Attachment 1. Performance Work Statement.pdf
PDF 642 KB Posted
- Solicitation number
- N4523A26Q5709
About this file
Performance Work Statement Summary
This is a Performance Work Statement (PWS) for a major overhaul of a Caterpillar 3408B Power Generation Diesel Engine (S/N 78Z05911) currently stationed at Puget Sound Naval Shipyard (PSNS). The contract is a firm-fixed price, non-personnel service contract with a 10-week period of performance from when the engine is shipped to the contractor's facility. PSNS is responsible for initial shipping to the contractor's location; the contractor is responsible for return shipping to PSNS in Bremerton, Washington. The work must be performed by a Caterpillar OEM-certified repair facility specializing in power generation diesel generator sets, with preference for ASE-certified diesel mechanics with T2-diesel and 3408B experience.
The primary objective is to completely rebuild the engine with new, remanufactured, or reconditioned parts to minimize future engine failure risk and avoid costly removal and replacement operations. The overhaul includes 36 major repair tasks spanning cylinder head reconditioning, turbo cartridge replacement, fuel injection system rebuilding, bearing replacement, gear train service, and comprehensive parts replacement per OEM specifications using only genuine OEM parts. The contractor must perform disassembly and inspection, submit findings and recommendations to PSNS within 24 hours, complete all authorized repairs, and conduct minimum testing including engine break-in, dynamometer testing at all RPMs, and safety device verification. Deliverables include inspection findings reports, unexpected findings reports, test reports, final condition assessment, dyno performance results, and component replacement documentation, all due within two weeks of service completion. The Contracting Officer Representative will oversee technical aspects and performance monitoring, while the contractor maintains close liaison with government personnel throughout the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
CATERPILLAR 3408 DIESEL ENGINE MAJOR OVERHAUL
Part 1
General Information
1. GENERAL: This is a non-personnel service contract to provide major overhaul maintenance on a Caterpillar 3408B POWER GENERATION Diesel Engine, S/N 78Z05911. The Government shall not exercise any supervision or control over the contract service providers performing the services herein.
Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, shipping, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform Diesel Engine Major Overhaul as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.
1.2 Background: The crane’s “power generation” diesel engine, Mfr. Caterpillar (CAT) 3408 has reached its recommended threshold for a Major Overhaul. This diesel was removed from an Amclyde Crane stationed at Puget Sound Naval Shipyard.
1.3 Objectives: Caterpillar OEM Certified repair facility to perform repairs/open and inspect/refurbishment/replacement on Caterpillar 3408B Power Generation Diesel Engine as described in Part 5, Specific Tasks, such that repaired equipment functions as intended. Contractor maintains close liaison and good communications with Government. Also, provide a final Condition Report of assessment.
1.4 Scope: The following work outlined in Part 5, Specific Tasks, must be accomplished by a Certified OEM engine repair facility; the repair facility shall be specifically OEM certified to repair/service “power generation” diesel generator sets, such is the model listed above. The repairs shall be performed per OEM specifications, using ONLY Genuine OEM parts. It is preferred the service personnel are ASE certified diesel mechanic(s). (T2-diesel engines, 3408B experience preferable).
1.5 Type of Contract: The government will award a Firm-fixed Price Contract.
1.6 Period of Performance: The contractor shall have 10 weeks beginning on or after the period of performance includes shipping receiving/delivery or physical pickup/delivery of the diesel to and from
PSNS.
1.6.1 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.7 Place of Performance: The work to be performed under this contract will be performed at the contractor’s repair facility.
1.8. Pickup and Delivery. Puget Sound Naval Shipyard will be responsible for shipping of diesel to the awarded vendors location. The contractor will be responsible for shipping return of the diesel to Puget
Sound Naval Shipyard. Coordination of the shipping delivery/receive, and possible pickup/drop-off will be made with the Planning point of contact, , listed under 1.10, Government Point of Contact.
Puget Sound Naval Shipyard 1400 Farragut Ave Bremerton, WA 98314
1.8.1 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer (KO), Contracting Officers Representative (COR), and other approved appointed Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.
1.9 PHYSICAL Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.
1.9.1 Special Qualifications: Contractor must have the ability to test the unit fully described in Part 5, Specific Tasks. It is preferred that the service personnel are ASE certified diesel mechanic(s). (T2-diesel engines, 3408 experience preferable)
1.10 Contracting Officer Representative (COR): The COR is not authorized to modify any terms or conditions of the contract. The Contracting Officer's Representative (COR) will be identified by a separate letter. The COR oversees all technical aspects of the contract and assists with contract administration. Their responsibilities include ensuring the Contractor meets the technical requirements, conducting necessary inspections, and maintaining written and oral communication with the Contractor regarding technical matters. With the support of the designated TA/TPOC, the COR can issue written interpretations of technical specifications, including government drawings, designs, and specifications. They monitor the Contractor’s performance, notify both the Contracting Officer and Contractor of any deficiencies, coordinate the availability of government-furnished property, and facilitate site access for Contractor personnel. A letter of designation sent to the COR and a copy provided to the Contractor outlines the COR’s responsibilities and limitations, particularly regarding changes in cost, price, estimates, or delivery schedules.
Contracting Officer Representative: (COR):
1.11 Government Technical Points of Contact (TA/TPOC):
The TA/TPOC(s) are responsible for monitoring all technical aspects of the contract and assisting with contract administration. They are authorized to perform these duties after being appointed by the COR and having a signed TA form on file. Their responsibilities include ensuring the Contractor meets the technical requirements, helping with inspections related to contract performance, maintaining written and oral communication with the COR about technical matters, issuing written interpretations of technical requirements such as government drawings, designs, and specifications, assisting in monitoring the Contractor’s performance and reporting any deficiencies to the COR, coordinating the availability of government-furnished property, and helping to facilitate site access for Contractor personnel.
The TA/POC(s) are NOT authorized to change any of the terms and conditions of this contract. If the contractor believes any Government Personnel has effectively issued a change resulting in a change in effort and price/cost of the contract, the Contractor shall immediately notify the COR or Contracting Officer.
1.12. Identification of Contractor Employees: NA
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS
2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and/or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor if that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5. DELIVERABLE. Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the person(s) that are listed in the proposal.
2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.12. WORKDAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation GFP Government Furnished Product HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out PIEE Procurement Integrated Enterprise Environment POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit
2.1.1. All Definitions unless defined within the Contract are as defined within FAR Part 2.
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Equipment: The Government will provide submitting the Caterpillar 3408B POWER GENERATION Diesel Engine, S/N 78Z05911 into the PIEE GFP process.
3.1.1 Contractors are required to report receipt and transfer of all GFP through PIEE.
Contractors guide on PIEE on how to obtain access.
https://piee.eb.mil/xhtml/unauth/web/homepage/vendorCustomerSupport.xhtml
I. The Contractor will be Property Shipper, Contractor Property Receiver, and Contractor Property Manager Roles.
You can find all trainings on the GFP Module at https://dodprocurementtoolbox.com/
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Part 3 of this PWS.
4.3. Materials: The Contractor shall furnish their own tools, test equipment, parts and ancillary equipment needed to complete the work described in Part 5, Specific Tasks.
PART 5
SPECIFIC TASKS
5. SPECIFIC TASKS:
5.1. Basic Services. The contractor shall provide services outlined for a Major Overhaul of a Cat 3408 POWER GENERATION diesel.
5.2. Tasks
The following work shall be accomplished by a Certified OEM engine repair facility and Power Systems Certified; the repair facility shall be specifically OEM certified to repair/service “power generation” diesel generator sets, such is the model listed above. The repairs shall be performed per OEM specifications, using ONLY Genuine OEM parts. It is preferred the service personnel is ASE certified diesel mechanic(s).
(T2-diesel engines, 3408 experience preferable).
***The PSNS desired outcome of the overhaul is that the engine is completely rebuilt with new parts (new/remanufactured/reconditioned) to ensure that there is a lesser probability for additional engine work or failure in the near future due to reusing “suitable” old parts. This is to avoid the extremely expensive and time-consuming work to remove and replace a crane engine***
5.2.1 Disassembly and Inspection:
Disassembly and Inspection of provided Cat 3408 POWER GENERATION diesel, to include:
A. Perform initial inspection, to include:
a. Disassembly of all components.
b. Visually inspection of all components.
B. Submit findings to PSNS. Additionally, provide any recommendations for repair beyond the items authorized for repair in 5.2.2 to include a price quote and lead time to repair.
B.1. Do not repair additional items not identified within section 5.2.2 unless approved in writing by Contracting Officer (KO).
5.2.2 Repair Actions:
A. Clean engine on arrival.
B. Clean all components. Perform disassembly and inspection directions above (5.2.1)
C. All parts replaced will be OEM industry standards.
D. Perform the following repair actions: Rebuild the engine: replace all the listed parts and any additional parts needed that are not listed here to achieve the PSNS desired outcome:
Tasks for the Major Overhaul:
1. CYLINDER HEADS (RECONDITION/REMAN)
2. TURBO CARTRIDGES (RRECONDITION/REMAN)
3. FUEL INJECTORS (REMAN)
4. REPLACE INJECTION PUMP (REMAN)
5. JW WATER PUMP (REMAN)
6. REPLACE JACKET WATER TEMP REGULATORS (NEW)
7. AUX WATER PUMP (REMAN)
8. WATER TEMP REGULATORS (THERMOSTAT) (NEW)
9. AFTERCOOLER CORE (CLEAN/TEST)
10. OIL SAMPLE (TEST/REPORT)
11. OIL FILTERS (NEW)
12. FUEL FILTERS (NEW)
13. ALL REQUIRED GASKETS, SEALS, O-RINGS (NEW)
14. PAINT BARE COMPONENTS: Items 1-13 PER ABOVE PARTS LIST
15. CYLINDER PACKS (RODS/LINERS/PISTONS/RINGS)
16. ENGINE OIL PUMP (REMAN)
17. AFTERCOOLER CORE (RECONDITIONED/REMAN)
18. ENGINE OIL COOLER CORE (REMAN)
19. FUEL TRANSFER PUMP (REMAN)
20. CRANKCASE BREATHERS AND CLAMPS (NEW)
21. CRANKSHAFT MAIN BEARINGS AND THRUST PLATES (NEW)
22. INSPECT AND REPLACE CRANK BALANCER IF REQUIRED
23. CONNECTING ROD BEARINGS (NEW)
24. ROCKER ARMS ASSEMBLIES - INTAKE/EXHAUST
25. AIR CLEANER ELEMENT (NEW)
26. CAMSHAFTS AND LIFTERS (REMAN)
27. CAMSHAFT BUSHINGS/BEARINGS
28. REPLACE CAMSHAFT BALANCER ASSEMBLY
29. FRONT GEAR TRAIN GEARS AND BUSHINGS
30. REAR GEAR TRAIN GEARS AND BUSHINGS
31. FRONT AND REAR MAIN CRANKSHAFT SEALS
32. VIBRATION DAMPER
33. PISTON COOLING JETS
34. COOLANT HOSES
35. INSPECT CRANKSHAFT UPON TEAR DOWN
36. INSTALL ADDITIONAL PARTS LISTED:
1ea - 4P-3864 COVER 1ea - 4N0362 COVER A 1ea - 7C-0307 GASKET 1ea - 4N1156 GASKET 1ea - 6N1410 ELBOW 1 1ea - 6N1411 ELBOW 1 1ea - 6N1656 GOV DRIVE G 1ea - 4N7651 PIPE 1ea - 1W9070 DIODE A
1ea - 2W7553 MANIFOLD 1ea - 4N6145 SUPPORT 1ea - 1052508 PUMP AS 1ea - 1736996 SOLENOID AS 1ea - 1342252 SENSOR GP EL 1ea - 4499582 KIT-GASKET 1ea - 6N9076 TUBE “A” OIL 2ea - 1078106 MANIFOLD 2ea - 1078112 MANIFOLD 1ea - 155-2260 PLUG KIT-CON 1ea - 108-3190 SWITCH 3ea - 8T-8730 CONNECTOR 1ea - 7E3903 TUBE 1ea - 7E3904 TUBE 1ea - 7E3902 TUBE 1ea - 7E3901 TUBE
E. All seals and gaskets will be replaced with new and all hardware torqued to CAT spec.
F. Valves and fuel system timed and adjusted to CAT guidelines.
G. Upon approval by the Contracting Officer via a contract modification, perform recommended additional repair items identified under 5.2.1-B.
H. After completion of repairs, perform the minimum testing listed below:
a. Test run engine to include initial break-in
b. Perform engine dyno at all engine RPMs and record HP and Torque for customer records
c. Test and report on the condition of Safety devices.
I. Once successful testing for normal operation, return the completed engine to Puget Sound Naval
Shipyard.