About this file
This document is a set of bid documents for a roof replacement project at the Henderson Building on the campus of Blue Ridge Community College. The project includes the demolition of the existing roof membrane, cover board, and insulation, and the installation of a new 20-year warranted TPO roofing system with R-30 polyisocyanurate insulation. The scope of work also includes related carpentry, sheet metal flashing and trim, and joint sealants. Additive alternates include adding a fall arrest system for the roof access hatch and expanding the roof replacement scope to include a lower roof area. The contractor is required to field verify all dimensions and conditions prior to the start of work, and to coordinate access and staging areas with the college.
Pricing information is not included in the provided documents. The successful contractor will be required to provide a 20-year warranty on the new roofing system. No information is provided regarding incumbent contractors, funding sources, or set-asides. The documents indicate this is a bid set, but do not specify response due dates or award timelines.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B5
A-104
B3
A-104
RD RD
ROOF ACCESS HATCH
OS OS
/4
/4
/4
/4
/4
LOWER ROOF - NOT IN
SCOPE
LOWER ROOF - NOT IN
SCOPE
EXISTING ANTENNA
1 1
D1
A-105
B5
A-104
B5
A-104
A1
A-104
*ADD ALTERNATE #2: ADD LOWER ROOF
WITHIN DESIGNATED AREA TO SCOPE.
*DEMO EXISTING ROOF MEMBRANE, COVERBOARD, AND INSULATION WITHIN AREA OF SCOPE.
A3
A-104
1. LOCATIONS AND SIZES OF MECHANICAL EQUIPMENT ARE APPROXIMATE.
2. ALL LOW SLOPED ROOFS TO BE MINIMUM 1/4" PER FOOT. ALL ROOF DRAINS TO
BE INSTALLED IN 3'-0" X 3'-0" SUMP TYPICAL UNO.
3. PROVIDE CRICKETS AT ALL CURBS AND EQUIPMENT RAILS SET
PERPENDICULAR TO ROOF SLOPE WHICH ARE GREATER THAN 24" WIDE.
4. SLOPE ALL COPINGS BACK TO ROOF UNO.
5. WOOD BLOCKING SHOWN IN ROOF DETAILING SHALL BE FIRE-RETARDANT
TREATED. USE FASTENERS COMPATIBLE WITH TREATED WOOD.
6. EXTEND ALL PENETRATIONS, CURBS, AND COMPONENTS A MINIMUM OF 8"
ABOVE THE ROOF SURFACE.
7. IF NOT DETAILED, APPLY MOST STRINGENT CONDITION OF NRCA AND SMACNA
(CURRENT EDITIONS) STANDARDS FOR ROOF DETAIL CONDITIONS.
8. FIELD VERIFY NUMBER AND LOCATION OF ALL PIPE PENTRATIONS. PIPE
PENETRATION LOCATIONS SHOWN ON ROOF PLAN ARE APPROXIMATE.
SINGLE PLY TPO
NEW R-30 POLYISOCYANURATE INSULATION
NEW 1/2" ROOF COVER BOARD
NEW TPO MEMBRANE ROOFING
EXISTING STEEL BEAM OR STEEL JOIST
R1
EXISTING METAL ROOF DECK
*CONFIRM ORIGINAL ROOF
THICKNESS WITH PROPOSED NEW IN
ORDER TO ACHIEVE R-30. NOTIFY
ARCHITECT IF DISCREPANCIES
OCCUR. MINIMUM ROOF SLOPE TO BE
1/4" / 12".
*DEMO EXISTING ROOF MEMBRANE,
COVERBOARD, AND INSULATION WITHIN
AREA OF SCOPE.
1. Wood Blocking: For blocking not used for attachment of other construction, Utility, Stud, or No. 3 grade lumber of any species may be used provided that it is cut and selected to eliminate defects that will interfere with its attachment and purpose. For blocking and nailers used for attachment of other construction, select and cut lumber to eliminate knots and other defects that will interfere with attachment of other work. All concealed wood blocking shall be fire-retardant treated.
A. Set carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit carpentry accurately to other construction. Locate nailers, blocking, and similar supports to comply with requirements for attaching other construction. Provide blocking and framing as indicated and as required to support facing materials, fixtures, specialty items, and trim.
B. Install where indicated and where required for attaching other work. Form to shapes indicated and cut as required for true line and level of attached work. Coordinate locations with other work involved.
2. TPO Roofing: ASTM D6878/D6878M, internally fabric- or scrim-reinforced, fully-adhered TPO sheet. All TPO shall be 60 mil, white membrane.
Roofing insulation shall be polyisocyanurate board insulation: ASTM C1289, Type II, Class 2, Grade 2, glass-fiber mat facer on both major surfaces.
Cover board: ASTM C1177/C1177M, glass-mat, water-resistant gypsum board or ASTM C1278/C1278M fiber-reinforced gypsum board, 5/8-inch thick. Warranty shall be 20 years. Acceptable manufacturers include Carlisle SynTec Inc., GAF Materials Corp., and Versico Inc.
A. Provide all accessories and materials necessary for installation of TPO including but not limited to fasteners, sheet flashing, bonding adhesive, and metal termination bars as recommended in writing by TPO manufacturer.
B. Roofing Inspection: Contractor and Manufacturer's assigned representative shall inspect the roof deck, documenting deficiencies requiring correction prior to start of roofing as a condition of acceptance.
C. Roofing Performance Requirements: Roof membrane shall withstand 2000 hours of exposure when tested according to ASTM G152, ASTM G154, or ASTM G155. Roof membrane shall resist impact damage when tested according to ASTM D3746, ASTM D4272, or the "Resistance to Foot Traffic Test" in FM Approvals 4470. Design roofing system to resist the wind uplift pressures indicated when tested according to FM Approvals 4474, UL 580, or UL 1897.
3. Joint Sealants: For non-traffic surfaces provide Single Component, Nonsag, Neutral-Curing Silicone Sealant; Type S, Grade NS, Class 100/50, Uses include NT (non-traffic), M, G, A and O; non-staining and field-tintable. For traffic surfaces provide Single-Component, Traffic Exposure, Neutral- Curing Silicone Sealant; Type S, Class 100/50, Uses include M, A, and O. For joints including but not limited to expansion joints, control joints, vertical joints on exposed surfaces, and perimeter joints provide Single-Component, Nonsag, Urethane Joint Sealant: ASTM C 920, Type S, Grade NS, Class 25, for Use NT. Acceptable manufacturers for all joint sealants include Pecora Corp., Sika Corp., Dow Chemical Company, and Tremco, Inc.
4. Sheet Metal Flashing and Trim A. Aluminum Sheet: ASTM B209, alloy as standard with manufacturer for finish required, with temper as required to suit forming operations and performance required; with smooth surface.
1. Aluminum Finish: Mill, U.O.N. in Drawings
2. Locations: Roof and as indicated.
B. Stainless Steel Sheet: ASTM A240/A240M, Type 304, dead soft, fully annealed; with smooth surface.
1. Stainless Steel Finish: ASTM A480/A480M, No. 4 (polished directional satin).
C. Underlayment Materials:
1. Felt: ASTM D226/D226M, Type II (No. 30), asphalt-saturated organic felt; nonperforated.
2. Self-Adhering, High-Temperature Sheet Underlayment: Minimum 30 mils thick, consisting of a slip-resistant polyethylene- or polypropylene-film top surface laminated to a layer of butyl- or SBS-modified asphalt adhesive, with release-paper backing;
specifically designed to withstand high metal temperatures beneath metal roofing. Provide primer in accordance with underlayment manufacturer's written instructions.
a. Basis-of-Design Product: Grace Ice and Water Shield (High Temperature) as manufactured by GCP Applied
Technologies.
D. Fasteners for Aluminum Sheet: Aluminum or Series 300 stainless steel.
E. Fasteners for Stainless Steel Sheet: Series 300 stainless steel.
F. Epoxy Seam Sealer: Two-part, noncorrosive, aluminum seam-cementing compound, recommended by aluminum manufacturer for exterior nonmoving joints, including riveted joint
- NOT IN SCOPE / EXISTING TO REMAIN
- ROOF REPLACEMENT SCOPE
- OVERFLOW SCUPPER
- ROOF DRAIN
OS
RD
1. THE PROJECT CONTRACTORS AND THEIR REPRESENTATIVES SHALL BE ADVISED THAT ALL CAMPUS AREAS OTHER THAN THE AREAS
DESIGNATED FOR REQUIRING WORK SHALL BE "OFF LIMITS".
COORDINATION:
1. VERIFY DIMENSIONS, ELEVATIONS AND EXISTING CONDITIONS AT THE SITE BEFORE COMMENCING WORK AND REPORT
DISCREPANCIES TO THE ARCHITECT FOR RESOLUTION PRIOR TO THE START OF WORK.
2. SHOULD THE SPECIFICATIONS FAIL TO PARTICULARLY DESCRIBE THE MATERIAL OR KIND OF PRODUCTS TO BE USED IN ANY PLACE, THEN IT SHALL BE THE DUTY OF THE CONTRACTOR TO SUBMIT A REQUEST FOR INTERPRETATION.
3. ANY WORK INSTALLED IN CONFLICT WITH THE ARCHITECTURAL DRAWINGS SHALL BE CORRECTED BY THE CONTRACTOR AT HIS
EXPENSE AND AT NO ADDITIONAL COST TO THE COLLEGE.
4. DO NOT SCALE DRAWINGS. CONTRACTOR SHALL VERIFY ALL DIMENSIONS, ELEVATIONS AND ALL EXISTING CONDITIONS AT THE SITE
BEFORE COMMENCING WORK AND REPORT ANY DISCREPANCIES TO THE ARCHITECT PRIOR TO THE START OF WORK.
5. CONTRACTOR'S MATERIALS AND ACTIVITIES SHALL NOT BLOCK ANY EXIT.
6. THE CONTRACT DOCUMENTS ARE COMPLIMENTARY, AND WHAT IS REQUIRED BY ONE SHALL BE AS BINDING AS IF REQUIRED BY ALL;
PERFORMANCE BY THE CONTRACTOR(S) SHALL BE REQUIRED TO THE EXTENT CONSISTENT WITH THE CONTRACT DOCUMENTS, REASONABLE INFERABLE FROM THEM AND REASONABLY FORESEEABLE, USING THE MEANS, METHODS AND PROCEDURES
NECESSARY TO PRODUCE THE INTENDED RESULTS.
7. THE CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND CONDITIONS, INCLUDING, BUT NOT LIMITED TO, CRITICAL DIMENSIONS PRIOR TO THE COMMENCEMENT OF THE WORK. SHOULD A DISCREPANCY OCCUR THE CONTRACTOR IS TO NOTIFY THE ARCHITECT PRIOR TO THE COMMENCEMENT OF THE WORK. THE CONTRACTOR(S) SHALL CORRECT ALL DEVIATIONS AND MAKE ANY
ADJUSTMENTS TO THE WORK BEFORE HE BEGINS HIS PORTION OF THE WORK.
8. THE CONTRACTOR SHALL VISIT THE SITE AND BE KNOWLEDGEABLE OF CONDITIONS THEREON. HE SHALL INVESTIGATE, VERIFY AND BE FAMILIAR WITH CONDITIONS OF THE PROJECT. HE SHALL NOTIFY THE OWNER AND ARCHITECT OF ANY CONDITIONS REQUIRING
MODIFICATION BEFORE PROCEEDING WITH THE WORK.
9. PROVIDE SHOP DRAWINGS TO GUIDE THE FIELD INSTALLATION OF ALL SYSTEMS. THE CONTRACTOR AND HIS SUBCONTRACTORS SHALL NOT USE THESE DIAGRAMMATIC CONTRACT DOCUMENTS AS THEIR SHOP AND COORDINATION DRAWINGS.
10. OWNER WILL DESIGNATE CONTRACTOR'S STAGING LOCATIONS.
DIMENSIONS:
1. CONTRACTOR AND MANUFACTURERS TO COORDINATE ALL DIMENSIONS PRIOR TO PROCUREMENT.
2. THE CONTRACTOR SHALL, TO THE EXTENT PRACTICABLE, VERIFY DIMENSIONS AND FIELD CONDITIONS AT THE SITE. ANY AND ALL
CONFLICTS, OMISSIONS AND DISCREPANCIES SHALL BE REPORTED IN WRITING TO THE ARCHITECT FIVE (5) BUSINESS DAYS PRIOR TO THE PROPOSAL SUBMISSION, OTHERWISE THE CONTRACTOR(S) SHALL BEAR ALL COSTS TO COMPLETE THE WORK AS INTENDED ON THE DRAWINGS. THE CONTRACTOR(S) WARRANTS BY RENDERING HIS PROPOSAL THAT THE WORK IS BUILDABLE AS SHOWN.
SYSTEMATIC METHODOLOGIES:
1. ALL DIMENSIONS, NOTES, AND FINISHES SHOWN ON TYPICAL PLANS, SECTIONS OR DETAILS SHALL APPLY TO ALL SIMILAR, SYMMETRICAL OR OPPOSITE HAND PLANS, SECTIONS OR DETAILS, U.O.N.
2. TYPICAL, OR "TYP." SHALL MEAN THAT THE CONDITION IS REPRESENTATIVE FOR SIMILAR CONDITIONS THROUGHOUT, UNLESS
REQUIRED OTHERWISE (URO). DETAILS ARE USUALLY KEYED AND NOTED "TYP" ONLY ONE TIME WHEN THEY FIRST OCCUR.
3. LARGE SCALE DRAWINGS TAKE PRECEDENCE OVER SMALL SCALE, DETAILS TAKE PRECEDENCE OVER ALL.
PROTECTION OF EXPOSED TO VIEW WORK:
1. ANY WORK THAT IS NOT FORMED AS REQUIRED OF FOR ANY REASON IS NOT OF ALIGNMENT, NOT LEVEL, OR SHOWS A DEFECTIVE
SURFACE, AS DETERMINED BY THE ARCHITECT, SHALL BE REMOVED AND REPLACED FROM THE JOB AND RECONSTRUCTED PER CONTRACT DOCUMENTS AT NO ADDITIONAL COST TO THE OWNER, AND NO INCREASE IN PROJECT SCHEDULE, UNLESS THE ARCHITECT GRANTS PERMISSION TO REPAIR THE DEFECTIVE AREA. PERMISSION TO PATCH ANY SUCH AREA SHALL NOT BE CONSIDERED A WAIVER OF THE ARCHITECT'S RIGHT TO REQUIRE A COMPLETE REMOVAL OF DEFECTIVE WORK IF THE REPAIR DOES NOT IN HIS OPINION, SATISFACTORY RESTORE THE QUALITY OF THE WORK. THE ARCHITECT SHALL BE THE SOLE JUDGE OF
ACCEPTABILITY.
2. PROTECTION: MATERIALS EXPOSED IN THE FINISHED WORK FORMS AN IMPORTANT PART OF THE COMPLETED DESIGN. AS SUCH, THE CONTRACTORS' ATTENTION IS DIRECTED TO PROTECTION OF MATERIALS EXPOSED IN THE FINISHED WORK DURING AND AFTER INSTALLATION. DAMAGE TO MATERIALS EXPOSED IN THE FINISHED VIEW SHALL BE DEEMED DEFECTIVE AND SHALL BE CAUSE FOR REJECTION OF THE WORK. DAMAGE SHALL INCLUDE, BUT IS NOT LIMITED TO: PHYSICAL DAMAGE (CHIPPING, CRACKING, SCRATCHING, DENTS, TOOL MARKS, ETC.) OR STAINING DUE TO CONTRACTOR'S OPERATIONS, PHYSICAL DAMAGE OR STAINING DUE TO AIR BORNE CONTAMINANTS (DUST, WIND BORNE DEBRIS, ETC.), THERMAL OR MOISTURE STRESS DAMAGE, AND
PHYSICAL DAMAGE SHALL BE REPLACED, AT NO ADDITIONAL COST TO THE OWNER.
DISSIMILAR METALS:
1. ALL DISSIMILAR METALS SHALL BE EFFECTIVELY ISOLATED FROM EACH OTHER TO PREVENT MOLECULAR BREAKDOWN, CORROSION
AND GALVANIC ACTION.
HAZARDOUS MATERIALS:
1. SHOULD THE CONTRACTOR ENCOUNTER ANY MATERIALS IDENTIFIED AS HAZARDOUS MATERIALS, HE SHALL IMMEDIATELY REFER
TO THE GENERAL CONDITIONS AND NOTIFY OWNER AND THE ARCHITECT.
PROTECTION OF NEW WORK:
1. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROTECTION OF NEW MATERIALS, WALL FINISHES, ACCESSORIES, ETC. DURING CONSTRUCTION OPERATIONS. ANY DAMAGE TO THESE MATERIALS AND FINISHES SHALL BE REPAIRED
AND OR REPLACED AS DIRECTED BY THE OWNER AND THE ARCHITECT.
2. CONTRACTOR SHALL PROVIDE FLOOR/WALL PROTECTION FOR ALL AREAS BEING TRAVELED BY THE CONTRACTOR TO ACCESS WORK SPACE, DURING CONSTRUCTION ACTIVITIES. ANY DAMAGE TO PROTECTION COVERING MATERIALS SHALL BE REPAIRED DURING
CONSTRUCTION.
3. CONTRACTOR SHALL DOCUMENT DAMAGE TO WALL AND FLOOR FINISHES, DEVICES, DOORS, ETC. PRIOR TO CONTINUING THE WORK BY PHOTOGRAPHS OR VIDEOS AND WRITTEN DOCUMENTATION ON THE LOCATION OF THE DAMAGE. THE CONTRACTOR SHALL REFER TO THE GENERAL CONDITIONS, NOTIFY AND REVIEW THESE LOCATIONS WITH THE OWNER AND THE ARCHITECT PRIOR
TO CONTINUING THE WORK.
4. CONTRACTOR SHALL CLEAN COMPLETED AREAS OF THE WORK THAT BECOME TRACKED WITH CONSTRUCTION MATERIALS AND DUST BEFORE AND AT PROJECT COMPLETION. AREAS UTILIZED FOR CONTRACTOR STAGING AREAS AND BUILDING ACCESS LOCATIONS SHALL BE RESTORED TO THEIR ORIGINAL STATE PRIOR TO THE COMPLETION OF CONSTRUCTION.
5. CONTRACTOR WILL BE ALLOWED TO UTILIZE A DESIGNATED TOILET OR TOILETS AS DETERMINED BY THE OWNER. CONTRACTOR WILL BE RESPONSIBLE FOR MAINTENANCE OF THE TOILETS DURING CONSTRUCTION AND WILL BE RESPONSIBLE FOR CLEANING THE TOILETS DURING CONSTRUCTION AND AT THE COMPLETION OF CONSTRUCTION. ALL PAPER PRODUCTS SHALL BE PROVIDED BY THE CONTRACTOR. THE OWNER RESERVES THE RIGHT TO REQUIRE THE CONTRACTOR TO PROVIDE TEMPORARY TOILETS.
SITE/BUILDING ACCESS:
1. THE OWNER WILL PROVIDE ACCESS ON SITE TO AN AREA TO BE USED FOR CONTRACTOR'S AND STAGING.
2. CONTRACTOR SHALL REGULARLY COORDINATE WITH THE COLLEGE'S PROJECT MANAGER ON DAILY AND WEEKLY PLANS
FOR ACCESS TO THE SITE SUCH THAT THE SITE IS SECURED AT THE END OF EACH WORK DAY.
T H
E L
IN
E
S H
O W
N A
B O
V E
I S
E
X A
C T
L Y
O
N E
I N
C H
L O
G
A
T T
H
IS
S H
E E
R
IG
IN
A
L P
A G
E S
IZ
E
L S
P
P R
O J E
C T
ORIG
SUBMISSION:
SHEET NAME:
SHEET:
A
B
C
D
E
1 2 3 4 5 6
DATE DESCRIPTION∆
COPYRIGHT 2021 ALL RIGHTS RESERVED. PRINTED OR
ELECTRONIC DRAWINGS AND DOCUMENTATION MAY
NOT BE REPRODUCED IN ANY FORM WITHOUT WRITTEN
PERMISSION FROM LS3P ASSOCIATES LTD.
/7
/2
:3
:1
A
M
A-103
ROOF PLAN
-2
04/16/2021
Blue Ridge Community College
W
C a m p u s D r.
F la t R o c k N
C
H e n d e rs o n
B u il d in g
R o o f R e p la c e m e n t
BID SET
1/8" = 1'-0" A-103
A1
ROOF PLAN
WWW.LS3P.COM
2 WEST WASHINGTON STREET STE 600
GREENVILLE, SOUTH CAROLINA 29601
TEL. 864.235.0405 FAX. 864.233.4027
ROOF PLAN SHEET NOTES
SPEC NOTES
ROOF PLAN NOTES BY NUMBER
NUMBER NOTE
1 MECHANICAL / ROOFTOP EQUIPMENT. FIELD VERIFY LOCATION AND
DIMENSIONS OF ALL EQUIPMENT PRIOR TO CONSTRUCTION. NEW
CRICKETS TO BE BUILT AROUND EQUIPMENT. NEW CURB, 8" MIN.
HEIGHT. SEE CURB DETAIL D5/A-104
2 ANTENNA CABLE STAY. FIELD VERIFY LOCATION.
3 NEW CRICKET TO BE BUILT AROUND ROOF HATCH. FIELD VERIFY
LOCATION AND DIMENSIONS PRIOR TO CONSTRUCTION.
4 PIPE PENETRATION, FIELD VERIFY LOCATION PRIOR TO
CONSTRUCTION. SEE DETAIL D3/A-104
5 EXPANSION JOINT LOCATED HERE.
6 ADD ALTERNATE #1: PROVIDE FALL ARREST SYSTEM FOR ROOF
ACCESS HATCH.
ROOF PLAN LEGEND
AREA MAP - BUILDING LOCATION
GENERAL PROJECT NOTES
jaimehenderson Cloud jaimehenderson Text Box
ADDENDUM 2
jaimehenderson Line jaimehenderson Rectangle
FIELD CAP MEMBRANE PLY
DRAIN STRAINER
REINFORCING MEMBRANE PLY
30" (76.2 cm) SQUARE MINIMUM, 2 1/2 LB. TO 4 LB. LEAD FOR 16 oz. COPPER
FLASHING SET IN BED OF MASTIC,
PRIME TOP SURFACE BEFORE
INSTALLING REINFORCING PLY
TPO ROOF
MEMBRANE
COVERBOARD
THERMAL
INSULATION
EXISTING MTL
ROOF DECK
CLAMPING RING
EXISTING DRAIN BOWL
DRAIN FLASHING, FIELD
BASE, REINFORCING AND
MEMBRANE PLIES EXTEND
UNDER CLAMPING RING
AND TURN LEAD DOWN
INTO BOWL 1" MIN.
INSTALL A MINIMUM 8"
WIDE BED OF MASTIC
ONTO THE DRAIN
FLANGE AND OUT ONTO
THE INSULATION PRIOR
TO EMBEDDING THE
FIELD BASE MEMBRANE
PLY INTO THE MASTIC.
AFTERWARD, APPLY
ANOTHER BED OF
MASTIC ON TOP OF THE
BASE PLY PRIOR TO THE
APPLICATION OF THE
PRIMED DRAIN LEAD
FLASHING
MINIMUM 4' DRAIN SUMP IN
ANY ONE DIRECTION - OR
THAT ADDITIONAL TAPER TO
PROVIDE POSITIVE
DRAINAGE
1/4" / FT SLOPE MIN.
TAPERED INSUL. CRICKET
TAPERED INSULATION
CENTER LINE
OF ROOF DRAINS
4'-0"U.N.O.
ROOF DRAIN
OVERFLOW SCUPPER
M
IN
EXTEND NEW BASE
FLASHING OVER
WOOD BLOCKING
NEW TRD WOOD
BLOCKING
NEW STRUCTURAL
FRAMING TO BE SIZED BY
CONTRACTOR PER EQUIPT.
MANUF. REQUIREMENTS
NEW CONT. NEOPRENE STRIP
NEW CONT. SHEET METAL COPING
NEW SHEET METAL COUNTERFLASHING
NEW 2" WIDE SUPPORT CLIP
NEW ROOF CURB, EXTEND TO 8" MIN. HEIGHT
WITH TRD WOOD BLOCKING AS REQUIRED
NEW TAPERED INSUL.
EXISTING METAL
ROOF DECK
NEW STAINLESS STEEL
CLAMPING RING BY GC. EXTEND TO 8" AS
NECESSARY
NEW FLASHING MEMBRANE
NEW TPO MEMBRANE
ROOFING
EXISTING PIPE, FIELD VERIFY
LOCATIONS AND DIMENSIONS
NEW PREMOULDED PIPE SEAL BY GC
M
IN
NEW CONT. BARRIER FLASHING LAP OVER
CONT. CLEAT EXTERIOR SIDE AND OVER TOP
OF BASE PLY FLASHING INTERIOR SIDE
EXISTING METAL ROOF DECK
NEW TPO MEMBRANE ROOFING
NEW 1/2" ROOF COVER BOARD
NEW R-30 POLYISOCYANURATE INSULATION
NEW CONTINUOUS BASE FLASHING PLY
M
IN
/2
M
IN
REPLACE EXISTING METAL COPING WITH NEW
EXISTING WALL ASSEMBLY. FIELD VERIFY
MATERIALS AND DIMENSIONS
NEW CONTINUOUS TREATED WOOD
BLOCKING
NEW CONTINUOUS TREATED WOOD
BLOCKING AS NEEDED
NEW CONT. BARRIER FLASHING LAP OVER
CONT. CLEAT EXTERIOR SIDE AND OVER TOP
OF BASE PLY FLASHING INTERIOR SIDE
NEW TPO MEMBRANE ROOFING
NEW 1/2" ROOF COVER BOARD
NEW R-30 POLYISOCYANURATE INSULATION
NEW CONTINUOUS BASE FLASHING PLY
REPLACE EXISTING METAL COPING WITH NEW
EXISTING WALL ASSEMBLY. FIELD VERIFY
MATERIALS AND DIMENSIONS
NEW CONTINUOUS BASE FLASHING PLY
NEW CONTINUOUS TREATED WOOD
BLOCKING AS NEEDED
(LAP OVER METAL SCUPPER)
NEW METAL OVERFLOW SCUPPER
NEW CONTINUOUS TREATED WOOD
BLOCKING
EXISTING THROUGH WALL FLASHING, REPAIR
AS NEEDED
NEW CONT. BARRIER FLASHING LAP OVER
CONT. CLEAT EXTERIOR SIDE AND OVER TOP
OF BASE PLY FLASHING INTERIOR SIDE
NEW CONTINUOUS BASE FLASHING PLY
M
IN
/2
M
IN
REPLACE EXISTING METAL COPING WITH NEW
NEW CONTINUOUS TREATED WOOD
BLOCKING AS NEEDED
NEW TPO MEMBRANE ROOFING
NEW 1/2" ROOF COVER BOARD
NEW R-30 POLYISOCYANURATE INSULATION
SLOPE TO DRAIN
EXISTING ANTENNA
EXISTING METAL DECK
EXISTING CONCRETE BASE FOR
ANTENNA: +/-10" THICK
*PHOTO OF EXISTING CONDITION - FOR REFERENCE ONLY
NEW PREFINISHED ALUMINUM EXP. JOINT
COVER TO MATCH METAL COPING. DETAIL TO
BE A SLIP CONNECTION PER SMACNA
MANUAL.NEW CONTINUOUS BASE FLASHING PLY
NEW 1/2" ROOF COVER BOARD
NEW TPO MEMBRANE ROOFING
NEW 1/2" ROOF COVER BOARD
NEW R-30 POLYISOCYANURATE INSULATION
REPAIR / REPLACE EXISTING EXPANSION
JOINT AS NEEDED
NEW CONTINUOUS TREATED WOOD
BLOCKING AS NEEDED
EXISTING WALL ASSEMBLY. FIELD VERIFY
MATERIALS AND DIMENSIONS
NEW CONTINUOUS TREATED WOOD
BLOCKING
EXISTING WALL ASSEMBLY. FIELD VERIFY
MATERIALS AND DIMENSIONS
EXISTING ROOF ASSEMBLY, NOT IN
SCOPE
T H
E L
IN
E
S H
O W
N A
B O
V E
A
C T
E
I N
C H
L O
T
H
IS
S H
E E
IG
IN
A
L P
A G
E S
IZ
E
L S
P
P R
O J E
C T
ORIG
SUBMISSION:
SHEET NAME:
SHEET:
A
B
C
D
E
1 2 3 4 5 6
DATE DESCRIPTION∆
COPYRIGHT 2021 ALL RIGHTS RESERVED. PRINTED OR
ELECTRONIC DRAWINGS AND DOCUMENTATION MAY
NOT BE REPRODUCED IN ANY FORM WITHOUT WRITTEN
PERMISSION FROM LS3P ASSOCIATES LTD.
/7
/2
:3
:1
A
M
A-104
ROOF DETAILS
-2
04/16/21
Blue Ridge Community College
W
C a m p u s D r.
F la t R o c k N
C
H e n d e rs o n
B u il d in g
R o o f R e p la c e m e n t
BID SET
WWW.LS3P.COM
2 WEST WASHINGTON STREET STE 600
GREENVILLE, SOUTH CAROLINA 29601
TEL. 864.235.0405 FAX. 864.233.4027
1 1/2" = 1'-0" A-104
D1
ROOF DRAIN DETAIL, TYP.
12" = 1'-0" A-104
E1
ROOF SLOPING DIAGRAM
12" = 1'-0" A-104
D5
CURB DETAIL, TYP.3" = 1'-0"
A-104
D3
PIPE PENETRATON DETAIL, TYP.
1 1/2" = 1'-0" A-104
B5
PARAPET, TYP. - COPING & BASE FLASHING1 1/2" = 1'-0"
A-104
B3
OVERFLOW SCUPPER, TYP. - COPING & BASE FLASHING
1" = 1'-0" A-104
A1
ROOF DETAILS - ANTENNA BASE 1 1/2" = 1'-0"
A-104
A3
EXPANSION JOINT - COPING & BASE FLASHING
jaimehenderson Cloud jaimehenderson Text Box
ADDENDUM 2
jaimehenderson Line jaimehenderson Rectangle jaimehenderson Text Box
5/7/2021 ADDENDUM 2
PHOTO 1PHOTO 3 PHOTO 4 PHOTO 2
REMOVE AND REPLACE
SEALANTS AND BACKER RODS
AROUND EACH WINDOW UNIT.
REPAIR FLASHING AS NEEDED.
*CONTRACTOR TO ENSURE
WATERPROOFING OF
SEALANTS, FLASHING, AND
TERMINATION BAR PRIOR TO
FINISHING WORK.
BUILDING EXPANSION JOINT
LOCATED HERE. PERFORM
NECASSARY WORK TO
MAINTAIN WATERPROOFING.
ENSURE ALL FASTENERS AND
PERFORATIONS IN FLASHING
ARE SEALED AND SLOPED TO
DRAIN.
APPLY SEALANT TO ANY
PERFORATIONS OR GAPS IN
FLASHING OR EXTERIOR BRICK.
ENSURE WATERPROOFING
PRIOR TO FINISHING WORK.
REMOVE ANY DEBRIS AND APPLY
BACKER ROD WHERE NEEDED
BEFORE APPLYING SEALANT
T H
E L
IN
E
S H
O W
N A
B O
V E
A
C T
E
I N
C H
L O
T
H
IS
S H
E E
IG
IN
A
L P
A G
E S
IZ
E
L S
P
P R
O J E
C T
ORIG
SUBMISSION:
SHEET NAME:
SHEET:
A
B
C
D
E
1 2 3 4 5 6
DATE DESCRIPTION∆
COPYRIGHT 2021 ALL RIGHTS RESERVED. PRINTED OR
ELECTRONIC DRAWINGS AND DOCUMENTATION MAY
NOT BE REPRODUCED IN ANY FORM WITHOUT WRITTEN
PERMISSION FROM LS3P ASSOCIATES LTD.
/1
/2
:4
:2
P
M
A-105
WINDOW
ELEVATIONS AND
EXISTING PHOTOS
-2
04/16/21
Blue Ridge Community College
W
C a m p u s D r.
F la t R o c k N
C
H e n d e rs o n
B u il d in g
R o o f R e p la c e m e n t
BID SET
WWW.LS3P.COM
2 WEST WASHINGTON STREET STE 600
GREENVILLE, SOUTH CAROLINA 29601
TEL. 864.235.0405 FAX. 864.233.4027
1/4" = 1'-0" A-105
D1
CLERESTORY WINDOWS - ELEVATION
12" = 1'-0" A-105
B5
PHOTO 112" = 1'-0"
A-105
B3
PHOTO 2
12" = 1'-0" A-105
A5
PHOTO 312" = 1'-0"
A-105
A3
PHOTO 4
| Sheets |
| A-103 - ROOF PLAN |
| A-104 - ROOF DETAILS |
File details come from the government source that posted it. Updated .