Attachment 1 MOVERS Governance and Replan.pptx

PPTX presentation 3 MB Posted

Attached to
Request for Proposal (RFP) for Project Management Services
Solicitation number
300000263931336
Issued by
Missouri

About this file

This is a governance and project planning presentation for the MOVERS system implementation, detailing the organizational oversight structure and phased implementation schedule across multiple fiscal years. The project is organized under an Oversight Committee responsible for executive oversight and strategic direction, a Change Control Board that approves material changes to program baselines in scope, schedule, and budget, and a Program Team managing day-to-day operations. The governance model allocates decision-making authority by category, with approximately 75% of decisions at the operational level, 20% at the tactical level, and 5% at the strategic level for issue escalation. The implementation follows a four-release schedule spanning fiscal years 2026 through 2028: Release 1 (scheduled for March 1, 2027) includes Recruit and Core HR functions; Release 2 (July 1, 2027) encompasses enterprise resource planning modules including general ledger, fixed assets, accounts payable and receivable, inventory, costing, purchasing, budget control, expenses, manufacturing, order management, cash management, and reporting functions; Release 3 (January 1, 2028) covers human capital management including payroll, time and labor, compensation, benefits, and talent management; and Release 4 (January 1, 2028) addresses narrative reporting and 1099 functions. The schedule notes pending proof-of-concept approval for MoBGT restructuring and includes a custom solution to maintain balance synchronization between MOVERS and SAMII systems.

Ongoing maintenance and operations support will commence following the post-launch support period for each release and includes ticket triage through JIRA and ServiceNow, quarterly and monthly updates, and Oracle service request management. The presentation does not specify pricing terms, funding amounts, contract duration, or other financial details.

View the file

Other files

File Type Posted
Attachment 4 - SOW Requirements.docx DOCX document
Attachment 3 SOW Project Management.pdf PDF
Attachment 2 SOW Secondary IV&V.pdf PDF
MOVERS Project Management RFP.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Governance Structure Overview

Governance Chart Oversight Committee Deliver executive oversight, establish strategic direction, and champion the project Resolve high-impact issues Approve key project milestones and changes Ensure resource commitment Change Control Board Approve material changes to the program baseline (scope, schedule, budget, delivery) Provide recommendations to Oversight Committee for strategic decisions Program Team Oversees day-to-day project activities including managing scope, schedule, budget Manage stakeholders and project resources Escalate issues as needed

Governance Escalation Thresholds

Strategic ~5% of decisions Tactical ~20% of decisions Operational ~75% of decisions

RePlan Schedule

CY2026CY2027CY2028
FY26FY27FY28

Release 2 (ERP): GL, Fixed Assets, AP, AR, Inventory, Costing, Purchasing, Budget Ctrl, Expenses, Manufacturing, Order Management, Cash Mgmt. Reporting, PPM COA, Leasing, PPM, Custom solution to keep balances in sync between MOVERS and SAMII (FCCS or Acct Hub), MoBGT Restructure (Pending Proof of Concept Approval)

Release 3 (HCM): Payroll, Time & Labor, Comp, Benefits, Absence Mgmt, Talent, Employee Self-Service, Remaining Core HR, Knowledge Center

Release 1: Recruit, Core HR, EDMCS

Release 4: Narrative Reporting (ACFR), 1099

Go Live March 1, 2027

Go Live July 1, 2027

Go Live January 1, 2028

Go Live January 1, 2028

Maintenance & Operations (M&O) Ongoing support for Planning & Budgeting, Solicitation, Learn (MOVERS Production) including JIRA/ServiceNow Ticket Triage, Quarterly/Monthly Updates & Oracle SR Triage. Will begin for each release following the post go-live support period.

image5.png image1.png image4.jpeg