Attachment 1 - Drawing Abatement area B67 G26.pdf
PDF 457 KB Posted
- Attached to
- 531-26-2-5408-0065 Asbestos Removal Bldg. 67
- Solicitation number
- 36C26026Q0727
About this file
This document is an asbestos abatement plan for Building 67 Records at a VA Medical Center facility. The project involves the removal of approximately 475 square feet of asbestos black mastic located under non-asbestos floor tile in two locations: Location A contains 225 square feet under old medical records platforms that may be removed within the containment prior to abatement if desired, and Location B contains 250 square feet where platforms must be removed after abatement begins due to poor floor condition from past water damage.
The removal parameters specify that the contractor must establish a full negative pressure enclosure with HEPA-filtered air exhausted outside, using 6-mil polyethylene walls. The contractor may set up either one larger containment or two smaller containments at their discretion. Removal must be performed using wet methods only with no sanding, and all asbestos waste must be sealed in 6-mil polyethylene bags and/or sealed plastic drums labeled as asbestos waste. A one-stage decontamination system is required to prevent airborne asbestos migration. Room G26 requires a splash guard on hard walls and plastic flooring on non-asbestos areas to prevent damage or staining. Third-party involvement includes visual clearance by VA Industrial Hygiene and aggressive air sampling for final clearance, with the option for the contractor to subcontract the industrial hygiene company (Atlas) or have VA coordinate. The contractor may use the STG2 exterior exit with nearby parking and may keep the door open during work but must seal it closed afterward. VA Construction Shop will provide project management while a VA Industrial Hygienist will provide abatement oversight.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26026Q0727 0001.pdf | ||
| Attachment 3 - Statement of Work.pdf | ||
| 36C26026Q0727.docx | DOCX document | |
| Attachment 2 - WageDetermination P07 Boise DBA.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
-475 SQ FT ASBESTOS BLACK
MASTIC UNDER
NON-ASBESTOS FLOOR TILE
BUILDING 67 RECORDS ASBESTOS ABATEMENT
ASBESTOS TYPE AND AMOUNT
-475 SQ FT - ASBESTOS BLACK MASTIC UNDER NON-ASBESTOS FLOOR TILE
ASBESTOS FLOORING IS UNDER OLD MEDICAL RECORDS PLATFORMS WHICH
MUST BE REMOVED AS PART OF THE ABATEMENT.
- LOCATION A - PLATFORMS MAY BE REMOVED WITHIN THE
CONTAINMENT, BUT PRIOR TO BEGINNING THE ABATEMENT, IF DESIRED.
IF ANY FLOOR TILE COMES UP WITH THE PLATFORMS WORK SHOULD
STOP UNTIL ASBESTOS ABATEMENT BEGINS.
- LOCATION B - PLATFORMS MUST BE REMOVED AFTER THE ASBESTOS
ABATEMENT BEGINS, THE FLOOR TILE UNDERNEATH IS IN POOR
CONDITION DUE TO PAST WATER DAMAGE.-250 SQ FT
REMOVAL PARAMETERS - CONTROLS FOR ABATEMENT
- FULL NEGATIVE PRESSURE ENCLOSURE W/HEPA FILTERED AIR
EXHAUSTED OUTSIDE
- 6-MIL POLY WALLS SHOULD BE USED FOR THE ENCLOSURE
- CONTRACTOR MAY SET UP 1 LARGER CONTAINMENT OR 2 SMALLER ONES
ATTHEIR DISCRETION.
- HARD WALLS IN ROOM G26 NEED SPLASH GUARD, NON ASBESTOS
FLOORING (REST OF G26) NEED A PLASTIC FLOOR TO ELIMINATE RISK OI-
DAMAGE OR STAIN
- 1-STAGE DECON TO ASSIST IN PREVENTING THE MIGRATION OF
AIRBORNE ASBESTOS OUTSIDE THE CONTAINMENT
- USE WET METHODS TO REMOVE BLACK MASTIC. NO SANDING.
- ALL WASTE MUST BE SEALED IN 6-MIL POLY BAGS AND/OR SEALED
PLASTIC DRUMS LABELED AS ASBESTOS WASTE
- WASTE BAGS AND EQUIPMENT MUST BE WIPED DOWN PRIOR TO EXITING
THE NEGATIVE PRESSURE ENCLOSURE
-225 SQ FT[
3RD PARTY INVOLVEMENT
- VISUAL CLEARANCE DONE BY VA INDUSTRIAL HYGIENE
- AGGRESSIVE AIR SAMPLING REQUIRED FORTHE FINAL CLEARANCE
- AAI MAY SUBCONTRACT THE INDUSTRIAL HYGIENE COMPANY (ATLAS).
OR VA WILL COORDINATE.
1G02C | qj□Q
LOGISTICS
- AAI MAY USE THE STG2 EXTERIOR EXIT, THERE IS A NEARBY LOCA TION
WHERE TO PART A CONTRACTOR VEHICLE
THIS DOOR CAN REMAIN OPEN DURING WORK, BUT MUST BE SEALED
CLOSED AFTERWARDS.
- VA CONSTRUCTION SHOP WILL PROVIDE PROJECT MANAGEMENT, VA
INDUSTRIAL HYGIENIST WILL PROVIDE ABATEMENT OVERSIGHT
G26
□□□—Q □