Attachment 1 - FPS-117 Tower Structural Analysis PWS.pdf
PDF 237 KB Posted
- Attached to
- AEWS Tower Surveys
- Solicitation number
- FA8217-26-R-B005
About this file
This is a Performance Work Statement (PWS) for structural analysis engineering services on AN/FPS-117 radar towers located in Alaska. The contract number is FA8217-26-TBD, prepared by AFLCMC/ESGH (Atmospheric Early Warning System Program Office), dated August 4, 2026.
The contractor must perform visual inspection, structural analysis, and above-ground/grade foundational analysis of four radar towers: Fort Yukon, Indian Mountain, Tatalina, and Sparrevohn. All work must be performed by an actively certified, licensed Professional Structural Engineer (PE) in the state of Alaska who is capable of climbing stairs, ladders, and accessing confined spaces. The structural analysis shall determine load-bearing capacity, evaluate exposed foundation concrete, identify missing or damaged rebar, and conduct a complete failure modes and effects analysis (FMEA). Inspection areas include the crawl space, first floor, second floor, external catwalk, and third floor inside the radome. The contractor must deliver an initial high-level summary of findings within 7 calendar days after on-site work, followed by a comprehensive technical report (CDRL A001) certified and stamped by an Alaska-licensed PE within 30 days. The report must address all Government comments from the draft review. A Technical Interchange Meeting (TIM) must be conducted and held no later than 14 calendar days after final report delivery, with Microsoft Teams dial-in capability for remote participants.
Travel is reimbursed on a Time-and-Materials basis for actual incurred costs under Joint Travel Regulations and RFO 31.205-46, with no profit or fee applied. The contractor must submit written travel requests to the Contracting Officer's Representative (COR) at least 14 days prior to departure and submit Site Arrival Requests (SAR) to PACAF Regional Support Center (PRSC) 14-30 days before arrival. All contractor personnel must be favorably vetted by the PRSC Security Team prior to site arrival, and a DISS request must be submitted for access to restricted areas. The PWS references four Technical Orders and provides attachment documents including site criteria and tower specifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
AN/FPS-117 Radar Tower Engineering Structural Analysis
Contract Number FA8217-26-TBD
Prepared By:
AFLCMC/ESGH
Atmospheric Early Warning System (AEWS)
AN/FPS-117 Program Office
Date:
04 August 2026
Version: 1.0
Table of Contents
Post Award Changes
Overview
Scope
Applicable Documents
Travel
Engineering Services/Requirements
Contractor Personnel
Onsite
Deliverables
TIM
Security
Service Summary
Attachments/References
Post Award Changes
Initiator Rev # Date Change Summary
1. Overview
1.1. Scope
This PWS outlines the primary requirements when performing structural analysis engineering services on the FPS-117 radar towers in Alaska along with the expected data deliverables.
1.2. Applicable Documents
1.2.1. Government Furnished Information (GFI)
The Contractor shall reference all relevant Technical Order’s (TO) and industry standards for structural analysis. Upon request, the Government will provide any available, applicable documentation which may include site-specific historical condition data, current site photographs, “as-is” drawings (original baseline/intended tower structure drawings – which may be unavailable/incomplete), previous inspection reports, and Reference document FPS-
117TECHDATA.pdf; “FPS/117 Transceive Group/Tower Interface Criteria”.
1.2.2. Technical Order’s
• 31P6-2FPS117(I)-21-1 (AN/FPS RADAR SYSTEM AN/FPS-117(V)1 7326377G1
AND AN/FPS-117(V)4 7326378G4)
• 31P3-2FPS6-232-7 AB-259 (TOWER AB-259/FPS-6)
• 31P6-2FPS3-375-2_AB199 (TOWER AB-199 USAF PART NUMBER AB-199)
• 31P1-2GPS-15 (Rigid Radome; CW-396A/GPS, CW-396B/GPS)
2. Travel
The Contractor is responsible for all travel arrangements for their personnel to and from the tower locations, travel costs, and adherence to the Joint Travel Regulations (JTRs) and RFO 31.205-46. All travel must receive prior written approval from the Contracting Officer or Contracting Officer’s
Representative (COR) prior to booking transportation or incurring costs and must be coordinated with the
Alaskan site POC. To obtain approval, the Contractor shall submit a written travel request (via email) to the COR no later than fourteen (14) days prior to the planned departure. This request must include the traveler names, dates, purpose of the trip, and an itemized estimate of all expected costs (including airfare, charter flights, lodging, and per diem).
Travel shall be reimbursed on a Time-and-Materials (T&M) basis for actual incurred costs, strictly limited to the regulations and per diem allowances outlined in the Joint Travel Regulations (JTR) and RFO
31.205-46 (Travel Costs). Total reimbursement shall not exceed the Not-To-Exceed (NTE) ceiling established in the Travel CLIN. No profit or fee shall be applied to travel costs. Due to the remote site locations, this contract specifically requires and authorizes the use of chartered aircraft, bush planes, and off-road transport when standard commercial routing is unavailable or impractical to meet mission requirements.
To be allowable for reimbursement, the Contractor must provide supporting documentation with their invoices, including the date and place of the expenses, the purpose of the trip, the name and title of the traveler, and itemized receipts for each individual expenditure of $75.00 or more, in accordance with RFO
31.205-46.
Site visitors shall be processed through a Site Arrival Request (SAR). SARs must be submitted to PRSC
14-30 days prior to site arrival and approved prior to booking transportation to the site and incurring travel costs (see reference section for link to SAR submittal).
If site access is required sooner than 14 days, then the Government Program Office program manager will work with the Contractor to provide justification to the PACAF Regional Support Center Office (PRSC).
3. Engineering Services/Requirements
3.1. Contractor Personnel
The engineering services/analysis shall be performed by an actively certified licensed Professional
Structural Engineer (PE) in the state of Alaska and be capable of meeting any/all physical demands of on-site inspections to include climbing stairs and ladders and accessing confined spaces without assistance.
3.2. On-Site
The contractor shall perform visual inspection, structural, and above-ground/grade foundational analysis of the following towers:
• Fort Yukon
• Indian Mountain
• Tatalina
• Sparrevohn
The structural analysis shall determine the towers' load-bearing capacity (based on above-ground structures), evaluate all exposed foundation concrete (identifying issues such as missing or damaged rebar), and identify any areas of concern requiring further investigation.
3.2.1. Inspection Areas
• Crawl Space (Ground level)
• First floor/Main level
• Second floor
• Catwalk (external to Radome)
• Third floor (inside the Radome, located around the radar unit)
3.2.2. Structural Analysis
The contractor shall perform a compete structural analysis of tower, foundation, and related components to identify and quantify spalling, buckling, cracking, corrosion, deterioration, structural shifting, and current condition of any previous repairs, and conduct a full load path analysis and Failure Modes and Effects Analysis (FMEA).
3.3. Deliverables
The Contractor shall deliver a comprehensive technical report, Contract Data Requirement List (CDRL)
A001; Technical Report-Study/Services, per tower, to the Government NLT thirty (30) days after work on site is performed, and IAW DI-MISC-80508B.
An initial, high-level summary of findings, per tower, shall be delivered to the Government NLT seven (7) calendar days after work on site is performed.
The initial draft report shall contain:
• Summary of findings
• Details of the structural analysis on tower and foundation including methods used and photographic evidence/examples focused on bucking, shifting, and cracking o All requests and justification for official or business-related imagery must be detailed in the SAR and shall be coordinated through the ARS PM (see PACAF memo in reference section)
• General observation of the tower
• Contractor’s recommendations for any further investigations that concern areas may warrant
• Contractor’s recommendations for any repairs that may be necessary before tower undergoes new radome installation
The full, comprehensive technical report should expand upon the initial findings and must be certified/stamped by the Alaska-licensed PE.
3.4. Tower Structure Technical Interchange Meeting (TIM)
The Contractor shall hold a TIM with the program office after each tower’s final delivery of CDRL A001 for purposes of discussing methods used/results of each structural analysis. The date and time of TIM(s) shall be coordinated with the Government, held NLT 14 calendar days after A001 final comprehensive technical report delivery, and include a Microsoft Teams dial-in option for geographically separated participants.
4. Security
(From PACAF memo; see reference section)
All visiting personnel are required to be favorably vetted by the PRSC Security Team prior to arrival at the site, without exception.
All coordination with the security team will be done through the PRSC Program Management Office.
SARs will not be approved without documented vetting by the security team.
Access to restricted areas must be requested and detailed in the SAR and shall be vetted through the
PRSC Security Team. A DISS (Defense Information System for Security) request MUST be submitted for access to Restricted Areas for all cleared personnel.
5. Service Summary:
Performance
Objective
PWS
Reference
Acceptable Quality Level (AQL) Method of
Surveillance
1. Perform On-Site
Structural
Inspection &
Analysis
Section 3.1
& 3.2
100% of defined inspection areas evaluated. Site inspection must be physically led by a certified Alaska-licensed Professional Engineer (PE). No safety violations during site visit.
100% Inspection /
Direct Observation by
Government Site
POC.
2. Deliver Initial
Draft Technical
Report
Section 3.3 Delivered No Later Than (NLT) 7 calendar days after work on site is performed. Report must include all 5 required elements (summary, methods/photos, observations, investigation recs, repair recs). Zero missing sections.
100% Review by
Government Program
Manager / Lead
Engineer.
3. Deliver Final
Comprehensive
Technical Report
Section 3.3
& CDRL
A001
Delivered NLT 30 days after work on site is performed. Document must be officially certified/stamped by an active Alaska-licensed PE. Must successfully incorporate or address 100% of Government
100% Review by
Government Lead
Engineer / Technical
Evaluator.
comments generated from the Draft
Report review.
4. Conduct
Technical
Interchange
Meeting (TIM)
Section 3.4 Scheduled and held NLT 14 calendar days after Final Report delivery. Meeting logistics successfully coordinated with the
Gov, including a functional Microsoft
Teams dial-in for remote participants.
Direct Observation by
Government
PM/Participants.
6. Attachments/Reference Documents
• FPS/117 Transceive Group/Tower Interface Criteria
FPS-117TECHDATA.p df
• 31P6-2FPS117(I)-21-1 (AN/FPS RADAR SYSTEM AN/FPS-117(V)1 7326377G1 AND
AN/FPS-117(V)4 7326378G4)
31P6-2FPS117(I)-21-
2.pdf
• 31P3-2FPS6-232-7 AB-259 (TOWER AB-259/FPS-6)
31P3-2FPS6-232-7_
AB259.pdf
• 31P6-2FPS3-375-2_AB199 (TOWER AB-199 USAF PART NUMBER AB-199)
31P6-2FPS3-375-2_
AB199.pdf
• 31P1-2GPS-15 (Rigid Radome; CW-396A/GPS, CW-396B/GPS)
31P1-2GPS-15_396A
Installation Proceedures.pdf
• FY26 Base Support Letter ARS (October 2025)
FY26 Base Support
Letter ARS.pdf
• Site Arrival Request (SAR) Link:
https://forms.osi.apps.mil/pages/responsepage.aspx?id=jbExg4ct70ijX6yIGOv5tM5OUa5-oGFPgULRQ_r_m4RURVpUVUJCVkkyOVZHRlpRQ0YwNjk4MjlGOC4u&route=shorturl https://forms.osi.apps.mil/pages/responsepage.aspx?id=jbExg4ct70ijX6yIGOv5tM5OUa5-oGFPgULRQ_r_m4RURVpUVUJCVkkyOVZHRlpRQ0YwNjk4MjlGOC4u&route=shorturl https://forms.osi.apps.mil/pages/responsepage.aspx?id=jbExg4ct70ijX6yIGOv5tM5OUa5-oGFPgULRQ_r_m4RURVpUVUJCVkkyOVZHRlpRQ0YwNjk4MjlGOC4u&route=shorturl
File details come from the government source that posted it. Updated .