the edges of the planter beds where they border turf or grassy areas.
(2) 5.2 Bed Liner Technical Specifications:
(a) Material Type: Commercial-grade, heavy-duty steel landscape edging, matching the existing basewide architectural standard.
(b) Dimensions: 1/8 inch (0.125") thickness by 8 inches depth/height.
(c) Finish: Corrosion-resistant, polyester powder-coated finish (color: black or dark bronze) or hot-dip galvanized.
(3) 5.3 Installation Requirements:
(a) Edging shall be set in a clean, hand-excavated trench to ensure a crisp, professional border.
(b) The liner shall be installed such that the top of the metal edge sits exactly 2 inches above the finished grade of the adjacent turf/grass (to contain rock and block grass encroachment), with the remaining 6 inches buried below grade to anchor the bed and block turf roots.
(c) Edging shall be secured using matching heavy-duty steel anchor stakes
(minimum 12 inches in length) driven flush into the integrated staking slots at a maximum spacing of 3 feet on center, and at every joint overlap.
(d) Sections shall be joined using manufacturer-approved interlocking joint connectors to ensure continuous, smooth curves and straight lines.
vi. Task 6: Place Decorative Rock
(1) 6.1 Contractor shall carefully re-deposit the washed and stored decorative rock back into the planters over the newly installed weed barrier fabric.
(2) 6.2 Contractor shall supply and install new matching decorative rock as needed to supplement the washed rock and achieve a uniform average depth of 3 inches across the 14,511 SF of planter beds.
(3) 6.3 Decorative Rock/Gravel Technical Specifications:
(a) Material Type: Clean, washed, durable decorative river gravel or stone
(rounded river gravel or granite stone) matching the size, shape, and color of existing basewide landscaping stone.
(b) Sizing: Sized between 1 inch and 4 inches in diameter. The rock must be certified 100% clean and free of sand, clay, soil, organic fines, and weeds to prevent weed seeds from establishing in the stone layer.
(4) 6.4 Placement Requirements:
(a) Rock shall be placed gently over the new weed barrier to avoid tearing, shifting, or pulling the fabric and staples.
(b) Around the trunks and stems of retained plants, the rock shall be feathered down to a depth of approximately 1 inch, leaving a clear 2-inch buffer zone of exposed subgrade around the immediate root collar of the plant to prevent crown rot and allow proper aeration in accordance with UFC 3-201-
02.
(c) The Contractor shall sweep/rake and clean up any decorative rock, soil, or debris spilled onto adjacent walkways, roads, or turf during placement.
c. The Contractor shall reference Tasks 1 through 6 in CLIN 001 above for each of the seventeen (17) additional CLINS for planter area identified in the table below.
d. Break out of approximate quantities of planter edging, rock, and weed barrier to be replaced per CLIN:
CLIN Planter Area Edging (LF) Area (SF)
001 Building 5000 65 1464
002 Building 5002 157 751 003 Building 5006 62 417 004 Building 5008 129 832 005 Building 5010 98 647 006 Building 5016 3 824 007 Building 5020 40 161 008 Building 5022 77 393 009 Building 5024 0 352 010 Building 5026 121 956 011 Building 5028 132 556 012 Building 5036 59 261 013 KC-135 Tail Display 0 216 014 Minute Man Memorial 151 1810
Miscellaneous Areas (See Attached Breakout) 120 1886
016 Pavilion Work Area 51 182 017 Static Display 292 2280 018 Wing Sign 107 523
TOTAL 1664 14511
4. DELIVERABLES: Contractor shall provide all material submittals to the contracting office for review using the Air Force Form 3000 (AF3000).
5. SCHEDULE:
c. Performance period: The period of performance (PoP) for this project shall be proposed by the contractor and negotiated with the government from the date that Notice to Proceed
(NTP) is issued. All work must be scheduled to be complete within this timeframe. Any modifications or extensions must be requested through the 126th Civil Engineer Squadron
(126 CES) and the Contracting Officer for review and discussion. Contractor must provide construction milestones to 126 CES and the Contracting Officer.
d. Prior to beginning construction, Contractor shall provide to the CO and 126 CES construction milestones in sufficient detail to accurately identify all phases/disciplines of work to be performed.
e. Contractor shall provide general construction schedule, showing, at a minimum, the critical path items.
f. Contractor will be required to provide 2-week look ahead at each meeting described above.
g. Construction may be authorized by the Contracting Officer upon acceptance and approval of the schedule and equipment/material submittal approvals.
6. SPECIFICATIONS:
c. All work performed shall comply with all applicable UFC, NFPA, NEC and other local and federal regulations and code. This includes but is not limited to:
i. Unified Facilities Criteria (UFC) 1-200-01 General Building Requirements
ii. UFC 3-201-02 Landscape Architecture
iii. UFC 3-250-01 Pavement Design for Roads and Parking Areas
iv. Air Force Corporate Facilities Standards
v. Scott Air Force Base Architectural Compatibility Guidelines
vi. ASTM D4632 (Grab Tensile), ASTM D6241 (CBR Puncture), ASTM D4491 (Water
Permeability), and ASTM D4355 (UV Resistance)
7. GENERAL CONDITIONS:
c. There is known soil contamination in the area. All soil must remain on site or be sent to an approved landfill or disposal facility. The use of groundwater is prohibited. All soil profiles and disposal manifests must be approved by the Environmental office prior to waste leaving Scott AFB.
d. An alternate method can be proposed for any of the above tasks and will be reviewed.
Any alternate methods or deviations from the requested work shall be called out or highlighted in the Contractor’s proposal in a manner that is clearly identifiable. Any approved alternate methods will result in a SOW modification prior to the commencement of work. The Government will assume any additional design or construction costs associated with the approved alternatives but will not assume any costs associated with the Contractor processing this required modification.
e. A phased approach is to be used in the construction of these projects to minimize disruptions.
f. Contractor must ensure that all accesses to the building be left clear of construction materials when not on the worksite. Ensure material/tools/equipment do not hamper operations during operating hours.
g. Contractor shall supply any dumpsters required to properly dispose of any construction materials.
h. Contractor shall coordinate with CE for enter/exit points to access job site, for this facility. Contractor to coordinate with CE for location of dumpster.
i. Contractor shall site verify all dimensions and/or existing site conditions prior to the commencement of work. Commencement of work shall begin within ten (10) calendar days upon the receipt of the NTP issued by the Contracting Officer.
j. Contractor shall be completed within the agreed upon PoP as stated within the contract issued by the Contracting Officer.
k. Contractor shall be required to apply for and submit to the Contracting Officer an AF
Form 103, Work Clearance Request, for all work to be accomplished under this delivery order five (5) days prior to the commencement of work. The AF Form 103 can be obtained from and approved by 126CES.
l. Contractor shall brief all Sub-Contractors on all safety and fire prevention regulations, emphasizing the requirement to obtain a daily AF Form 592, Welding, Cutting, and
Brazing Permit, when welding, cutting, or brazing operations are to occur under this delivery order. The AF Form 592 can be obtained from and approved by 126CES.
m. Contractor shall complete and submit the appropriate DD Form 1354, Transfer and
Acceptance of DoD Real Property to the 126CES for records. The DD Form 1354 can be obtained from 126 CES.
n. Contractor shall provide an inventory, utilizing Microsoft Excel, of all removed systems to ASTM-E1557-09 Uniformat II, Level 4 system detail. Detail data includes
Facility Number, ID Number (if available); Equipment Type; Equipment Make;
Serial Number; Model; Capacity; Manufacturer; and Location. Contractor shall provide the government two copies of CD/DVD media with an electronic copy of the removed systems inventory as part of the final close out document package.
o. Contractor shall provide an inventory, utilizing Microsoft Excel, of newly installed systems to ASTM-E1557-09 Uniformat II, Level 4 system detail. Since section detail data can be recorded for equipment and non-equipment section types, some of the data elements may not apply to component-sections. The Contractor must provide section detail data for those data elements that do apply (see Attachment 4).
i. Section detail data includes Facility Number; Level 2 Group Element (System)
Description; Level 3 Individual Element (Component) Description; Level 4
Sub-Element (Section) Description; Sub-Element Description; Equipment
Type; Equipment Make; Serial Number; Model; Capacity; Manufacturer;
Warranty Company; Warranty Expiration Date; Location; Date
Manufactured; Control Type/Make and Year Installed.
ii. Contractor shall provide the government two copies of CD/DVD media with an electronic copy of the installed systems inventory as part of the final close out document package.
p. Contractor shall provide an electronic draft copy of the installed systems inventory for review and issuance of the applicable inventory ID Number and bar-code labels at least 30 days prior to O&M handover walk-through (conducted prior to contract close out).
q. Contractor shall, during construction, keep an accurate electronic record of as-built conditions, all variations from the contract drawings (that have been approved by the contracting officer or COR in writing in advance of any such variations - including those made because of the selection of optional materials), shall be clearly indicated.
These variations shall be shown in the same general detail utilized in the initial contract drawings. The as-built drawings shall be maintained in a current condition during construction. The as-built drawings shall be furnished to the Contracting
Officer and 126 CES not later than ten workdays after the final inspection date. As part of the as-built drawings a separate set of plans shall be marked-up showing areas found/known to contain asbestos.
r. Contractor shall install bar-code labels on all newly installed systems, as required.
Bar-code labels must match applicable component-sections standardized on the Base.
s. All documents related to the disposal of hazardous material must be supplied to 375
CONS and 126 CES. The Contractor must obtain the proper documents from 126
CES to ensure all materials leaving Scott Air Force Base can be tracked and accounted for, in accordance with all governing laws.
t. Under the 1992 Clean Air Act, all products used in executing this project must not be related to the Class I Ozone Depleting Chemicals (ODCs) identified in Air Force
Policy. The following products are considered Class I ODCs: CFC-11, CFC-12, CFC-
113, CFC-114, CFC-115, Halon 1211, Halon 1301, Halon 2402, CFC-13, CFC-111, CFC-112, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, CFC-217, Carbon tetrachloride, and Methyl Chloroform.
u. Respondents are encouraged to prioritize the utilization of utility company energy savings incentives as a key funding mechanism for the implementation of proposed projects. These incentives should be thoroughly explored and integrated into the proposed plan to maximize cost-effectiveness and ensure alignment with energy savings measures. Demonstrating a proactive approach to leveraging these incentives will be viewed favorably during the evaluation process.
v. The awardee of this solicitation will need to determine if any components of this project are eligible for the local utility companies' energy efficiency rebate/incentive program. The awardee will be responsible for preparing and submitting the application to the utilities program. New Construction/Custom applications require a preapproval from the local utility's energy efficiency program prior to placing an order for material with a vendor. The awardee is responsible for the general rules and requirements of the local utility's EE application.
8. FIELD CONDITIONS:
The Contractor shall be responsible for all field measurements to accomplish work.
Quantity and sizes of materials shall be determined from site visits and drawings. The
Contractor shall carefully examine the entire site and building(s) and shall make all necessary investigations to become thoroughly aware of the existing conditions and all difficulties involved in the completion of the work in accordance with the contract documents.
9. ACCOMPLISHMENT OF WORK:
The work areas of the existing building will be in occupied and unoccupied areas. The
Contractor must ensure that all access to the existing building always remains clear for occupants and emergency access during the construction period. All temporary closures, barriers, and protective procedures shall be coordinated with the Contracting Officer. All work shall be accomplished during the standard 8-hour day, 5-day week, Monday through
Friday, between the hours of 7:30 A.M. and 4:30 P.M. local time, excluding Federal
Legal holidays and nonwork days resulting from holidays occurring on weekends.
However, power outages shall be accomplished on weekends or 126ARW down days
(calendar provided). The 126ARW has a compressed schedule and does have roughly two down days per month, typically on Fridays. Please reference the 126ARW calendar to coordinate the construction schedule to not work on scheduled down days unless required.
10. WORK CONDITIONS:
The Contractor shall coordinate work with the Contracting Officer, in conjunction with the
User and 126 CES. The Contractor shall notify the Contracting Officer or the 126 CES inspection representative the day before he/she moves onto the work site to commence work.
The Contractor shall again provide notification the day he moves back to the work site after an interruption of work of two or more days in duration. The Contractor shall also provide an original work schedule and updates if required. This schedule shall describe major work items and projected completion dates.
11. PROTECTION OF BUILDING PROPERTY:
The Contractor shall protect from damage all building property located in or adjacent to the building and shall repair, replace, or otherwise be held liable for all such damage. Building properties include but are not limited to, furniture, vehicles, or items of supplies. Exercise control measures of all dust and toxic fumes associated with construction operations, to prevent hazards or illness to base and Contractor personnel.
12. CLEANUP:
The Contractor shall cleanup each work site at the end of each workday to the satisfaction of the Contracting Officer. Upon completion of the work, all construction equipment and debris shall be removed from the site and the area shall be left in a neat and completely acceptable condition as required by the General Provisions. Contractor must always recycle materials, such as, but not limited to cardboard and paper. The Contractor will use whatever means necessary to store all recyclable materials and is responsible for turning in recyclable materials to the Base Recycling Center.
13. PATCHING AND REPAIRING:
After the work has been completed, holes, cuts, and damages made in the finished surfaces of the work site and adjacent areas shall be properly repaired and restored to match the existing finishes. Any abrasion or disfigurement of the finish work or any portion of the building where any such abrasion or disfigurement is caused by the activities of the Contractor shall be repaired and neatly refinished to match the adjacent work to the satisfaction of the
Contracting Officer. Contractor shall maintain integrity of all fire walls/barriers.
14. PRODUCTS:
All products shall conform to their respective manufacturing and performance publications.
All materials and equipment used in the work area shall be the products of manufacturers regularly engaged in the manufacture of construction products.
15. SUBMITTALS:
The Contractor shall submit for approval all items as required by other parts of these specifications. The Contracting Officer may request submittals in addition to those required by the other parts of this Statement of Work when deemed necessary to adequately describe the work. Submittals shall be made to the Contracting Officer in five (5) copies using AF
Form 3000, Material Approval Submittal. In general, submittals shall be provided a minimum of thirty (30) calendar days in advance of scheduled installation to allow satisfactory time for Government review. Additionally, unless stated otherwise submissions on test results and other submissions of a similar nature shall be made within fourteen (14) calendar days after the work or test is performed. Each submittal shall be complete and in sufficient detail for ready determination of compliance with contract requirements.
Submittals shall include such items as Contractor’s or manufacturer’s shop drawings, descriptive literature, catalog cuts, samples, certifications, installation procedures and recommendations, templates, and other descriptive literature as may be required by the
Contracting Officer. Catalog cuts and other descriptive data which may have more than one model or type shall be clearly marked to show the model, type, size, and all optional or accessory equipment the Contractor proposes to install. Submittals on component items forming a system or interrelated items shall be submitted at one time as a single submittal to demonstrate that the items have been properly coordinated and will function as a unit.
Approval of submittals will not relieve the Contractor of compliance with the project drawings and specifications. Submittal items that are disapproved will be promptly corrected and resubmitted by the Contractor. No materials shall be installed until submittals are approved by the Contracting Officer. All submittals involving color selections, patterns, and other decorative architectural features shall be submitted at the same time for both interior and exterior materials.
16. SPECIFICATIONS:
Work shall be performed in strict accordance with these contract general specifications, as well as all applicable local, state, and national Building and Life Safety Codes, American
Society for Testing and Materials (ASTM) specifications. Safety plans and procedures issues must adhere to all applicable Occupational Safety and Health Act (OSHA) regulations.
17. PROJECT POINTS OF CONTACT:
The project points of contact for this project are:
Contracting Specialist/Officer
MSgt Jonathan Middleton 126th Contracting Office
Project Manager
Capt Brett Luithly
126th Civil Engineer Squadron
Construction Inspector/Manager
Mr. Larry Fuller
126th Civil Engineer Squadron
Real Property Manager
Mr. Eric Bennett
126th Civil Engineer Squadron mailto:benjamin.james.1@us.af.mil mailto:brett.luithly@us.af.mil mailto:larry.fuller@us.af.mil mailto:eric.bennett.11@us.af.mil