Attachment 1. Statement Of Work.pdf

PDF 377 KB Posted

Attached to
East Fork Campground Emergency Road Reconstruction Federal contract opportunity
Solicitation number
127EAW24R0068
Issued by
Department of Agriculture Forest Service

About this file

This document is a Statement of Work for the East Fork Campground Emergency Road Reconstruction project on the Lower Trinity Ranger District of the Six Rivers National Forest in Trinity County, California.

The work includes emergency repairs to the East Fork Campground access road that was damaged by storm flows in January 2024. The repairs required include removing asphalt overhangs, filling in washed out sections of the road bed, compacting fill, pumping slurry under the water crossing, and surface grading. The period of performance is 60 days after the Notice-to-Proceed. The project is a total small business set-aside with an estimated value between $25,000 and $100,000. The contracting agency is the U.S. Department of Agriculture Forest Service. Interested contractors must submit proposals by the deadline and may submit Requests for Information by August 14, 2024.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

East Fork Campground Emergency Road Reconstruction

Lower Trinity Ranger District Six Rivers National Forest

Trinity County

1 GENERAL SPECIFICATIONS

1.1 SCOPE OF WORK

The intent of this contract is to secure services for repairs on the Lower Trinity Ranger District of Six Rivers National Forest on the East Fork Campground. Road work is required at East Fork Campground for the purpose of public use of the roadway.

The East Fork of Willow Creek runs through the East Fork Campground site. In January 2024, excessive flows from storms resulted in a substantial log jam at the water crossing within the campground. This log jam built up, blocked the water way of the crossing, and water routed along the right bank, washing out the road and portions of the day use area. An image of the damage is shown below (Figure 1).

Figure 1. Storm Damage of Rd 06N21.

A rough estimate of material that needs to be placed is approximately 1000 CY.

This contract includes emergency repairs sufficient to reopen the site for public access. Where asphalt is creating an overhang above the rutted out sections, asphalt will be cut off (using a concrete/asphalt cutter or equivalent) to create a vertical face and a clean edge. Select fill (subbase) will be brought in, building up minimum 2:1 (or shallower) from the base (where road is washed out), and base course aggregate placed to create a level shoulder.

At the water crossing, storm flows scoured out bank material under abutments. Using 3 ½ to 4 ½ sacks, pump slurry under abutments of water crossing. 10 CY of slurry is estimated to be required. After pumping slurry, cap with fill.

Project work includes:

• Breaking off overhang of asphalt above washed out section of road bed

• Filling in washed out section of road bed, building up minimum 2:1 from base o Using select fill for subbase, class A or B for base

• Compaction of fill

• Pumping slurry (3 ½ to 4 ½ ) under water crossing

• Surface grading of rutted areas in day use area and where needed

• Re-establishing drainage ditches where needed

Unless otherwise noted, the Contractor shall furnish all labor, transportation, equipment, tools, supervision, materials and any incidentals necessary to accomplish work. The period of performance shall be 60 days after the Notice-To-Proceed has been issued.

Site Visit A formal site visit will not be scheduled, but informal contractor site visits are highly encouraged.

The Contracting Officer's Representative (COR) for this project will be Katelyn Brady. Ms.

Brady can be reached at katelyn.brady@usda.gov or (707)672-2527.

License Contractor shall be licensed as a C-12 Earthwork Contractor or other state equivalent.

1.2 PROJECT LOCATION AND ACCESS

The project area is on the Lower Trinity Ranger District of Six Rivers National Forest.

Access to East Fork Campground: From Eureka take Highway 101 North to Highway 299 (10 miles). Take Highway 299 to East Fork Campground (Road 6N12) (35 miles). The estimated time of travel is approximately 45 miles.

mailto:katelyn.brady@usda.gov

1.3 OPERATING SEASON

Operating season shall be year-round except when prohibited by snow or wet weather. Between October 15th and May 15th wet weather operating restrictions shall apply and work will be tightly controlled and monitored for erosion control and preventive measures. At the discretion of the Forest Service, work may be suspended for wet weather before startup or during operations when conditions warrant.

Some roads also have limited operating periods (LOPs) due to wildlife protection measures.

Limited operating periods, if any, are shown in the road logs.

1.4 - EQUIPMENT

All equipment shall be suitable for the purpose intended and shall meet all requirements of the Occupational Safety and Health Act. The Contracting Officer may order the removal or require the replacement of any unsatisfactory equipment.

All vehicles and machinery operating on or from the traveled way or road shoulder shall have flashing lights or rotary beacons operated continuously while work is in progress. All equipment shall be equipped with a standard slow moving vehicle emblem. Truck headlights shall be on while operated. Backup warning devices shall be required on self-propelled equipment in excess of 8,000 pounds gross vehicular weight.

Vehicles and machinery not currently used in decommissioning operations shall be parked off the traveled way at a location that minimizes interference with normal use of the road.

1.5 - EQUIPMENT CLEANING

The contractor shall clean all vehicles and equipment before entry into the Lower Trinity Ranger District unless the cleaning requirement is waived in writing by the Forest Service. Thereafter, all vehicles and equipment that leave the Lower Trinity Ranger District or enter infested portions of the district must be cleaned prior to their reentry, unless waived in writing by the Forest Service. All cleaning of vehicles or equipment shall be done at sites agreed to by the Forest Service and the Contractor. The water used for washing will be from a source in a non-infested drainage. The Forest Service shall inspect all vehicles and equipment prior to entry, as appropriate and determined necessary. Infested and uninfested areas will be determined by the Forest Service. Cleaning shall include the removal of soil by steam cleaning or use of high pressure water spray.

2 STANDARD SPECIFICATIONS

STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS (FP-14) is included in this solicitation by reference only (FP14 | FHWA (dot.gov)). The requirements contained in these Standard Specifications are hereby made part of this Solicitation and any resultant contract.

Special Project Specifications are physically incorporated within this solicitation, beginning after the list of applicable Standard Project Specifications.

The following Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects issued in 2014 (FP-14) are applicable to this contract:

AAPPLICABLE FP-14 STANDARD SPECIFICATIONS DATE

Section 101. — TERMS, FORMAT, AND DEFINITIONS 2014 Section 102. — BID, AWARD, AND EXECUTION OF CONTRACT 2014 Section 103. — SCOPE OF WORK 2014 Section 104. — CONTROL OF WORK 2014 Section 106. — ACCEPTANCE OF WORK 2014 Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC 2014 Section 108. — PROSECUTION AND PROGRESS 2014 Section 109. — MEASUREMENT AND PAYMENT 2014 Section 151. — MOBILIZATION 2014 Section 153. — CONTRACTOR QUALITY CONTROL 2014 Section 154. — CONTRACTOR SAMPLING AND TESTING 2014 Section 155. — SCHEDULES FOR CONSTRUCTION CONTRACTS 2014 Section 156. — PUBLIC TRAFFIC 2014 Section 201. — CLEARING AND GRUBBING 2014 Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS 2014 Section 204. — EXCAVATION AND EMBANKMENT 2014 Section 302. — MINOR CRUSHED AGGREGATE 2014 Section 303. — ROAD RECONDITIONING 2014 Section 703. — AGGREGATE 2014

2.1 SUPPLEMENTAL SPECIFICATIONS

Roads that have specified road requirements shall conform to the standards set forth in the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP14-US Customary Units). This contract includes supplemental specifications that modify or change the parent specifications contained within FP14 and pertain to the specific work identified in the Schedule of Items and noted in the Road Logs (FP-14 | FHWA (dot.gov)).

The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract. The following Forest Service Supplemental Specifications (FSSS) to the FP- 14 are applicable to this contract:

https://highways.dot.gov/federal-lands/specs/archives/fp-14 https://highways.dot.gov/federal-lands/specs/archives/fp-14 https://highways.dot.gov/federal-lands/specs/archives/fp-14

Description Revision Date Preface 5/14/2020 101 - Terms, Format, and Definitions 11/9/2016

101.01 Meaning of Terms 11/9/2016

101.03 Abbreviations. 11/9/2016

101.04 Definitions. 1/22/2020

102 - Bid, Award, and Execution of Contract 11/9/2016 103 - Scope of Work 11/9/2016 104 - Control of Work 11/9/2016

104.06 Use of Roads by Contractor 11/9/2016

106 - Acceptance of Work

106.01 Conformity with Contract Requirements. 7/18/2017

106.02 Visual Inspection 11/9/2016

106.07 Partial and Final Acceptance 11/1/2016

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims. 7/18/2017

108 - Prosecution and Progress 11/9/2016 109 - Measurement and Payment 11/9/2026

109.01 Measurement of Work 2/22/2019

109.02 Measurement Terms and Definitions 11/9/2016

155 - Schedules for Construction Contracts 11/9/2016 201 – Clearing and Grubbing

201.01 Combined 2/26/2018

3 SUBMITTAL REQUIREMENTS

The following submittals are required for this project:

Referenced by Specification No

Time of Government Approval After Submittal

Construction Schedule FAR 52.236-15 14 days Safety Plan FAR 52.236-13 14 days Traffic Control Plan FP-14 156 14 days

4 SPECIAL CONSIDERATIONS

Use of Premises

(a) Forest Service Regulations for Use of Campground prohibits occupancy of developed recreation sites for other than primarily recreation purposes. One camp unit will be allowed at the project site for use by a watchman.

(b) A storage site will be permitted at a designated site within the project area. The Forest Service assumes no liability for materials stored within the storage site. The Contractor will be allowed to erect a temporary fence to secure materials and equipment; however, the fence shall be removed, and the site restored prior to final acceptance of the contract.

(c) When the Contractor’s operations require a temporary electrical power distribution system, the system shall comply with the National Electrical Code, applicable local codes, and utility regulations. The Contractor shall make all arrangements with the serving utility for temporary power and shall pay the serving utility for all applicable fees and power consumed.

(d) Potable water and sanitary facilities are NOT available for use during construction.

(e) The Contractor is authorized to use roads that are part of the construction project and those Forest Service Roads designated below for performance of work under this contract.

(f) The Contractor is responsible for all road maintenance and repair work caused by their operations.

Load Limits - All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, over-width permits.

Forest Service overload permits for this project may be obtained from the Lower Trinity District Ranger.

Heritage/Archeology

(a) In the event that cultural resources are discovered during implementation, all work in the area shall cease and the Forest Heritage Program Manager shall be notified immediately.

Any inadvertent discoveries within the project boundary shall be protected utilizing Standard Protection Measures as stipulated in the First Amended Region 5 Programmatic Agreement (2018

R5 PA).

(b) Should inadvertent effects to or unanticipated discoveries of human remains be made on Region 5 lands, the County Coroner (California Health and Safety Code 7050.5(b)) shall be notified immediately. If the remains are determined to be Native American or if Native American cultural items pursuant to NAGPRA are uncovered, the provisions of NAGPRA and its regulations at 43 CFR 10 and ARPA at 43 CFR 7 shall be followed on federal lands (R5 PA Stipulation 7.9 (a)).

East Fork Campground Emergency Road Reconstruction
1.1 SCOPE OF WORK
1.2 PROJECT LOCATION AND ACCESS
1.3 OPERATING SEASON
1.4 - EQUIPMENT
1.5 - EQUIPMENT CLEANING