This is a Performance Work Statement (PWS) issued by the 97th Air Mobility Wing (AETC) at Altus Air Force Base, Oklahoma, dated 12 May 2026.

The contractor shall install two Model 2000E25-P, 25HP reciprocating air compressor systems with 120-gallon tanks in Hangars 514 and 518 at Altus AFB. Work must be completed within 20 calendar weeks of contract award, performed Monday-Friday, 0700-1900 hours, excluding federal holidays. The contractor is responsible for providing all labor, tools, materials, equipment, supervision, and administration necessary to accomplish the installation. Key deliverables include: disconnecting and removing existing air compressors and disposing of them; installing new compressors in the same locations; adding or replacing concrete base pads as needed to meet facility requirements; providing complete electrical and mechanical installation of all components to meet existing facility requirements; supporting system start-ups to ensure proper operation; and providing a minimum 12-month warranty on installation commencing from the commissioning date. The contractor must deliver a turn-key operating electrical system and ensure equipment operates properly before departure. All electrical work shall comply with the National Electric Code and applicable local, state, and federal requirements. The contractor must coordinate material deliveries with the government project manager, provide detailed records of all parts and warranty information, handle their own disposal of debris (not using government bins), and maintain daily site cleanup. Security requirements include DOD background checks for personnel, government-issued photo identification at all times, compliance with Air Force security protocols, adherence to Force Protection Condition Bravo measures, and reporting of suspicious activities to base Security Forces. Personnel obtaining Common Access Cards must complete Antiterrorism Level I training within 30 days.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

97TH AIR MOBILITY WING (AETC)

ALTUS AIR FORCE BASE OKLAHOMA

VICTORY BEGINS HERE!

12 May 2026

PERFORMANCE WORK STATEMENT

INSTALLATION OF TWO - MODEL 2000E25-P, 25HP RECIPROCATING AIR

COMPRESSOR WITH 120GAL TANK - SYSTEMS FOR HANGARS 514 AND 518

• SCOPE: The contractor shall provide all legally required licenses, plant, labor, tools, equipment, travel, material, parts, supervision and administration necessary to perform the installation of electrical/mechanical to the air compressors with air dryer.

• AREA OF WORK: Contractor shall work only in the areas designated by Contracting Officer Representative (COR). The work area will be accomplished within the mechanical, northwest comer of Hangar 514 and the mechanical/boiler room, northwest corner of Hangar 518 at Altus AFB, Oklahoma.

• PERIOD OF PERFORMANCE: Work must be completed within 20 calendar weeks of contract award date. Work will be accomplished during the work week, Monday-Friday 0700-1900, reference Section 9, Government Working Hours. Work will cease if Altus AFB Mission requirements deem necessary.

• DESCRIPTION OF WORK: The work to be accomplished consists, in general, of the following principal items. This does not mean the work consists only of these items, but that it consists of this principal items along with all incidental minor work which becomes necessary to complete in order to accomplish the overall project in satisfactory and workman like manner meeting the approval of the customer and Contracting Officer/QA

• Contractor will furnish: all labor, tools, materials, personnel, and equipment as listed below:

a. Disconnecting, removing, and disposal of existing air compressors to allow new air compressors to be installed into the existing locations within buildings.

b. The new air compressors will be installed in the spot of the old, existing air compressors.

i. If additional concrete is needed for mounting to base pad, contractor will be responsible for adding to or replacing the concrete base pad to meet facility requirements.

c. Provide complete electrical installation of all components required for operation to meet existing facility requirements.

d. Provide complete mechanical installation of all components required for operation to meet existing facility requirements.

VICTORY BEGINS HERE!

e. Contractor must support start-ups to ensure compressors operate.

f. Contractor must provide warranty on installation for no less than 12 months beginning on the date of commissioning.

Preparation: The site to be installed is in the mechanical/boiler rooms, northwest corner of Hangar 514 and northwest corner of Hangar 518; the floor is level and will not require any excavation or concrete cutting.

Finished Product: Contractor will provide a tum-key operating electrical system to the air compressors and dryers and ensure equipment is operating properly prior to departure.

MATERIAL & EQUIPMENT ACCOUNTABILITY:

• The contractor shall notify the government project manager prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the government project manager. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.

SUBMITTALS:

• Contractor is responsible to provide detailed records of all parts, as well as any and all warranty information to the customer.

GENERAL CONDITIONS:

• All electrical work shall be performed in accordance with the National Electric Code and all applicable local, state, and federal requirements.

• Contractor and all personnel shall comply with the Air Force safety, security guidelines and policies, and shall work within the tirneline specified by COR.

• Contractor shall field verify all site conditions, quantities, measurements, and project requirements. Contractor shall protect and barricade all work areas at all times to protect workers from injury.

• Contractor shall protect all structures, utilities, vegetation, sidewalks, and vehicles from damage at all times.

• Contractor shall replace damaged materials with new materials to the satisfaction of the Government, at no additional cost to the Government.

DIFFERING SITE CONDITIONS:

• Contractor is to bring any unforeseen project conditions to the attention of the CO immediately. Differing site conditions, which may alter the scope of work, shall be approved by the CO prior to such work being performed.

GOVERNMENT WORKING HOURS:

• Work hours shall be Monday through Friday 0700-1900 hours, except for Federal holidays.

Contractor must have prior approval in writing to work outside these guidelines.

UTILITIES:

• Government will permit the use of the men's and women's restrooms in Hangar 514 and 518.

• 120 Volt A/C will be available for small electrical tool use.

DISPOSAL OF MATERIALS AND CLEANUP:

• The contractor shall not use any government disposal bins, dumpsters, or trash receptacles for any reason at any time (unless otherwise specified). The contractor shall provide appropriate disposal bins/trash receptacles. Approval of disposal bins/trash receptacle location(s) shall be coordinated through the government project manager. The contractor shall not allow debris to leave the work area due to potential damage to aircraft engines.

Contractor shall clean up after each work period and dispose of all debris at the close of each day.

SECURITY:

• Altus Air Force Base Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. All deliveries shall be coordinated with the COR to arrange for their entrance onto Altus Air Force Base property. Personnel may be required to pass a DOD background check prior to working.

ESCORTS:

• All Contractor personnel shall have a minimum of one (1) government issued current form of photo identification with them at all times.

ANTI-TERRORISM:

• Altus Air Force Base has an Antiterrorism program that is responsible for securing and protecting the base and its personnel from terrorist attacks. All contractor personnel and sub-contractors are required to obey all orders from Security Forces and adhere to all security measures implemented during Force Protection Condition (FPCON) changes and Random Antiterrorism Measures (RAMs). Security Forces members may conduct inspections of your company as well as your sub-contractors while operating on the installation. Unescorted entry into any are marked as a "CONTROLLED AREA" or "RESTRICTED AREA" is strictly prohibited.

• Altus Air Force Base is currently in FPCON Bravo, meaning an increased and more predictable threat of terrorist activity exists. All contractor personnel and sub-contractors are expected to report any suspicious persons, activities, packages, or items you see while conducting work on Altus Air Force Base to base Security Forces. Suspicious activities could include personnel conducting surveillance, unauthorized personnel requesting access, or information probing pertaining to security operations or assets on the installation.

• In the event of an emergency, there are multiple mass warning notification systems on

Altus Air Force Base (AtHoc, weather radios, telephone notification, and giant voice system).

• Any contractor personnel or sub-contractor that obtains a Common Access Card (CAC)

MUST complete the Antiterrorism Level I training within 30 days of receiving your CAC (see paragraph 4.8.1.) Altus AFB has an Antiterrorism binder available for review at the Visitor Control Center, building 428. If there are any questions in regards to Antiterrorism, contact 580-481-7350.

END PWS

PERFORMANCE WORK STATEMENT
INSTALLATION FOR TWO NEW AIR COMPRESSORS SYSTEMS FOR HANGARS 514 AND 518
MATERIAL & EQUIPMENT ACCOUNTABILITY:
SUBMITTALS:
GENERAL CONDITIONS:
DIFFERING SITE CONDITIONS:
GOVERNMENT WORKING HOURS:
UTILITIES:
DISPOSAL OF MATERIALS AND CLEANUP:
SECURITY:
ESCORTS:
ANTI-TERRORISM: