Attachment_1_-_Description_Specifications.docx

DOCX document 55 KB Posted

Attached to
MRG SFD CENTRIFUGAL PUMPS (Trailer Mounted)
Solicitation number
140R4026Q0022
Issued by

About this file

This is a Description/Specifications document for a Bureau of Reclamation solicitation requiring the purchase of two new 6-inch centrifugal pumps mounted on fully enclosed, DOT-compliant trailers. Each unit must be powered by a diesel engine with integrated sound-attenuating panels and will support field operations including water pumping for dust abatement and soil compaction activities at the Socorro Field Division in Socorro, New Mexico.

The technical specifications require 6-inch flanged suction and discharge connections with a minimum flow rate of 2,200 GPM and maximum total head of 182 feet. Each pump must feature a stainless steel dual-vane impeller capable of passing 3-inch spherical solids, ductile iron housing, tungsten carbide mechanical seals, and self-priming capability with a maximum suction lift of 25 feet. The diesel engine must be EPA Tier 4 compliant, rated at minimum 60 HP at 1,800 RPM, water-cooled, with an 80-gallon fuel tank and 12-volt industrial battery. The enclosed trailer shall include a 4-inch OLED display showing engine RPM, flow rate, battery voltage, and coolant temperature; LED lighting; two rear leveling jacks; four D-rings; spare tire; toolbox; electric brake hubs; and weigh 3,600 lbs dry and 4,000 lbs wet. The all-inclusive price must cover equipment furnishing, delivery to Socorro Field Division, setup, orientation and training for personnel, and handling charges. Key submittal requirements include an original project schedule within 28 days of contract award, manufacturer product data at least 14 days before equipment purchase, operation and maintenance manuals before final acceptance, and warranty information with final payment. Equipment must carry a minimum 12-month manufacturer warranty from acceptance date. Delivery must occur within 28 calendar days of contract award, coordinated with facility management at the Socorro location during normal business hours Monday through Thursday, 7:00 AM to 5:30 PM.

View the file

Other files

File Type Posted
Sol_140R4026Q0022_Amd_0002.pdf PDF
Attachment_3b_-_Exhibit_1_0002.pdf PDF
Attachment_3a_-_Amd_0002_Qs_As_0002.docx DOCX document
Sol_140R4026Q0022_Amd_0001.pdf PDF
Attachment_3_-_Amd_0001_Qs_As_0001.docx DOCX document
Attachment_2_-_Price_Schedule_Centrifugal_Pumps.docx DOCX document
Sol_140R4026Q0022.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Description/Specifications Bureau of Reclamation- Upper Colorado Region- Albuquerque Area Office Socorro Field Division- Purchase of two (2) 2026 6” attenuated sound, DOT trailer mounted, centrifugal pumps

NAICS 333914 Centrifugal Pumps Manufacturing

Abbreviations, Definitions, and Acronyms The Bureau of Reclamation commonly used definitions are listed below:

AAOAlbuquerque Area Office
BORBureau of Reclamation (Reclamation)
COContracting Officer
COTRContracting Officer Technical Representative
FARFederal Acquisition Regulation
GPMGallons per Minute
HPHorsepower
LBPounds (lb or lbs)
PSIPounds per Square Inch
RPMRevolutions Per Minute
MPHMiles Per Hour
PTOPower take-off
BTUBritish Thermal Unit
UCUpper Colorado Region
SFDSocorro Field Division
GPMGallons Per Minute
INInch(es)
FTFeet
HPHorsepower

Foreword The Bureau of Reclamation, Upper Colorado Region, Albuquerque Area Office, Socorro Field Division requires the purchase of two (2) new 6-inch centrifugal pumps mounted on fully enclosed, DOT-compliant trailers, each powered by a diesel engine with integrated sound-attenuating panels. These pumps will replace aging equipment and support critical field operations, including:

· Pumping water from natural and constructed sources into water trucks for dust abatement

· Supporting soil compaction activities at various job sites

General Requirements The contractor shall provide two (2) new 6-inch centrifugal pumps mounted on fully enclosed DOT-compliant trailers. Each unit shall:

· Be powered by a diesel engine

· Include integrated sound-attenuating panels to reduce operational noise to safe levels

· Allow safe access for operation, maintenance, and inspection

Technical Specifications

1. Package Overview

· Connections: 6-inch flanged suction and discharge

· Minimum Flow Rate: 2,200 GPM

· Trailer: DOT-compliant, dual-axle, suitable for safe transport and operation

2. Pump Specifications

· Impeller: Stainless steel, dual-vane, enclosed, capable of passing 3-inch spherical solids

· Pump Housing: Ductile iron, meeting or exceeding industry standards

· Backplate & Volute: Ductile iron construction

· Mechanical Seals: Tungsten carbide faces, oil-lubricated

· Total Head: Not to exceed 182 ft

· Self-Priming: Maximum suction lift of 25 ft; priming time ≤ 5 minutes

· Dry Run Capability: Up to 5 minutes without damage

3. Engine

· Diesel engine rated at minimum 60 HP at 1,800 RPM

· Water-cooled system (50/50 coolant mixture)

· Uses standard 15W-40 oil

· Compliance with EPA Tier 4 emission standards

· Equipped with 12-volt industrial battery

· Includes 80-gallon fuel tank

4. Engine Control Panel

· 4-inch OLED display showing:

· Engine RPM

· Flow rate (via integrated flow meter, accurate to ±5%)

· Battery voltage

· Coolant temperature

· Toggle switch for RPM adjustment

5. Enclosed DOT Trailer

· Fully enclosed with sound-attenuating panels

· LED lighting on all sides for visibility and DOT compliance

· Two rear leveling jacks with swivel lock mechanisms

· Four D-rings for secure tie-down

· Spare tire with mount

· Toolbox(es) for seals and hose clamps

· Dry weight ≤ 3,600 lbs; wet weight ≤ 4,000 lbs

· Electric brake hubs with breakaway system and DOT safety chains

· 7-pin connector plug

Price Inclusion:

The offered price shall be all-inclusive and cover all costs necessary to furnish and deliver the specified equipment in accordance with contract requirements. This includes, but is not limited to:

· Furnishing Equipment:

Supply the specified centifugal pumps mounted on DOT-compliant trailers, complete with all required accessories and components.

· Delivery and Setup:

Delivery to the designated location, including all costs for transportation, shipping, unloading, positioning, and initial setup of the equipment.

· Orientation and Training:

Provide operational orientation for SFD/Reclamation personnel at the time of delivery and setup. Orientation shall include basic operating procedures, safety considerations, and maintenance requirements.

· Handling and Unloading Charges:

Any applicable costs for handling, rigging, or unloading the equipment at the delivery site.

No additional charges beyond the offered price shall be permitted unless authorized in writing by the Contracting Officer.

Submittal Requirements

· Language: All documents must be prepared in English.

· Accessibility: Submitted documents must comply with Section 508 requirements.

· Labeling: Each submittal must include the contract number, title, and the Required Submittal Number (RSN).

· Measurement Units: Use U.S. Customary Units.

· Tracking: Assign a unique transmittal tracking number to each submittal.

· Certifications:

· Required certifications must be conducted by a registered professional.

· Manufacturers’ certifications must be signed by an authorized representative.

Government Review Process

· Review Time: The Government requires a minimum of 14 days to review and/or approve each submittal or resubmittal unless otherwise specified.

· Additional Time: If extra review time is needed, the Contracting Officer may extend the contract completion date accordingly.

Submittal Categories

· A – Action: Requires Government approval.

· I – Informational: Requires Government review and written receipt.

Submission Process

· Submit electronic copies for review and approval to Johnny Jaramillo, “Acting” COR, at JJaramillo@usbr.gov

RSN
Required Submittal and Description
Due Date or Delivery Time
Type
S1
Original Project Schedule including all key elements (timeline for deliverables and Government acceptance of two 6” pumps). Submit revised schedule if any dates change by more than 5 working days.
Original: within 28 days after contract award.

Revised: within 5 working days of any significant date change.

A

S2
Manufacturer or Supplier Product Data and General Information for all new equipment and accessories
At least 14 days prior to purchasing new equipment.

I

S3
Manufacturer’s Installation, Operation, Service & Maintenance, and User Manuals
At least 14 days prior to final acceptance

I

S4
Manufacturer’s Product Warranty Information
Furnish with final payment
I

Warranty All equipment furnished under this contract shall be warranted to be free from defects in materials and workmanship under normal use and service. The warranty shall apply to the Government as the original purchaser. The Contractor shall provide the longest manufacturer warranty available at no additional cost to the Government, but in no case shall the warranty period be less than twelve (12) months from the date of acceptance.

Delivery of Equipment Within twenty-eight (28) calendar days after contract award, the Contractor shall provide the Government with a proposed delivery schedule, including date and time, for coordination purposes. The schedule shall include any required site visits, delivery activities, and equipment setup.

Site Visit, Delivery, and Setup It shall be the responsibility of the contractor to arrange delivery to Bureau of Reclamation, Socorro Field Division, Socorro, NM 87801. Socorro Field Division will accommodate delivery needs during normal business hours of Monday thru Thursday 7:00am – 5:30pm. (Special arrangements can be made on Fridays if given 24hrs notice) Please contact the following:

Tomas Rosales, Facility Manager Bureau of Reclamation Socorro Field Division 2401 State Road 1, P.O. Box VV, Socorro, NM 87801-2170 Phone No: (575) 517-0518 Cell No: (575) 835-8657 Email: TRosales@usbr.gov

Brian Skornia, Construction Control Representative Bureau of Reclamation Socorro Field Division 2401 State Road 1, P.O. Box VV, Socorro, NM 87801-2170 Phone No: (575) 838-1202 Cell No: (505) 388-8324 Email: bskornia@usbr.gov

Johnny Jaramillo, “Acting” Construction Control Representative Bureau Of Reclamation Socorro Field Division 2401 State Road 1, P.O. Box VV, Socorro, NM 87801-2170 Phone No: (575) 838-1202 Cell No: (575) 517-5602 Email: jjaramillo@usbr.gov

The Contractor shall ensure that all parts and equipment are fully protected against corrosion, deformation, dents, scratches, punctures, abrasions, and any other damage during storage, handling, transportation, and delivery. Protective measures shall be adequate to maintain the equipment in new condition until final acceptance by the Government.