This document is a site improvement plan for the Newtown Estates Park Perimeter Trail, dated June 26, 2025. The project involves comprehensive park infrastructure upgrades, including resurfacing a 1,600-foot long and 8-foot wide shell perimeter trail with asphalt, extending the trail by 30 feet to connect with existing concrete sidewalks, and adding 1,040 linear feet of accessible public sidewalks. Key modifications include replacing a 16-foot mortise fence with five 6-inch round bollards, installing a 5' x 10' x 3' deep concrete box culvert for trail drainage, and relocating a pecan grove with options for placement near the baseball field, which will be converted to a multi-purpose field.
The plan includes specific design details such as regrading the area for erosion control, adding a 3-foot wide person gate at the mortise fence to accommodate wheelchairs, and maintaining specific setback distances for the pecan grove relocation. The total perimeter loop trail will be 2,640 linear feet (approximately 1/2 mile), with provisions for accessibility and improved park infrastructure. The document provides two options for pecan grove relocation, both maintaining 30 feet from the field and 10 feet from the trail, suggesting flexibility in the implementation of the park improvements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Newtown_Estates_Park_Asphalt_Trail.pdf | ||
| Attachment_10.jpg | JPG image | |
| Attachment_9.jpg | JPG image | |
| Attachment_8.jpg | JPG image | |
| Attachment_7.jpg | JPG image | |
| Attachment_6.jpg | JPG image | |
| Attachment_5.jpg | JPG image | |
| Attachment_4.jpg | JPG image | |
| Attachment_3.jpg | JPG image | |
| Attachment_2.jpg | JPG image | |
| 2025-QQ-564_Requirements.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCALE:
0'
1"=100'
50' 100'
11"x17" ORIGINAL SCALE IF ALTERED
PARK IMPROVEMENTS
11"x17" ORIGINAL SCALE IF ALTERED
NEWTOWN ESTATES PARK PERIMETER TRAIL
JUNE 26, 2025
NO CHANGE: INCORPORATE EXISTING
CONCRETE SIDEWALKS TO PERIMETER TRAIL
M
A R
T
I
N
L
U
T
H E
K
I N
G
J
W
A
Y
POINT OF BEGINNING: RESURFACE SHELL
PERIMETER TRAIL WITH ASPHALT.
1600 FT LONG x 8 FT WIDE = 12,800 SF
REPLACE 16 LF MORTISE FENCE WITH (5) 6"
ROUND BOLLARDS AT 3'-6" ON CENTER.
END OF NEW ASPHALT PAVING.
EXTEND NEW TRAIL 30 FEET PAST EXISTING
SHELL BASE TO MAKE CONNECTION TO
EXISTING CONCRETE SIDEWALK.
ACCESSIBLE PUBLIC SIDEWALKS CONNECT
TO MAIN ENTRANCE AND ADD 1040 LF.
TOTAL PERIMETER LOOP TRAIL = 2640 LF
= 1
2 MILE
INSTALL 5' LONG x 10' WIDE x 3' DEEP
CONCRETE BOX CULVERT AT TRAIL
REGRADE TO WEST FOR EROSION CONTROL;
PROVIDE RIP RAP TO EAST
PECAN GROVE TO BE RELOCATED AND
BASEBALL FIELD TO BE REPLACED WITH
MULTI-PURPOSE FIELD
BY OTHERS
ADD 3' WIDE PERSON GATE AT MORTISE
FENCE TO ALLOW WHEELCHAIRS
PECAN GROVE RELOCATION AREA
OPTION 2
MAINTAIN 30 FEET FROM FIELD AND 10 FEET
FROM TRAIL
PECAN GROVE RELOCATION AREA
OPTION 1
MAINTAIN 30 FEET FROM FIELD AND 10 FEET
FROM TRAIL
N E W T O W N B L V D
| Sheets and Views |
| REBUILD_CONCEPT_1 |
File details come from the government source that posted it. Updated .